+ All Categories
Home > Documents > Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to...

Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to...

Date post: 16-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
30
US Army Corps of Engineers Hydrologic Engineering Center Design of Flood Control Improvements by System Analysis: A Case Study October 1971 Approved for Public Release. Distribution Unlimited. TP-51
Transcript
Page 1: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

US Army Corps of Engineers Hydrologic Engineering Center

Design of Flood Control Improvements by System Analysis: A Case Study October 1971 Approved for Public Release. Distribution Unlimited. TP-51

Page 2: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Standard Form 298 (Rev. 8/98) Prescribed by ANSI Std. Z39-18

REPORT DOCUMENTATION PAGE Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ORGANIZATION. 1. REPORT DATE (DD-MM-YYYY) October 1971

2. REPORT TYPE Technical Paper

3. DATES COVERED (From - To)

5a. CONTRACT NUMBER

5b. GRANT NUMBER

4. TITLE AND SUBTITLE Design of Flood Control Improvements by Systems Analysis: A Case Study

5c. PROGRAM ELEMENT NUMBER

5d. PROJECT NUMBER 5e. TASK NUMBER

6. AUTHOR(S) Howard O. Reese, Arnold V. Robbins, John Jordan, Howard V. Doyal

5F. WORK UNIT NUMBER

7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) US Army Corps of Engineers Institute for Water Resources Hydrologic Engineering Center (HEC) 609 Second Street Davis, CA 95616-4687

8. PERFORMING ORGANIZATION REPORT NUMBER TP-51

10. SPONSOR/ MONITOR'S ACRONYM(S) 9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 11. SPONSOR/ MONITOR'S REPORT NUMBER(S)

12. DISTRIBUTION / AVAILABILITY STATEMENT Approved for public release; distribution is unlimited. 13. SUPPLEMENTARY NOTES Presented at the ASCE National Meeting on Environmental Engineering, October 1971. 14. ABSTRACT A hydrologic-economic simulation model was developed to evaluate alternative protection schemes in the design of an authorized federal flood control project for 125 miles of the Tibbee River floodplain in Mississippi. The model requires input consisting of unit hydrographs, streamflow routing coefficients and storage functions, a pattern storm, rainfall loss rate functions, and flow-damage-frequency relations. A single synthetic pattern storm was used in conjunction with flow-frequency curves at index locations to generate a series of floods for comparing alternative protection schemes with existing conditions. The effect of channel improvements on flood runoff characteristics was evaluated by using storage routing functions that account for change in storage-discharge relations. Based on results obtained from using the model, a channel improvement plan was tentatively selected for the Tibbee River basin from the alternative schemes evaluated. 15. SUBJECT TERMS flood control, systems analysis, Mississippi, model studies, flood damage, hydrologic aspect, economics, mathematical models, design, analytical techniques, methodology, channel improvement, flood protection, stream improvement, Tibbee River, case study 16. SECURITY CLASSIFICATION OF: 19a. NAME OF RESPONSIBLE PERSON a. REPORT U

b. ABSTRACT U

c. THIS PAGE U

17. LIMITATION OF ABSTRACT UU

18. NUMBER OF PAGES 30 19b. TELEPHONE NUMBER

Page 3: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Design of Flood Control Improvements by Systems Analysis: A Case Study

October 1971 US Army Corps of Engineers Institute for Water Resources Hydrologic Engineering Center 609 Second Street Davis, CA 95616 (530) 756-1104 (530) 756-8250 FAX www.hec.usace.army.mil TP-51

Page 4: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Papers in this series have resulted from technical activities of the Hydrologic Engineering Center. Versions of some of these have been published in technical journals or in conference proceedings. The purpose of this series is to make the information available for use in the Center's training program and for distribution with the Corps of Engineers. The findings in this report are not to be construed as an official Department of the Army position unless so designated by other authorized documents. The contents of this report are not to be used for advertising, publication, or promotional purposes. Citation of trade names does not constitute an official endorsement or approval of the use of such commercial products.

Page 5: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

DESHW OF n O O D GOMTROL IHWOBrlEmNTS BY SYSTEMS M L Y S I S : A CSE s ~ F ~ " J ( ~ )

bps

( 4 ) Howard 0. ease!" Arnold V. ~ o b b i n s !3' John 8. Jordan,

and' Harold V, ~ o ~ a l ( ~ )

A hydrologic-economic simuBae9~n m d e l was developed tto evaluate alter-

na t ive protec t ion schemes i n the design of an authorized fede ra l f lood

contro l p ro jec t f o r 125 m i l e s of the Tibbee River f lood p l a i n i n M s s i s s i p p i .

The model requi res input cons is t ing of u n i t hydrographs, s t r e m f l o w rout ing

c o e f f i c i e n t s and s to rage functions, a p a t t e r n storm, r a i n f a l l l o s s r a t e

functions, and Plow-damge-frequency r e l a t i o n s . A s i n g l e syn the t i c pa t t e rn

storm was used i n conjunction with flow-frequency curves a t index loca t ions

t o generate a series of f loods f o r comparing a l t e r n a t i v e protec t ion schemes

with e x i s t i n g condit ions. The e f f e c t of channel improvements on flood

runoff c h a r a c t e r i s t i c s was evaluated by using s torage routing functions

t h a t account f o r changes i n storage-discharge r e l a t i o n s , Based on r e s u l t s

obtained from using the model, a channel. i q r o v e e w e plan was t e n t a t i v e l y

se lec ted f o r the Tibbee River basin from the al tematiave schems evaluated.

( I ) For presenta t ion a t the ASCE National Meeting on Environmental Engineering, October 1971.

(2 ) Chief, Special Assistance Branch, The Hydrologic Engineering Center, U. S. A m y Corps of Engineers, Davis, Ca l i fo rn ia ,

(3) Civi l Engfneer, P ro jec t Development Seceioa, Nobile D i s t r i c t , U. S. Army Corps of Engineers, Mobile, Alabama.

' 4 ) Chief, Hydrology Sect ion , Mobile D i s t r i c t , U. S. Amy Corps of Engi neers , Mobile, ABabam,

'5) C iv i l Engineer Technician, Hydraulic Data Section, Mobile D i s t r i c t , U . S. Army Corps of EngBneers, Mobile, ABabam.

Page 6: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

A federal project involving extensive stream clearing,

straightening and enlargement was authorized by Congress in 1958.

The purpose of the project is to achieve flood control and drainage

on 466 miles of flood plain along 22 tributary streams of the upper

Tombigbee River in Mississippi and Alabama. A current study conducted

on a cooperative basis by the Mobile District and The Hydrologic

Engineering Center, Corps of Engineers, is concerned with a portion

of the overall project, namely 125 miles of f.l.ood control improvements

authorized for a system of 1.0 streams in the Tlbbee River basin,

Mississippi (figure 1). The objectives of the study are to determine

the effect of alternative channel improvement schemes on flood runoff

characteristics in the stream system, to determine the reductions in

flood damage associated with the alternative plans, and to select

from among the alternatives the plan that would most economically

achieve the fl..ood control ob jecti.ves . The methodology adopted for the study required the development

of a generalized hydrologic-economic ma$hematical model to simulate the

flood runoff characteristics of the basin under existing conditions and

for alternative improvement schemes, including detention structures

that are planned by the U. S. Soil Conservation Service. This paper

describes the simulation model and study procedures and presents some

of the results of the study.

Page 7: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

The total , area of %he Tibbee River basin is

1,121 square miles, of which about U O s q w e miles are i n the flood

p la in of %he 10 s taems authorized for improvement. The basin has

a maximum width of 30 miles, an average width or" 2 l m i l e s , and a

stream length of 74 miles (from the mouth of Tibbec River to the head

of Sakatonchee Creek, %ts longest t r i b u t a q ) . '$ke t e r r a in is f a i r l y

rugged with rather high r e l i e f varying from elevgution la Lo 400 f ee t ,

rn.s.1.

The Tibbee River i s fomed a t the junction of Line and Sakatonchee

Creeks and it flows easter ly about 24 mil-es to join the Tonabjigbee River

through the r ight bank about 35 miles northwest of Colmbus, Mississippi.

It has an average gradient of 1.5 f ee t per mile. Its %ributaPies

range i n length from about 5 miles t o 50 miles with gradients generally

steeper than tha t of' the main stem. The fl,ood plain along the Tibbee

River and i ts tribuLaP.ies awrages about E mile In width and i s subject

t o frequent flooding,

The basin area i s located within the Tombigbee H i U s and Black

Prair ie d i s t r i c t s of the Gulf Coastal Halain physiowaplaic province.

The downstream 4 on. 5 miles of the Ti.bbee River traverses the Tombigbee

H i l l s d i s t r i c t with topography rangiwg from 9 . 0 ~ ~ smoothly rounded

hi l . ls t o h i l l s and ridges separated by nwrow valleys. The upstrem

reach of the Tibbee River and i t s t r ibu ta r i e s i s located i n the Black

Page 8: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Pra i r i e d i s t r i c t where the topography var ies from nearly f l a t

t o smoothly rounded h i l l s or Low r e l i e f .

Climatology. The Tibbee River basin has a temperature climate

with warm sumners and m i l d winters. The normal annual temperature

is 64 degrees with monthly normals ranging from 47 degrees i n

January t o 81 degrees i n July. '1111e minimu? recorded temperature

i s -10 degrees and the maximum is 113 degrees. The frost- f ree

period normally l a s t s from April t o November.

Precipi ta t ion during the year is abundant and f a i r l y well

d is t r lbuted. The normal annual. r a i n f a l l i s almost 49 inches, of

which 58 percent f a l l s i n the winter and spring, 24 percent in the

summer, and 18 percent in the f a l l . The average annual snowfall is

about 35 inches.

Flood producing storms may occur a t any time but a r e more

frequent during the winter and spring. Such storms a r e usualQ of t he

f ron ta l type covering large meas and l a s t i ng from 2 t o 4 days. S m e r

storms a re generally of the thunderstorm type with high in tens i ty

over small. areas. Recorded rainfall .1~ i l l the basin include maximums of

3.20 inches i n a 1-hour period, 6.53 inches i n 1.2 hours, and 7.43

inches i n 24 hours. The 1- and 12-hour maximums occurred during a

storm on June 1-2, 1947, and the 24-how maximum occurred i n

January 1950.

Land Use. About half of the t o t a l basin area i s i n farms. Sixty

percent of .the farmland acreage i s about equblly divided between

Page 9: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

cropland and other uses such a s house l o t s , roads, pastures andl

wasteland. The remaining 40 percent is woodland. More than

80,000 acres a r e i n t h e flood pla in along the 10 project streams.

It is estimated t h a t 30 percent of %his flood p la in land is i n

cul t ivat ion, 15 percent i s i n pastme o r id le , and 55 percent i s wood-

land. It i s estimated t h a t flood amages t o flood p la in development;

average $1.,837,000 a yew, consist ing mainw of agricul.tural. losses.

The improvement of t he project streams would reduce these flood

damages and permit more intensive agr icu l tu ra l use of t h e flood

plains.

INVEST IGAT TON

General. To accomplish the study objectives, it was concluded

t h a t a systems analysis of various a l te rna t ive schemes of basin develop-

ment f o r the Tibbee River was required, and t h a t a hydrologic-economic

simulation model should be developed t o f a c i l i t a t e the analysis . It was

recognized t h a t extensive channel improvement works i n a r i ve r system

could cause an adverse peaking e f f e c t on runoff; i.e., peak r tnoff r a t e s

could l i ke ly be la rger because of t he more rapid concen%ration of runoff

resu l t ing from more e f f i c i e n t conveyance. Therefore, %he model was

developed primari1.y for the purpose of epretl.uating t he e f fec t s of

a l t e rna t ive channel improvement plans on the flood runoff charac te r i s t i cs

of timing and magnitude of peak runoff ra te . Another major purpose o f the

model was t o determine the reductions i n flood damage fo r the a l te rna t ive

Page 10: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

plans. A general.ized computer program (ra infa l l - runoff model)

developed by The Hydrologic Engineering Center was used f o r

mode1:ing purposes.

The appl ica t ion o f the general ized simulat ion model required

t h e devel.opment of c e r t a i n hydrologleal and economic inputs, such as

(1) u n i t hydrograph and l o s s rate c r i t e r i a , (2) channel rout ing c r i t e r i a ,

(3) s y n t l ~ e t i c pa t t e rn storm, (4) d i jcharge-frequency and stage-discharge

r e l a t i o n s , and ( 5 ) stage-damage r e l a t i o n s .

Economic Studies. The procedure used f o r determining reductions

i n f lood damage a t t r i b u t a b l e Lo chanael improvement works was t o

compute the d i f ference i n average annual flood damages1 between

e x i s t i n g conditions and improved conditions. Average annual f lood

damages f o r e x i s t i n g condit ions were computed from known o r derived

stage-discharge, discharge-frequency, and stage-damage re la t ionships .

For 'mproved conditions, average annual f lood damages are usually computed

from these same rel.a-kionships with t h e stage-discharge re la t ionsh ip modified

t o r e f l e c t t h e changes i n stage. However, f o r t h i s study i t was a l s o

necessary t o modify t h e discharge-frequency re la t ionsh ip t o r e f l e c t t h e

magnitude of the peaking e f f e c t on runoff resul . t ing from upstream channel

improvement works. The need f o r modifying t h i s r e la t ionsh ip made the

determination of flood damage reduction more d i f f i c u l t .

I n formulating the optimal plan of channel. improvement works f o r

t h e Tibbee River basin, es t imates of f lood damage reduction a t t r ibutable

' ~ v e r a ~ e annual f lood damage i s defined as t h e expected value of annual flood damage computed by in tegra t ing t h e damage-exceedence frequency function.

6

Page 11: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Co each alternative plan evaluated were determined. For this

determination, the flood plains of the Tibbee River and its

tributaries were subdivided into 21 plannirng reaches vanyi.ng in length

from 2 to 17 miles (figure 1). Based on detaiLed economic studies,

flood damages were deteMned for each planni~lg reach and related

to stage at the index station (representatiw reference point)

selected for the reach. Using stage-discharge and discharge-frequency

relationships, average annual. flood damages were computed at each

index station for existing conditions and for each alternative plan

as described later in the paper.

Hydrologic and IQnirau3.i~ Studies. A discharge-frequency

statistical analysis was made from stremflow data for gaging stations

located on the Tibbee River and its tributaries and on adjacent streams

of similar size and comparable hydrologic characteristics. A relationship

of drainage area versus the annual mean was devel.oped, A skew coefficient

of zero and a standard deviation of 0.24 were adopted and used with this

relationship for determining the discharge-frequency relationship at

each index station for existing conditions in the basin.

Extensive backwater computations for existing conditions and for

alternative plans of improvement were made to determine stage-discharge

relations at each index station, pertinent water surface profiles, and

storage-outflow relations for the selected channel routing reaches. Data

on surveyed cross-sections and topographic maps were available. The

Page 12: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

roughness coeff ic ients used i n Manningqs f0muZ.a were based on

known high water marks and r a t i ng s ta t ions i n t he basin.

FOP study purposes, the Tibbee River basin was subdivided in to

216 subareas. Synthetic uni t hydrographs were derived fo r each

subarea by the Clark un i t hydrograph method using generalized

coeff ic ients . Unit hydrograph and r a i n f a l l loss r a t e coefficients

were derived for 22 stream gaging l x a t i o n s i n the Tibbee River basin

and other adjacent stream basins from an analysis of streanflow and

r a i n f a l l data f o r a t o t a l of 89 runoff events (2 t o 8 per location).

The r e su l t s of t h i s analysis were used for developing generalized

coeff ic ients for application t o ungaged locations.

The methodology adopted fo r evaluating the e f f ec t of channel

improvements on flood runoff character is t ics required the development

of a single representati.ve synthetjc pat tern storm for the Tibbee River

basin. It a l so provided for computing a synthetic pattern flood for

each submea from the pattern storm and, using mu.l.tiples of the

pat tern flood, for determining other floods of pertinent magnitudes or

frequencies.

A uniform a rea l d i s t r ibu t ion of rainfall . was used f o r computing

the pattern storm. In t h i s way, each portion of the basin had a

representative e f f ec t on flood dalerminations. Although a single pat tern

storm may not be to ta l ly representative fo r the en t i r e Tibbee River

basin as well a s the headwater areas, it would have been extremely

d i f f i c u l t and laborious t o attempt many representative storm centerings

Page 13: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

within the basin. Also, it is doubtful t h a t r e s u l t s would have

been s u b s t a n t i a l l y d i f f e r e n t than those obtained from a s ing le

uniform storm pa t t e rn . While t h e e f f e c t s of t r i b u t a r y runoff would

actual.1.y va-y, depending on storm centering, the ne t e f f e c t of all

centerings and a11 storm magnitudes would probably not be s u b s t a n t i a l l y

d i f f e r e n t from t h a t computed using a uniform d i s t r i b u t i o n .

The area-depth-duration r e l a t i o n adopted fo r t h e pa t t e rn storm

was of p a r t i c u l a r importance because the r e s u l t i n g pa t t e rn fl.oods

were t o be representa t ive of h i s t o r i c a l f loods. 1% was determined

t h a t i f t h e peak-to volume re la t ionsh ips of t h e pa t t e rn floods a r e

representa t ive of h i s t o r i c a l f loods throughout the basin, then o the r

f loods derived a s mul.tiples o f t h e pa t t e rn f loods would be equally

r ep resen ta t ive because peak-to-volume r a t i o s of h i s t o r i c a l f loods a r e

r e l a t i v e l y independent of flood magnitude. The adopted c r i t e r i a f o r the

storm were a r a i n f a l l i n t e n s i t y of 5-year recurrence in te rva l , 8. r a i n -

fa1.l dure t ion o f 48 hours, and an a r e a s i z e of 200 square miles. Based

on r a i n f a l l da ta i n Weather Bwreau Technical Papers 40 and 49, it was

determined t h a t the t o t a l s t o m r a i n f a l l was 5.7 inches.

For t h i s study, the pa t t e rn f lood a t any loca t ion i n t h e bas in i s

defined a s the runoff from t h e pa t t e rn storm. Tke pa t t e rn flood

hydrograph f o r each subarea was computed by applying t h e pa t t e rn storm

r a i n f a l l excess t o t h e syn the t i c u n i t hydrograph. The pa t t e rn flood

hydrographs f o r the o ther locat ions i n the bas in were determined by

rout ing and combining these subarea pa t t e rn flood hydrographs. The

Page 14: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Muskingum rou t ing method was used f o r t h e smaller streams i n the head-

water a reas and the nonlinear s torage rout ing method (modified ~ u l s )

was used f o r the o t h e r stream reaches. The l a t t e r method required t h e

development of storage-outflow r e l a t i o n s Tor each sel.ected channel

rou t ing reach f o r e x i s t i n g and improved condit ions. I n t h i s r e l a t i o n ,

t h e s torage value is t h e volume of water i n t h e channel and overbank

wi th in the rout ing reach corresponding t o a given steady s t a t e water

surface p r o f i l e . The storage-.outflow r e l a t i o n f o r e x i s t i n g condit ions

was adjusted t o r e f l e c t the changes i n s torage f o r each plan of

channel improvement considered. Therefore, although t h e same pa t t e rn

storm was used, t h e r e s u l t i n g pa t t e rn f loods a t a given loca t ion were

d i f f e r e n t f o r each a l t e r n r t i v e plan as i l l u s t r a t e d i n f i g u r e 2 fo r

one of t h e index s t a t i o n s on Catalpa Creek.

A s e r i e s o r s e t o f nine syn the t i c flood hydrographs a t a l l

l oca t ions i n t h e bas in was developed f o r e x i s t i n g condit ions and f o r

each considered plan o f improvement. The s e t of f lood hydrographs was

synthesized by mult iplying al.1 of t h e subarea p a t t e r n f lood hydrograph

ordinates by nine predetermined r a t i o s and by rou t ing and combining

the s u b ~ r e a pa t t e rn f loods computed f o r each mult iple. Tlie same

mult iples used f o r e x i s t i n g condit ions were used f o r each plan of

improvement. Multiples were se lec ted t o produce f lood magnitudes

corresponding t o a frequency range from four t o twelve times per year

(zero flood damage s t age ) t o approximately once i n 200 years.

Page 15: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Using discharge-frequency curves, an exceedence p robab i l i ty was

assigned t o each mult iple flood a t each index s t a t i o n locat ion f o r

e x i s t i n g conditions. For each plan of improvement, the exceedenee

probabi l i ty f o r each mul.tiple flood was assumed t o be the same a s t h a t

es tabl i shed f o r e x i s t i n g conditfons, The p r o b a b i l i t i e s associa ted

with each mul.tip1.e were used, i n conjui~cQion with flow-damage c w v e s ,

t o compute average annual flood damages a t each index s t a t i o n f o r

e x i s t i n g condit ions and f o r each plan of improvement. The assigned

range of p robab i l i ty of each mult iple f lood is mul t ip l ied by the

damage caused by t h a t f lood, and the sum of these cross products f o r

a l l of the nine mul t ip le f loods is the average annual damage f o r the

given condit ion.

RESULTS

Some of t h e r e s u l t s of t h e inves t iga t ion a r e i l . l u s t r a t ed on

f igures 2 through 6 f o r two of the planning reaches analyzed. The

resul - t s f o r these two loca t ions a r e representa t ive of t h e o the r

Locations i n the basin.

Examples of computed flow-probability-damage re l .a t ions and average

annual flood damages f o r e x i s t i n g conditons and various a l t e r n a t i v e

plans of basi n development a r e shown on f igures 3 and 5. The flood

damage reduction a t t r i b u t a b l e t o the a.l . le~'native plans is a l s o shown

on these f igures . For the a l t e r n a t i v e plan providing f o r channel

improvements on a l l 10 streams i n the Tibbee River bas in , t h e increase

i n the peak flow r a t e of the pa t t e rn f lood (f lood 6 on f igure 5)

Page 16: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

a t r i v e r mi1.e 17.7 on t h e Tibbee River would be 35 percent. However,

because of changes i n the stage-d ischarge r e l a t i o n , f lood damage

reduction i n t h e planning reach would decrease 62 percent. Shown on

f igure 6 i s a comparison o f stage-frequency r e l a t i o n s a t t h i s

loca t ion f o r e x i s t i n g conditions, channel improvements on a l l 10

streams, and channel. improvements on Tibbee River only. The d i f ference

between the two r e l a t i o n s f o r improved condit ions i s due t o the peaking

e f f e c t catused by upstream channel improvements.

The e f f e c t s of vari.ous upstream a l t e r n a t i v e plans of bas in develop-

ment on the runoff c h a r a c t e r i s t i c s of t iming and magnitude o f peak flow

r a t e a r e i l l u s t r a t e d by t h e p a t t e r n f lood hydrographs shown on f i g u r e s

2 and 4 and the f low-probabil i ty da ta tabula ted on f i g u r e s 3 and 5.

The r e s u l t s of t h e inves t iga t ion a t a l l index s t a t i o n locat ions show t h e

following general t r ends on increases i n peak flow rates from upstream

channel improvements:

(1) Peak fl.ow r a t e s increase a s t h e percentage of stream length

improved inc reases , a s would be expected.

(2) For given length of stream t o be improved, peak flow rates

increase a s t h e degree o f p ro tec t ion (deslgn capaci ty of improved

channel) increases . This e f f e c t is I l l u s t r a t e d by t h e pa t t e rn f lood

hydrographs shown on f i g u r e 2 f o r e x i s t i n g condit ions and four a l t e r n a t i v e

plans .

(3) For given improved condit ions, t h e increase i n peak flow rates

decreases percentagewise with increases i n f lood magnitude.

12

Page 17: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

CONCLUSTORS

The most important concept of t h e inves t iga t ion m s t h e

determination o f the runoff peaking e f f e c t of channel improvement

works based on changes i n the storage-outflow r e l a t i o n of t h e f lood

p l a i n and streams. Another important rand unique concept was t h e

computation of syn the t i c f lood hydrographs at nmerous l .ocations a s

multip1.e~ of p a t t e r n f loods derived from one s i n g l e representative

syn the t i c pa t t e rn s t o m f o r a stream system.

Upstream channel improvement works fo r f lood control would tend t o

increase t h e magnitude of peak flow r a t e s now experienced on t h e Tibbee

River main stem. !hey would a l s o tend t o increase t h e average annual

flood damages on the main stem unless it was enlarged t o accommodate t h e

increased discharges. The magnitude of these e f f e c t s was assessed with a

reasonable mount of computation using a s implif ied hydrologic-economic

simulat ion model of t h e basin, along with c e r t a i n necessary assumptions

and genera l iza t ions .

The procedure described here in f o r the evaluat ion ?f flood con5rol

channels i n r u r a l a reas could a l s o be appl ied t o the study of urban flood

problems. The genera l iza t ions would, of course, he t a i l o r e d t o the

s p e c i f i c a rea of s tudy, but the methodology and eomputalional procedure

would be the sme. Future s t u d i e s should inves t iga te the p o s s i b i l i t y of

adding t o the model an optimizat ion rout ine t o provide f o r t h e s e l e c t i o n

of p ro jec t s involving a combination of two o r more s t r u c t u r a l measures

(denteartion s t r u c t u r e s together with levees or cha.lnels, e t c . ) which a r e

t o achieve a given objec t ive (protec t ion aga ins t a spec i f i ed f lood) .

13

Page 18: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Many persons i n t h e Mobile D i s t r i c t Corps of Engineers o f f i c e

have been involved i n t h i s study. Mr. Leo R. Beard, Direc tor of

The Hydrologic Engineering Center, who developed the simulat ion

model, described here in , has given h i s support and suggestions f o r

i t s use i n t h i s study. Mr. Herbert W. Hereth and Mrs. Marilyn Hulst

of the HEC s t a f f , and M r . Lewis G. Hulman, formerly o f the HEC staff

and now of t h e Atomic Energy Commission, furnished valuable

a s s i s t ance .

Page 19: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

REFERENCES

1. The Hydrologic Engineering Center, General ized Computer Program, "HEC-1 Flood Wydrograph Package," Corps of Engineers, October 1970.

2. Clark, C . O . , 9qStorage and t h e Unit Hydrograph," Trans. ASCE, 1945.

Page 20: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

$9 miles

TPBBEE RIVER 3ASlX (1,121 sq. m i ) ..--

FIGURE 1

Page 21: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary
Page 22: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

gamz: %$tern ~ ~ o o d ie ~ ~ o o d 6) A L ~ " W ~ T ~ =RAN

- - E X P S T m C O m n Z O N S - . -- Clear md Q m g

-- -

_- _EL QQQ DAflAGE 5 --!?PUT FLOOD O A ~ G E S FOR S ~ A T I O F J NO. FkON PRO8 .-.- ~&--- ~-I=-sv~--. . PRO6 - - - S UfQ .

- 1 2272. .go4 -00 Z 2625. 1 .270 2 _ 3 ~ 1 0 , 10270 .01

4.26 3 3761. 18067---- ----- 3 4153. 1 .067 I . 45 4 5146. 6827 4.77 4 5 5 6 6 , .82'7 3. 17 -.-.-- - -- - - 5 . 6861, _ - 2 s A-QL S 7292. - 4 6 5 2.72 6 9608. .338 3924 S l , .... l - - -__&Z--. 7 _ 1394.7. -- .16Z .- --- 2.09 - 7 14114. .I62 I .8%. 8 1 9 5 5 6 . . 8 6 l l . O Z - . @ 19621. _ _ - .Obi . 9.1

.--.--.- % --.-. 22.Ia25 5- - - Z Q Z ~ -----..--...--- A, 9 27266 . .029 * 46

h. ------ - DAMAGE REDUCTION 8.89

FLOOD D A W G E S f OR STAT18~ - -- -- - -- NO, FLOd PRO8 $i uN-

A m 25 Foot CBPamel

- - - -- - - - - - - - - - - - . - FL.000 DAMAGES FOR STATIOW

__iYQ3LELe)w P R O L X Y ! ! 1 24-34. *804 *60

_,_Z_-- 3g%s* 1 * 270 -----dm-- 5432. 1.067 * OO

- 1229 Q 27 -- .a0 5 8822 . .465 0 0 0

- -- - - - - - -- - - - .- .- -- - -- - - - -- - A v G ANN DMC _ - . 2, as- _ PVG AMM DDMG 1-78

-. -- - 19.61 - D A M E REQ-UCTXQM ----.-.-- ---- . DAMAGE E D - U C f f PM ?o.si

FLOOD DAMAGES FOR ~7"@Tf&?&-- - -- No. FLOW P R O 6 $019

--.L ZBL._ -,B&- ,ao 2 e 1,270 * 00 3 -.-. ------ . QO L - ~ ~ Q Q ? --.---

4 ,827 - 0 0 5 9705, *A@!! 00-._ CATATJIPA K 6 12456. .330 . D O R.M. 6.36 7 15738, @ \ 6 i ? *21 B 2 0 9 8 6 - sOBl *38

. . * 33 --

AVG ANN DUG - *7+--=_

Page 23: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

AND DETENTION S

TIBBEE RIVER R.M. 17.70

D.A. = 928 Sq. Mi.

Page 24: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

FLOW-PR(?XA 9SI'T~ITY-r)~WGE RELATTONS 'III.BBEE RTVER R.M. 17.70

EXISTING CONIITTIONS DEZ'ENTION STRUCTURES

Feuoo DAMAGES F O R STATION NO. FLOW P R O 0 S UH I 6449 3.269 I6aRIS 2 9712 1 ,237 2 0 9 9 1 3 1 4 6 6 3 ,896 23.27 4 2 0 5 5 4 6645 22e87 5 28948 0455 219 73 6 42723 9304 18.43 7 62043 0134 9 9 7 1 8 90665 ,048 4939 9 133410 , 022 2e56

AVG ANN DYG 140 9 7 6

FLOOD DAMAGES FCIR S T A T I O N NO. FLOW P R ~ H SUM P 5786 3,269 IL'3ol.3 2 8802 1 9 2 3 7 1 8 e 4 8 3 12989 ,896 2 0 e 9 2 4-- 11963 .a645 20 s 3.3, 5 24925 0455 P9e 3 9 6 35973 9304 16. 72 7 52'740 ,134 8 9 93 8 7 6 5 7 2 ,048 3.94 9 PI3200 9022 2 - 2 9

BVG ANN DYG 123e90

DAMAGE REDUCTION 16987

WOTE: Pattern Fl.ood is Flood 6

CHANNEL IMPROVEr.IENTS

FLOOD DAMAGES FOR NO9 FLOW P R O 0 P 1 5 0 2 9 3,269 2 2 0 4 4 8 1 ,233 3 2 7 2 2 1 .896 4 34666 ,646 5 44442 9455 6 5 7 6 6 6 9304 7 7 7 0 6 2 .134 8 1 0 6 1 8 9 e048 9 149526 9022

STATInN SUM

0 9

1 9 5 3 5921

1 1 - 6 5 120 40 11 *39

6.66 3.34 2 9 06

AVG ANN OYG 5 4 e 2 3 .,

CHANNEL IMPROVEMENTS A M ) DETENTION STRUCTURES

FLOOD DAMAGES FOR NO, FLOW PRO9

1 13767 3,269 2 P S O 4 6 f 923 7 3 25614 ,896 4 32242 ,646 5 40671 9455 6 52450 a304 I 8 8 2 7 4 ah34 8 9 2 3 4 7 a048 9 1 2 9 2 7 3 ,022

STATION SUM

0 9

965 3 e 4 4 8,99

PfeOO p0a25

5993 2- 88 1080

A V G ANN DYG 44.93

DAMAGE HEOUCTPON 86e54 DAMAGE REDUCTION 9SaR3

Page 25: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary
Page 26: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary
Page 27: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Technical Paper Series TP-1 Use of Interrelated Records to Simulate Streamflow TP-2 Optimization Techniques for Hydrologic

Engineering TP-3 Methods of Determination of Safe Yield and

Compensation Water from Storage Reservoirs TP-4 Functional Evaluation of a Water Resources System TP-5 Streamflow Synthesis for Ungaged Rivers TP-6 Simulation of Daily Streamflow TP-7 Pilot Study for Storage Requirements for Low Flow

Augmentation TP-8 Worth of Streamflow Data for Project Design - A

Pilot Study TP-9 Economic Evaluation of Reservoir System

Accomplishments TP-10 Hydrologic Simulation in Water-Yield Analysis TP-11 Survey of Programs for Water Surface Profiles TP-12 Hypothetical Flood Computation for a Stream

System TP-13 Maximum Utilization of Scarce Data in Hydrologic

Design TP-14 Techniques for Evaluating Long-Tem Reservoir

Yields TP-15 Hydrostatistics - Principles of Application TP-16 A Hydrologic Water Resource System Modeling

Techniques TP-17 Hydrologic Engineering Techniques for Regional

Water Resources Planning TP-18 Estimating Monthly Streamflows Within a Region TP-19 Suspended Sediment Discharge in Streams TP-20 Computer Determination of Flow Through Bridges TP-21 An Approach to Reservoir Temperature Analysis TP-22 A Finite Difference Methods of Analyzing Liquid

Flow in Variably Saturated Porous Media TP-23 Uses of Simulation in River Basin Planning TP-24 Hydroelectric Power Analysis in Reservoir Systems TP-25 Status of Water Resource System Analysis TP-26 System Relationships for Panama Canal Water

Supply TP-27 System Analysis of the Panama Canal Water

Supply TP-28 Digital Simulation of an Existing Water Resources

System TP-29 Computer Application in Continuing Education TP-30 Drought Severity and Water Supply Dependability TP-31 Development of System Operation Rules for an

Existing System by Simulation TP-32 Alternative Approaches to Water Resources System

Simulation TP-33 System Simulation of Integrated Use of

Hydroelectric and Thermal Power Generation TP-34 Optimizing flood Control Allocation for a

Multipurpose Reservoir TP-35 Computer Models for Rainfall-Runoff and River

Hydraulic Analysis TP-36 Evaluation of Drought Effects at Lake Atitlan TP-37 Downstream Effects of the Levee Overtopping at

Wilkes-Barre, PA, During Tropical Storm Agnes TP-38 Water Quality Evaluation of Aquatic Systems

TP-39 A Method for Analyzing Effects of Dam Failures in Design Studies

TP-40 Storm Drainage and Urban Region Flood Control Planning

TP-41 HEC-5C, A Simulation Model for System Formulation and Evaluation

TP-42 Optimal Sizing of Urban Flood Control Systems TP-43 Hydrologic and Economic Simulation of Flood

Control Aspects of Water Resources Systems TP-44 Sizing Flood Control Reservoir Systems by System

Analysis TP-45 Techniques for Real-Time Operation of Flood

Control Reservoirs in the Merrimack River Basin TP-46 Spatial Data Analysis of Nonstructural Measures TP-47 Comprehensive Flood Plain Studies Using Spatial

Data Management Techniques TP-48 Direct Runoff Hydrograph Parameters Versus

Urbanization TP-49 Experience of HEC in Disseminating Information

on Hydrological Models TP-50 Effects of Dam Removal: An Approach to

Sedimentation TP-51 Design of Flood Control Improvements by Systems

Analysis: A Case Study TP-52 Potential Use of Digital Computer Ground Water

Models TP-53 Development of Generalized Free Surface Flow

Models Using Finite Element Techniques TP-54 Adjustment of Peak Discharge Rates for

Urbanization TP-55 The Development and Servicing of Spatial Data

Management Techniques in the Corps of Engineers TP-56 Experiences of the Hydrologic Engineering Center

in Maintaining Widely Used Hydrologic and Water Resource Computer Models

TP-57 Flood Damage Assessments Using Spatial Data Management Techniques

TP-58 A Model for Evaluating Runoff-Quality in Metropolitan Master Planning

TP-59 Testing of Several Runoff Models on an Urban Watershed

TP-60 Operational Simulation of a Reservoir System with Pumped Storage

TP-61 Technical Factors in Small Hydropower Planning TP-62 Flood Hydrograph and Peak Flow Frequency

Analysis TP-63 HEC Contribution to Reservoir System Operation TP-64 Determining Peak-Discharge Frequencies in an

Urbanizing Watershed: A Case Study TP-65 Feasibility Analysis in Small Hydropower Planning TP-66 Reservoir Storage Determination by Computer

Simulation of Flood Control and Conservation Systems

TP-67 Hydrologic Land Use Classification Using LANDSAT

TP-68 Interactive Nonstructural Flood-Control Planning TP-69 Critical Water Surface by Minimum Specific

Energy Using the Parabolic Method

Page 28: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

TP-70 Corps of Engineers Experience with Automatic Calibration of a Precipitation-Runoff Model

TP-71 Determination of Land Use from Satellite Imagery for Input to Hydrologic Models

TP-72 Application of the Finite Element Method to Vertically Stratified Hydrodynamic Flow and Water Quality

TP-73 Flood Mitigation Planning Using HEC-SAM TP-74 Hydrographs by Single Linear Reservoir Model TP-75 HEC Activities in Reservoir Analysis TP-76 Institutional Support of Water Resource Models TP-77 Investigation of Soil Conservation Service Urban

Hydrology Techniques TP-78 Potential for Increasing the Output of Existing

Hydroelectric Plants TP-79 Potential Energy and Capacity Gains from Flood

Control Storage Reallocation at Existing U.S. Hydropower Reservoirs

TP-80 Use of Non-Sequential Techniques in the Analysis of Power Potential at Storage Projects

TP-81 Data Management Systems of Water Resources Planning

TP-82 The New HEC-1 Flood Hydrograph Package TP-83 River and Reservoir Systems Water Quality

Modeling Capability TP-84 Generalized Real-Time Flood Control System

Model TP-85 Operation Policy Analysis: Sam Rayburn

Reservoir TP-86 Training the Practitioner: The Hydrologic

Engineering Center Program TP-87 Documentation Needs for Water Resources Models TP-88 Reservoir System Regulation for Water Quality

Control TP-89 A Software System to Aid in Making Real-Time

Water Control Decisions TP-90 Calibration, Verification and Application of a Two-

Dimensional Flow Model TP-91 HEC Software Development and Support TP-92 Hydrologic Engineering Center Planning Models TP-93 Flood Routing Through a Flat, Complex Flood

Plain Using a One-Dimensional Unsteady Flow Computer Program

TP-94 Dredged-Material Disposal Management Model TP-95 Infiltration and Soil Moisture Redistribution in

HEC-1 TP-96 The Hydrologic Engineering Center Experience in

Nonstructural Planning TP-97 Prediction of the Effects of a Flood Control Project

on a Meandering Stream TP-98 Evolution in Computer Programs Causes Evolution

in Training Needs: The Hydrologic Engineering Center Experience

TP-99 Reservoir System Analysis for Water Quality TP-100 Probable Maximum Flood Estimation - Eastern

United States TP-101 Use of Computer Program HEC-5 for Water Supply

Analysis TP-102 Role of Calibration in the Application of HEC-6 TP-103 Engineering and Economic Considerations in

Formulating TP-104 Modeling Water Resources Systems for Water

Quality

TP-105 Use of a Two-Dimensional Flow Model to Quantify Aquatic Habitat

TP-106 Flood-Runoff Forecasting with HEC-1F TP-107 Dredged-Material Disposal System Capacity

Expansion TP-108 Role of Small Computers in Two-Dimensional

Flow Modeling TP-109 One-Dimensional Model for Mud Flows TP-110 Subdivision Froude Number TP-111 HEC-5Q: System Water Quality Modeling TP-112 New Developments in HEC Programs for Flood

Control TP-113 Modeling and Managing Water Resource Systems

for Water Quality TP-114 Accuracy of Computer Water Surface Profiles -

Executive Summary TP-115 Application of Spatial-Data Management

Techniques in Corps Planning TP-116 The HEC's Activities in Watershed Modeling TP-117 HEC-1 and HEC-2 Applications on the

Microcomputer TP-118 Real-Time Snow Simulation Model for the

Monongahela River Basin TP-119 Multi-Purpose, Multi-Reservoir Simulation on a PC TP-120 Technology Transfer of Corps' Hydrologic Models TP-121 Development, Calibration and Application of

Runoff Forecasting Models for the Allegheny River Basin

TP-122 The Estimation of Rainfall for Flood Forecasting Using Radar and Rain Gage Data

TP-123 Developing and Managing a Comprehensive Reservoir Analysis Model

TP-124 Review of U.S. Army corps of Engineering Involvement With Alluvial Fan Flooding Problems

TP-125 An Integrated Software Package for Flood Damage Analysis

TP-126 The Value and Depreciation of Existing Facilities: The Case of Reservoirs

TP-127 Floodplain-Management Plan Enumeration TP-128 Two-Dimensional Floodplain Modeling TP-129 Status and New Capabilities of Computer Program

HEC-6: "Scour and Deposition in Rivers and Reservoirs"

TP-130 Estimating Sediment Delivery and Yield on Alluvial Fans

TP-131 Hydrologic Aspects of Flood Warning - Preparedness Programs

TP-132 Twenty-five Years of Developing, Distributing, and Supporting Hydrologic Engineering Computer Programs

TP-133 Predicting Deposition Patterns in Small Basins TP-134 Annual Extreme Lake Elevations by Total

Probability Theorem TP-135 A Muskingum-Cunge Channel Flow Routing

Method for Drainage Networks TP-136 Prescriptive Reservoir System Analysis Model -

Missouri River System Application TP-137 A Generalized Simulation Model for Reservoir

System Analysis TP-138 The HEC NexGen Software Development Project TP-139 Issues for Applications Developers TP-140 HEC-2 Water Surface Profiles Program TP-141 HEC Models for Urban Hydrologic Analysis

Page 29: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

TP-142 Systems Analysis Applications at the Hydrologic Engineering Center

TP-143 Runoff Prediction Uncertainty for Ungauged Agricultural Watersheds

TP-144 Review of GIS Applications in Hydrologic Modeling

TP-145 Application of Rainfall-Runoff Simulation for Flood Forecasting

TP-146 Application of the HEC Prescriptive Reservoir Model in the Columbia River Systems

TP-147 HEC River Analysis System (HEC-RAS) TP-148 HEC-6: Reservoir Sediment Control Applications TP-149 The Hydrologic Modeling System (HEC-HMS):

Design and Development Issues TP-150 The HEC Hydrologic Modeling System TP-151 Bridge Hydraulic Analysis with HEC-RAS TP-152 Use of Land Surface Erosion Techniques with

Stream Channel Sediment Models

TP-153 Risk-Based Analysis for Corps Flood Project Studies - A Status Report

TP-154 Modeling Water-Resource Systems for Water Quality Management

TP-155 Runoff simulation Using Radar Rainfall Data TP-156 Status of HEC Next Generation Software

Development TP-157 Unsteady Flow Model for Forecasting Missouri and

Mississippi Rivers TP-158 Corps Water Management System (CWMS) TP-159 Some History and Hydrology of the Panama Canal TP-160 Application of Risk-Based Analysis to Planning

Reservoir and Levee Flood Damage Reduction Systems

TP-161 Corps Water Management System - Capabilities and Implementation Status

Page 30: Design of Flood Control Improvements by System Analysis: A ... · The purpose of the project is to achieve flood control and drainage on 466 miles of flood plain along 22 tributary

Recommended