+ All Categories
Home > Documents > Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

Date post: 07-Apr-2018
Category:
Upload: rajat-jhingan
View: 221 times
Download: 0 times
Share this document with a friend

of 8

Transcript
  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    1/8

    Determinants of the cost

    ofInternational Projects

    &their Management

    byRajat Jhingan

    PGDM FT (08-10)

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    2/8

    Capital BudgetingCapital budgeting requires estimation of a projects

    incremental cash flows - which are determined by

    estimating worldwide cash flows with and without the

    project.There are two main methods of international capital

    budgeting, centralized and decentralized

    Centralized requires exchange rate forecasts

    Decentralized requires a local-currency cost of capital.

    The method a firm selects should depend on its

    comparative advantage in estimating each

    By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    3/8

    International Project : Objectives

    Shareholders wealth is created when return in the

    Present Value is more than Investment Cost

    Firm that could source funds internationally rather

    domestically will have lower cost of capital.

    Greater Opportunities to raise funds

    Positive NPVs

    APV Model given by Donald Lessard (1985)

    By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    4/8

    Determinants of cost of International Projects

    Cash flows

    Marginal corporate tax rate

    Operating cash flow

    Incremental revenues & operating costRestricted funds

    Concessionary loans

    WACC

    AdditionalTransfer Pricing Strategies, LicensingAgreements, Royalty Agreements

    By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    5/8

    ADJUSTED PRESENT VALUE Given by: Donald Lessard (1985)

    ValueAdditivity approach to capital budgeting.

    Each cash flow is discounted at a rate of discount consistent with the

    risk inherent in the cash flow.

    Useful for:

    MNC for analyzing one of its domestic capital expenditure

    Foreign subsidiary of the MNC, a proposed capital expenditure

    from the subsidiarys viewpoint.

    A project may have a positive APV from the subsidiarys

    perspective and a negative APV from the parents perspective.

    The model recognizes that the cash flows will be dominated in a

    foreign currency and will have to be converted into the currency of

    the parent. By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    6/8

    Estimate Future Expected Exchange Rate

    It is required to Estimate Future Expected Exchange Rate in order toimplement the APV framework.

    PPP theory is helpful in Estimate Future Expected Exchange Rate.

    St = So (1+ d)t

    (1+ f) t

    St= future expected exchange rate

    T= no of years

    d= expected long run annual rate of inflation in the homecountry

    F= rate of foreign land

    So= current exchange rate

    By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    7/8

    Political Risk Centralized capital budgeting requires expected cash

    flows to be adjusted for political risk - not cost of

    capital.

    Foreign political risk is unlikely to be systematic to the

    risks of domestic shareholder portfolios.

    Sensitivity analysis is an alternative to calculation of

    exact political risk probabilities: solve for probability

    that sets NPV=0 and then ask whether its reasonable -

    if so, NPV is quite possibly negative.

    By: Rajat Jhingan

  • 8/4/2019 Determinants of the Cost of International Projects & Their Management by Rajat Jhingan

    8/8

    Thank You!!!!

    By: Rajat Jhingan


Recommended