DETAILS OF SUCCESSDESIGNING AND CONSTRUCTING GREEN
INFRASTRUCTURE TO MAXIMIZE PROJECT BENEFITS
Beyond the Basics Stormwater Management Conference
September 14, 2016
Dan Christian, PE, D.WRE
Tetra Tech
Sustainability Goals
• Triple Bottom Line
• Economic
• Social
• Environmental
• Goals like “14. Enhance
stormwater
management” are easy
• Look for synergistic
opportunities
• Green roof = energy
reduction
• Tree plantings = reduced
energy consumption, etc.
LID Process
• Identify Regulatory Needs
• Conduct Hydrologic and
Geotechnical Survey
• Protect Natural Features
• Use Drainage and Hydrology as
Design Elements
• Establish Clearing and Grading
Limits
• Reduce/Minimize Total and Effective
Impervious
• Select LID Practices
Design Criteria
• Water Quality Treatment Volume
• ~90% non-exceedance, ~1.0 inch rainfall
• Typically focus on runoff retention
• Channel Protection
• Purpose – maintain stable channel hydrology
• Typically designed for 2-year event (3.0 in)
• Commonly volume and peak flow control
• Municipal Sewer Conveyance
• Used to size sewer pipes and open channels
• 5 to 10-year events commonly used (3.7 - 4.2 in)
• Commonly sizing pipes for post-development peak flow
• Local Flood Control
• Manage local drainage to prevent problem flooding
• 25 to 100-year events commonly assumed (5.1 – 6.6 in)
• Commonly detention storage with peak flow limited to pipe capacity
Sizing
• How do you size these things for all the different criteria?
• Hand calculations
• Spreadsheets
• Dedicated hydrologic modeling software
• Calculating complete hydrographs is important
HSPF
WMS
PIHM
CUHP
IWFM
HydroBEAM
CWYET
Final Site Design
• Place practices at the appropriate locations
• Size practices to meet hydrologic design criteria
• Verify that geotechnical and drainage requirements have been met
• Complete designs such as finish details and notes
• Complete the site plans
BIORETENTION PROFILELet’s take a quick sidetrack and look at the typical components of a
bioretention system and example cross sections
Bioretention
Aggregate Reservoir
In situ soil
Choker Course
Planting Soil/Filter
Mulch
Surface storage
Underdrain
Swale - Small
Swale - Large
Parking Lot Swale
Bioretention Parking Lots
Bioretention at Building Sites
Linear Planter - Small
Linear Planter - Large
Planter Box Next to Building
Curb Extension
Neighborhood Scale
BIORETENTION DETAILSNow let’s look a little closer at the component details
Bioretention Engineered System
Soil Media
Temporary
Ponding Area
Cleanout
UnderdrainOverflow
Inlet
On-line
Off-line
Off-line
When full, water backs up on street
and flows down to catch basin
On-line
All runoff enters the bioretention
Outlet
Outlet
Inlet
• Sized to capture design flow
• Location and elevation
• Prevent clogging and sediment accumulation
• Guard against excessive inlet velocities
Inlets
Outlet and Overflow
• Water needs a way to get out
• In-line versus off-line
• Location and elevation
• Mulch and topsoil should
stay in
Outlets
Pretreatment
• Capture large sediment
(sometimes trash and debris)
• Prevent erosion
• Level weir wall
• Options
• Filter strips
• Grass channels
• Sumps
• Hydrodynamic devices
• Screens and baskets
• Design based on dynamic
settling and Stokes Law
Pretreatment
Primary Storage Area
• Level soil surface
• Encourage even
infiltration and
reduce erosion
Sloped Surface• Within each cell:
• Soil and aggregate are level
• Maximizes storage
• Promotes infiltration
• Between cells:
• Separating wall
• Overflow from one cell
cascades to next one
downstream
• Can be constructed as
continuous swale.
• System used for
conveyance, not just storage
• Reduced storage volume.
• Increased likelihood of
surface flooding
downstream.
Sloped Surface
Vegetation
• Water Uptake
• Stabilization
• Impeding Flow
• Filtration
• Infiltration
• Nutrient Uptake
• Toxin Uptake
• Pollutant Breakdown
• Plants for Stormwater Design : Species Selection for
the Upper Midwest, by D. Shaw and R.Schmidt, 2003.
• Plants for Stormwater Design: Species Selection for
the Upper Midwest, Volume II. By D. Shaw, T.
Randazzo, H. Johnson, R. Schmidt, B. Ashman, 2007.
Ideal Plants – Functional Perspective
• Deep rooting
• Climate and water adaptability
• Overall enhancement of soil infiltration over time
• Tolerant of pollutants
• Targeted pollutant removal
• Habitat value
• Lack of invasiveness
Transpiration Rates of Various Plants
Plant Name Plant Type Transpiration Rate
Perennial rye Lawn grass 0.27 in/day
Alfalfa Agriculture crop 0.41 in/day
Common reed Wetland species 0.44 in/day
Great bulrush Wetland species 0.86 in/day
Sedge Wetland/prairie species 1.9 in/day
Prairie cordgrass Prairie species 0.48 in/day
Cottonwood Tree (2 year old) 2-3.75 gpd/tree
Hybrid poplar Tree (5 year old) 20-40 gpd/tree
Cottonwood Tree (mature) 50-350 gpd/tree
Weeping Willow Tree (mature) 200-800 gpd/tree
Source: Plants for Stormwater Design Volume II by D. Shaw and R. Schmidt (ITRC 2001)
Plant Selection
Consider maintenance
Public PerceptionUnderstanding the “human” side of
new forms of green infrastructure
for Detroit vacant propertieshttp://graham.umich.edu/media/pubs/Det
roit-Green-InfrastructureFactsheet_0.pdf
Cues to Care• Defined edges
• Mowing lawn panels or strips
• Flowering plants, colorful trees,
showy flowers
• Massing and structure
• Trimmed shrubs, plants in rows,
linear planting designs
• Bold patterns
• Color composition
• Wildlife feeders and houses
• Fences, architectural details, lawn
ornaments, pathways
Soil• A special or engineered soil
specified by the particular practice
• Chosen for specific porosity –
infiltration of stormwater
• May have special characteristics to
treat or absorb nutrients and other
pollutants
Soil
• Light fluffy soil for
vegetation
• Avoid excessive
compaction
• Often specialized
• May reuse soil with
amendments
Example Mixesa) 60-70% sand, 15-25% topsoil, 15-25% organic matter (good for growing plants, likely to
leach nutrients)b) 70-85% sand, 15-30% organic matter (likely to leach nutrients, dries out quickly)c) 85-88% sand, 8 to 12% fines, 3-5% organic matter (fines sorb more dissolved
phosphorous and metals, dries out quickly)d) 60-75% sand, min. 55% total coarse and medium sand, <12% fine gravel less than 5 mm,
2-5% organic matter (best for pollutant removal, moisture retention and growth of most plants)
Soil Characteristics
• Porosity: void space of soil
(space for water)
• Infiltration: movement of water
through soil
• Field Capacity: proportion of void
space that stays wet due to
surface tension (i.e. after water
drains by gravity)
• Wilting Point: point at which
plants can no longer withdraw
water fast enough to keep up
with transpirationSource: FISRWG
Infiltration Capacity
• Dry Soils, Little or No Vegetation
• Sandy soils: 5 in/hr
• Loam soils: 3 in/hr
• Clay soils: 1 in/hr
• Dry soils with Dense Vegetation
• Multiply by 2
• Saturated Soils
• Sandy soils: 1 to 4 in/hr
• Loam soils: 0.25 to 0.50 in/hr
• Clay soils: 0.01 to 0.06 in/hr
Source: Rawls, W.J., D.L. Brakensiek, and N. Miller, “Green-Ampt Infiltration Parameters
from Soil Data” J. Hydr Engr. 109:62, 1983), EPA SWMM 5 Users Manual, and FISRWG
42
POROUS PAVEMENTS
Porous Pavements
Aggregate storage
In situ soil
Filter coarse (as required)
Pervious Pavement
Geotextile
Underdrain
Choker coarse or setting bed (as required)
Porous Pavements
Source: American Concrete Pavement Association, 2006
Typical system with underdrain Rock trench along pavement edge
Open trench along pavement edge Rock trench extending beyond pavement
Asphalt
• Installed with standard HMA paving
equipment and no special training
• Mix Design is required
• Binder Content 5.0 - 6.5%
• Air Voids ≥ 18%
• Drain down ≤ 0.3%
• Evaluate for Moisture Susceptibility
• Typical cross-section
• 2 to 4-inch asphalt layer
• Choker course, 1 to 2 inches thick
composed of 0.5-inch diameter stone
• Aggregate subbase, thickness varies
Porous Asphalt Pavements for Stormwater
Management: Design, Construction and Maintenance
Guide. Information Series 131. National Asphalt
Pavement Association (NAPA). 2008.
Concrete
• Pervious designed as regular concrete pavement, but has lower strength• Ranges from 400 psi to 4000 psi
• Strength decreases linearly as void ratio increases
• 15% to 20% void ratio can result in 7-day compressive strengths of 2900 to 3300 psi
• ACPA PerviousPave software for design www.acpa.org/perviouspave/
• Most “car traffic only” pavements are 6 inches of pervious concrete
• Use certified professionals (list available on nrmca.org)
• Water content is critical to success
• Cover during curing
Illinois Ready Mixed Concrete Association, Pervious Concrete.
http://www.irmca.org/site/page23.aspx
National Ready Mixed Concrete Association. Pervious Concrete.
http://www.perviouspavement.org/
FHWA www.fhwa.dot.gov/pavement/concrete/pubs/hif13006/index.cfm
Other Aggregate Based Paving Systems
• Flexi®-Pave (kbius.com)
• Filterpave® (http://filterpave.com)
• Glass (recycled) or aggregate
• elastomeric binder
• PorousPave
(www.porouspaveinc.com )
• Recycled tires, aggregate and
urethane binder
• Sidewalks, driveways, play areas,
parking lots
• Gravel Driveway
• and many more…
Open-Jointed Paving Blocks
• Water drains between pavers
• Concrete and clay materials
• Typical cross-section
• Paver stone
• Bedding course 1 to 2 inches thick,
typically ASTM No. 8
• Aggregate subbase, thickness varies,
typically ASTM No. 57
• Edge restraints are required
Interlocking Concrete Pavement Institute
www.icpi.org
Brick Industry Association
www.gobrick.com
Open-Celled Paving Grids
• Similar design and installation as the open-jointed paving blocks
• Pavers contain large openings
• Voids filled with various materials
• Concrete blocks
Plastic Geocells and Porous Turf
• Various manufacturers
• Vertical load supported by honeycomb structure
• Void space typically filled with granular material
• May be vegetated
Working on slopes
• Pervious concrete successfully
used on 16% slopes
• Asphalt surfaces <= 5% (NAPA
recommended)
• Check Dams or Soil Berms
• Terrace the bottom
COMMON DETAILSBioretention and
Porous Pavement
working from the bottom up
Supported Sides
Supported Sides
• Compact materials under
sidewalk and roads
• Light fluffy soil in bioretention
Aggregate Storage
• Can be used to increase storage
volume
• Open graded aggregate
• Load bearing
• Crushed concrete
• increases pH for years
• impedes vegetation growth
• Steffes R., Laboratory Study of the
Leachate From Crushed Portland
Cement Concrete Base Material, Iowa
DOT. MLR-96-4. September 1999.
Aggregate
• Water storage reservoir
• 30 to 40% void space
• Level bottom surface to
promote even infiltration
Other Types of Storage
• Manufactured
devices
• Plastic and
CMP arches
• Pipes
• Precast
concrete boxes
• Etc.
Filter or Choker Layer• Challenges
• Often specified wrong
• Common failure point of system due to clogging
• Information Needed• Grain size analysis of in situ soil
• Required drainage rates (permittivity of filter)
• Geotextiles (filtration, separation, stabilization, permanent erosion control, and silt fence)
• Aggregate Filter
• 𝐷15, 𝐶𝑜𝑎𝑟𝑠𝑒 𝑆𝑢𝑏𝑙𝑎𝑦𝑒𝑟 ≤ 5 ∗ 𝐷85, 𝑆𝑒𝑡𝑡𝑖𝑛𝑔 𝐵𝑒𝑑
• 𝐷50, 𝐶𝑜𝑎𝑟𝑠𝑒 𝑆𝑢𝑏𝑙𝑎𝑦𝑒𝑟 ≤ 25 ∗ 𝐷50, 𝑆𝑒𝑡𝑡𝑖𝑛𝑔 𝐵𝑒𝑑
• AASHTO Standard Specification for Geotextile Specification for Highway Application. M 288-06. 2011.
• Departments of the Army and the Air Force. Engineering Use of Geotextiles. TM 5-818-8, AFJMAN 32-130. 1995.
• Franks, C., A. Davis, and A. Aydilek. Geosynthetic Filters for Water Quality Improvement of Urban Storm Water
Runoff. ASCE Journal of Environmental Engineering. 2012.
• US Department of Agriculture, NRCS National Engineering Handbook Part 633. Chapter 26 Gradation Design of
Sand and Gravel Filters. 1994
Choker Layer
• Separation layer
between soil and
aggregate reservoir
• Material may be
aggregate or geotextile
Underdrain
• Optional based on infiltration capacity of in situ soil
• Purpose to ensure drainage
• 4-inch diameter or larger
• Types• Rigid PVC
• Flexible HDPE
• SmartDrain(www.smartdrain.com)
• May be paired for redundancy
• Clean-out fittings
• 45 deg bends
• Anti-seep collar, trench dam, clay dam
• Outlet is commonly used to control allowable discharge rate• Orifice end plate
• Valve to allow for flow adjustments
• Upturned elbow• Enhance nutrient removal
• Increase retention depth
Underdrain
• Location and elevation
• May connect to valve
Bioretention Areas(Determine BMP Function and Configuration)
Underdrain Outlet
Trench Dam, Anti-seep Collar, Clay Dam
• Keep retained water where
intended
• Water follows path of least
resistance
• Use along underdrain pipes
• Clay (Bentonite), plastic, concrete,
steel, etc.
Anti-seep collar
Photo: Liberty Nature Preserve
Anti-seep collar
Photo: Liberty Nature Preserve
Source:
The bottom• Level bottom preferred
• On slopes terrace the bottom or
use check dams / baffles
• In situ soil below stormwater
practices typically do not (should
not) be compacted before placing
aggregate and/or soil overtop
• Loosen and scarify soils
• Before planting
• Before placing aggregate or soil layer
Bottom
• Level bottom surface to
promote even infiltration
Hydraulic Restriction Layer
• 30 mil PVC Liner (ASTM D-7176)
• Concrete
• Clay (Bentonite)
Impermeable Liners
• Groundwater Recharge Zone
• Soil contamination is expected or present
• Karst geology presents risk of sinkhole formation
• Runoff from a stormwater hotspot
• Within 100 feet of a water supply well or septic drain field
• Within 10 feet of a structure/foundation
• Infiltrated water may interfere with utilities
• Requires an underdrain
WRAPPING UP DESIGN
Layout the BMPs
Locate Utilities
Common Design Mistakes
• Not understanding the tributary area (size and surface coverage)
• Inadequate inlet
• Sloped surface resulting in reduced infiltration and erosive velocities
• Wrong mulch, floats away and clogs the outlet
• Lack of pretreatment
• No soil tests
• Poor plant selection
• Overly complex
• No maintenance plan
• Wrong geotextile specified
CONSTRUCTIONPlanning
Typical Construction Sequencing
• Preconstruction Meeting
• Planning – schedule, RFIs, submittals,
• Site Preparation – major demolition and
excavation
• Concrete Work
• Hydraulic Controls – hydraulic restrictions,
drainage layer and underdrains
• Bioretention - media barrier, soil,
vegetation, mulch, and energy dissipation
• Porous pavement – aggregate and
pavement
• Testing
Construction Sequencing
Roadside rain garden construction
followed by adjacent retaining wall
construction
• Spoils from retaining wall construction
should not have been placed on rain
garden
• Protection of rain garden should have
occurred
• Improvement to sequence possible?
• Identified at preconstruction meeting?
Construction Planning
• Expect more Requests for Information
• Submittals commonly requested for:
• Aggregates
• Geotextiles
• Liners
• Soil media
• Mulch
• Vegetation
• Construction specifications should be specific
• Verify available materials – up to one month
lead time
• Order and stockpile materials where possible
Organic Matter
Material
Aged bark fines, hardwood chips,
leaf litter, or similar plant-derived
organic material. Studies have also
shown newspaper mulch to be an
acceptable additive (Kim et al.
2003; Davis 2007). Organic matter
should not include animal manure
or by-products.
Infiltration Rates 0.5 to 6 in/hr (1-2 in/hr
recommended for comprehensive
pollutant treatment and hydrologic
benefit; Hunt et al. 2012)
pH6 to 8
Cation Exchange
Capacity (CEC)Greater than 5 milliequivalents
(meq)/100 g soil
Phosphorus Total phosphorus should not
exceed 15 ppm
Substitutions and Certifications
• Check and certify before accepting
• Shop drawing submittals for all critical
components
• Watch out for substitutions (e.g. plants)
Is it washed? As-Built Certification
Drainage Area• Practices are sized for the drainage area
• Know the intended drainage area
• Field changes may necessitate design changes
Tributary Drainage Area
Bioretention
Curb Extension
Construction Equipment
75
Effects of
Compaction on
Infiltration Rates
• Decreased infiltration
• Decreased root growth
• Increased runoff
Source: Pitt R., S.E. Chen, S. Clark
75
2.40.260All other clayey soils (compacted and dry, plus all wetter conditions)
1.59.818Noncompacted and dry clayey soils
1.31.439Compacted sandy soils
0.41336Noncompacted sandy soils
COVAvg Infil (in/hr)
Number of tests
Source: R. Pitt, S.E. Chen, S. Clark
75
CONSTRUCTIONSoil Erosion and Sedimentation Control
Soil Erosion during Construction
• Keep soil erosion sediment off
• Aggregate storage reservoirs
• Planting soil
• Permeable pavements (all types)
• Bioretention is designed to work AFTER
construction is completed and the
watershed is STABLE
• Do not install if exposed soil is obvious
or surrounding drainage is not stabilized
• Use standard erosion and sedimentation
control measures to stabilize disturbed or
potentially erosive surfaces for onsite
and potential offsite sources
Not Protected Protected
Protect BMPs During Construction
December 09, 2014 LID Operation and Maintenance 79
CONSTRUCTIONGrading, Demolition, Excavation and Utilities
Concrete Work
Site Grading
• Protect Key Hydrologic
Features
• Areas of natural hydrologic
function
• Possible areas for
infiltration
• Establish Clearing and
Grading Limits
• Define the limits of clearing
and grading
• Minimize disturbance to
areas outside the limits of
clearing and grading
Footings, Retaining Walls, Structures
Inlets and Outlets
CONSTRUCTIONSubgrade Preparation
Protect Subgrade for Infiltration
• Consider leaving last 6 inches of soil in the base
• Finish excavation after concrete work complete
• Recommended in areas where fine sediment can clog the subgrade
NEVER Compact the Subgrade with Heavy Equipment
Soil Conditioning
Soil Conditioning• Create an environment where water can
infiltrate
• Favorable environment for plants to succeed
• Begins to restore soil structure & ecology
Source: Tyner 2009
Subgrade
compaction
Minimum
subgrade
treatment
Specification
Low Scarification Loosen the top 6 to 9 inches of subgrade using the teeth of an excavator
bucket (or comparable).
Low-Medium Ripping Using a subsoil ripper or metal bar, rip the subgrade to a depth of 9 to 12
inches, every 3 feet (on center).
High Trenching Excavate 1-foot-deep by 1-foot wide trenches into the subgrade, every 6
feet (on center). Fill the bottom of the trench with one-half inch of coarse
sand, and top off trench with washed aggregate (No. 57 stone or
comparable).
Infiltration Testing• During Construction
• Infiltration rate of in situ native soil
• Bottom of excavation
• Purpose: if not testing during design phase, provides
measured infiltration capacity of soil
• Immediately After Construction
• Purpose: baseline measurement for future comparisons
• Vegetated Areas
• Permeable Pavements
CONSTRUCTIONHydraulic Controls
Dams, baffles, hydraulic restriction layers, reservoirs, underdrains
Hydraulic Restrictions
Underdrain
• Pipe orientation
• Clean washed aggregate
• Pipe material and bends (45 deg)
• Trench dam / anti-sep collar
• Connections
Failure 1: Slotted pipe
with dirty drainage
aggregate
Failure 2: ‘Burrito-
wrapped’, 2 layers over
top, slowed flow
Photo credit: Andy Szatko
Underdrain Connection
CONSTRUCTIONBioretention
Inlets
• Proper elevation grading is paramount
• Practice design, drainage area and runoff volume are intricately linked
• Field changes may require design changes
• Inlets must let water in
Pretreatment
Inlet from street lower than
weir around sediment trap
Level Spreader
Weir not constructed level,
concentrates flow
Bioretention Soil
• Inspect Media
Bioretention Soil Placement
• Install in 6 to 12 inch lifts. Scarify the top of each lift before placing next lift.
• Compact each lift
• Soak with water, gently tamp or boot
• 80 to 85%
• Compaction Test Methods
• Bulk Density. Critical bulk density are different for each soil texture.
• Standard Proctor ASTM D 698. Readings are impacted by soil organic matter. Root growth impeded at 90%.
• Penetration Resistance Method. Not very accurate. 75-250 psi target. Root growth impeded at 400 psi..
• Where travel over installed soil is unavoidable, limit paths and scarify soil driven on
• If soil placed loose expect about 10% consolidation
Bioretention Surface Sloped
Unprotected During Construction
Notice drift on outlet
because surface is clogged
Infiltration Testing• During Construction
• Infiltration rate of in situ native soil
• Bottom of excavation
• Purpose: if not testing during design phase, provides
measured infiltration capacity of soil
• Immediately After Construction
• Purpose: baseline measurement for future comparisons
• Vegetated Areas
• Permeable Pavements
Storage Volume of Practice
• Drainage area equates to a volume of runoff
• Build practices to meet design volume
Category % of Design
Volume
% of Practices
in Category
Severely Undersized <-25% 28%
Moderately Undersized -25% to -10% 22%
Adequate -10% to 10% 17%
Moderately Oversized 10% to 25% 17%
Severely Oversized >25% 17%
Assessing the Accuracy of Bioretention Installation in
North Carolina (2011) B. Wardynski and W. Hunt.
Reference Elevation
• Fixed elevation
• Level
• Stable
• Grade from
• Intentional
• Maintenance friendly
CONSTRUCTIONPorous Pavement
Clean Washed Stone
Source: NCSU BAE
No. 57 No. 2
Aggregate
• Compact
• Surface graded smooth
• Angular not natural rounded
stone
Aggregate
• River rock
• Rolls
• Won’t compact
Transition Strip
Elevation
Pervious Concrete
• Inspect the mix when delivered
• Certified professional
• Test batch and panel
Pervious Concrete
Too wetToo dry
Pervious Concrete Placement
• Covered for 7 to 14 days to cure properly
Pervious Concrete Curing
Porous Asphalt
• Different mix design
• Same construction equipment
Wrong binder
Permeable Interlocking Pavers
• Setting bed
• Cut to fit
• Compact in place
• Fill joints
Washed No. 57 Stone
Pea Gravel
Pavers
Sequence
• Dirt can be removed
• Asphalt cannot
PARTING THOUGHTS
Michigan Ave, Lansing MI
• This garden holds the 25-year storm event
• 75% decrease in average annual runoff
• 2007
• Ultra-Urban
• 5-ft wide planter box style bioretention
• 30 bioretention gardens
• 7,631 square feet
• 4.1 acre tributary area
• 4 blocks, both sides
• ADA compliant
• Adaptable to community needs
Maine Mall Road, Portland ME
• 0.35 miles long
• AADT 16,750 vehicles per day
• Design hourly volume – 2412
• Percent heavy trucks – 5%
• Open graded friction course
• Asphalt treated permeable
pavement
• Reservoir stone 50 year storm
volume
• 2009
QUESTIONS AND
DISCUSSIONS
Daniel P. Christian, PE, D.WRESenior Project Manager, Water Resources