+ All Categories
Home > Documents > Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW...

Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW...

Date post: 27-Aug-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
61
Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)Detailed Design Functional Design Specifications Rev 1A © 2018 Vista Automation Network LLC PROPRIETARY & CONFIDENTIAL Page 1 of 61 Document No.: VA/DP/PE/03/F10-4 Rev 2.0 Detailed Design Functional Specifications for Phase One & Phase Two Scada Solution for the National Command Centre For Palestinian Electricity Transmitting Authority (PETL) Submitted by: Vista Automation Network LLC Submitted To: CoolNet Broadband Solutions – Main Contractor Consultant: AECOM Client: Palestine Electricity Transmission Limited
Transcript
Page 1: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 1 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Detailed Design Functional Specifications

for

Phase One & Phase Two Scada Solution for the

National Command Centre For Palestinian

Electricity Transmitting Authority (PETL)

Submitted by: Vista Automation Network LLC

Submitted To: CoolNet Broadband Solutions – Main Contractor

Consultant: AECOM

Client: Palestine Electricity Transmission Limited

Page 2: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 2 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

REVISION HISTORY The information contained on all pages of this document is confidential and proprietary to Vista Automation Network LLC who is the sole owner of the

Intellectual Property of this Document and all attachments. This information is furnished in confidence to the parties involved in this project with the

understanding that it may not be reproduced or used by, in whole or in

part, for any purpose other than the evaluation of this document.

Rev. Date Prepared By Approved By Comments

0 17/7/2018 AS AH

0A 6/8/2018 AS AH

1 16/1/2019 AS AH For Approval, changes

highlighted in yellow colour

1A 20/1/2019 AS AH Final

Page 3: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 3 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

CONTENTS

1. INTRODUCTION.................................................................................................................................. 5

1.1. PURPOSE ................................................................................................................................................ 5

1.2. DEFINITIONS, ABBREVIATIONS AND ACRONYMS ........................................................ 5

2. SYSTEM ARCHITECTURE ................................................................................................................ 8

3. REAL TIME SYSTEM OVERVIEW ................................................................................................ 9

3.1. HARDWARE AND SOFTWARE SCOPE OF SUPPLY (PHASE 1) ................................. 10

3.2. HARDWARE AND SOFTWARE SCOPE OF SUPPLY (PHASE 2) .................................. 11

3.3. REAL-TIME MODEL.......................................................................................................................... 13

3.4. SCADA SOLUTION OVERVIEW ................................................................................................. 14

3.5. MULTI ETAP-RT SERVERS (REDUNDANCY SOLUTION) ............................................. 14

3.6. ETAP-RT SYSTEM COMMUNICATION .................................................................................... 16

4. SCADA (ETAP RT) SOFTWARE DESIGN OVERVIEW ..................................................... 16

4.3. ETAP RT ENTERPRISE SERVER (VERSION 18 OR LATEST) ..................................... 17

4.4. ETAP 18 WORKSTATION FOR OPERATOR/ENGINEER ............................................... 17

4.5. BASE MODE ......................................................................................................................................... 17

4.6. BASIC DESIGN PREMISES .......................................................................................................... 17

4.7. DESIGN OVERVIEW ........................................................................................................................ 18

4.8. TAG DEFINITIONS .......................................................................................................................... 19

4.9. SCADA TYPICAL COMPONENTS ............................................................................................... 20

5. USER PERMISSIONS REQUIREMENTS ................................................................................. 23

5.3. SQL SERVER ........................................................................................................................................ 24

5.4. DCOM SETTINGS REQUIREMENTS ......................................................................................... 24

6. REAL TIME WORKSTATION CONSOLE (ETAP CONSOLES) ....................................... 25

6.1. GRAPHICAL REPRESENTATION ............................................................................................... 25

6.1.1. PRIMARY PRESENTATION ................................................................................................. 25

6.1.2. REAL-TIME SERVERS & CONSOLES ............................................................................... 26

6.1.3. ETAP CONSOLES ...................................................................................................................... 26

6.2. SUBSTATION PRESENTATIONS ............................................................................................... 27

6.2.1. ETAP PRESENTATION DISPLAY DYNAMICS ............................................................ 27

6.3. ETAP CONTROL OVERVIEW ....................................................................................................... 29

6.3.1. PROTECTIVE DEVICE CONTROL OVERVIEW ............................................................ 29

Page 4: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 4 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.3.2. BREAKER CONTROL ............................................................................................................... 31

6.4. TABULAR DASHBOARD ................................................................................................................. 34

6.4.1. PROCESS MONITOR ............................................................................................................... 35

6.4.2. SERVICE TAG EDITOR (OPERATOR NOTES) ............................................................ 36

6.4.3. USER ACCESS MANAGEMENT ........................................................................................... 39

6.4.4. COMMON NAVIGATION ....................................................................................................... 42

6.5. REAL TIME CONSOLE –ALARMS /EVENT/ WARNING FUNCTIONALITY .......... 42

6.5.1. EVENT LOG .................................................................................................................................. 46

6.5.2. TRENDING ................................................................................................................................... 51

6.5.3. ETAP USER DEFINED REPORTS ....................................................................................... 54

7. ETAP ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS) ................... 60

7.1. ELICTRICAL SUPERVISORY CONTROL & DATA ACQUISITION (ESCADA) ...... 60

7.2. DISTRIBUTOION MANAGEMENT SYSTEM (DMS) .......................................................... 61

7.3. OUTAGE MANAGEMENT SYSTEM (OMS) ............................................................................. 61

Page 5: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 5 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

1. INTRODUCTION

1.1. Purpose

This document presents the Detailed Design Functional Specifications for Phase One & Phase Two Scada Solution. VISTA Automation will provide the

proposed application, engineering service and implementation of project.

The SCADA solution is based on ETAP Real-Time Software for all four substations of Palestine Electricity Transmission Limited.

The information provided in this document is subject to approval by AECOM/PETL,

pending review with Vista Automation as deemed necessary.

1.2. DEFINITIONS, ABBREVIATIONS AND ACRONYMS

A O

A/D Analog-To-Digital O&M Operation & Maintenance

ADC Analog-to-digital

Converter OM Operation Monitor

AI Analog Input OEM Original Equipment

manufacturer

APS Auxiliary Power Supply OPC OLE for Process Control

ANSI American National Standards Institute

OLV One Line View

OS Operating System / operator station/outage scheduler function

OTI Oil Temperature Indication

OWS Operator Workstation

B OTI Operation Technology Inc.

BPS Bits per second

C P Potential Transformer

CA Contingency Analysis PT Protective Devices

CT Current Transformer PD Power Distribution

CB Circuit Breaker PDS Power Distribution System

D PSMS Power System Monitoring

and Simulation

Page 6: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 6 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

DB Database PMS Power Management System

DI Digital Input Q

DNA Dynamic Network Analysis

QA Quality Assurance

DNC Dynamic Network Coloring

QC Quality Check / Quality control

DNM Dynamic Network Model QAS Quality Assurance System

DNS Domain name system

DO Digital Output R

DCOM Distributed Component Object Model

RAID Redundant array of independent disc

RAM Random Access Memory

E RC Remote Console

EC Equivalent Circuit RTDB Real Time Database

ETAP Electrical Transient

Analyser Program RTS Real Time Server

EWS Engineering Workstation

S

EPC

Engineering, Procurement and Construction

SA Sub Station Automation

SAT Site Acceptance Test

F SCA Short Circuit Analysis

FAT Factory Acceptance Test SCADA Supervisory control and data

acquisition

FC Fibre Connector SE State Estimator

FO Fibre-Optic SO Switching Optimization

FTP File Transfer Protocol SLE State and Load Estimation

G

GUI Graphical user interface T

TCP/IP Transmission Control

protocol/internet protocol

H T&D Transmission and

Distribution

HDD Hard disk drive

HTTPS Hyper Text Transfer

Protocol secure U

HIS Historical Information UI User interface

HMI Human Machine

Interface USB Universal Serial Bus

HV High Voltage UG Under-Ground

Page 7: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350

Project Name: Phase One & Phase Two Scada Solution for the “National Command Centre For Palestinian Electricity

Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 7 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

HTML Hyper Text Mark-up language

I V

IP Internet Protocol VDU Visual Display Unit

I/O Input / Output

IEC International Electro

technical commission

IED Intelligent Electronic

Devise

IEEE Institute of Electrical and

Electronics engineer VPS Video Protection System

J W

WAMS Wide Area Monitoring system

K WAN Wide Area Network

KBPS Kilobits per Second WFM Workforce Management

KVM Keyboard Video Mouse WS Workstation

L X

LFA Load Flow Application XML Extensible Mark-up language

LAN Local Area Network

LG Line to Ground Y

LL Line to Line

LLG Line to Line to Ground Z

M

MCC Motor Control Centre

MFM Multi-function Meters

MFR Multi-function Relay

MMF Multi-Mode Fibre

N

NC Normally Closed

NCA Network Connectivity

analysis

NML Network Management

Layer

NMS Network Management

system

NO Normally Open

Page 8: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 8 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

2. SYSTEM ARCHITECTURE

JENIN SUBSTATION Connection Point 1 (Typical for

200 connection points)

National Control Center

Telecommunication Backbone

New Redundant SERVERS

EXISTING SWITCH

SARRA SUBSTATION

EXISTING SWITCH

TARQOMIA SUBSTATION

EXISTING SWITCH

RAMALLAH SUBSTATION

EXISTING SWITCH

New OperatorWorkStation 1

New OperatorWorkStation 2

New OperatorWorkStation 3

New OperatorWorkStation 4

RTU DataAcquisition

SERVER (M2M)(FUTURE)

SUBSTATION (5-10)

EXISTING SWITCH

GPRS Communication

Connection Point RTU

Microwave Communication

Microwave Communication

Microwave Communication

Microwave Communication

Microwave Communication

Microwave Communication

FUTUREFUTUREFUTUREFUTUREFUTURE

GPRS Communication

New TV

Existing Redundant SERVER

Existing TV

Existing Engineering& Operator WorkStation

EXISTING SWITCH

New SERVER

New TV

Page 9: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 9 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

3. REAL TIME SYSTEM OVERVIEW

The SCADA Software would integrate with General Electric CCU 1000 supported with

power Software 5.8.0. and IED’S (F650 Protection Relays) Release to fulfil the monitoring and control requirements for SCADA System and Real Time Analysis.

The SCADA software (ETAP Real-Time) modules provided with this project include:

APPLICATIONS PURPOSE

Real Time Enterprise Server Enterprise Server Software Data Logger OPC/Modbus TCP Interface

Data Historian Server Historian Software

Real Time Monitoring Consoles Console Software

Advanced Monitoring

Real-Time Monitoring Bad Data Detection and Correction

Alarm / Notification Management and Processing

Trending and Reporting Customizable Reports

Tabular dashboards

Event Playback and Analysis

Event Playback Server Sequence of Event Recorder

Replay archived historian data Investigate cause & effect

Explore alternative actions Replay “what if” scenarios

Real Time Application Consoles 2000 Bus Simulation Capability

Real Time Driver Interface OPC DA Client Server and IEC6185

Microsoft SQL Server 2008 R2 Standard Edition (Includes 4 Client Access Licenses)

Page 10: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 10 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

3.1. Hardware and Software Scope of Supply (Phase 1)

Sr.

No. Hardware Description/Specification Quantity

1 SCADA Enterprise

Server

ProLiant DL380 Gen10 Tower

CPU: 1 x 4110 Xeon-S/8 Core /85W/

2100/Skylake-SP

MEM: 32GB 2Rx8 PC4-2666V-R Smart

Kit

CAGE: DL380 Gen10 8-SFF Hot Plug

HDD: 3 x HPE 600GB SAS 10K SFF

HDD

CTR: HPE Smart Array P408i-a/2GB SR

Gen10Ctrlr

ODD: HP 9.5mm SATA DVD-RW Optical

Drive

NIC: HP 1Gb 4-port 331i Adapter

PSU: 1 x 500W Power Supply Kit

(Gen10)

RAIL: HP 2U SFF - Easy Install Rail Kit

OS: Windows Server 2012 R2 MGMT: iLO5 Standard

1

2

Operator &

Engineering

Workstations

HP Z240 Tower Workstation

CPU: Intel Core i7-7700 3.6GHz (up to

4.2GHz) 8M Cache 4 Cores

MEM: 16GB DDR4-2400 nECC (2x8GB)

HDD: 1TB7200 RPM SATA Hard Drive

ODD: HP 9.5mm Slim DVD-RW Optical

Drive

2

3 Monitor HP N240 23.8-inch IPS Monitor, Micro-

edge 1

4 Additional OWS

Monitor LG 55” LED Screen (55LJ615Y) 1

5 Managed Ethernet

Switch

HP J9776a fully managed gigabyte layer

2 switch 24 port 1

6 Cabinet 22 U Server Cabinet 1

Page 11: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 11 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

3.2. Hardware and Software Scope of Supply (Phase 2)

Sr.

No. Software Description Quantity

1

ETAP Real Time

Enterprise Server

(ETAP 1800 or Latest

at the Time of

Commissioning)

ETAP RT Power Monitoring Server

(OPC/Modbus TCP Interface) 1

2 ETAP Real Time

Operator Console ETAP RT Operator Workstation 1

3

ETAP Real Time

Engineering Work

Station

ETAP Engineering Workstation 1

4 Microsoft Office Microsoft Office 2016 Home & Business 1

5 ETAP Historian

Software

Microsoft SQL 2016 Std. server with 5

CAL 1

Sr.

No. Hardware Description/Specification Quantity

1 Redundant SCADA

Enterprise Server

ProLiant DL380 Gen10 Rack

Mounted

CPU: 1 x 4110 Xeon-S/8 Core /85W/

2100/Skylake-SP

MEM: 32GB 2Rx8 PC4-2666V-R Smart

Kit

CAGE: DL380 Gen10 8-SFF Hot Plug

HDD: 3 x HPE 600GB SAS 10K SFF

HDD

CTR: HPE Smart Array P408i-a/2GB SR

Gen10Ctrlr

ODD: HP 9.5mm SATA DVD-RW Optical

Drive

NIC: HP 1Gb 4-port 331i Adapter

PSU: 1 x 500W Power Supply Kit

(Gen10)

RAIL: HP 2U SFF - Easy Install Rail Kit

OS: Windows Server 2012 R2 MGMT: iLO5 Standard

1

2 Operator Workstation

HP Z2G4 Tower Workstation

CPU: Intel® CoreTM i7-8700 3.2GHz (up to 4.6GHz) 12M Cache 6 Cores

MEM: 16GB (1x16GB) DDR4 2666 UDIMM

4

Page 12: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 12 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

NECC

HDD: 1TB 7200 RPM SATA 1st 3.5in WKS

ODD: HP 9.5mm Slim DVD-RW Optical

Drive

3 Monitor (8) + server

monitor (1)

Monitor: HP N240 23.8-inch IPS

Monitor, Micro-edge 9

4 Wall mounted screens

LG Television LED 65UK6300YVB 65''

Black, IPS panel, UHD, 50 Hz, HDR

active, Audio 20W, Smart TV Web OS

3.5, Quad processor, Wi Di, Miracast, 3

HDMI, 2 USB, with magic remote,

satellite built in

2

5 Office Printer

Kyocera ECOSYS M5526cdw

Color, laser, 26 ppm, Ethernet, wifi,

printer, scanner, fax, 4,3” touch panel

display, A4 size only, one year warranty

not including consumables

1

6 APC UPS SURTD5000XLI APC Smart-UPS RT 5000VA 230V including Batteries and Network Management Card

2

7 APC Cabinet

AR2400FP1+AP9568

- NetShelter SV 42U 600mm Wide x

1060mm Deep Enclosure with Sides,

Black

- Single Rack Rack PDU,Basic,Zero

U,10A,230V, (15)C13

1

8 Ethernet Switch J9776A Aruba 2530 24G Switch 1

Page 13: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 13 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

3.3. Real-Time Model Verified and Validated real-time model of the Electrical Network for Palestine Electricity Transmission Limited and its substations issued by Vista Automation to

PETL/Design Consultant for review. The model contains ratings, normal operating conditions, typical load profiles & ratings, switchgear type & ratings, area and zone

information, equipment information’s and other information pertaining to the PETL electrical network covered under this project. The same model will be used for making minor modifications / engineering according to the requirements. ETAP Model

will be equipped with Real time Digital and Analog Data which will be coming from CCU 1000 and IED’S.

The master model database will be stored in the Application servers. Every time the

SCADA application is launched on a workstation opening the model database, it will Synchronize the model Data with the Application on the Active server and if the Active Server Fall down ( Power disconnected ) the standby server will work as active server

, consistency is maintained between the master and local databases. When the master database is modified, the local databases will be synchronized automatically

Sr.

No. Software Description Quantity

2 ETAP Real Time

Enterprise Server

Redundancy license to the base license

of ETAP 18.1.1. 1

4 ETAP Real Time

Operator Console ETAP RT Operator Workstation(new) 4

4 ADMS License

Advanced Distribution Management

System Including:

Distribution Load Flow, Short Circuit,

Distribution State Estimation, Fault

Location Isolation & Service

Restoration, Switching Optimization,

Time Domain Load Flow, Load

Forecasting, Event Play Back

1

6 Microsoft Office Microsoft Office 2019 Home & Business 4

7 ETAP Historian

Software

Microsoft SQL 2019 Std. server with 5

CAL 1

Page 14: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 14 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

by re-starting or re-opening the local database. Utilizing the ETAP database integrator allows the dispatchers, engineers, and operators with an open database

from which they can extract information. No additional software is required in the ETAP workstation consoles to operate the system.

3.4. SCADA Solution Overview The SCADA application servers (ETAP Real-Time Servers) will communicate with the GE’s implemented CCU 1000 and IED’S (F650 Protection Relays) located in every

substation and collect electrical data/parameters via OPC Client-Server protocol and IEC61850. The GE CCU 1000 and IED’S (F650 Protection Relays) is communicating with all the field devices in the substation to collect field electrical data. The SCADA

application server will reside in the control room located in PETL Office

The GE System will act as Server and SCADA application Server will act as Client, thus SCADA Server interfaces with GE CCU 1000 and IED’S (F650 Protection Relays)

to collect electrical data and thus realize Real-time SCADA solution All the shared electrical data between the SCADA Server and GE System will be stored

in the “Tag Database” of the ETAP-RT software. All tags will be created and edited through the “SCADA Integrator” tool provided in ETAP-RT SCADA software.

For archiving the GE CCU 1000 and IED’S (F650 Protection Relays) system values and Reporting and Trending information, ETAP Historian server will be used. This

server will include the Microsoft SQL server database tool. The ETAP console will communicate with the ETAP Historian server to run the Trending and generating

Reports. ETAP Real-Time server software will be installed on the Application server. The ETAP

console will communicate with the ETAP Real-Time server and get the necessary data for Real time visualization, monitoring and control.

The system offered as part of this project is Redundant Real Time Server with built in historian servers, One Engineering Workstation and Five operator Workstations.

The licence offered is Redundancy license and maximum Five users can use the ETAP license at any given point of time.

3.5. MULTI ETAP-RT SERVERS (REDUNDANCY SOLUTION)

The Provided Solution is based on Redundant ETAP – RT SERVERS which will achieve the high efficiency of Data Recovery in case of failure in any of the servers.

Page 15: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 15 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

The communication between the OPC Server and the ETAP Real-Time Server software is based on the Distributed Component Object Model (DCOM). DCOM, the

Microsoft technology for the implementation of distributed and object-oriented applications, is standard communication for client servers including OPC. The active

and redundant ETAP Real-Time Servers monitor each other continuously via TCP/IP. PM Server 1 is the primary server and will remain active. In the event that PM Server 1 goes down, the redundant PM Server 2 would take over as the Active

Server and automatically pick up the load. This is done via a “stable leader algorithm.”

ETAP Consoles are also linked to all servers via a full duplex Named-Pipes connection. The information

exchanged between the server and consoles include SLE and monitored data, as well as a signal from each

server indicating its status and connected ETAP consoles to the active server. If the active server becomes inactive, the consoles will cease communication with the inactive server and switch

to the activated server.

Page 16: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 16 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

3.6. ETAP-RT SYSTEM COMMUNICATION

The logical networking is displayed below:

ETAP

ARCHIVER

ETAP

SOFTWARE

SQL

SERVER

REDUNDANT REAL TIME

SERVERS

ETAP

SOFTWARE

ENGINEERING

WORKSTATION

ETAP

SOFTWARE

FIVE OPERATOR

WORKSTATIONS

The ETAP Consoless will be linked to all ETAP Real time Servers via a full duplex

named-pipe connection. The information exchanged between the server and consoles include monitored data, Raw and Processed data.

The following image depicts the server initialization status:

4. SCADA (ETAP RT) SOFTWARE DESIGN OVERVIEW The following software is provided with the system for ETAP RT SCADA applications.

Page 17: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 17 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

4.3. ETAP RT ENTERPRISE SERVER (VERSION 18 or Latest) ETAP Real Time server software will communicate with GE CCU 1000 and IED’S (F650

Protection Relays). Mapping information between the two systems will be stored in a MongoDB database that is created through an ETAP Application named the “ETAP SCADA Integrator”. The ETAP Real Time Integrator Database will be residing in the

real time server and console workstation will connect to that database.

The ETAP Real Time Server version that will be installed is ETAP Real-Time Server Version 18/ latest ETAP-RT software Version at the time of commissioning. The ETAP Real Time Server Software will serve the Real-Time data to the ETAP

Consoles.

The Real-Time Server utilizes Memory Map database for RTDB and it is constructed automatically and internally for fast processing. No need to create an independent

RTDB, the historian database is used to archive data for reproduction and analysis.

ETAP Real-Time Historian server will be operating as a built in application provided

to archive data from ETAP Real-Time PSMS server; the data will be available for operators/engineers for Real time SCADA operations

4.4. ETAP 18 WORKSTATION FOR OPERATOR/ENGINEER

Operators will be using the workstations to monitor the following substations and up to 10 substations and 200 utility connection points under PETL with ETAP RT SCADA

Solution:

• Jalameh Jenin

4.5. BASE MODE The Base mode in ETAP is designed for the creation and management of the ETAP

RT Model database. This mode provides an easy to use, fully Graphical User Interface (GUI) for constructing one-line diagrams and database for the ETAP-RT model. The graphical one-line diagram and database serves as one common platform for all

ETAP-RT applications.

4.6. BASIC DESIGN PREMISES

Page 18: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 18 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

The creation of the database is transparent to the users. The user (Administrator) can graphically construct the ETAP model by connecting buses, branches, motors,

generators, and protective devices in any order from the One-Line Diagram Edit toolbar. The user (Administrator) can connect elements to buses graphically (by

dragging lines from the device element) or by using the Info page of the Device Property editor (double-click on the element and its property editor will open). In addition, the user (Administrator) can graphically add, delete, relocate, connect

elements, zoom in or out, display grid off or on, change element size, change element orientation, change symbols, change equipment / device color, create personalized

viewing themes, hide or show protective devices, enter properties, set operating status, etc.

As the user (Administrator) builds the graphical interface, ETAP generates the database without any intervention from the user

4.7. DESIGN OVERVIEW

This section describes the overall capabilities of the Base mode in ETAP. This mode is equivalent to the Power Applications Network Builder.

From the Base mode, the user has access to:

• Data Editing • Graphics Editing

Data Editing

ETAP keeps track of the detailed data for each PMS component. Data editors are

designed to speed up the data entry process.

Using these editors, the user can assign the engineering properties of the element, such as its ratings, settings, loading, connection, etc. All editors in ETAP are designed

with intelligence so that electrical relationships between fields are followed. This speed up the process of entering information requiring the minimum data. The editors have been structured in the most logical manner for entering data for different

types of applications. Marked changed data, undo, search, and navigate are some of the standard features in each editor.

Graphics Editing

Page 19: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 19 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

In this section, some of the most common functions of the graphical user interface for the one-line diagram are explained. The detailed instructions provided here will

assist you in creating and editing your one-line diagram presentation.

4.8. TAG DEFINITIONS For ETAP, tags are defined in the ETAP SCADA Integrator. For ETAP RT SCADA

Solution the tag database includes the following metered parameters: MW, MVAr, kV, PF, Hz, Amps and switching devices status.

ETAP Real-Time System shall integrate following signal from the GE CCU 1000 located at control room, to perform Real time analytic, SCADA applications

- DIGITAL SIGNALS o Switch Status (Breakers & Isolators) o Contactors

o Fuse o Earth Switch

- ANALOG STATUS

o Transformer Tap Position

o Current (Amps) – 3 Phase o Voltage (Vmag) – 3 Phase

o Frequency o Power Factor o Active Power (MW)

o Reactive power (MVAr)

Above signals will be applicable for all the feeders of HV Switchgear, Incomer, Bus coupler, ACB Outgoing and Outgoing feeders.

The ETAP SCADA Integrator is a tool which allows for Administrators to add/remove

Real-Time measurements to the system and link these measurements to ETAP components. The ETAP SCADA Integrator allows users to link the ETAP Components within an ETAP Model with physical devices in the field. Fundamentally, the ETAP

SCADA Integrator uses a template approach where users can create a model of a device type and reuse this model for multiple ETAP Components. This allows users

to only have to define those parameters which are unique to a given device in the field (for instance IP Address).

With this tool, Administrators can write custom calculations, create measurements, etc.

Page 20: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 20 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

4.9. SCADA TYPICAL COMPONENTS This chapter describes the typical elements that will be used for ETAP PMS Model.

Component symbols for electrical equipment. Sr.

No.

Element /

Component

Component Symbol

1 Power Grid

2 Bus

Page 21: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 21 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Sr.

No.

Element /

Component

Component Symbol

3 Generator

4 Transformer

5

High Voltage Circuit

Breaker (The symbol

for a high voltage circuit breaker

(>1kV) is shown below.)

Page 22: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 22 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Sr.

No.

Element /

Component

Component Symbol

6 Switch

7 Lump Load

8

Multi-Meter (The Multi

Meter symbol is shown below.

The multi-meter

component will be hidden. There will be

an option to display if

desired.)

9

Capacitor

Bank

10 Cable

11

Low Voltage Circuit Breaker

Page 23: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 23 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Sr.

No.

Element /

Component

Component Symbol

12

Induction Motor

5. USER PERMISSIONS REQUIREMENTS All users will be stored within the Active Directory which is stored on the Domain

Controllers. The follower user types will be created for the system:

PSMS Server Service Account

• Associated Software: ETAPSrvc

• Permissions Required:

o Grand Local Admin

o Enable Logon as a Service

• Machine/Users: PSMS Servers

• Purpose: This service launches etapspm.exe and requires local admin

privileges.

• Machine/Users: Playback Servers

• Purpose: Playback services require Local Admin and DB Creator privileges.

Database Download

• Associated Software: ETAPS

• Permissions Required:

o Read access to OTI_Image Folder

o Access to OTI_Image Share

• Machine/Users: All ETAP Real-Time Users

• Purpose: The project files are downloaded from this folder.

Database Maintenance

• Associated Software: ETAPS

• Permissions Required:

o Read/Write access to Psmssvr folder in the root ETAP installation.

o Read/Write access to OTI_Image folder

• Machines/Users: All ETAP Maintenance Users

Page 24: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 24 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

• Purpose: OTI_Image to update the project for all users, Psmssvr folder to create Real-Time files.

Trending/Archived Reports User

• Associated Software: ETAPS

• Permissions Required:

o Create Database Permission in SQL Instance

• Machine/Users: All Trending / Archived Reports Users

• Purpose: Trending/Archived Reports requires these permissions in order to properly collect data from the database

5.3. SQL SERVER

Historical and Playback data shall be archived to the SQL Server instance on the Historian servers. A standard TCP/IP name pipes connection shall be utilized to

transfer data from the Real-Time Server. Please see details below:

• Instance Name: ETAPARC

• Login Type: Mixed (SQL and Windows)

• Permissions: See previous section of this document for granular permissions however at a minimum there must be one system administrator which has full

permissions.

5.4. DCOM SETTINGS REQUIREMENTS To enable the capability of ETAP accessing remote OPC Servers, the DCOM

(Distributed COM) needs to be set up in both the OPC Server and ETAP Server.

Before setting up DCOM, the first step to allow communication between two computers is to setup a trust domain. It is recommended that you setup all the machines running OPC Servers that will be connected to ETAP to run under the same

domain. Otherwise, it will run into the problem of setting up trust domains, which makes the setup much more complicated. If you want to use multiple domains, then

you need to setup trust relationship on both domains since there will be communication both ways. Consult Windows help on how to setup trust domains.

Page 25: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 25 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6. REAL TIME WORKSTATION CONSOLE (ETAP Consoles) ETAP consoles are workstations that will be running the ETAP software. ETAP

communicates to the ETAP Real-Time server software to collect available online data and archive in historian for Trending and Reporting functions

Each workstation will contain a copy of the ETAP Model database. The workstation is setup to automatically select the ETAP Model database when ETAP is executed.

6.1. GRAPHICAL REPRESENTATION

6.1.1. Primary Presentation ETAP SCADA is graphically represented by the one-line diagram. This one-line

diagram is based on the approval of ETAP Model by PETL. The diagram is constructed to match the PETL Power System Network for Phase one as much as possible so

operators/ engineers do not have to familiarize themselves with two different representations.

The primary representation or “Sys Monitor” will display the individual Substations as a composite network, loads, and transmission \ distribution lines.

Figure below, depicts a sample/typical of the graphical representation of the ETAP SCADA model.

Page 26: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 26 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.1.2. REAL-TIME SERVERS & CONSOLES ETAP Real-Time server software will reside in the ETAP-RT Server and processes the

data to all ETAP consoles. There will be ETAP Real-Time servers, running as a Redundant system.

The ETAP-RT solution is equipped with Tow high performance Historical Servers ( As Redundant SERVERS) to store all ETAP SCADA values and to perform power system

analysis and studies based on the archived data.

6.1.3. ETAP CONSOLES ETAP consoles are Operator/Engineering workstation (OWS/EWS) that will be running

the ETAP software. The workstation will contain a copy of the ETAP PSMS Model database. The workstation is setup to automatically select the ETAP Model database when the ETAP Client application is started. If the master database is updated, the

Page 27: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 27 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

system administrator has the option of updating the consoles or waiting until the local ETAP Client application is re-started, so it synchronizes automatically. The

master database will reside in the ETAP Server.

6.2. SUBSTATION PRESENTATIONS The substations presentation will be composite networks within the Primary Presentation. The following Figure depicts a sample of the graphical representation

of the substation presentation:

6.2.1. ETAP PRESENTATION DISPLAY DYNAMICS Each presentation in online mode will have the following display behaviour:

1. Black Background

Page 28: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 28 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

2. Energized components in Lime Green 3. State Estimation Results will be displayed in Red next to line\feeder flow with

direction arrow to the positive direction of real-power flow 4. Real-Time data is displayed in blue color

5. Components IDs in White Color

6. Override Data and Bad Quality flags in brackets “[ ]”

• [B] Bad Quality

• [C] Closed Device

• [O] Open Device

• [####] Override Analog Measurement

7. Analog Measurements will be brought in by Meter Component Model

8. Alarmed Component will be displayed in red

The following figure demonstrates the dynamic display on ETAP PDS Presentations

when online:

Page 29: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 29 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.3. ETAP CONTROL OVERVIEW

6.3.1. PROTECTIVE DEVICE CONTROL OVERVIEW The Protective Device (PD) control is used to manually open, close, pin open, or pin closed any breaker in the system. The breaker control can be used to make appropriate changes as long as the corresponding Input and Control tags have been

established in the system. See the Administrator’s Guide for more information on setting up tags for the PD control.

The protective device control section can be launched up by double-clicking on a “PD” symbol on the one-line diagram presentation (Sys Monitor). A circuit breaker is used

as the example shown below:

Real-Time

Each PD has a Real-Time section which allows the operator to change the configuration in the system or simulate a configuration change. Any restriction to

this is due to the permission given to the console. Refer to the PD Console Permission

Page 30: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 30 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

section for more details on PD control permissions. The device types that have PD

Controls are as follows:

Device Type Device Type Device Type

HVCB Double Throw Switch Ground Switch

LVCB Recloser

Single Throw Switch Contactor

Scanned

This displays the Real-Time configuration of the breaker.

Control

Page 31: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 31 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

This column allows the user to change the configuration of the breaker on the field. Note that each configuration should have a corresponding Control tag setup for the

digital output to be written into the system. If the user decides to change the configuration, a confirmation display will appear asking the user to confirm the

configuration change. The Confirm Control Action display is shown below:

Pin

This column allows the user to simulate the effect of switching the configuration of the breaker on the system. Once a breaker is pinned either open or close, the pin will be shown in a diagonal position. This option does not control the actual position

of the breaker. Pinning a breaker position allows the operator to overwrite or supersede the status signal received from the Real-Time system, and affects the

calculations made by the State and Load Estimator (SLE) that are displayed in the Sys Monitor presentation. The Sys Monitor presentation will show both the Real-Time value and the pinned value in [] brackets.

Alarm

Check this box for “Close”, “Open”, or both to set an alarm for each configuration.

This option is only used when CB Status in the system alarm page is set to individual.

6.3.2. BREAKER CONTROL User Access Level

The following access levels can take full control of and may make any changes to the Circuit Breaker.

Page 32: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 32 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Access Breaker Control

Note: You must be in online mode to access the Breaker Control 1. Double Click on the breaker in your One-Line Diagram

Project Editor

Base Editor Controller

Operator

Breaker Control X X X X

Page 33: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 33 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Open a Breaker

Open a breaker and verify that the breaker opened in the field by the status is shown in the scanned display.

1. Double-click Element to Launch Controller View 2. Select the TRIP button

3. Click OK to confirm

Close a Breaker

Close a breaker and verify that the breaker closed in the field by the status is shown in the scanned display.

1. Double-click Element to Launch Controller View 2. Select the CLOSE button

3. Click OK to confirm

Page 34: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 34 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.4. TABULAR DASHBOARD

This Application will allow Operator and User to analyze the Project configured data

in Tabular manner with Real time Data and also enable user to customize, make groupings, Filtration and save project specific themes. The purpose of this tool is to provide a graphical interface to monitor and control all configured tags in the SCADA

Integrator System in a tabular way. It provides an interface to observe all configuration details from a tag as well as its current values, states, alarms and

quality messages. It also provides a component view which allows the user to observe all values for a specific component.

Key Highlights

• Monitor All Tags (Digital, Analog and Tag Link) in Tabular way

• Observe all configuration details from a tag as well as its current values, states, alarms and quality messages

• Provides a component view which allows the user to observe all values for a specific component.

• Defining Customized Themes using different Filtering

Screen View Concept of Tabular Dashboard

Page 35: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 35 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.4.1. PROCESS MONITOR

Dedicated PMS Application to monitor the heartbeats of all the application involved

in SCADA PMS Application and running all over the network. ETAP Process monitor can also control the various application within ETAP according to operator and system design function and operation. It can start, shutdown, restart

and Monitor the current status through heartbeat.

Key Highlights

➢ ProcMon Service functions based on Process heartbeats ➢ Monitor Status and Health of all process on same machine as well as other

machine on network. ➢ If the process fails it can take action based on :

• Indication on ProcMon Viewer • Alarm Event Generation

Page 36: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 36 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

• Automatic Restart of:

o Process that has stopped on the same machine

o ProcMon Service on another machine

Screen View Concept of ETAP Process Monitor

6.4.2. SERVICE TAG EDITOR (OPERATOR NOTES)

Operator Note is a Real-Time interface for operators to communicate information about ETAP Components and areas in the OLV, Distribution view and Feeder View.

These information could be different types such as information, or notes about maintenance, Alarm Inhibit (Do not generate alarm for this component or area) or control Inhibit (Do not send control command).

There are 4 different types of Service Tag with the below priorities:

• TOP PRIORITY: Control Inhibit • Alarm Inhibit • Maintenance

• LOWEST PRIORTY: Informational

Tags will be displayed on the Sys Monitor OLV or Distribution view or Feeder View and will be indicated based on the Type. If there are multiple types of tags, the highest priority image will be used and there will be an indication on the corner of

the image of the number of the tags Note: Tags are displayed offline and online.

Page 37: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 37 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Key Highlights

➢ Real-Time interface for operators: o To communicate information about ETAP Components and areas or even

a Location in the OLV and Distribution and Feeder view. ➢ Service Tag Editor is used to:

o Create Notes with different Priorities (Types)

o Option to set Customized Images for different types of Notes from ETAP o Capability to create Notes for Multiple Components.

➢ Developed for all the Views: o One Line View o Distribution View

o Feeder View ➢ Supported in HMI Viewer as well.

Screen View Concept of Service Tag Editor

Page 38: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 38 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Page 39: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 39 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.4.3. USER ACCESS MANAGEMENT

ETAP provides program security by relying on two tiers of user access control. The first level is controlled by the operating system under which ETAP is running (Windows 7, Windows 8 and Windows 10). The user must be an authorized user as determined by the operating system administrator.

Page 40: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 40 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

ETAP provides the second level of access control by assigning one or more of the ten access level permissions to an authorized user for each individual project. These

access levels are listed in the following table.

Key Highlights

➢ Two level Authentication : Windows as well as ETAP Software ➢ Several Standard users and roles :

Page 41: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 41 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

➢ Can Manage Access for Switching order management and Load

shedding.

➢ Manage Windows users and Assign those specific roles and responsibility.

Page 42: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 42 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.4.4. COMMON NAVIGATION

Custom Menu Buttons

6.5. REAL TIME CONSOLE –ALARMS /EVENT/ WARNING FUNCTIONALITY

Alarms represent warnings of field conditions defined in software that could cause problems, and require an operator attention. The objective of an alarm is to indicate

that something has gone wrong, or that a particular stage of value has been reached.

Events represent normal system status messages and do not require an operator response. An event is defined as a detectable occurrence, which may or may not be

associated with an alarm. For example, Event in Industrial automation can be simple logging of Operator with his username to the Real-time application.

Page 43: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 43 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Warnings are similar to alarms except that warnings do not have pick delay (seconds) nor require an acknowledgment.

In ETAP Alarms and Warnings are shown in the dock able Alarm Page, where further you can acknowledge, filter and mute the respective alarms. Alarms and warnings

are used in ETAP Real-Time to notify the user of an event of interest that has occurred in the system.

PSMS alarm sequence is a three-tier process: Detection Evaluation Annunciation.

The following three “containers” are utilized to filter alarms through the above

process:

Note that an alarm can only exist in only one container at a given time.

Detection PSMS detects an alarm condition when the measured/monitored values reach

the alarm set point limits as specified in the alarm setup page. If an alarm

condition is detected the alarm becomes active (“ON” state).

Evaluation Depending on the existing alarm states and the alarm settings (i.e. the alarm pickup delay) PSMS performs several checks to evaluate the alarms prior to their annunciation.

Upon detection of an alarm (alarm signal on), PSMS checks all three of the containers

(TD, Alarm, and ACK; see diagram) for a matching alarm type and condition. The following describes the evaluation process of detected alarms: • For alarms detected (alarm signal on) in the Alarm container that are active (alarm

condition exists, alarm not acknowledged), PSMS will bypass the TD container and update the “Current % Value” fields. (The alarm will not be added to the TD

container).

Page 44: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 44 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

• For alarms detected (alarm signal on) in the Alarm container that are inactive

(alarm condition no longer exists, alarm not acknowledged), the status of the alarm is changed from Inactive to Active. (The alarm will not be added to the TD

container; TD container is bypassed). Date, Time and % value fields remain the same as when the alarm condition became true originally and the “Current % Value” fields are updated according to the new alarm value. If Audible / Siren

options are checked a beep / siren is played accordingly.

• For alarms detected in the ACK container that are active (alarm condition exists,

alarm acknowledged), PSMS will bypass the TD and Alarm containers (The alarm

will not be added to the TD or Alarm container). • If the alarm is in the TD container, PSMS will track the alarm pickup delay

expiration time and update the % Value (Note that the expiration time will not be

reset).

• For an alarm that is in the TD container (counting down to expiration), if during

the next scan the state of the alarm is changed to “OFF” (alarm signal off) the

alarm is removed from the TD container and is set to “Free” state.

• If the alarm is not in any of the three containers, PSMS will add the alarm to the

TD container. The TD container will keep track of the expiration time for alarms.

Expiration time is the time delay before the alarm is activated (annunciated).

• If an alarm time delay expires, the alarm is then moved to the alarm container as

an active alarm (see annunciation). If Audible / Siren options are checked a beep / siren is played accordingly. The meter or element in the OLD for which the alarm condition becomes true is displayed in red (or the color specified in the Etaps.ini

file).

Note: Alarms with pickup delays equalling to zero (0) will be treated as

instantaneous alarm (no intentional delay).

Annunciation Annunciation of alarms is the process of posting and acknowledging alarms in Alarm View and ACK View.

Active Alarms

Active Alarms are defined as alarms, which are detected by PSMS (alarm signal ON) and exist in the Alarm and/or ACK containers. Alarms in the TD container (with time

delay) are not considered to be active.

Page 45: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 45 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Depending on the selections made for alarms in the Alarm Setup dialog box, PSMS

may also do any of the following:

• Sound a discrete signal (i.e. beep) • Sound a siren (a continuous sound) • Flash the alarmed component

• Automatically display the “Alarm View” window

• Alarm Display Viewer:

• Additionally, all alarm events can be configured to generate an SMS and/or an

Email message. • Within the System Alarm dialog, operators with appropriate permissions can turn

off alarm audible for all alarm conditions. Since all operator audio is managed by the Operating System, the standard OS volume control will allow users to increase/decrease the audio level. The alarm audio is global for all audible alarms.

This is configurable as a .wav file.

Active Warnings Active warning both Local and System warning is defined with the high and low set

points in the Server setting The Local and System Warning can be viewed by clicking on the Warning button

located on the Real-Time toolbar.

Page 46: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 46 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.5.1. EVENT LOG

Event Viewer The Event Viewer module is a useful tool to display events and alarms on the system.

1. To launch the Event Log, click on the Real-Time Menu and select the Logs and Reports icon.

2. Select the Event Log icon

3. This will launch the Event Viewer

Page 47: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 47 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Note: This functionality requires initial setup of MongoDB and additional software

configuration. Contact your local system administrator to install and configure this function.

Filtering Displayed Based on a Message Column Each one of the columns displayed can be filtered based on specific criteria. Any

column can be filtered based on specific criteria. Note that this only filter based on displayed data. To filter all events, use the Filtering Options.

1. Click on the filter button located on the left side of the column

2. Specify the criteria to sort 3. Click on "Filter" to apply filter 4. Click on "Clear Filter" to remove filter

Query Events Based on time period Events can be filtered by using the filter bar located on the bottom left of the Event

Viewer window

Page 48: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 48 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

1. Select the "From" and "To" dates to specify the time period 2. The Event Viewer window will sort all events based on the selected time range

3. Click on "Execute"

Filter Events using Filtering Options

Events can be filtered by using the filter bar located on the top left of the Event Viewer window

1. Select column(s) to filter and filter rules from Filtering Options 2. Adjust time range if needed from Timeframe

3. Click on "Execute" Filter Events using Filtering Options (Advanced)

Events can be filtered by using the filter bar located on the bottom left of the Event Viewer window

1. Select "Advanced Free Form Filter" 2. Write the script to filter 3. Adjust time range if needed from Timeframe

4. Click on "Execute"

Sorting Events on Event Viewer

Each one of the displayed columns can be filtered by clicking on the column title. Click on column you wish to sort; this will make the column to be sorted ascending

or descending. Any column can be sorted.

Page 49: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 49 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Showing/Hiding Columns in the Viewer

Event Viewer can be customized to show or hide all available columns for an event. 1. To show or hide on a column right click on the column title, this will show all

column titles. 2. Select the columns you wish to add or hide. Any column that is checked will

be shown and any column unchecked will be hidden from the window.

3. Click on any record, this will refresh the window with updated selection.

Launch Event Viewer Theme Manager All Event log queries may be stored as a theme. Each one can be loaded using the Event Viewer Theme Manager.

To Launch Event Viewer Manager:

1. Click on Configuration tab 2. Select Event Viewer Manager Themes

Add Event Viewer Theme Event Log themes may be stored and shown on Existing Themes.

To add a new Event Viewer Theme: 1. Create a personalized configuration (search criteria, columns to show, etc.

using any filter tools) 2. Launch Event Viewer Theme Manager 3. Under Save Current, enter a new name for your filter configuration

4. Include a time range (optional) 5. Click Add

6. New Filter will now display under "Existing Themes" Apply Existing Event Viewer Theme

Event Log themes stored can be launched from Existing Themes. To launch an existing Event Viewer Theme:

1. Select the theme you wish to apply from Existing Themes 2. Click on Apply

Delete Existing Event Viewer Theme

Event Log themes stored can be deleted from Existing Themes. 1. Select the theme you wish to delete from Existing Themes 2. Click on Delete

3. Event will no longer show in "Existing Themes"

Page 50: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 50 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Display Event Viewer Log in Different Time Zone Event Log may be viewed using other time zones other than the local time zone.

1. Select Configuration Tab

2. From the Time zone select the time zone you wish to use 3. Time Stamp column will automatically be updated upon selection.

Export & Print Events from the Event Log

Events displayed on the existing window can be exported as a Microsoft Excel file. To export the file, click on the Export icon on the ETAP icon menu and select a location

where the file will be saved. To print the current view, click on the print button.

Type of data shown as messages in event viewer:

Event Viewer can display different data for every element used in the ETAP project as follows:

Value Change Value change defines the change in any digital tag. This change includes changes

such as change of state for protective devices and digital indicators.

Alarm & Warning Conditions Alarm and warning condition messages are configured through the System Alarm

and Events. There are three different type of messages displayed in event viewer: • Component entered in Alarm/Warning State

• Component left in Alarm/Warning State • Component Alarm Acknowledged by user.

User Logging Event Log keeps track of all users logged into the ETAP system. The following

messages are displayed on Event Viewer

Page 51: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 51 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

• User Login into ETAP Real-Time • User Log out from ETAP Real-Time

Server Messages

Event Viewer also keeps track of the status of the drivers and communication quality from the drivers.

• Driver Started

• Driver Rebooted • Lost communication from driver.

6.5.2. TRENDING

ETAP Trending is an ideal tool for charting and trending Real-Time as well as forecasted information. ETAP Trending allows the user to generate unlimited number

of charts with up to 20 channels of information on each trend. ETAP Trending also has the functionality to display dissimilar electrical parameters (for example MW and Voltage) on the same chart. ETAP Trending will allow the user to view any archived

parameter whether it is electrical or non-electrical on a continuous basis and is updated periodically as new data becomes available.

The Trending Main View is an organized tree list of all the trends that have been

previously created and a list of all meters that can be trended.

Page 52: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 52 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

There are three main folders or first level folders in the main view with additional sublevels under each as shown below:

• Trends - Contain a list of all previously created trends on that ETAP console. • Forecasted Meters – Contain a list of meters that have been Forecasted

• Real-Time – List of meters and parameters being monitored and archived

Trending Setup In order to run the ETAP Trending application, no manual file manipulation is required

beyond the configuration of ET Config.

The Trending Main View is an organized tree list of all the trends that have been previously created and a list of all meters that can be trended.

Trend configuration and time settings The trends folders contain a list of all previously created trends on that ETAP console. Measureless trends can be added to the Trends folder by right-clicking on the

“Trends” main folder and clicking on “New”.

In ETAP Trending ribbon, Various option is available as highlighted below Pointer, save option, print preview & Print option, Plot option …etc. as shown below.

Pointer

Print Preview

Page 53: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 53 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Print

Grid

Show Table

Plot Options

Display Point Markers

Single/ MultiAxis

Page 54: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 54 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

6.5.3. ETAP USER DEFINED REPORTS

The ETAP’s Real-Time User Report application is designed to capable user to design and generate user defined (OnDemand) and automatic (Schedule) reports. To

generate reports, user needs to design Measurement Groups, define report type and templates and then use report viewer to create & display reports.

Page 55: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 55 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Overview

The user defined reports support the following report types, formats and categories.

Report Types The User Report supports two different report types:

Historical Reports

Historical report will be based on all available values in Historical database with following options:

o User Defined

o Daily

o Weekly

o Monthly

o Yearly

Summary Reports Summary report will be based on all available values in database with following

options:

Page 56: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 56 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

o User Defined

o Daily

o Weekly

o Monthly

o Yearly

o Customized Reports

Report Format The User Report supports configurable report format with following options:

o PDF Format (default report format)

o PDF + Excel formats

Report Time Interval

The User Report supports Configurable Time Interval for measurements within: o 5 minutes

o 15 minutes

o 30 minutes

o 60 minutes

Report Category The User Report supports capability to define reports in two different categories:

o OnDemand Reports: These reports will be generated per user

request.

o Scheduled Reports: These reports will be generated automatically

based on report’s Period setting.

LAUNCHING ETAP USER DEFINED REPORTS The user defined reports application can be launched from the real-time toolbar from

the logs and reports section.

Page 57: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 57 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

USER REPORTS TOOLBAR

The User reports toolbar will appear on the screen when user launches the User

reports application. It has list of options to define period, time interval, format and options to print, save and make modifications to reports.

Period

This is used to display the reports according to selection based on the reports.

Date and Time Selector

This is used to select the from and to times used to view the reports at desired dates

and time. Display

This option is used to display the reports according to the format and time period selected.

Decimal Selection This is used for selecting the number of decimal places the values on the reports will

show.

Time Interval

Page 58: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 58 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

This is used to define the time interval between values shown in the report.

Format Selection This is used to select the format in which the report needs to be displayed.

Save This is used to save the reports in pdf or excel formats.

Print

This is used to print the reports on the user reports application. Page Up and Down

This is used to navigate through pages of the generated report.

Zoom In This is used to zoom in into the reports.

Zoom Out This is used to zoom out of the reports.

Pan This is used to navigate to different areas on the user report application.

Find

This is used to find a particular field in the user reports. USER REPORT TEMPLATES

The user report application can be used to generate the on demand and the

scheduled reports. These reports are listed on the User report applications on left hand side toolbar.

On Demand Templates The on-demand templates can be used to show the historical data and summary.

These are listed on the user reports according to the areas. The areas are defined by the measurement group belonging to that particular area.

Page 59: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 59 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

Scheduled Reports

The scheduled reports are organized as daily, weekly, monthly and yearly. They contain the historical data and summary. The scheduled reports are also listed

according to the area in which the measurement group belong.

Page 60: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 60 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

7. ETAP ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS)

ETAP ADMS™ is a combined planning and operation solution to manage, control, visualize, and optimize electrical power distribution network comprising of:

• Electrical Supervisory Control & Data Acquisition (eSCADA)

• Distribution Management System (DMS) • Power Management System (PMS) • Outage Management System (OMS)

Its Scalable and modular solution to manage, control, visualize, optimize and automate utility distribution networks from large cities to rural cooperatives.

Integrated network model for planning, protection, reliability and operations, Intuitive and user-friendly graphical user interface used by Distribution Network

Operators (DNOs), Dispatchers, Planning Engineers, Reliability Analysts and Managers. Advanced Analytics including Distribution State Estimation, Volt/VAR Optimization

(VVO), Conservative Voltage Reduction (CVR), Fault Location, Isolation & Service Restoration (FLISR), Outage Prediction, Load Forecasting, Unified AC & DC Power

Flow, Distributed Generation Modeling, Protection, Load Shedding. Situational Intelligence provides efficient and reliable grid analysis and management during rapidly changing network state. Standardization with majority of industry

applications and easy integration with legacy and third party software.

7.1. ELICTRICAL SUPERVISORY CONTROL & DATA ACQUISITION (eSCADA)

eSCADA provides real-time visualization via intelligent graphical user interface comprising of one-line schematics, substation views, distribution feeder layout,

geospatial diagrams and analytical dashboards.

eSCADA provides real-time visualization via intelligent graphical user interface comprising of one-line schematics, substation views, distribution feeder layout, geospatial diagrams and analytical dashboards.

Page 61: Detailed Design Functional Specifications for Phase One ...-4 Rev 2.0 3. REAL TIME SYSTEM OVERVIEW The SCADA Software would integrate with General Electric CCU 1000 supported with

Project Number: 700-180350 Project Name: Phase One & Phase Two Scada Solution or the “National Command Centre For Palestinian Electricity Transmitting Authority (PETL)”

Detailed Design Functional Design Specifications Rev 1A

© 2018 Vista Automation Network LLC

PROPRIETARY & CONFIDENTIAL

Page 61 of 61

Document No.: VA/DP/PE/03/F10-4 Rev 2.0

7.2. DISTRIBUTOION MANAGEMENT SYSTEM (DMS)

ETAP Distribution Management System (DMS) is an intelligent and robust collection of GIS based advanced distribution network applications that enhance electric utility performance.

ETAP DMS proactively reduces peak demand, optimizes network assets, while assisting distribution networks deliver electricity more efficiently, reliably, securely

and economically Distribution Management System is built on existing and proven ETAP Real-Time™solution and integrates with GIS, eSCADA, OMS and other applications such

as Automated Meter Reading (AMR), and Customer Information Systems (CIS)

7.3. OUTAGE MANAGEMENT SYSTEM (OMS) Integrated Outage Management System (OMS) and Mobile Workforce Management

(MWM) solutions minimize outage disruption by enabling faster detection and restoration through enhanced situational awareness, automation, and effective use of field crews.


Recommended