Developments at theDevelopments at theAtomic Weapons Establishment: Atomic Weapons Establishment:
The local impact of Trident The local impact of Trident replacementreplacement
Peter BurtPeter BurtNuclear Information ServiceNuclear Information Service
nuclearinfo.orgnuclearinfo.org
NISNIS
• Role of the Atomic Weapons Establishment.
• The Nuclear Weapons Capability Sustainment Programme.
• AWE's Site Development Strategy.
• Campaign agenda and role for local authorities.
NIS
What we will talk about:
“The current warhead design is likely to last into the 2020s, although we do not yet have sufficient information to judge precisely how long we can retain it in-service.Decisions on whether and how we may need to refurbish or replace this warhead are likely to be necessary in the next Parliament.”- 2006 White Paper
A new UK nuclear warhead?
NIS
NIS
The Atomic Weapons Establishment
AWE is responsible for designing and building Britain's arsenal of Trident nuclear warheads.
Work at AWE covers the entire life cycle of nuclear warheads:• Initial concept, assessment
and design.• Manufacture and assembly.• In-service support.• Decommissioning and
disposal.
NIS
The Atomic Weapons Establishment
NIS
Coulport / Faslane
The Nuclear Warhead Cycle
Aldermaston / Burghfield
NIS
AWE's current role
• Just under 200 W-76 Mk4 warheads produced for Trident: production ended in 1999.
• AWE operational role currently mainly maintenance and surveillance.
• Research and development work also underway to upgrade current warheads and prepare for development of a successor to current warhead.
“Agreement has been reached with AWE Management Ltd. (AWE ML) to take forward a programme of investment in sustaining key skills and facilities at the Atomic Weapons Establishment. This will include the provision of necessary extra supporting infrastructure.
“The purpose of this investment of some £350 million over each of the next three years is to ensure that we can maintain the existing Trident warhead stockpile throughout its intended in-service life.”
- John Reid, Written Statement, 19 July 2005
Nuclear Weapons Capability Sustainment Project
NIS
Nuclear Weapons Capability Sustainment Project
NIS
• Inception in November 2002 - but not announced until July 2005.
• Life extension and upgrade of warheads to W-76 Mk4A design: wider range of targetting options.
• Allow joint research work with USA to continue and ensure AWE is able to develop and build a new warhead if asked to.
• Investment in new facilities at AWE.• Recruit and train scientists to retain
key skills.
• Rebuild facilities at Aldermaston and Burghfield.
• Lack of investment at AWE in 1980s and 1990s.
• Key facilities do not meet modern building and safety standards.
• Large, complex, facilities which can typically take ten years to design, build, and commission.
NIS
AWE's Site Development Strategy
“At its peak the construction work will make AWE one of the largest construction sites in the UK – similar in scale to the Terminal 5 project at Heathrow”
- ‘AWE Today’December 2005 NIS
AWE's Site Development Strategy
NIS
Annual expenditure at AWE
Source: Parliamentary Questions, 10 October 2005 and 11 December 2007.
0100200300400500600700800900
1000
2000
-1
2001
-2
2002
-3
2003
-4
2004
-5
2005
-6
2006
-7
2007
-8
2008
-9
2009
-10
2010
-11
Year
£ m
illio
n
NIS
To put this in context ...
Projects already commenced: 'Orion' nuclear test laser
Projects already commenced: New IT buildings
Projects already commenced:'Gemini' office complex
Planning permission granted:
Project Site Planning Application
Small Scale Components Facility
Burghfield September 2007
High Explosives Fabrication Facility
Aldermaston November 2007
Conventional Manufacturing Facility
Aldermaston June 2008
NIS
NIS
Planning Permission granted:'Mensa' Assembly / Disassembly Facility
NIS
Planning Permission granted:'Pegasus' Enriched Uranium Facility
NIS
Coming soon:'Hydrus' Hydrodynamics Facility
Planning permission beyond 2010:
NIS
Project Site
Systems Engineering Facility Aldermaston
Small Scale Formulations Aldermaston
Chemical Processing Burghfield
Emergency Response Capability Facility Training Extension
Burghfield
Combined Non Metallurgy and Material Science
Burghfield
High Performance Computer Aldermaston
New Office Accommodation Phase 3 Aldermaston
NIS
Campaign agenda
• Rethink Trident: defer for five years.
• Review the need for Trident replacement in the Strategic Defence Review.
• No new warhead or upgrade programme.
• Cancel facilities aimed at cheating the CTBT.
• Increase verification and decommissioning work.
NIS
The role for local authorities
• Look at diversification opportunities for AWE.
• Encourage West Berkshire Council to treat AWE planning applications objectively.
• Highlight Trident costs and the sacrifice for local services.
• Push publicly for disarmament.
Thank you, friends …Thank you, friends … happy campaigning!happy campaigning!