Office of Environmental Services
April 2018
Guidance for Developing Purpose and Need
Addressing Transportation Problems by Identifying Needs
OES-Policy-April 2018
- 1 - | P a g e Guidance for Developing Purpose and Need April 2018
Table of Contents
Chapter Page #
Introduction 2
Legal Requirements 3
Linking Planning and NEPA 3
Importance of Purpose and Need (P&N) 4
Preparation and Development
When Does P&N Development Begin?
When is a P&N Required?
Who is Involved in P&N Development?
How is the P&N Formatted?
Why is Identifying Primary and Secondary Needs Important?
Need Element Definitions
4
5
5
6
7
10
12
Logical Termini and Independent Utility 17
Public Involvement 18
Points to Remember 18
This guidance replaces the ODOT-OES P&N Quick Guidance that was released on July 6, 2017
OES-Policy-April 2018
- 2 - | P a g e Guidance for Developing Purpose and Need April 2018
Introduction
This guidance is written for transportation
professionals, environmental specialists and project
managers that prepare and review Purpose and
Need’s (P&N) for ODOT projects. Furthermore, this
guidance is designed to ensure those involved in the
NEPA decision-making process and P&N development
are able to:
a) Recognize the importance of having a P&N
b) Identify at what point in ODOT’s Project
Development Process (PDP) a P&N is prepared
c) Identify transportation based needs
d) Identify Primary and Secondary Needs and how
that is key for integrating Performance Based
Project Development (PBPD) into the P&N
e) Provide a baseline to effectively develop,
evaluate and eliminate or advance alternatives
The P&N specifies the purpose as to why the project
has been initiated and identifies the transportation
needs (problems) to be addressed based on the
analysis of quantified data. The P&N for a project
must be established prior to the development of
alternatives and serves as a baseline in the
development, evaluation and elimination or
advancement of alternatives, including selection of
the preferred. The analysis conducted for the P&N
can be used to justify impacts and project
prioritization.
Identifying needs can be part of the overall
transportation planning process prior to a project
being programmed.
Initial transportation
planning studies and
technical reports prepared
by Local Public Agencies
(LPAs), Metropolitan
Planning Organizations
(MPOs), or others can be
used to establish a P&N
prior to programming a
project
Development of the P&N
can begin as early as the
initiation of NEPA studies
conducted as part of the
Planning Phase of ODOT’s
PDP
The P&N is based on
analysis of various data
sources that can include
traffic studies, crash
records, bridge/culvert
inspection reports or other
technical type documents
As the project advances
through the PDP the project
scope becomes more
refined, and as a result, the
P&N evolves
The P&N is not FINAL until
the environmental document
is approved
OES-Policy-April 2018
- 3 - | P a g e Guidance for Developing Purpose and Need April 2018
Legal Requirements
The P&N is a critical element of the environmental
process that is necessitated by the National
Environmental Policy Act of 1969 (NEPA).
The P&N is required documentation in accordance
with existing Council on Environmental Quality (CEQ)
regulations at 40 CFR 1502.13 (CEQ) and Federal
Highway Administration (FHWA) regulations at 23 CFR
771.111(f).
Based on the regulations above, the FHWA Technical
Advisory T 6640.8A directs State DOT’s to “identify
and describe the proposed action and the
transportation problem(s) or other needs which it is
intended to address.” The Technical Advisory
highlights factors that may be helpful in establishing
a project’s need that includes safety, transportation
demand and legislative mandates.
Linking Planning and NEPA
Initial planning activities and studies conducted as
part of the overall transportation planning process for
a project are sources of information that can be used
to develop a P&N. Detailed forecasts of vehicle miles
of travel, travel demand, highway and travel speeds,
traffic diversion, time of day characteristics, and
traffic accident rates are data that can be provided.
The overall planning process can also help estimate
the benefits and costs associated with highway and
transit projects when developing the P&N.
OES-Policy-April 2018
- 4 - | P a g e Guidance for Developing Purpose and Need April 2018
Importance of P&N
Establishing and defining the P&N is a necessary task
that is started as part of the transportation planning
process or begins as early as the initiation of NEPA
studies. The P&N is essential as it plays a key role in
determining the range of alternatives that will be
considered, including selection of the preferred. The
P&N is also instrumental in illustrating that a No Build
alternative will not solve an existing transportation
problem.
A well-defined P&N is especially important for
projects that may be subject to other laws (e.g.
Section 404 of the Clean Water Act or Section 4(f) of
the Department of Transportation Act) that require
sound justification of impacts. Furthermore, the P&N
is used to support ODOT’s process of acquiring right-
of-way from public and/or private interests. Without
establishing a sound P&N for a project, it becomes
difficult for ODOT to successfully justify acquistion of
right-of-way through the appropriations process.
Preparation and Development
Although a P&N is not required for planning or
corridor studies, these documents may provide
relevant data that pertains to transportation needs.
The level of detail needed to develop a P&N depends
on the type of project and level of complexity. An
adequate level of detail is needed in order to describe
how the proposed action was initiated, how the
transportation needs were identified, and to define
logical termini and independent utility.
Environmental Impact Statements (EIS) and
Environmental Assessments (EA) typically require a
greater level of detail than Categorical Exclusion (CE)
level documents.
An adequate level of detail
is needed in order to
describe how the proposed
action was initiated, how
the transportation needs
were identified, and to
define logical termini and
independent utility
OES-Policy-April 2018
- 5 - | P a g e Guidance for Developing Purpose and Need April 2018
When does P&N development begin?
Although the framework of a P&N may be established
prior to programming, development of the P&N begins
during the Planning Phase of ODOT’s PDP, (Scoping
Task 1.3.H). As part of this phase, initial project
development includes:
Identification or refinement of project scope
Scoping activities to determine if environmental
resources are present
Identification of potential impacts to the human
and natural environment
Collecting and analyzing existing and future
transportation conditions
These activities help further define a project’s P&N,
which is a critical element needed to advance to the
next phases of the PDP that involve developing
feasible alternatives, Stage 1 Design, cost estimates,
NEPA approval, etc. If a P&N is not properly
developed, this can lead to the development of an ill-
conceived project or alternatives that do not address
needs.
When is a P&N required?
Projects designated as C1 and C2 CEs (typically
PDP Path 1 or Path 2 projects) do not require
preparation of a P&N based on FHWA rulemaking
Although these low level projects do
not require a written P&N,
quantified data is still obtained to
support the need for a project and
the project must still be justifiable.
Supporting data may be
uploaded to the EnviroNet
project file for C-listed
projects
OES-Policy-April 2018
- 6 - | P a g e Guidance for Developing Purpose and Need April 2018
Projects designated as D-listed CEs (typically
PDP Path 3 or Path 4) require that a P&N be
written in EnviroNet (see formatting, page 7).
These types of projects can have complex issues
associated with impacts that may require a
certain level of analysis relevant to the P&N.
The exception are Disposal of Excess Right-of-
Way projects or projects with unusual
circumstances that are elevated to a D1.
Projects that require an EA or EIS, (typically PDP
Path 5) must also have a P&N. These are formal
stand-alone documents submitted to ODOT-OES
via the EnviroNet project file. These types of
projects typically have a higher level of complex
issues and impacts that involve in-depth analysis
and project management team collaboration.
While PDP Paths are loosely correlated with the
level of environmental document, it does not
match up exactly. For example, if a Path 3 project
is designated as a C2 CE, no P&N is required. A
Path 2 project that requires a D1 CE due to impacts
would require a written P&N.
Who is Involved in P&N Development?
ODOT District Role
As part of the Planning Phase of the PDP, specific
activities are conducted (i.e. secondary resource
review, initial field investigations) to establish
project scope and identify potential impacts. Once
scoping activities are completed, establishment of
transportation needs are based on studies conducted.
This process is designed to include district Subject
Matter Experts (SMEs) that are familiar with safety
concerns, engineering requirements, design,
environmental regulations, etc.
The P&N for D-listed CEs is
considered FINAL upon
approval of the CE
P&N format for EA’s and
EIS’s is not incorporated in
EnviroNet
For these projects, the P&N
is considered FINAL once
the FONSI or ROD has been
issued
Districts can prepare P&Ns
for projects designated as
D1 CEs, as well as review
and accept DRAFT P&Ns for
D1 CEs prepared by a
consultant or a Local Public
Agency (LPA), prior to the
development of feasible
alternatives to ensure
quality control
OES-Policy-April 2018
- 7 - | P a g e Guidance for Developing Purpose and Need April 2018
Based on a project’s complexity, the district or LPA
may task a consultant to prepare the P&N, which may
include additional research and/or analysis of data.
These activities assist in the identification of
transportation needs. As the P&N progresses, the
district and/or LPA seeks local stakeholder
concurrence that the needs identified are appropriate
and that concerns are addressed.
ODOT-OES Role
The OES Policy Staff can advise and assist with P&N
development. This can include defining/identifying
primary and secondary needs, logical termini and
independent utility. All DRAFT P&Ns for D2 and D3
CEs, and EA’s and EIS’s are reviewed and accepted by
OES Policy early in the PDP process (Planning Phase)
prior to the development of feasible alternatives.
Local Public Agencies (LPA) and Consultants
A pre-qualified consultant can perform technical
studies as well as prepare the P&N on higher level
projects on behalf of ODOT or an LPA. All P&Ns
prepared by an LPA or consultant must be accepted
by OES or the District (as determined by CE level).
How is the P&N Formatted?
To ensure consistency when developing a P&N, the
following format has been incorporated into
EnviroNet (ODOT’s Environmental Documentation
System) for D-listed CE’s. For EA’s and EIS’s this
format is followed in a stand-alone document.
Project History
This section provides essential background and
context on the existing facility and a detailed account
of how the project was initiated and developed. This
can include a summary of prior investigations/studies
All DRAFT P&Ns for D2 and
D3 CEs, and EA’s and EIS’s
are reviewed and accepted
by OES early in the PDP
process (Planning Phase)
prior to the development of
feasible alternatives
The Project Description
does not suffice as Project
History
When citing prior studies in
Project History, do not
include statements that
specify a preferred
alternative or solution
OES-Policy-April 2018
- 8 - | P a g e Guidance for Developing Purpose and Need April 2018
completed to date (e.g. traffic, safety, planning
activities, inspection reports, etc.), funding status,
land use and zoning considerations, transportation
demand, and legislative mandates. The intent of this
section is to provide an account that substantiates
project development.
Purpose Statement
The purpose statement is comprised of one or two
sentences that articulates the project’s primary
objective.
The Purpose defines the transportation
problem(s) to be addressed
Multiple purposes may correlate with needs
identified. For example, if the needs identified
include congestion, roadway geometrics, and facility
deficiencies, the purpose of a project may be to
improve mobility and access.
Reference to solutions or prescriptive outcomes is not
included, meaning the purpose statement is not
written to indicate a particular action (e.g. replacing
a two-lane bridge with a four-lane bridge or
replacement rather than rehabilitation) provides a
desired result to correct the transportation problem.
Rather the statement identifies the problems to be
addressed.
Need Elements
This section of the P&N is the main component that
defines the transportation problem. Need elements
are derived from ODOT maintained databases (e.g.
speed/congestion data) and/or quantified data
obtained through technical analysis of traffic studies,
crash records, roadway geometric data, etc.
Purpose Statement Examples
An intersection improvement
project:
The purpose is to improve
mobility and safety at the
intersection of US Route 30
and Davis Boulevard
A bridge rehabilitation,
reconstruction, or replacement
project:
The purpose is to improve
facility deficiencies and
roadway geometrics to
maintain connectivity over
the Scioto River
New roadway on new
alignment or interstate
widening/new interchange
projects:
The purpose is to improve
mobility, system linkage and
access between IR 71 and IR
75 to facilitate current
economic growth within
Hamilton County
OES-Policy-April 2018
- 9 - | P a g e Guidance for Developing Purpose and Need April 2018
It is imperative that SMEs (specifically engineers)
be involved in the analysis of these data to ensure
the needs identified are truly causing a
transportation problem.
When establishing needs, the focus is on those critical
elements necessary for the project. Critical need
areas are defined as primary needs. Additional needs
that are identified as part of the project, but are not
necessarily critical, are considered secondary needs.
Identifying a project’s primary and secondary needs
as part of the P&N reduces time spent on technical
studies/reports, data analysis, and expenditure of
funds on designing a practical solution. The goal is to
incorporate a collaborative approach that involves
engineers, environmental specialists, project
managers, etc.
Primary needs are existing or future conditions that
are truly causing a transportation problem. These
needs MUST be addressed to the extent feasible in
order to satisfy the P&N and typically are the majority
of the project’s needs.
Secondary needs are existing or future conditions
that may or not meet standards but are not the cause
of localized or system failures. Essentially, these are
elements that may or may not be addressed by the
project based upon the cost and impacts they create.
Secondary Needs can also be based on a community
perspective that considers aesthetic design and/or
are consistent with local development plans.
These are considered optional and discretionary
and include items that typically are a result of the
overall NEPA planning process. They are not the
deciding factor in alternative development.
The ‘Need’ is quantified
data that supports the
purpose statement
Common Primary Needs
Mobility/Congestion
Safety
Facility Deficiencies
Previously, Goals and
Objectives was included
within the P&N format, but
is now considered to be
part of secondary needs
This section will be
removed from the P&N Tab
of D-listed projects as part
of a future EnviroNet
enhancement
OES-Policy-April 2018
- 10 - | P a g e Guidance for Developing Purpose and Need April 2018
For example, a municipality may have approved a
Complete Streets Master Plan in which components
may be considered Secondary Needs to incorporate
during alternative development.
Secondary needs can be addressed during the
Preliminary Engineering (PE) Phase of the PDP (usually
in the Feasibility Study) if warranted based on the
balancing of benefits vs. costs and/or environmental
impacts.
Why is identifying Primary and Secondary
Needs Important?
The majority of projects typically have one or two
well defined needs, which is better than several
poorly defined or poorly-justified needs. Avoid the
temptation to include poorly supported needs to
simply “bulk up” the P&N, which will make it harder
to defend. It is best to stick with one or two well-
supported needs.
During the Planning Phase, quantified data obtained
from technical studies, along with stakeholder input,
helps identify a project’s primary and secondary
needs.
Need elements are essential to Performance Based
Project Development (PBPD), which is a design
philosophy promoted by FHWA and adopted by ODOT.
The emphasis of PBPD is improving existing conditions
or “Designing Up”, essentially improving the system
but not necessarily meeting every design standard.
Using this concept is a practical way to stretch public
dollars and avoid designing solutions that cannot be
funded.
ODOT’s L&D Manual Volume
1- Section 1000 defines PBPD
as:
“…a planning and design
philosophy being promoted
by FHWA and State
Departments of
Transportation. The general
premise of PBPD is that
proposed improvements
should be targeted and right
sized based on project
specific needs. It is
understood that no one
project is more important
than the overall system.
Consequently, savings
obtained from targeted PBPD
solutions on specific projects
can be reinvested in the
overall system.”
OES-Policy-April 2018
- 11 - | P a g e Guidance for Developing Purpose and Need April 2018
The underlining philosophy of PBPD is that it is better
to build many “good” projects rather than just a
couple of “perfect” projects or no project at all due
to funding constraints.
Once the P&N is refined and accepted early in ODOT’s
PDP, the design solutions explored during
development of alternatives will focus on the primary
needs in order to satisfy the P&N. The intent is to
focus on what is truly causing the problem (primary
needs) versus what may not be up to standard but is
not causing undue issues (secondary needs).
Therefore, the Need Elements section includes:
Well-defined primary and secondary needs based
on quantified data from technical analysis
(needs are identified as primary or secondary
within this section)
Existing and future conditions associated with
primary and secondary needs (this will assist in
determining if a need is primary or secondary)
Do not quantify the desired condition as the intent
is to improve existing transportation problems and
not achieve a specific metric. For example, LOS C
may be the standard to achieve on Urban Arterials,
however, reducing LOS from F to D improves the
condition even if C is not met.
Subsequent Preliminary Engineering activities such as
the Feasibility Study, Alternative Evaluation Report,
Structure Type Study, etc., will identify solutions that
address the primary and secondary needs. Secondary
needs identified may be addressed if the relative
costs and impacts can be justified.
Definitions (including data sources) for common and
less common needs associated with transportation
projects, are provided on the following pages.
Critical Success Factors
(CSF)
CSFs are defined metrics
established by ODOT that
measure the condition or
rating of a particular
aspect of the
transportation system
Metrics to be considered as
part of P&N development are:
System Conditions
(Bridges, Pavement
Conditions, Maintenance,
and Travel Time
Reliability)
Safety (Fatalities, Serious
Injuries, and Crashes)
Considering CSF’s as part
of project development
incorporates ODOT’s goal
of providing safe and
reliable transportation
infrastructure, and to
achieve maximum return
and investment
OES-Policy-April 2018
- 12 - | P a g e Guidance for Developing Purpose and Need April 2018
Mobility: The ability to meet traffic demand and
level of ease in moving people, goods, and
services
Although closely associated with congestion,
access, and connectivity, characteristics of
mobility include traffic flow, “reasonable” travel
time, lost time, and type and condition of
transportation system. This need is typically
identified during the overall planning process with
respect to all modes of travel (e.g. transit, rail,
aviation).
Congestion: Occurs as use increases, and is
characterized by slower speeds, longer travel
times, and increased vehicular queueing
This need is supported by quantified data that
identifies the cause of congestion and identifies
existing and future congestion. The cause of
congestion can be traffic influencing events,
traffic demand, and/or physical highway features.
These causes lead to recurring congestion that
consists of predictable back-ups caused by a
location that is over-capacity, such as an
interchange or lack of access management.
Typical Data Sources to
Include for Mobility
Average daily hours of
travel per person
Average minutes per mile
Average vehicle minutes of
delay
Total passenger and ton-
miles traveled
Travel rate index (how
much time is added to a trip
during rush hour conditions
compared with free-flow
conditions)
A range of measures can
define congestion
Level of Service (LOS)
Volume-to-Capacity (V/C)
Vehicle Hours of Delay
Typical Data Sources to
Include for Congestion
Certified Traffic Plates
No Build Traffic Data
Mainline LOS
SHIFT Counts/Growth Data
Traffic Analysis Software
(Travel Demand Model and
Highway Capacity Manual)
OES-Policy-April 2018
- 13 - | P a g e Guidance for Developing Purpose and Need April 2018
Facility Deficiencies: Existing transportation
system, including roads, bridges, and culverts
that are in disrepair or deteriorated condition,
or that have substandard roadway geometrics
This need is supported by data maintained by
ODOT and/or LPA’s. The majority of data is stored
within ODOT’s Pavement Management System,
Structure Management System, and Maintenance
Management System. These data bases include
Pavement Condition Rating (PCR), Bridge
Condition Rating, Bridge General Appraisal
Ratings, and Structurally Deficient Ratings. This
need may also include sub-standard design (e.g.
vertical or horizontal curves, turning radius, etc.)
that does not meet standards.
Safety: Reduction of serious injuries and
fatalities based on accepted engineering
practices and quantified data to support the
overall surface transportation planning process
Safety is rarely the sole need for a project and is
almost always related to some other need, such as
facility deficiency or congestion. Establishing
safety as a need involves a two-step process to
understand if the project is within a safety priority
location:
1. The first step involves reviewing the Safety
Integrated Project (SIP) maps which can be
found on ODOT’s Highway Safety Webpage. If
the study area includes a high crash/high
priority location(s) (represented by a red dot),
or a low priority area (represented by a blue
dot), additional analysis and consideration is
required.
Typical Data Sources to include
for Facility Deficiencies
Bridge Inventory Reports
Bridge Inspections
Culvert Inspections
PCR Forms
System Conditions is a CSF
metric ODOT uses to
measure General Appraisal
ratings for bridges,
pavement distress on
priority, general and urban
roadways, and roadway
maintenance operations
Safety is a CSF metric that
ODOT uses to measure the
number of motor vehicle
crashes on ODOT-maintained
roadways that includes
fatalities, serious injuries,
non-serious injury and
property damage
OES-Policy-April 2018
- 14 - | P a g e Guidance for Developing Purpose and Need April 2018
If after analysis and consideration of data obtained
safety is considered a need, the second step would
not be necessary. However, if the location is not on
the SIP map, proceed to the second step:
2. This step involves reviewing the most recent
three years of crash data within the project
study area corridor. Completing this task is
accomplished using ODOT’s GIS Crash Analysis
Tool (GCAT) that is used to understand the
crash types included in the SIP maps.
If a high crash location is identified, a pattern of
crashes exist, or there have been fatal or serious
injury crashes within the project study area, safety
will most likely be a need.
In accordance with ODOT’s PDP, all project P&N’s
that identify safety as a need are required to analyze
proposed alternatives as part of the Feasibility Study
(FS) and the Alternatives Evaluation Report (AER)
using Highway Safety Manual (HSM) methodologies
(HSM may not cover every situation, such as
quantifying deficient super elevation). This
requirement is intended to reduce identifying safety
as a need if not supported by data.
System Linkage: Provides a link between
existing facilities to alleviate congestion or
provide an alternate route not currently
available (likely associated with mobility,
congestion and/or access)
Although not as common, System Linkage can be a
primary or secondary need. The need may be
identified within local or regional long-range
transportation or development plans. Existing land
uses within the area can be a factor in determining
if System Linkage is a need.
Crashes are typically a
symptom of another known
deficiency, such as:
Congestion
Facility Deficiencies
Roadway Geometrics
Crash data is collected by
law enforcement agencies
such as the Highway Patrol
and County Sheriffs
Crash reports are made
available to ODOT by the
Ohio Department of Public
Safety
The ODOT Office of Systems
Planning and Program
Management is responsible
for collecting and
organizing this data
OES-Policy-April 2018
- 15 - | P a g e Guidance for Developing Purpose and Need April 2018
Early endeavors may include preparation of
Origin/Destination (OD) and Access Management
Studies.
Access: Providing access to land parcels/uses
adjacent to all manner of roadways and/or
improving the flow of traffic along heavily
traveled corridors
Although not as common, access can be a primary
or secondary need, and is closely associated with
mobility and congestion. The need derives from
the proactive management of existing
transportation networks to provide efficient
modes of travel and safety. Access is aimed at the
preservation of functional integrity and overall
operational viability of street and road systems.
Another need element that has become more relevant
of late is Economic Development.
Economic Development: Based on a master
plan/vision for community growth and
prosperity that may be tied to planned
infrastructure, but is primarily based on planned
land use changes that are tied to employment,
schools, commercial and business development
Existing and/or planned transportation facilities are rarely the sole factor for economic development needs. However, transportation infrastructure and public transportation modes influence community growth and facilitate land use changes.
Transportation projects can be drivers of development in the benefits they bring to job creation, commercial/business development, accessibility to places of business, and efficiency of travel for goods and freight.
ODOT maintains an
analytics tool/database to
determine OD
OES-Policy-April 2018
- 16 - | P a g e Guidance for Developing Purpose and Need April 2018
In order for Economic Development to be considered
a primary need, the P&N must focus on existing
transportation problems that are keeping
development from taking place or that may be
worsened when development is realized. This focus
will help avoid defining a broad purpose that may
require a vast range of transportation and/or non-
transportation alternatives for promoting economic
development.
Sources for determining if ecomomic development
would be considered a need on a project are:
Zoning and Development Master Plans
Regional Planning Studies
Origin Destination Studies
Local Economic Plans/Visioning Documents
Access Management Studies
Corridor Freight Studies
Sustainibility Studies
If Economic Development is a Need, the Purpose
Statement is not:
The purpose is to promote growth/economic
development
It must reflect a transportation focus (problem):
The purpose is to provide transportation
infrastructure, and improve mobility and access
to support planned community
growth/development as identified in the [plan]
OES-Policy-April 2018
- 17 - | P a g e Guidance for Developing Purpose and Need April 2018
Logical Termini and
Independent Utility
Logical Termini
Establishing logical termini is largely determined by
quantified data that indicates where the
transportation problem begins and ends.
For example, a project with an identified facility
deficiency supported by pavement condition ratings
begins where the pavement condition is poor and in
need of improvement, and ends where the pavement
is in better condition.
Independent Utility
Independent Utility establishes a project’s
independent significance. A project is considered to
have independent utility when it can be constructed
without relying on other projects to be constructed
within or adjacent to the project area. In other
words, the project cannot be dependent upon another
project in order to function. It must be a usable and
reasonable expenditure of funds even if no additional
transportation improvements in the area are made.
Please note Independent Utility is different from
project construction phasing. Portions of a multi-
phase project that depend upon other phases of
the project do not have independent utility.
Projects phased for construction are evaluated as
a single undertaking with one P&N and one
environmental document. Phases of a project that
would be constructed even if the other phases
were not built can be considered as a separate and
complete project with independent utility.
City boundaries, municipal
end points, county lines,
etc. are not used as logical
termini end points
OES-Policy-April 2018
- 18 - | P a g e Guidance for Developing Purpose and Need April 2018
Public Involvement
For projects designated as D-listed CEs, EA’s or EIS’s,
stakeholders, the public, and resource agencies are
provided the opportunity to participate in the review
and/or refinement of the P&N as part of Public
Involvement (PI) activities. This can begin as part of
the transportation planning process, at the initiation
of NEPA studies, or during different stages of the PDP,
as appropriate. Obtaining input is valuable in assisting
the project management team to be aware of project
elements that may be of concern to the local
community or key stakeholders.
All decision-making regarding P&N development are
documented and shared with all interested parties to
ensure issues are resolved as early as possible.
The level of involvement is determined by the
sponsoring agency based on the project’s type and
complexity. The methods used and the timing of PI is
flexible, and the lead agency(s) coordinate
beforehand regarding when and in what form PI will
occur. All outreach and PI activities must be
publicized and may occur in the form of public
workshops or meetings, solicitations of verbal or
written input, postings on project website,
distribution of printed materials, or any other
involvement technique.
Points to Remember
Why is a P&N Needed?
It is required by law. Furthermore, a well-written and
well-justified P&N helps validate the expenditure of
public funds and impacts upon the human and/or
natural environment.
Please refer to ODOT’s
Public Involvement Manual
for additional information
regarding PI requirements
OES-Policy-April 2018
- 19 - | P a g e Guidance for Developing Purpose and Need April 2018
The P&N provides a baseline to develop and
adequately evaluate, eliminate and advance project
alternatives. Establishing a solid P&N that defines
existing and future transportation problems enables
alternatives to be designed that address primary
needs and includes secondary needs, if practical.
Level of Detail
The level of detail can vary and is dependent on
project type and complexity. Transportation projects
classified as a CE will have less complicated and
detailed needs than those projects classified as an EA
or EIS. It is not unusual for higher level CEs (especially
D2 or D3) to have an extensive project history and/or
need elements.
A brief discussion of one or two paragraphs per need
element for CE projects typically suffices, whereas EA
or EIS projects typically involve complex
environmental and engineering decisions that require
a more detailed discussion. The P&N for EA or EIS
projects typically comprise 3-5 pages of text.
Documentation
All supporting analyses, quantified data (existing and
future conditions) and acceptance documentation are
uploaded to the P&N Section of the project file in
EnviroNet. The appropriate dropdown options are
available to properly upload Bridge Condition Rating,
Crash Data, LOS Data, Pavement Condition Rating,
and Traffic Data. Other data (e.g. economic data) not
listed as dropdown options can be uploaded and
named appropriately. This includes relevant mapping,
illustrations, photographs, charts, graphics, and/or
spreadsheets associated with the P&N.
Avoid writing long, verbose
and hard to follow P&N’s as
they will be harder to
defend than those written
in a concise, succinct and
focused manner
Follow existing ODOT NEPA
File Management and
Documentation Guidance to
ensure proper naming
conventions are used