+ All Categories
Home > Documents > Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team...

Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team...

Date post: 30-Dec-2015
Category:
Upload: jody-day
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
23
Design Partition, Design Partition, Project Plan, Task Project Plan, Task Assignments and Assignments and Conceptual Designs Conceptual Designs September 13, 2006 September 13, 2006 Team Moondogs Team Moondogs Chris Culver Chris Culver Rahul Kirtikar Rahul Kirtikar Elias Krauklis Elias Krauklis Christopher Sampson Christopher Sampson Michael Widerquest Michael Widerquest
Transcript
Page 1: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Design Partition, Design Partition, Project Plan, Task Project Plan, Task Assignments and Assignments and

Conceptual Conceptual DesignsDesignsSeptember 13, 2006September 13, 2006

Team MoondogsTeam MoondogsChris Culver Chris Culver Rahul KirtikarRahul KirtikarElias KrauklisElias KrauklisChristopher SampsonChristopher SampsonMichael WiderquestMichael Widerquest

Page 2: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Design Partition GoalDesign Partition Goal

The goal of this project is to create a The goal of this project is to create a canister which allows a person to canister which allows a person to easily and inexpensively compact easily and inexpensively compact trash. trash.

The system shall be manual and not The system shall be manual and not require permanent installation. require permanent installation.

SubsystemsSubsystems Trash Canister, Container, Enclosure, Trash Canister, Container, Enclosure,

and Compactor and Compactor

Page 3: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

SubsystemsSubsystems Trash CanisterTrash Canister

Responsible for sustaining the unit that holds the Responsible for sustaining the unit that holds the trashtrash

Square, circular, and rectangular canistersSquare, circular, and rectangular canisters Trash ContainerTrash Container

The actual unit that holds the trashThe actual unit that holds the trash Trash bags, separate canisters, and plastic liningsTrash bags, separate canisters, and plastic linings

Trash EnclosureTrash Enclosure Encloses the trash into the trash canister from the Encloses the trash into the trash canister from the

visual publicvisual public Hinged lids, removable lids, pull-out systems, and Hinged lids, removable lids, pull-out systems, and

flapsflaps

Page 4: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

SubsystemsSubsystems

Trash CompactorTrash Compactor Two major parts of this assembly must include Two major parts of this assembly must include

a compaction plate and a device that moves a compaction plate and a device that moves the compaction plate into the trash the compaction plate into the trash

A circular or rectangular plate for the A circular or rectangular plate for the compaction surface, as well as a hydraulic lift, compaction surface, as well as a hydraulic lift, a ratchet jack system, a crank system, a a ratchet jack system, a crank system, a scissor jack, and an auger scissor jack, and an auger

Movements can come from the top to bottom Movements can come from the top to bottom of the canister, from the bottom to top of the of the canister, from the bottom to top of the canister, or from the walls of the canister canister, or from the walls of the canister

Page 5: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Task AssignmentTask Assignment Chris SampsonChris Sampson

Team leaderTeam leader Lead weekly reportsLead weekly reports Coordinate and mediate Coordinate and mediate

group meetingsgroup meetings

Rahul KirtikarRahul Kirtikar Website managerWebsite manager Maintenance of Maintenance of

deliverablesdeliverables CADCAD

Michael WiderquistMichael Widerquist Construction managerConstruction manager Purchasing and Purchasing and

fabrication of design partsfabrication of design parts Part drawingsPart drawings

Chris CulverChris Culver Construction managerConstruction manager Purchasing and Purchasing and

fabrication of design partsfabrication of design parts Prototype developmentPrototype development

Elias KrauklisElias Krauklis Patent researchPatent research Engineering analysisEngineering analysis Material acquisitionMaterial acquisition

Page 6: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16December

23 28 6 13 18 25 2 9 16 23 30 6 13 20 27 6Deliverable:Team Selection AllProject Bids AllProject Selection AllProblem Statement CS, RKWebsite MaintenanceConceptual Design AllDesign Parition CSProject Plan CC, MWTask Assignments RKPatent/Product Search EKSelection Analysis AllMidterm Presentation AllPost Midterm Review AllLayout DrawingsRecess AllEngineering Analysis CS, EKPart DrawingsPrototype Review/ConstructionFinal ReportFinal PresentationPosterboard DisplayFinal Term ChecklistPeer Evaluations All

CC- Chris CulverRK- Rahul KirtikarEK- Eli KrauklisCS- Chris SampsonMW- Mike Widerquist

CC, MW

CC, MW, RK

November

Project Plan

RKCC, MW

All

CS, EK

RK

August September October

All

Project PlanProject Plan

Page 7: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Foot Pedal DesignFoot Pedal Design

Page 8: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Foot Pedal DesignFoot Pedal Design

First, compacts the First, compacts the trash by placing the trash by placing the lid on the containerlid on the container

Then, a foot pump Then, a foot pump motion lifts an motion lifts an inner trash inner trash container straight container straight up onto a up onto a compacting plate compacting plate stabilized by ones stabilized by ones handhand

Page 9: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

Maximizes a person ability to apply force by using the leg to lift the inner container +

Applies an additional force from the person placing the lid on the container +

Eliminates the need for trash bags +

Disadvantages  

Can contain only a moderate level of trashCan contain only a moderate level of trash -The inner container needs to be continually cleaned to keep

sanitary -

Circular design could pose problems for rectangular trash articles -

Interesting

A simple design that should have a large compression ratio

Page 10: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Grinder DesignGrinder Design

Page 11: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

Simple and reliable build design +

Easy intuitive of operation for user +

Large crank handle allows for increased grinding force +

Concealed trash receptacle is sanitary.

Disadvantages  

Possibility of trash backup -

Not all types/sizes of trash could fit -

Design may not produce most efficient compacting ratio. -

Interesting

The grinder wheels have the ability to shred and destroy trash that a normal compactor may not be able to accomplish.

Page 12: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Side Trash CompactorSide Trash Compactor

Page 13: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Side Trash CompactorSide Trash Compactor The trash lid has to be The trash lid has to be

removed to lift the side panel removed to lift the side panel out from in front of the out from in front of the compaction plate compaction plate

Once the side panel is Once the side panel is removed the lid can be removed the lid can be replaced and the compaction replaced and the compaction can begin can begin

The compaction in this The compaction in this design has the ability to be design has the ability to be very strong since a foot very strong since a foot mechanism or a long hand mechanism or a long hand crank can be placed one foot crank can be placed one foot off the ground off the ground

The side panel may not be The side panel may not be needed if a trash bag could needed if a trash bag could be used in this design be used in this design

Page 14: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

This design can use many different mechanisms to compact it from from the sidethe side +

The foot or a long hand crank can be used for more strength since the center of compaction is about a foot off the ground +

Could be used with trash bags or without trash bags potentially +

Disadvantages  

Removal of side panel could cause potential leakages and problems Removal of side panel could cause potential leakages and problems (if a trash bag is able to be used then the side panel would not (if a trash bag is able to be used then the side panel would not be needed)be needed) -

A outer container would be needed to house the compaction A outer container would be needed to house the compaction mechanism on the sidemechanism on the side -

Would compact the trash to one side causing the user to have to place the trash on a certain side of the trash can -

Interesting

A unique compaction design from the side which could maximize the users strength since the center of compaction is about a foot off of the ground

Page 15: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Auger DesignAuger Design Auger with grooves Auger with grooves

reversed to cause reversed to cause compaction instead of compaction instead of extrusionextrusion

Trash is placed into Trash is placed into canister through lid canister through lid openingopening

With an adequate amount With an adequate amount of trash the auger is rotated of trash the auger is rotated which causes compactionwhich causes compaction

Spring Loaded plate is then Spring Loaded plate is then released to allow waste to released to allow waste to fall into canisterfall into canister

Auger Crank

Lid

Canister

Release Point

Page 16: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

No need to remove lid to insert trash or operate compacting mechanism

+

Simple cranking mechanism in a fixed position +

Auger will supply adequate amount of compaction +

Disadvantages  

Difficult to have pin release support force of compactionDifficult to have pin release support force of compaction -

Container may have to be much wider to allow adequate compaction

-

Circular design could pose problems for rectangular trash articles

-

Interesting

The crank is fixed in one place and does not ascend or descend

Page 17: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Hydraulic Lift and Hydraulic Lift and Compaction DesignCompaction Design

Hydraulic bottle jack Hydraulic bottle jack attached to base of attached to base of outer canouter can

Easily operated by a foot Easily operated by a foot pedalpedal

Capable of applying Capable of applying hundreds of pounds of hundreds of pounds of forceforce

Upper lid is retracted Upper lid is retracted into the trash can to into the trash can to compress the trash as a compress the trash as a mechanism of the mechanism of the hydraulic jack.hydraulic jack. Hydraulic Lift and

Compaction Design

Page 18: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Hydraulic Lift and Hydraulic Lift and Compaction DesignCompaction Design

Side view of open compactor

Open compactor view

Page 19: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

Capable of applying force from both the top and bottom +

Foot pedal is easy to handle and operate without being cumbersome

+

Bottle jacks are easy to operate and require almost no maintenance

+

Disadvantages  

Mechanisms are more advanced to incorporate the use of Mechanisms are more advanced to incorporate the use of the upper lidthe upper lid

-

Range of motion is still limited by aesthetics of the upper compaction arm

-

Inside of lid could become messy after compaction -

Interesting

The lid can actually serve as a compacting tool by a mechanism that translates the force provided by the hydraulic jack.

Page 20: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Hydraulic Bottle Jack Hydraulic Bottle Jack DesignDesign

Inverted hydraulic Bottle Inverted hydraulic Bottle Jack attached to inside of Jack attached to inside of lidlid

Easy to operate by pumping Easy to operate by pumping the lever to extend the jack the lever to extend the jack armarm

Capable of applying several Capable of applying several thousand pounds of forcethousand pounds of force

Easy to retract the arm by a Easy to retract the arm by a turn of the lever to release turn of the lever to release hydraulic pressurehydraulic pressure

Side removal of trash bagsSide removal of trash bags

Retracted Bottle Jack

Page 21: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Hydraulic Bottle Jack Hydraulic Bottle Jack DesignDesign

Extended Bottle JackBottle Jack Close-Up

Page 22: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

Advantages / Advantages / DisadvantagesDisadvantages

Advantages  

Capable of applying 1-½ tons of force +

Lever is easy to handle and operate without being cumbersome

+

Bottle jacks are easy to operate and require almost no maintenance

+

Disadvantages  

Bottle jack will be heavy (6lbs) and will have to be secured tightly

-

Range of motion is dependent on size of the jack (so a greater range of motion requires a larger jack)

-

Trash would have to be inserted from the side as opposed to the top eliminating the option of throwing away oversized objects

-

Interesting

Amount of force that can be applied is the greatest out of current concepts, but sides of container would have to be able to withstand such a great amount of pressure

Page 23: Design Partition, Project Plan, Task Assignments and Conceptual Designs September 13, 2006 Team Moondogs Chris Culver Rahul Kirtikar Elias Krauklis Christopher.

EndEnd


Recommended