+ All Categories
Home > Documents > DETAILED PROJECT REPORT FOR...

DETAILED PROJECT REPORT FOR...

Date post: 10-Mar-2018
Category:
Upload: nguyenhanh
View: 250 times
Download: 5 times
Share this document with a friend
26
DETAILED PROJECT REPORT FOR CONSTRUCTION OF COAST GUARD JETTY AT OOT VADINAR. Client: INDIAN COAST GUARD - OOT VADINAR Consultant Prof. R. SUNDARAVADIVELU MARCH -2015
Transcript
Page 1: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

DETAILED PROJECT REPORT FOR CONSTRUCTION OF COAST GUARD JETTY AT OOT VADINAR.

Client: INDIAN COAST GUARD - OOT VADINAR

Consultant Prof. R. SUNDARAVADIVELU

MARCH -2015

Page 2: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

SL.NO CONTENTS PAGE NO

1.0 INTRODUCTION

1.1 GENERAL

1.2 PORT LIMIT & SITE LOCATION

1.3 APPROACH TO SITE

2.0 SITE CONDITIONS

2.1 METEROLOGICAL DATA

2.2.1 CLIMATE

2.2.2 TEMPERATURE

2.2.3 RAINFALL

2.2.4 VISISIBILITY

2.3 OCEANAGRAPHIC DATA

2.3.2 TIDES

3.0 CONNECTIVITY & EXTERNAL INFRASTRUCTURES

3.1 ROAD LINK

3.2 RAIL LINK

3.3 POWER SUPPLY

3.4 WATER SOURCES

3.5 CONSTRUCTION MATERIAL

4.0 SURVEY & INVESTIGATION

4.1 BATHYMETRY

Page 3: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

4.2 BORE HOLES

5.0 COST ESTIMATES

5.1 GENERAL

5.2 ABSTRACT OF COST ESTIMATES

5.3 DETAILED COST ESTIMATE

6.0 DESIGN OF VESSELS

7.0 PORT FACILITIES & REQUIREMENT

7.1 BUILDINGS

8.0 PORT CRAFTS & AIDS TO NAVIGATION

8.1. TUGS

8.2 PILOT VESSELS

8.3 CHANNEL MARKER BOUY

8.4 LEADING LIGHTS

8.5 TRANSIST LIGHTS

9.0 DESIGN BASIS REPORT

10.0 CONCLUSION & RECOMMENDATIONS

Page 4: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

1.0 INTRODUCTION

1.1 GENERAL:-

The Regional works Commander, Coast Guard region (NW), Gandhinagar

intended to construct Coast guard station at vadinar, Gujarat. The Construction of

Coast guard Jetty at OOT Vadinar is to be carried out as a deposit work by Kandla

Port Trust. Kandla Port Trust has accepted the proposal for the constructing of a

Jetty length 175 m along with approach road to the jetty of length 275 m. IIT

Madras, Chennai agreed to prepare Detailed Project Report (DPR) and Feasibility

study for the project. The site visit was made on 16th and 17th June 2014 with the

officials of Indian Coast Guard and Kandla Port Trust. On basis of the

requirements and specification of Indian Coast Guard –Vadinar the Detailed

Project Report for construction of Coast guard Jetty at OOT Vadinar is prepared.

1.2 SITE LOCATION & PORT LIMIT :

Vadinar is small coastal town located in Jamnagar district of the state

of Gujarat, India. The offshore oil terminal of the Kandla Port Trust (K. P. T.) is

located in Vadinar and contributes in a large way to the total earnings of this

major port. Vadinar is now notable due to the presence of two refineries which are

close by - one promoted by Reliance Industries and the other by Essar Oil Ltd.

A salt production unit is located in Vadinar. The famous Narara Island, which is

part of Marine National Park, is situated 7 kilometers away from town. Two

single-buoy moorings (SBM) of the Kandla Port Trust offshore oil terminal of

the Indian Oil Corporation are located at this port along with a similar buoy of the

Essar refinery.

Page 5: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

The proposed Coast Guard Jetty is subjected to the Kandla Port Trust

conservancy. The Jetty is located at pathfinder inlet creek, lies between the two

islands, Kalubhar Tapu and Narara Bet. The port limit on the land side lies 2 km

from Nichoni creek, situated 3 km towards south from the proposed Coast Guard

Jetty. The port limit on the sea side lies at the 30 m contour, situated 5.9 km

towards north from the proposed Coast Guard Jetty. The port limit exist from

22°29'11"N - 69°39'7"E , 22°29'14"N - 69°41'9"E in the sea side and 22°25'25"N-

69°39'33"E , 22°25'25"N - 69°41'11"E at the land side.

Figure: 1- Port Limit of Proposed Coast Guard Jetty at Vadinar

Page 6: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

2.0 SITE CONDITION

2.1 Metrological Data

In 1988, India Meteorological Department introduced the 16 parameter power

regression and parametric models and started issuing forecasts for the southwest

monsoon rainfall over the country as a whole. IMD introduced new statistical

forecasting system based on ensemble technique for the south-west monsoon

season (June to September) rainfall over the country as a whole. The local area

forecast station is situated at Rajkot which takes care of all kind of Meteorological

functions.

2.1.1 CLIMATE

Vadinar has a hot semi-arid climate, there are three defined seasons. The summer

season lasts from March to May and is extremely hot, humid, but dry. Rainy

season with extremely erratic monsoonal rainfall that averages around 630

millimeters. Tropical cyclones sometimes affects the region during this period.

The winter season is from October to February remains hot during the day but has

negligible rainfall, low humidity and cool nights to be by far the most comfortable

time of year.

Page 7: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

Page 8: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

2.1.2 TEMPERATURE

The temperature at vadinar is similar to the temperature recorded at Jamnagar, the district head

average high temperature recorded is 320C and average low temperature recorded is 26

temperature at all seasons is given in the table 1.

TABLE 1: TEMPERATURE DATA

TEMPERATURE DATA FOR JAMNAGAR ( 48 kms from Vadinar)

Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Record high °C (°F)36

(97)

38

(100)

44

(111)

45

(113)

47

(117)

46

(115)

40

(104)

39

(102)

41

(106)

43

(109)

Average high °C (°F)26.5

(79.7)

28.8

(83.8)

33

(91)

35.6

(96.1)

36.4

(97.5)

35.9

(96.6)

32.3

(90.1)

31.5

(88.7)

32

(90)

34.5

(94.1)

Daily mean °C (°F)18.6

(65.5)

20.9

(69.6)

25.4

(77.7)

28.6

(83.5)

30.9

(87.6)

31.4

(88.5)

29.2

(84.6)

28.4

(83.1)

27.9

(82.2)

28

(82)

Average low °C (°F)10.7

(51.3)

13

(55)

17.8

(64)

21.6

(70.9)

25.4

(77.7)

27

(81)

26.2

(79.2)

25.4

(77.7)

23.9

(75)

21.6

(70.9)

Record low °C (°F)1

(34)

1

(34)

9

(48)

13

(55)

18

(64)

20

(68)

10

(50)

12

(54)

16

(61)

11

(52)

Precipitation mm (inches)1

(0.04)

1

(0.04)

0

(0)

0

(0)

5

(0.2)

61

(2.4)

213

(8.39)

126

(4.96)

64

(2.52)

11

(0.43)

Source #1: Climate-Data.org (altitude: 23m),[9] Voodoo Skies for record temperatures[8]

Source #2: Jamnagar Weather[dead link]

Page 9: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

2.1.3 RAINFALL AND VISIBILITY

The Rainy season with extremely erratic monsoonal rainfall that averages around

630 millimeters. The Tropical cyclones sometimes affects the region during this

period. The following table shows the rainfall data of Jamnagar, district head

quarters located very near to vadinar. Throughout the year the visibility is good,

as the fog is infrequent at the sea in all seasons. However a minimum of 10 to 15

days can be considered as foggy days.

Table 2: Rainfall table

RAINFALL TABLEPERIOD: 1971-2010

Month

MeanTemperature(oC)

MeanTotal

Rainfall(mm)

MeanNumber of Rainy

Days

Mean Number of days with

DailyMaximum

DailyMinimum

Thunder FOG

Jan 28.2 12.3 1.0 0.1 0.1 1.6

Feb 30.4 14.3 0.7 0.2 0.2 2.3

Mar 35.1 18.5 0.1 0.0 0.0 1.8

Apr 38.7 22.2 1.4 0.2 0.4 0.6

May 40.2 25.0 4.8 0.1 1.3 0.1

Jun 37.5 26.2 115.2 5.0 4.6 0.0

Jul 32.9 25.2 215.6 8.7 2.8 0.0

Aug 31.6 24.2 127.1 7.2 1.9 0.1

Sep 33.5 23.4 78.3 4.4 2.8 0.5

Oct 35.7 22.2 21.1 1.6 1.7 2.3

Nov 32.9 18.3 10.9 0.6 0.4 0.9

Dec 29.6 14.2 0.5 0.1 0.1 0.7

Annual 33.9 20.6 576.6 28.3 16.3 10.9

Page 10: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

2.2 OCEANAGRAPHIC DATA

Oceanographic data of vadinar is obtained by several studies conducted by Indian

Oceanographic Data Center in and around coast of Jamnagar, Okha and Dwaraka. The

data’s are classified as Sea water temperature, salinity tides, wind, wave, current, sea bed

level and they are as follows

2.2.1 SEA WATER TEMPERATURE

Actual sea surface water temperatures close to shore can vary by several degrees

compared with these open water averages. This is especially true after heavy rain, close

to river mouths or after long periods of strong offshore winds. Offshore winds cause

colder deep water to replace surface water that has been warmed by the sun. The average

mean sea water temperature is 280 C at vadinar coast.

Figure 2: Sea temperature range for the coast of vadinar

Page 11: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

2.2.2 TIDE

Tide timetable for vadinar is generated in local time in India. Tidal variation: (+)5.72 m to( -) 0.11m.

Sl.no Description Level (m)1. Highest high Tide level (+) 5.722. Lowest low Tide Level (-) 0.11

Table 3:- tidal chart for Vadinar

3.0 CONNECTIVITY & EXTERNAL INFRASTRUCTURE:

3.1 CONNECTIVITY

3.1.1 Road Connectivity:

The proposed Coast Guard Jetty is subjected to the Kandla Port Trust conservancy,

which has an existing offshore oil terminal is well connected to the state highway.

The existing approach road to the proposed site is adjacent to the four-lane state

highway (SH-6).

3.1.2 Rail Connectivity

The nearest rail connectivity to the proposed Coast Guard Jetty is Modpur Railway

Station, which is situated 32 kms from proposed site. Jamnagar a major commercial

junction is 47 km for the proposed Coast guard Jetty.

3.1.3 Air Connectivity:

The airport is situated near Jamnagar and 39 kms away from the proposed coast

guard jetty. Jamnagar has a aerial connectivity from Mumbai and Delhi.

Page 12: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

3.2 EXTERNAL INFRASTRUCTURE

3.2.1 POWER SUPPLY

The proposed coast guard jetty is situated under the Kandla Port Trust

conservancy which has which has an existing offshore oil terminal is well

equipped with proper power backups. Further to the existing power supply

additional requirements are cited below are required. K.P.T shall provide the

Power supply for the proposed jetty purely on rental basis.

TABLE 4: POWER SUPPLY REQUIREMENTS

Sl.No Description Oty

1 2000KVA Distribution transformer 2

2 Distribution Transformer Substructure materials

1

9.14 Mtrs Special pole

Base plate

AB Switch

Post type Insulator

HG Fuse set

Lightening Arrestor

Stay set

Guy insulator, Jumpring, materials, Bolts and Nuts, Concreting Etc

Page 13: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

TABLE 5: POWER SUPPLY REQUIREMENTS

3.2.2 WATER SOURCES

The water supply to vadinar is tapped from Sasoi Dam which is situated 43 km from the site,

not only satisfies the water supply to residence but also fulfills the requirements of industries

situated nearby. This acts as the vital water resource. K.P.T shall provide the water supply for

the proposed jetty on a rental basis / free of cost depending on its administrative policies.The

water demand for the proposed Coast Guard Jetty has been worked out in the Table 6 below

for next 25 years, depending on the requirement demand may increase. However a pumping

station shall be provided for to the transfer Raw & Portable water.

TABLE 6: Estimated Water Demand at Proposed Coast Guard Jetty

Sl.No Description Oty1 Armored Aluminum cable Shall be decided while detailed design.

2 Armored Aluminum cable Shall be decided while detailed design

3 Pillar boxes with fuse arrangement of Fiber reinforced plastic

Shall be decided while detailed design

4 Pillar boxes for bays with MCB/Plug of fiber reinforced plastic

Shall be decided while detailed design

5 Lugs, Gland, Termination, Joint Kits Laying Etc., Shall be decided while detailed design

6 Requirement of Distribution & Junction box Shall be decided while detailed design

Page 14: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

Consumer Demand (litres/day)

Long Term Year 2040

A. Raw Water 20,000

B. Potable Water

Port Personnel 10,000

Port Users and Canteen 15,000

Ship Supply 15,000

Total Potable Water Demand (Litres/ day) 40,000Total Potable Water Demand (Litres/ day) 60,000

Page 15: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

4.0 SURVEY AND INVERSTIGATION

4.1 BATHYMETRIC SURVEY

The bathymetry survey was conducted by Marine Department (OOT Vadinar) of Kandla Port Trust

28/11/2010 to 1/12/2010. The bathymetry survey was conducted at Pathfinder Inlet which is situated in between two

islands, Kalubhar Tapu and Narara Bet. The Approach channel is of 23 m in depth and turning circle is

The bathymetry near the proposed landing jetty is around 14.0 m in depth. IIT Madras insists that there should be fresh

bathymetry conducted at the time of detailed design.

Figure 3: bathymetry chart of proposed coast guard jetty

Page 16: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

4.2 SOIL INVERSTIGATION REPORT:

Soil investigation was conducted by Kandla port trust in the year 1989 for the Oil Berthing Jetty. A total of 22 bore holes where bored at the site. The bore hole data has been furnished by Kandla Port Trust (vadinar). The key plan of bore hole data is mentioned below Fig: 4

Figure 4: Key plan of boreholes for the Proposed Coast Guard Jetty

Page 17: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

n value of the soil investigation shows that it 37 and its attained at 60 feet.

Page 18: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

A fresh soil investigation should be conducted near the proposed jetty at an interval of 25 m, with a minimum of 15 boreholes. The bore holes should be both marine and land bore holes. The soil investigation results shall be in both soft and hard copy satisfying the IS codal requirements.

Page 19: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

6.0 DESIGN OF SHIPS

The Design of ships are considered as per the requirements given by Indian Coast Guard Vadinar. They are as follows:

Table 7 : Design of ships for the Proposed Coast Guard Jetty

The B

Berth shall be designed for a maximum displacement of 3300 Tons.

Types Of

ShipDT in “T”

Length in

“m”

Width in

“m”

Draught in

“m”

PCVs 3300 94 15.5 4.5

AOPVs 2230 105 12.9 3.6

FPVs 306 48.1 7.5 2.0

IPVs 200 44 7.4 2.3

Description Vessel size with DT

Displacement 3300 Tons

Draught 4.5m

Overall Length 94m

Width 15.5m

Page 20: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

7.0 LAYOUT OF THE PROPOSED COASTGUARD JETTY:

The proposed Coast Guard Jetty is subjected to the Kandla Port Trust conservancy. The

Jetty is located at pathfinder inlet creek, lies between the two islands, Kalubhar Tapu

and Narara Bet. The port limit on the land side lies 2 km from Nichoni creek, situated 3

km towards south from the proposed Coast Guard Jetty.

Figure 7: General Layout for the Proposed Coast Guard Jetty

Page 21: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

After the joint inspection with the all above officials from K.P.T, Coastguard, Essar

and IIT madras the location was finalized. The proposed coastguard jetty would be

20m from the existing damaged Essar Jetty towards North. Area to be reclaimed is

50 m length towards the sea from the entrant point of the proposed Jetty (outer

boundary of Essar reclaimed area and 100m of length parallel to shoreline (towards

North), which are to be reclaimed for housing the proposed infrastructure facilities

such as Guard room , Power house, Security check, Arms storage (on war foot basis)

and Parking space.

One existing common mud road (15 m width) of length approximately 300 m from

KPT complex exists which is maintained commonly by both K.P.T & Esaar. KPT &

Essar accepted to use this mud road as approach to the proposed coast guard jetty.

Another approach road can also be formed from the backup area of K.P.T. adjacent

to back up area of Essar.

Page 22: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

8.0 PORT FACILITIES

The buildings catering to port, users, amenities etc are placed close to the gate.

They shall be planned as a multiple complex because of their non-related

functions The parking area is located towards the north west of proposed jetty

and it is envisaged that this shall primarily serve as waiting bay and movement

will be regulated into operational area. Workshop stores, maintenance bay and fire

station are suitably located near the p a r k i n g a r e a .

8.1 Buildings

The estimated building areas required for the proposed coast guard jetty areprovided in Table Below:

Table 8: Estimated Building Areas

a. Gate Complex 300 sqm

b. Administrative Building & PortOperations Building

1800 sqm

c. Electrical Sub Stations & Fire station 500 sqm

d Maintenance Work Shop cum Central Stores and Other Misc. Buildings

900 sqm

Total 3500 sqm

The general specifications for all the building works shall be as follows:

• The work shall be carried out as per General Technical Specifications for

Building Works of the State of Gujrath or C.P.W.D.

• The minimum grade of reinforced concrete shall be M 20 conforming to

IS: 456-2000 for columns, foundations and superstructure unless

otherwise specified.

• The reinforcement shall be high strength deformed bars of grade Fe415

conforming to IS: 1786 - 1985.

• All structural steel shall conform to IS: 226/IS: 2062 - Grade A.

• Proper Anti Corrosive Treatment (ACT) shall be done for the

reinforcement before placing.

• Construction joints shall be provided for buildings exceeding the length of

40m.

Page 23: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

• Loose Pockets in foundations shall be removed and filled up with PCC mix

(1:4:8).

• Back filling shall be done with granular soil in layers not exceeding

200mm and each layer shall be well compacted as per specifications.

• All reinforcement shall be sheared only. Flame cutting is not permitted.

All bars shall be bent at normal temperature.

• The flooring shall be 40mm thick Kota stone polished, with under layer of

30mm thickness in cement concrete mortar 1:2:4, as per specifications.

• All outdoor paved areas shall be cement concrete 1:2:4 - 40mm thick

laid in one layer, finished with floating coat of neat cement as per

Technical Specifications.

• All woodwork shall be of teak wood.

9.0 Tugs and Port Crafts.

The following port crafts are proposed for marine operations:

9.1 Tugs

The main activity of harbour tug is providing assistance to vessels entering /

leaving the harbour, turning of the vessel in the harbour and the berthing /

unberthing operations. The coast guard vessels are capable of self-berthing and

there is no need of tugs for berthing activity. However if required K.P.T shall

provide tugs on rental basis / free of cost depending on its administrative policies.

9.2 Pilot-cum-Survey Boats:

Pilot boats transfer pilots to and from the incoming / outgoing vessels. It is

recommended to provide one all weather type pilot launcher. The pilot launch

should be a twin screw with 15 to 20m overall length and of steel construction. The

speed range shall be 15-20 knots. This pilot launch will be provided with survey

equipment and it can be used for hydrographic surveys and for buoy lights

maintenance. It is observed that K.P.T has already deployed Pilot-cum-Survey

Boats &it is recommended to use those boats, if necessary one Pilot-cum-Survey

Boats shall be engaged specifically for Coast guard if only the traffic for existing

K.P.T berth is high.

Page 24: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

9.3 Channel Marker Buoys

The Channel marker Buoys marks are a pair of markers fixed a Channel Marker

Buoys (B1 & B2) at the either side of approach channel such that the vessel has a

clear view of the approach Channel.

Type - FRP

(3m dia)

Day mark - Single Green, Cone type

(Starboard buoy) Single Red, Can type (Portside buoy)

Radar reflector -

Fitted

Light characteristics - Fl G 3s 2m (star board

buoys)

Fl R 3s 2m

(portside buoys)

LED 20W

Halogen Lamps.

Power - Solar plus backup battery for optimum

autonomy. Anchoring arrangement - with 32mm diameter chain and 3.0

T anchor weight.

Since, it is observed that the existing K.P.T jetty and Essar jetty are operational,

the existing buoys are sufficient; the coast guard vessels shall use the existing

facilities.

9.4 Leading Lights / Lines

It is necessary to mark the centre line of the channel with leading lights to ensure

safe day and night navigation of vessels visiting the port.

The leading lines may meet the following

criteria: Useful range -

Navigation channel

Visibility range - 20 nautical miles

Page 25: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

The Leading lines and Leading lights are designed in accordance with IALA

Guidelines and recommendations and the details are as follows:

Height of Front Leading light (FLL) above CD -

12m Height of Rear Leading light (RLL) above

CD - 20m

Day mark - As per IALA Guidelines

Light Characteristics - Front Light Fl Y 1s Rear Light Occ.Y

3s

The leading lights will be controlled by a sun-switch to ensure that the lights

operate only during darkness or bad visibility. Power supply will be provided by

batteries, to be recharged by solar panel systems mounted on the supporting

structure, and/ or by power supply from the port distribution system. The

battery banks shall be sized to ensure 24 hours continuous operation of the lighting

system. Since, it is observed that the existing K.P.T berth has sufficient and well

maintained leading lights that can be utilized by coast guard vessels.

9.5 TransitLights

One set of transit lights are proposed to be provided, which will allow the ship to

be able to align with the centre of the turning circle after entering the harbour

basin. The details of these transit lights are as follows:

Transit Light Towers will be built of Concrete / Steel framework. Since these facilities are provided by K.P.T, coast guard vessels shall utilize the same.

Page 26: DETAILED PROJECT REPORT FOR …environmentclearance.nic.in/writereaddata/Online/TOR/07...requirements and specification of Indian Coast Guard –Vadinar the Detailed Project Report

Detailed Project Report for Dept of Ocean Engineering Construction of Coast guard Jetty at OOT Vadinar IIT Madras

[Type text]

10.0 Conclusion and Recommendations:-

The Proposal for Construction of Jetty at off Shore oil terminal, vadinar has been

finalized as 175x 13m landing jetty and 275x9m approach jetty. The location of jetty

shall been on a reclaimed earthen structure of 60x 100m. The parking area shall

primarily serve as waiting bay and movement will be regulated into operational area.

The administrative building, port building and other amenities shall be in the

prescribed reclaimed area limits. This Detailed Project Report cum feasibility report

has been prepared on the basis of the data furnished by the client, observations on site

visit, considering IS codal requirements and client requirements, the construction of

Coast Guard Jetty and it’s allied infrastructure are feasible. The proposal and Cost

estimation proposed by IIT Madras are only for project feasibility and for obtaining

project grants. For execution of work a detailed design should be carried out, and the

cost estimate shall be based on the detailed design. IIT Madras strongly recommends

to conduct a fresh soil investigation near the proposed jetty and reclamation area at

the time of detailed design since the soil investigation data available are very old. A

fresh bathymetry shall also conducted at the approach channel and near the berthing

areas.


Recommended