+ All Categories
Home > Documents > DESTRUCTIVE EXAMINATION METHODS FOR THE …

DESTRUCTIVE EXAMINATION METHODS FOR THE …

Date post: 16-Oct-2021
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
43
Slide 1 7015.ppt DESTRUCTIVE EXAMINATION METHODS FOR THE INVESTIGATION OF NORTH ANNA HEAD PENETRATION #54 Presentation to NRC Research Rockville, MD January 18, 2006 Gutti Rao Westinghouse Electric Company Work Funded by Electric Power Research Institute (EPRI)
Transcript
Page 1: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 1

7015.ppt

DESTRUCTIVE EXAMINATION METHODS FOR THE INVESTIGATION OF NORTH ANNA

HEAD PENETRATION #54

Presentation to NRC Research

Rockville, MDJanuary 18, 2006

Gutti RaoWestinghouse Electric Company

Work Funded by Electric Power Research Institute (EPRI)

Page 2: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 2

7015.ppt

Participants/Contributors

Westinghouse

Gutti Rao (Tech Lead)Joyce Conerman

Chris DeFlitchWarren Junker

Al Vaia

EPRI

Al Ahluwalia (Project Manager)Francois Cattant (Consultant)

Noel Peat (Consultant)

Page 3: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 3

7015.ppt

ObjectivesDestructive Examination of Complete Alloy 600/82/182 Penetration/Weld from Service

Physical Characterization and Identification of Head PenetrationWeld Defects

Identify Interrelationship between Various Types (Axial, Circ or Other) of Defects

Characterization of Annulus Environment & Wastage

Identify Mechanistic Aspects of Formation and Root Cause of Cracking

(Leading to Correlation of Discovered Defects with Prior Reported NDE Indications)

Page 4: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 4

7015.ppt

Summary of TasksPreliminary NDEDevelopment of Sectioning Plan – Identification Preliminary SectioningAdditional NDEDetailed Sectioning and MacroetchDetailed NDE on Azimuthal SectionsMetallographyChemistryHardnessFractography Fabrication History ReviewReview of Results Assessments and Conclusions

Page 5: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 5

7015.ppt

Project Status

Workscope 95% Completed

Draft Report Initiated

Final Report Scheduled for April 1, 2006

Page 6: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 6

7015.ppt

Presentation Focus

The Current Presentation is Focused on Two Aspects of theDestructive Examination

Effective Utilization of Additional NDE Technologies

Development of Innovative Sectioning Plan and Sectioning Methods

– To Maximize Defect Characterization Capabilities– To Minimize Man-Rem Exposure

Page 7: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 7

7015.ppt

As-Received Condition of CRDM Nozzle 54

Page 8: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 8

7015.ppt

Vendor Inspection Data (Provided)

Page 9: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 9

7015.ppt

Vendor Inspection Data (Provided)

0

2

4

6

8

10

0 10 20 30 40 50 60 70 80 90 100

110

120

130

140

150

160

170

180

190

200

210

220

230

240

250

260

270

280

290

300

310

320

330

340

350

360

Degrees

Isolated ID Indications

Indications 1,2

Indication 5Indication 7

Indications 3,4

Weld Profile

Possible Wastage

Dis

tan

ce F

rom

Bo

tto

m (

in)

Piece CPiece B Piece APiece A

Proposed CutsCompleted Cuts Major Initial Cuts Replica Indications

Cut on either side of this defect

machinemachine

machine

machine

machine

machine

machine

machine

machine

machinepreviously machined

previously machined

EC DoneEC ECEC ECEC Done

Page 10: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 10

7015.ppt

3-D Model of Indications Developed by Westinghouse To Guide Sectioning

• Developed a 3-D Model of Penetration Indications• Compared Model to Physical Cut Out to Identify Best Sectioning Plan

0° 180°

270°

90°

Page 11: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 11

7015.ppt

NDE Assessments – For Sub-Surface/Surface Emergent Crack Identification

Microset (High Resolution) Replication

Eddy Current Testing

Florescent Dye Penetrant Testing

Ultrasonic Testing

Page 12: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 12

7015.ppt

Replication to Preserve Data from Wetted ID Face Weld

Page 13: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 13

7015.ppt

Wetted ID Weld Surface Replication

Allows Identification of Crack Emergence on J-Weld Wetted ID Face and Observation of Weld Bead Interactions

Page 14: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 14

7015.ppt

Specific J-Weld Indication via Replication

Replication Allowed Identification of Several Wetted Face Emergent Cracks – this one at 300° Location

Page 15: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 15

7015.ppt

Penetration ID Surface ReplicationID Replica Across

J-weld Region

Surface ScratchID Scratch

Page 16: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 16

7015.ppt

EC Pencil Probe Tracing of Weld Interface To Confirm Profile of Weld Interface (Establishes Removable Excess Carbon Steel)

Page 17: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 17

7015.ppt

Sectioning Layout to Remove Excess Carbon Steel (3 Inch Clearance from Weld)

3 in. minimum clearance from interface

Page 18: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 18

7015.ppt

Rough Cutting of NA Penetration 54

Band Saw was Used with Appropriate Capacity (Modified Jet, 7x12” Horizontal/Vertical Band Saw). Recommend Use of Larger Saw.

A 3/4 in Bimetal 5/8 in Variable Pitch Blade (Blade was Changed Frequently, Especially when Cutting Through Weldment). Speed, Feed and Pitch of Blade were Dependant on Horsepower of Drive Motor and Rigidity of Fixturing.

Page 19: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 19

7015.ppt

Removal of Excess Carbon Steel

Fixture Capable of Rotational, Elevation and Lateral Adjustment

Sample Holding Fixture Clamped to Saw Base to Assure Rigidity Between Sample and Saw Blade

Top of CRDM Penetration Clamped to Fixture and Aligned with Blade

Ratchet Cargo Straps were used to Maintain Position and Rigidity During Cut

Piece in Fixture for Removal of Excess Carbon Steel

Page 20: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 20

7015.ppt

Initial Sectioning Plan

As-Sectioned Pieces A, B & C

0° 180°68°

Indication Group 3,4

Indication Group 1,2

Cut (270°)

Weld Area

Possible Wastage in CS

270°

Cut (60°)

Cut (150°)

Pc A

Pc B

Pc C

Penetration Tube

Page 21: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 21

7015.ppt

Further Rough Cutting of NA Penetration 54

Major Sectioning Conducted to Obtain “Pie” Sections:

– Multiple vises used to align sample with blade.– Cargo straps and wooden spacers and/or machining “toe”

clamps were used if support was required. Thinner Slices Were Cut off of the Major Pie Sections to Isolate Areas of Interest

Additional Machining Done to Sliced Faces:

– Multiple tilt machine vises and/or “toe” clamps were usedto hold piece as it was being milled.

Page 22: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 22

7015.ppt

Sectioning Through Weld and Penetration

Large Plywood Base Plate was Used to Support Sample

Various Shape and Thickness Wooden Spacers were Used to Align Sample with Blade

Ratchet Cargo Straps were Used to Maintain Position and Rigidity During Cut

60° Cut

Page 23: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 23

7015.ppt

Sectioning Through Weld and Penetration

270 Degree Cut

Page 24: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 24

7015.ppt

Piece A

270° Face60° Face

Page 25: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 25

7015.ppt

Piece A

Cut is parallel to wet face minimum 1 in above top of weld + butter

Cut is 1 inch minimum from bottom of last j-weld pass

Cut is 1 inch minimum from butter and carbon steel interface

60° Face

270° Face

Page 26: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 26

7015.ppt

Piece B

NDE Indications from NDE performed at W

60° face150° face

135° picture (replica)

70° picture (replica)

90° picture (replica)

Page 27: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 27

7015.ppt

Cut is 1 inch minimum from butter and carbon steel interface

Cut is 1 inch minimum from bottom of last j-weld pass

Cut is 1 inch minimum from end of j-weld

View of cuts from top

Ridge is an artifact of the cutting process

Page 28: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 28

7015.ppt

Piece C

150° Face

270° Face

Page 29: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 29

7015.ppt

Piece C

150° Face

270° Face

Cut is parallel to wet face minimum 1 in above top of weld + butter

Cut is 1 inch minimum from bottom of last j-weld pass

Cut is 1 inch minimum from butter and carbon steel interface

Cut is 1 inch minimum from butter and carbon steel interface

Wet Face

Wet Face

Page 30: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 30

7015.ppt

Subsequent Sectioning – Thinner Slices for More Detailed Examination

Based on Eddy Current/Replication Results and Vendor Inspection Results

Objective to Isolate Areas of Interest

Plan is To– Section– Additional NDE on Faces– Prepare Locations for Examination– Detailed Investigation of Defects

Same Slicing Process as “Rough Cutting”

Page 31: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 31

7015.ppt

Detailed Sectioning Plan

0

2

4

6

8

10

0 10 20 30 40 50 60 70 80 90 100

110

120

130

140

150

160

170

180

190

200

210

220

230

240

250

260

270

280

290

300

310

320

330

340

350

360

Degrees

Isolated ID Indications

Indications 1,2

Indication 5Indication 7

Indications 3,4

Weld Profile

Possible Wastage

Dis

tan

ce F

rom

Bo

tto

m (

in)

Piece CPiece B Piece APiece A

Proposed CutsCompleted Cuts Major Initial Cuts Replica Indications

Cut on either side of this defect

machinemachine

machine

machine

machine

machine

machine

machine

machine

machinepreviously machined

previously machined

EC DoneEC ECEC ECEC Done

Page 32: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 32

7015.ppt

Piece B1A

60° face

150° face

130°75°

machine

machine Already machined

Already machined

Page 33: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 33

7015.ppt

Piece A1A60° face

270° face

30°

0°330°

280°

machinemachine

machine

machine

ECEC

A1A1

A1A5

A1A4

A1A3

A1A2

Page 34: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 34

7015.ppt

Piece C1A

machine

machine

250°

190°165°

270° face

150° face

machine

EC

EC

C1A4

C1A3C1A2

C1A1

machine

Page 35: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 35

7015.ppt

Eddy Current Examination of Sectioned Faces

Use of + pt Eddy Current Tool to Examine Sectioned Faces

Attempt to Identify Defects/Indications Prior to Metallographic Preparation

Allows Identification of New Indications Missed by Original Section NDE

Allows Metallographic Examination to Focus on Specific Areas

Provide Continuing Observation and Tracking of Original NDE Indications through to Confirmatory Metallographic Observation

“Guides the Eye” to Abnormal Weld Microstructure Regions – Butter/Weld Interfaces – Internal Weld Defects

Page 36: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 36

7015.ppt

Example of Eddy Current and Subsequent Metallographic Examination of Sectioned Face

EC+ Butter/Weld

interface

Abnormal weld microstructure

Eddy Current Inspection Results for the 60 Deg. Face using the +Point Probe (Piece B1A5)Abnormal Weld Microstructure and Weld Butter Interface

Page 37: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 37

7015.ppt

Correlation of Features in Metallography and NDE “Images”

All Faces Examined (12 Azimuthal Sections)Allows Clarification of Defect Types from Different Views– + pt probe– Polished Section– Fluorescent Dye Penetrant– Etched Sections

Weld Butter Interface are Visible in Ground SectionsWeld Microstructure Visible in Several SectionsCracking Visible in Ground Sections – Clarified in Dye Penetrant ObservationsSee Observations on 0 Degree Section (Piece A1A3)

Page 38: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 38

7015.ppt

Comparison of Optical Metallography and Dye Penetrant Images

EC Indication

Butter/Weld interface

W/B interface + cracks

EC Indication

Defect looking like cracks with tiny

voids along it

Defect looking like branched cracks

Top of the annulus ends here EC Indication

Butter/Weld Interface

W/B interface +

cracksEC Indication

Defect looking like cracks with tiny voids

along it

Defect looking like branched

cracks

Top of the annulus

ends here

Page 39: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 39

7015.ppt

Comparison of Optical Metallography and Dye Penetrant Images

EC+ Butter/Weld interface

Abnormal weld microstructure

Series of cavities at the weld/base metal

interface

Major crack between 2 weld passes

Short lack of fusion at the end of the annulus

EC+ Butter/Weld interface

Abnormal weld microstructure

Series of cavities at the weld/base metal

interface

Major crack between 2 weld passes

Short lack of fusion at the end of the annulus

EC

Page 40: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 40

7015.ppt

Eddy Current Inspection Results for the 0 Deg. Face Using the +Point Probe (Piece A1A3)

EC Indication

Annulus Gap

W/B interface + cracks

EC Indication

Page 41: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 41

7015.ppt

Finding of NDE and Low Magnification Metallographic Observations of Sectioned Faces

Demarcation of Weld Butter Interfaces

Regions of Abnormal Weld Microstructures

– Regions of Weld Repair/OverlayCracks in Welds, Branched Cracks, Crack Networks

Void Alignment on Cracking/Series of Cavities

Lack of Fusion Regions (Including at the End of Annulus)

– Pursue Detailed Examination of Key Factors

Page 42: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 42

7015.ppt

Summary of Approach and Findings to Date

Removal of Excess Carbon Steel is Necessary and Time and Resource Consuming

Vendor NDE is a Good Starting Point but must be Supplimented by Lab. NDE and Replication

Replication was most Useful at Confirming Weld Defect Locations and Help Minimize Personnel Radiation Exposure

Replication was Helpful in Identifying Surface Cracks

Page 43: DESTRUCTIVE EXAMINATION METHODS FOR THE …

Slide 43

7015.ppt

Summary of Approach and Findings to Date (cont.)

3-D Model Aids Visualization of Defect Locations Facilitates Development of Sectioning Plan

Sectioning Procedures Employed Rigid Clamping and Simple Tooling Developed by Westinghouse Hot Cell Technicians

Use of NDE Methods on Sectioned Slices Provides an Innovative Way to Track Indications and to Properly Locate (Old and New) Defects


Recommended