Design-Build Overview – ASHE Potomac Section VDOT Alternative Project Delivery (APD) Division Jeff Roby, P.E., DBIA – Assistant State Engineer APD Division March 13, 2019
Transcript
Page 1: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Design-Build Overview – ASHE Potomac Section

VDOT Alternative Project Delivery (APD) Division

Jeff Roby, P.E., DBIA – Assistant State Engineer APD Division

March 13, 2019

Page 2: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

2

Route 7 over Dulles Toll RoadWagman/RDA(Awarded – June 2015 Completed – May 2018)

Page 3: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

3

Page 4: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Legal Authority for Design-Build

In 2001, the General Assembly amended Code of Virginia

§33.1-12 .(2).(b). and authorized Commonwealth Transportation Board (CTB) to award design-build contracts for construction projects.

Five projects per year <$20 million

Five Projects per year >$20 million

In 2006, the General Assembly modified the Code provision

HB 666 – Removes the current restrictions on the number of Design-Build projects the CTB may award

HB 671 – Would allow the use of design-build contracting by localities awarding transportation contracts

In 2014, the DB code section reference is revised to § 33.2-209 (b)

2016, the DB code further revised to allow Alternative Technical Concepts (ATCs)

Title 23: Highways, Part 636 – Design-Build Contracting

4

Page 5: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

2001 2005 2010 2015 2018

VDOT Design-Build Program Timeline

Code of Virginia amended to allow CTB authority to

award D-B contracts

Code of Virginia amended to remove restriction on number of D-B contracts awarded per FY

Code of Virginia amended to allow the use of Alternative Technical

Concepts (ATCs)

1st D-B Transportation Contract APM Terminal

Hampton Roads District

50th D-B Contract AwardedMark Center Ramp

Northern Virginia District

100th D-B Contract AwardedWarrenton Southern Interchange

Culpeper District

High Rise Bridge Awarded1st Project with ATC’s

Largest D-B Contract to Date ($410M)

Hampton Roads District

5

Page 6: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VDOT Design-Build Projects Statewide

6

Page 7: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

DESIGN-BUILD PROGRAM(Through February 2019)

Number of Contracts

Total Value(in Millions)

COMPLETED CONTRACTS 73 $1944

ACTIVE CONTRACTS 14 $1445

ACTIVE PROPOSALS 5 $120

CANDIDATE PROJECTS 1 $100

7

Page 8: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

8

0

10

20

30

40

50

60

70

80

90

$0

$100,000,000

$200,000,000

$300,000,000

$400,000,000

$500,000,000

$600,000,000

$700,000,000

$800,000,000

$900,000,000

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

To

tal E

stim

ate

d C

on

tra

ct V

alu

e

Year

Summary of D-B Contracts Advertised

Total Estimated DB Contract Value # of DB Contracts Advertised

Page 9: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Design-Build Procurement Methods

VDOT program has matured over last 15 years and has developed processes for several procurement methods

• Single Phase, Low Bid - for low risk, non-complex projects

• Two-Phase, Low Bid – For non complex projects that still demand highly qualified firms

• Two-Phase, Best Value – For high risk, complex projects

• Two-Phase, Base Scope + Alternatives – For complex projects with additional scope items

• Exploring the use of Progressive Design-Build

9

Page 10: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Rte 277/244 InterchangeShirley Contracting/Dewberry(AWARDED – SEPTEMBER 2011 COMPLETED – JULY 2015)

10

Page 11: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Design-Build Guidance Documents

Documents available on VDOT’s APD Websitehttp://www.virginiadot.org/business/design-build.asp

• Design-Build Manual

• Design-Build Evaluation Guidelines

• Design-Build QA/QC Manual

• IIM-APD-1 (DB Deliverables for RFQ and RFP Advertisement)

• IIM-APD-2 (Conflict of Interest Guidelines for DB Procurements)

• IIM-APD-3 (Selection Process for DB Candidate Projects)

• IIM-APD-4 (Federal Authorization Process for DB Projects)

11

Page 12: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VDOT’s Design-Build Contract

• Part 1 – Instructions for Offerors

• Part 2 – Technical Requirements

• Part 3 – Lump Sum Agreement

• Part 4 – General Terms & Conditions

• Part 5 – Amendments to Standard Specifications

• Design-Builder’s Technical and Price Proposal

• Includes any enhancements proposed by Design-Builder

12

Page 13: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Route 29 SolutionsLane-Corman JV /RK&K(Awarded – February 2015 Completed – July 2017)

13

Page 14: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

INDUSTRY TOPICS

14

Page 15: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VTCA DESIGN-BUILD COMMITTEE

Progressive Design-Build:

VDOT is laying the groundwork to be able to use “Progressive Design-Build” (PDB) as an additional project delivery tool.

Alternative Technical Concepts (ATC) :

“A Request for Proposal for transportation projects to be delivered on a design-build basis pursuant to this section may allow for the submission and consideration of alternative technical concepts in accordance with the procedures set forth in such Request for Proposal.”

Design-Build Performance Evaluations:

Construction Division has initiated performance evaluations to be completed quarterly by the VDOT Pm. Goal is to utilize the results as part of the selection process during procurement.

15

Page 16: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VTCA DESIGN-BUILD COMMITTEE

Stipend Levels:

VDOT and Industry currently evaluating the process for determining stipend amounts which is provided to the unsuccessful Offerors.

As-Built Plans

VDOT is coordinating on effort to clearly defining the as-built plan development and submittal process.

Entrusted Engineer in Charge (EIC):

Formerly Responsible Charge Engineer (RCE)

16

Page 17: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• 2018 QA/QC Guide – July 2018 Update

• Provides consistency with Department’s current contract documents

• Improves inspection practices on D-B projects

• Layered PDF of Technical Proposal Plans

• Comparison between RFP Conceptual Plan and Offeror’s Proposed Concept

• Electronic Signatures for Title Sheet

• Electronic Submittal of Title Sheets

• Eliminate the need for signing mylars

• VDOT DB Community of Practice

• Improves consistency with contract administration

• Quarterly Meeting with D-B Construction Project Managers

Design-Build Program Improvements & Innovations

17

Page 18: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

18

I-581/Valley View Boulevard Improvements Lane/STV(Awarded – March 2013 Completed – September 2016)

Page 19: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Candidate Projects

• I-95 Rappahannock River Crossing - RFQ Spring/Summer 2019

• Popes Head Road Interchange

• Boundary Channel Road Interchange

Locally Administered Projects

• Rte 28 Widening (Fairfax County) RFQ Spring 2019

• Rte 234 Balls Ford Road (Prince William County) - May 2019

• Northstar Blvd (Loudon County) – RFQ late 2019

19

Page 20: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Who is the “Engineer” for Design-Build Projects

• The Design-Builder is the Engineer of Record and responsible for the final design and construction

• In the Part 2 Technical Requirements and Design-Build Special Provisions you will see the terms:

• VDOT Project Manager

• Design-Builder

• Quality Assurance Manager

• Engineer

• Engineer is define as:

• “Engineer shall mean the Department’s Chief Engineer, who

acts directly or through his duly authorized representative, the

representative acts within the scope of the particular duties

assigned to him or the authority given to him.”

20

Page 21: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

21

I-581 & Elm Avenue InterchangeAmerican Infrastructure/RDA(Awarded – July 2012 Completed – July 2015)

Page 22: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

PROGRESSIVE DESIGN-BUILD

22

Page 23: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

PROGRESSIVE DESIGN-BUILD

Progressive Design-Build (PDB) facilitatesinvolvement of the design-build team during theearliest stages of the owner’s project development,ensuring they are part of the project teamdeveloping design solutions. This promotes thegreatest amount of collaboration between the threekey players in a construction contract – the owner,the designer and the contractor.

23

Page 24: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• No contractor involvement during design development

• Price is the only consideration for selection

• Project is totally defined at time of award

• No contractor involvement in ROW acquisition

Design-Bid-Build Attributes

24

Page 25: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Some early contractor involvement

• Proprietary meetings

• Opportunities for innovation

• Alternative Technical Concepts

• Risk transfer in ROW acquisition and Utility Relocation

• VDOT selects the most highly qualified teams

25

Design-Build Attributes (VDOT’s Two-Phase Best Value)

Page 26: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

A procurement tool that provides the following benefits onhigh risk, complex projects:

• Involvement of most qualified Design-Builder at theearliest point of project development

• Collaboration with the Design-Builder on key scope andrisk issues

• Owner’s involvement in the selection of subconsultants, subcontractors, vendors and suppliers (including DBE & SWaM)

• Transparency in cost development using open-bookpricing

As a result, PDB reduces project risk for Owner and Design-Builder

Progressive Design-Build (PDB)

26

Page 27: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Design-Builder becomes a strategic partner in planning and project definition

• Allows involvement of public and private stakeholders throughout design development

• Single point responsibility avoids Spearin liability (errors and omissions) as there is no design “handoff”

• Potential cost & schedule savings

• Preliminary Engineering - No duplication of effort as bridging documents are not required

• Use of early work packages (R/W acquisition and utility relocation)

• Expedited procurement

PDB Advantages

27

Page 28: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Design and Construction Challenges

• Interface with other planned construction

• Need for early contractor involvement

• Unproven technology

• Operational impacts during construction

• Input on specific performance parameters

• Urban areas with dense commercial and residential development

• Environmental Challenges

• NEPA

• Permits

• 4F Properties

• HAZMAT

• USACE

When to use PDB

28

Page 29: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Right of Way Challenges

• Large number of parcels impacted

• Federal and State property

• Third Parties (railroad and transit authorities)

• Utility Challenges

• High volume

• Unknown and/or dark utilities

• Stakeholder Involvement

• Extensive input during design development

• Advisory panels

• Business entities, developers

• Military, municipalities, governmental agencies, Homeowners Associations, Architecture Review Boards

• Public transit and airports

When to use PDB (cont.)

29

Page 30: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

RFQ RFPPhase 1A -

Proof of Concept

Phase 1B –Project

Development

Phase 2 –Final Design

and Construction

Progressive Design-Build Process

RFQ Advertisement

CTB Award(GMP)

GMP

Decision Point #1 Proof of Concept within

GMPor

Off Ramp

Decision Point #2Lump Sum Price Established

at 40-60% Designor

Off Ramp

30

Page 31: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Collaborative effort between Owner and Design-Builder

• Ongoing and transparent cost estimating process

• Goal is to stay below established GMP

• Similar to existing escrow information

• Real time quotes from Design-Builder, subcontractors and subconsultants

• Better understanding of risk

• High confidence in price throughout process

PDB – Open Book Pricing

• Quantity take-offs• Crew size and

shifts• Equipment• Direct labor

• Indirect costs• Bond rates• Insurance costs• Mark-up and contingency

31

Page 32: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Operates as a termination for convenience

• Commercial terms generally include:

• Right to use work product

• Design-Builder is paid for services rendered; VDOT owns design

• Right to contract directly with designer to finish the design

• Right to use any other type of delivery system

Owner’s Off-Ramp Rights

32

Page 33: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

CTB Objective Criteria

In October 2001 the CTB adopted Objective Criteria for the selection of Design-Build projects listed below:

1. Expedited Schedule

2. Established Budget

3. Well-defined scope

4. Risk Analysis

5. Prequalification of Design-Build Firms

6. Competitive Bidding Processesa. Best Value

b. Low Bid

c. Fixed Price

d. Guaranteed Maximum Price33

Page 34: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Route 460 Connector (Phase I)Bizzack Construction/AMT/ENTRAN/Janssen & Spaans(Awarded – August 2009 Completed – May 2015)

34

Page 35: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ALTERNATIVE TECHNICAL CONCEPTS & PROCESS

35

Page 36: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ALTERNATIVE TECHNICAL CONCEPTS (ATC)

In 2016, the General Assembly amended Code of Virginia

§33.1-12 .(2).(b). and authorized CTB to allow the submission and consideration of alternative technical concepts under design-build contracts.

HB 501 - Alternative Technical Concepts (ATC) :

A Request for Proposal for transportation projects to be

delivered on a design-build basis pursuant to this

section may allow for the submission and consideration

of alternative technical concepts in accordance with the

procedures set forth in such Request for Proposal.

For the purposes of this subsection, "alternative technical

concepts" means proposed changes to agency-supplied

base design configurations, project scope, design, or

construction criteria that provide a solution that is equal

to or better than the requirements in the Request for

Proposal.36

Page 37: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VDOT ATC PROCESS

The purpose of the ATC process is to allow for technical innovation, creativity, and flexibility to achieve the project’s goals and objectives which are equal to or better than the RFP requirements.

ATCs will not be accepted for :

• reduce scope, long term performance, quality or reliability

• changes to VDOT design standards and practices, such as those solely proposed for the purpose of relaxing a more stringent standard

• modify VDOT’s programmatic risk allocation procedures, such as responsibility for utility relocation, responsibility for ROW acquisition, QA/QC program requirements and minimum pavement section requirements

• impose an additional burden on VDOT for maintenance (i.e. purchase of specialized equipment)

37

Page 38: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

VDOT ATC PROCESS (CONT.)

Proprietary Meetings

• Each Offeror will participate in two (2) Proprietary meetings with VDOT and its representatives or consultants. The purpose of the Proprietary meetings is to give each Offeror, in a confidential setting, an opportunity to ask questions and discuss concerns related to the Project, details of the Project scope, administrative procedures, and for the Offeror to present and discuss conceptual ATCs.

• The meetings are also intended to enable VDOT to express, among other things, whether the Offeror is pursuing an approach that is unacceptable to VDOT and, when possible, to establish whether a proposed concept meets the definition of an ATC thereby requiring a formal ATC submittal.

38

Page 39: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ATC PROCESS (CONT.)

Proprietary Meeting #1:

The purpose of Proprietary Meeting # 1 is to discuss general issues and questions related to the Project including any potential ATCs the Offeror is considering. Offerors may bring exhibits or prepared graphics to the Proprietary Meeting for use in conveying their conceptual ATCs to Department staff.

39

Page 40: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ATC PROCESS (CONT.)

Proprietary Meeting #2:

The purpose of Proprietary Meeting #2 is for the Offerors to provide a presentation of the ATCs the Offeror plans to submit as Formal ATCs. Offerors may bring exhibits or prepared graphics to the Proprietary Meeting # 2 for use in conveying their conceptual ATCs to Department staff.

40

Page 41: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ATC PROCESS (CONT.)

Formal Submission of ATCs :

• If an Offeror desires to submit a formal ATC proposal, it shall do so by completing and submitting the Alternative Technical Concept (ATC) Submittal Form for each proposed ATC.

• The Offeror will only be permitted to submit ATC proposals for ATCS presented at Proprietary Meeting #2.

• Any ATCs submitted as formal ATC proposal that was not presented at Proprietary Meeting #2 will be rejected without consideration.

• If for any reason an ATC an Offeror was considering is withdrawn after Proprietary meeting #2 than no new ATCs can be introduced

41

Page 42: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ATC PROCESS (CONT.)

VDOT performs ATC Evaluation and Determination

• VDOT will issue final determinations in writing to the Offeror for all ATCs submitted on or before the ATC submission deadline as indicated in the RFP

• If at any time after formal ATC submission it is determined that clarifications or additional information are needed, VDOT will request the information from the Offeror prior to completing the ATC review.

42

Page 43: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

ATC PROCESS (CONT.)

Offeror includes approved ATC into their Proposal

• Offerors have the option of whether or not to include approved ATCs into their Proposal. The Offeror shall identify in the Technical Proposal any approved ATC(s) incorporated in its Proposal, identify where each ATC has been incorporated, and confirm agreement with all conditions that accompany the ATC approval(s).

Evaluation of ATC proposals

• ATCs will not be evaluated separately but rather will be considered to be part of the overall Proposal and graded/ranked accordingly to the evaluation criteria and project goals and objectives as established with the RFP.

43

Page 44: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

CONFIDENTIALITY OF THE ATC PROCESS

• ATC confidentiality is of the utmost importance to VDOT recognizing that Offerors invest a tremendous amount of effort into developing their ideas.

• ATC submissions are considered proprietary until the contract is awarded and unsuccessful Offerors have accepted stipends.

• The Department understands the importance of maintaining tight restrictions on the review and approval process during procurement and will adhere to the policies outlined in the Design-Build Evaluation Guidelines to ensure confidentiality is maintained.

44

Page 45: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Zion Crossroads Interchange Improvements Corman Construction Co./Parsons Transportation(Awarded – September 2012 Completed – April 2014)

45

Page 46: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• Nationally recognized program

• VDOT named 2016 Transportation Owner of the Year by Design-Build Institute of America (DBIA)

• D-B Project Awards

• 27/244 Interchange – 2016 DBIA Merit Award (Transportation)

• I-64 Capacity Improvements, Segment I – 2018 DBIA Merit Award (Transportation)

• I-66/Route 15 Interchange – 2018 DBIA Project of the Year Award (All Sectors)

• DBIA Mid-Atlantic Chapter – Numerous Awards

VDOT’s Design-Build Program

46

Page 47: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

47

Page 48: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

I-66/Route 15 InterchangeLane Construction/RDA(Awarded – May 2014 Completed – August 2017)

48

Page 49: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

• President- Ed Stelter (Faulconer)

• Vice President - David Lyle (Phillips and Jordan)

• Secretary - Ryan Masters (RK&K)

• Programs and Events Committee Chair - Bryan Stevenson (VDOT)

• Membership Committee Chair - Muriel Rodriguez (Schnabel)

• Sponsorship Committee Chair/Treasurer - Linnell Stanhope (Crowder)

• Legislative Committee Chair - Dusty Holcombe (RS&H)

DBIA Central Virginia Chapter – formed April 2018

49

Next Event: Thursday April 25th

Morning meeting at McGuire Woods in Richmond, Virginia

Speaker: L. Preston Bryant, Jr. (McGuire Woods Consulting, LLC)

Former Delegate and Secretary of Natural Resources will discuss the

General Assembly sessions and trends affecting our industry

Page 50: Design-Build Overview – ASHE Potomac Section VDOT ...potomac.ashe.pro/uploads(2)/PRE-05_20190313_J.Roby_VDOT.pdf · 3/13/2019  · Jeff Roby, P.E., DBIA – Assistant State Engineer

Thank You!!

Jeffrey A. Roby, PE, DBIA, PE, DBIA