Design Progress

Design Progress

Design Progress

Design ProgressImproved Bus Loading for Safety

Design Progress

Design Progress

Design Progress

Impact of Revisions, Cost & Design to Option D

Original budget approved for Pool Option D - 35,000 SF

• August 12, 2014 – Base Budget with 2% financing: $15,509,897

Adjustments to Date in Schematic Design:

• Additional square foot for Team Room - 700 SF $200,000

• Elevator to Mezzanine $96,000

• Mezzanine storage space – 300 SF $72,000

• Additional seating, 298 to 366, an increase of 68 seats $16,000

• Bus loop and parking $TBD

Current Budget $15,893,897

These adjustments, if approved by the Board, are within the allowances previously submitted for

• Site Improvements $500,000

• High Range Allowance $1,000,000

Summary & ConclusionOctober 13, 2014

1. Recommend approval of Natatorium addition designwith team room, additional seating, and bus drop off $ 15,893,897

2. Authorize proceeding with Design Development of pool with the proposed changes.

3. Authorize proceeding with Geotechnical Investigation for $ 35,000design and construction parameters.

TARGET COMPLETION DATE: September 2017


Recommended