+ All Categories
Home > Documents > Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection...

Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection...

Date post: 18-Jul-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
12
5/27/2013 1 29 th May 2013 Dr. William Mezzullo Project Development Manager Future Biogas Limited Development & Commissioning of a Biomethane Project Introduction to Future Biogas Background Brief overview of installations and pipeline Status of UK Renewable Energy Policy Current Renewable Energy Policy & Tariffs Focus on Biogas & Biomethane Technical & Regulatory Considerations of Biomethane Projects How to connect an AD plant to the gas grid Summary of experiences to date Issues encountered and lessons learnt Discussion Overview 27/05/2013 William Mezzullo 1
Transcript
Page 1: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

1

29th May 2013

Dr. William MezzulloProject Development Manager

Future Biogas Limited

Development & Commissioning of a Biomethane Project

Introduction to Future Biogas

• Background

• Brief overview of installations and pipeline

Status of UK Renewable Energy Policy

• Current Renewable Energy Policy & Tariffs

• Focus on Biogas & Biomethane

Technical & Regulatory Considerations of Biomethane Projects

• How to connect an AD plant to the gas grid

• Summary of experiences to date

• Issues encountered and lessons learnt

Discussion Overview

27/05/2013 William Mezzullo 1

Page 2: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

2

About Us

Future Biogas• A UK leader in the development and operation of

biomass AD plants

• Founded in 2008 – now a team of 23 staff

• First plant (1.4MWelec) generating since Summer 2011

• Second plant generating Feb 2012 (1.56MWelec)

• First biomethane plant commissioning 2013

• Two further biomethane plants to commission in 2014

• Close links to government and trade associations to influence development of the biogas market

27/05/2013 William Mezzullo 2

Spring Farm Norwich – 1.4MWelec

Reepham RoadNorwich – 1.6MWelec

Vulcan Way Doncaster – 4.5MWgas

HibaldstowLincolnshire - 4.5MWgas

ScottowNorfolk - 2.2MWelec

EgmereNorfolk – 4.5MWgas

Biomethane Injection Sites Electrical Sites

Sites across UK

27/05/2013 William Mezzullo 3

Page 3: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

3

Spring Farm, Taverham• Operational 2011• Power for over 3,000 homes

Reepham Road, Taverham• Operational 2012• Heat to adjacent Abattoir

Spring Farm and Reepham Road:• Annual carbon saving of 13,000 t CO2

• Working closely with 20+ local farmers Technology choice and biogas operations/support

• Crop opportunity for poor land

• Break for vegetable production

• HLS grass and Norwich Airport lawn!

• Perennials, biogas wildflowers and high energy grasses on trial

• Working on biofumigation, digestate starter fertiliser for OSR and nitrification inhibitors

Operational Sites

Vulcan Way• Doncaster (4.5MWgas)

• Operational 2013

Scottow• Lincolnshire (2MWelectrical)

• Operational 2013

Commissioning Sites

27/05/2013 William Mezzullo 6

Page 4: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

4

How renewables are incentivized in the UK?

Status of UK Policy

27/05/2013 William Mezzullo 7

EU Renewable Energy Target 20% by 2020

UK Renewable Transport Target10% by 2020

UK Renewable Elec. Target15% by 2020

UK Renewable Elec. Target15% by 2020

RTFO FIT ROC RHI

Liquid BiofuelsBiogas

WindPVHydroBiogas

WindAll biomassGeothermalLandfillSewageTidalWaveHydroBiogas

Biomass CombustionBiogas CombustionDeep GeothermalGround Source Heat PumpSolar Hot WaterBiomethane

Renewables Obligation (RO)• Financial mechanism incentivising large

scale

• Clean generators receive 0.25-2 ROCs/MWh (Renewables Obligation Certificates) AD is in top band at 2 ROCs/MWh

• Fossil generators buy ROCs to compensate for carbon emissions

Tariffs for Biogas

• Value of ROCs currently £46.21($71.80)/MWh

Biogas for Electricity

27/05/2013 William Mezzullo 8

Feed in Tariff (FiT)• Small-scale <5MW

• Inflation linked tariff for 20 years

Tariffs for Biogas

• Current tariffs for anaerobic digestion are grouped as;

• <250kW – 15.15p/kWh ($0.24/kWh)

• 250-500kW – 14.02p/kWh ($0.22/kWh)

• >500kW – 9.24p/kWh ($0.14/kWh)

Degression

• 5% annual degression + capacity trigger degression

• May fall by 20% next April for <500kW

Page 5: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

5

Supports

• Biomethane injection to the gas grid

• Biogas combustion below 200kW (direct or through CHP)

Tariffs for Biogas/Biomethane

• Biogas combustion – 7.3/kWh ($0.11/kWh)

• Biomethane Injection – 7.3/kWh ($0.11/kWh)

Future

• Expansion of combustion/CHP tariff to >200kW by April 2014

• Planned degression – too early too tell when this will happen

Biomethane or Biogas Combustion

27/05/2013 William Mezzullo 10

Renewable Heat Incentive (RHI)

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 11

Who is your GDN? Virtual Gas Market

Producers/ Importers

National Grid

GDNs

150 + Shippers, Gas Companies,Oil Companies, Banks and Traders

Page 6: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

6

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 12

Is gas injection a viable option?Available capacity in the grid

• Limiting factor will be existing gas consumption at low demand Will CV enrichment be required?

Costs of physical connection

• Distance from site to gas pipe (metres or kilometres?)

• What type of gas pipe? (low/medium/high pressure)?

Will it work

• Gas demand for lifetime of the project?

• Do the figures stack up (connection costs + CV enrichment) vs return?

Biomethane injection will be limited by the existing minimum demand of natural gas along a pipe. i.e. during the night in summer months.

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 14

Biomethane to Grid - equipment

Biogas Plant

Gas Pipe

Upgrade Check

Page 7: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

7

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 15

Clean Up Plant - Considerations Recovery Rate & Biomethane Quality

• Recovery Rate – how much CH4 can be recovered from biogas

• Methane quality – was is the purity of biomethane

Efficiency

• Electrical consumption (membrane = 0.3-0.4 kWhelec/m3 raw biogas, chemical absorption = 0.6 kWhelec/m3 raw biogas)

• Heat requirement high for some chemical washes

• Operating uptime, performance guarantees

Methane Slip

• Primary consideration due to UK Sustainability Requirements

• No more than 0.5% (otherwise use Thermal Oxidizer)

Biogas Plant

Gas Pipe

Upgrade Check

Why is this needed?

• UK natural gas grid operates between 37MJ/m3 to 42.3MJ/m3 (average =39.5MJ/m3)

• CH4 (100% quality biomethane is only 37.7MJ/m3)

• May not be relevant in Canada

Costs

• Propane injection equipment – approximately £110k

• Significant OPEX (up to £130k/annum for a 420m3/hr injection site)

Is there a solution?

• Yes – if gas pipe flow rate is large enough blending

• Yet to become common practice in the UK

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 16

Propane Injection

Biogas Plant

Gas Pipe

Upgrade Check

Page 8: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

8

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 17

Entry Facility

What is it?

• To ensure that gas entering GDN is acceptable in terms of quality, odour, pressure and flowrate

• Telemetry monitored by GDN and AD plant operator

Why do we need it?

• Requirement from GDN - obligatory

How much is it?

• Much work carried out by UK biogas Industry to reduce the CAPEX of these units. Originally costing in the region of £1million

• Typical cost is around £300k – although thesupply market is very limited

Biogas Plant

Gas Pipe

Upgrade Check

Connecting AD to Gas Grid

27/05/2013 William Mezzullo 18

Grid Control & ROV

What is it?

• A valve!

Why do we need it?

• GDN owned equipment to safeguard their network

• Default valve position is shut until acceptable gas is achieved

How much is it?

• Although it is GDN owned, the AD developer must pay

• Approximately £130k

Biogas Plant

Gas Pipe

Upgrade Check

Page 9: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

9

Biogas to Biomethane Flow

27/05/2013 William Mezzullo 19

Progress

• Broke Ground – September 2012

• Upgrade Facility expected June 2013

• Injection date – August 2013

Doncaster Biomethane Project

27/05/2013 William Mezzullo 20

May 2013March 2013December 2013September 2012

Page 10: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

10

Statistics

Doncaster Biomethane Project

27/05/2013 William Mezzullo 21

Plant Capacity & Information

• Agraferm – AD technology supplier

• Up to 35,000 tpa (4MWgas + 500kWelec CHP)

• Agricultural feedstocks: grasses, rotational breakcrops (sugar beet, sunflower, maize, rye), plusbiodiversity friendly feedstocks (wildflower

mixes, szarvasi grass – perennial crop)

Biomethane Upgrading

• Air Liquide membrane technology

• Elster Grid Entry Unit

• Flogas – Propane Injection

Issues Encountered

Doncaster Biomethane Project

27/05/2013 William Mezzullo 22

Acceptable Oxygen Limit

• All biomethane has an oxygen component

• UK Oxygen limit in the network is 0.2% (Germany has 2-3%)

• Stringent limit needs to be relaxed in order to facilitate injection

Propane Addition

• Blending biomethane with natural gas eliminates need for propane

• This is possible but GDNs are reluctant to date

• Fossil gas use reduces the carbon credentials of biomethane

Page 11: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

11

Issues Encountered

Doncaster Biomethane Project

27/05/2013 William Mezzullo 23

Ownership of Equipment

• ROV and Telemetry Unit was originally designed to be included in the Grid Entry Unit

• UK gas regulator changed regulation on this forcing GDN ownership of ROV Telemetry Unit

• This has additional expense and issues with ownership

Biomethane from Waste

• Biomethane produced from waste AD has several other layers of regulation

• Stringent limits on Siloxanes and Odour Masking

• Biomethane produced from waste AD is considered a ‘waste’ until it passes Biomethane Quality Protocol

Selling Biomethane

27/05/2013 William Mezzullo 24

Biomethane sales

• Biomethane can also be sold onto the gas market to gain additional income to the RHI

• Sales are extremely limited at present (only 1 commercial biomethane plant)

• Large gas shipper not able to trade below 5,000 therms/day – more than any current plant

• Novel biomethane trading schemes developed

Certification

• Certification schemes help differentiate biomethane to natural gas

• Certification schemes widely available across Europe, theUK has two:

• Green Gas Certificates

• Biomethane Certification Scheme

Status of biomethane market

Page 12: Development & Commissioning of a Biomethane Project...5/27/2013 5 Supports • Biomethane injection to the gas grid • Biogas combustion below 200kW (direct or through CHP) Tariffs

5/27/2013

12

Summary

27/05/2013 William Mezzullo 25

UK Policy

• Incentives for biogas to electricity have been present and operating successfully (through FIT) since 2010

• Strong incentives for biomethane injection present within the UK

• Technological & regulatory challenges have slowed deployment to date

Lessons learnt from developing a biomethane project

• Close relationship with GDN is essential – they must be part of the project

• Lifecycle GHG emissions are extremely important when select

• Communication amongst technology suppliers is key. This includes:

• AD technology, upgrade technology, grid injection technology, propane equipment, GDN, gas pipe installers

Thank you to CNG Services for their support

Dr. William MezzulloProject Development Manager

Future Biogas Limited

[email protected]+44 (0) 1483 375 930

Thank you


Recommended