Date post: | 12-Apr-2017 |
Category: |
Marketing |
Upload: | alok-kumar |
View: | 83 times |
Download: | 0 times |
DABHOLA POWER DEBACLE
Presentation By: Group 3
Anurag Singh Dushyant Singh Devvrat RaiyaniAnay Rekhde Arpit Modi Abhimanyu Singh Gavesha Beekray
INDIA’S POWER SCENARIO THEN India’s power needs were set to grow in 1992 Energy deficits of 18% was recorded leading
to frequent power cuts Emphasis on attracting private investments
on power in 8th five year plan(1992-1997) Export/Import reforms were enacted to bring
down costs in the power sector
INDIA’S POWER REGULATORY STRUCTURE The Industry was regulated at the Central or
National Level Power Sector - subject of concurrent list State governments responsible for managing
and operating state utility companies Central Government’s Ministry of Power is
responsible for regulating and is in charge of decisions on: Capacity additions Pricing/Tariffs Power-related investments
ENTRY OF ENRON Enron – world-leading multinational firm in
the natural gas industry Enron saw huge opportunities in India
To provide power To earn profits To obtain more projects if they were successful
with their first one India fit in nicely with their global objectives
at that time Enron proposed to build most modern power
plant at a time when most foreign players could not conceive such risk
WHY IN MAHARASHTRA? MSEB was profitable and this reduced the
revenue risk - the state board could pay Enron for power generated
A large demand for power existed in the state � Maharashtra already generated close to
10,000MW (12% of India’s generation capacity)
Location was close to a port making it easy to �transport fuel for the power plant.
Maharashtra was one of India’s more �developed states –institutional risks were comparatively lesser
BEST ALTERNATIVE – INDIA'S PERSPECTIVE
Ranking Alternatives Feasibility
Best Alternative
Contract a domestic private investor to build, own and operate the energy plant
Untenable then – pvt sector relied on state support
2nd Best Alternative
Domestic company becomes majority partner in power project
Untenable then – pvt sector relied on state support
3rd Best Alternative
Tap into alternative forms of energy sourced domestically (e.g. coal production)
Disregard of recommendations to explore domestic sources
4th Best Alternative
Have another foreign investor build, own and operate the energy plant
Sizeable cost advantage as a large multinational, foreign capital
BEST ALTERNATIVE – ENRON'S PERSPECTIVE At the time, ENRON was negotiating deal in
Qatar with state owned Qatar Gas & Pipeline Company to create a LNG facility
To avoid financial setbacks, ENRON needed to find large supply of consumers for the LNG
Israel, India and Pakistan were prime candidates
Israel had retracted from its commitment to lift 3 mn tones of LNG
Situation in Pakistan was volatile This left India as the only possible destination
THE CONTRACT A Power Purchase Agreement (PPA) was drawn
up wherein MSEB agreed to purchase a certain quantity of power from the Enron-led Dabhol Power Corporation (DPC) at a certain tariff.
DPC Ensured that adequate power will be made available
MSEB took care of demand risks with PPA. Initial price was Rs 2.4/KwH 20 year renewable concession was signed Dispute resolution was to be done through
international arbitration – not part of PPA but DPC shareholders agreement
RISK ANALYSIS
PROBLEMS WITH DPC Since the process was new to India, Govt. did
not consider the advantages of competitive bidding.
Agreement was directly negotiated between ENRON and Govt. through MoU
The secretive nature of the early negotiations between Enron and GoI led many to believe that project was allotted based on bribery and corruption
By proposing a negotiated deal between Enron and the MSEB, the Indian government was in the weak negotiating position
PROBLEMS WITH DPC World Bank Report expressed reservations
about the feasibility of such a huge project Central Electricity Authority (CEA)
determined that power tariff was too high and withheld approval
major debate between the MSEB and the central government ensued
Although the Congress party’s chief minister in Maharashtra was backed by his party in the central government when he signed the MOU, the central government via the CEA was reluctant to grant approval to the project
PROBLEMS WITH DPC Under GoI insistence CEA granted provisional
clearance for the project in November 1993, the MSEB took this as full clearance, and signed the final twenty-year PPA
The sale of electricity from DPC was never directly related to the demand in the market
Due to the Investment risk in India, the contracts had to be structured in such a way to guarantee a stable income stream for Enron
MSEB were prepared to commit to purchasing power to satisfy lender’s requirements
THE SAGA UNFOLDS Bharatiya Janata Party (BJP), a right-wing
party defeats the Congress and comes to power in 1995
BJP makes lots of nationalistic noise. Their leader says “we will not be dictated by foreign power giants”
Committee prepares a report on DPC Project is cancelled in August 1995
REASONS FOR CANCELLATION Lack of transparency and competition in the
bid process Some clearances were ignored based on the
‘fast-track’ nature of the project Cost of the project was greater than
comparable projects Enron cost Rs 4.49 Cr per MW Comparable projects cost Rs 3.6 Cr per MW
Tariffs were too high Environmental concerns and concerns raised
in a World Bank report were not addressed
BEST ALTERNATIVE - GOM The alternative of soliciting another investor
to take over a project which had become highly scandalized and plagued with financial uncertainties was improbable
Alternative of extracting domestic sources of energy to meet growing demand was also negligible
Throwing away the deal was also not advisable as it would give the impression of instability in the country and also have GoI confronting bill of nearly $300 million and bound by its guarantee for liability of non-payments
Thus renegotiating the deal was best alternative
BEST ALTERNATIVE - ENRON ENRON was aware that cost of International arbitration was
greater than procedure for renegotiating the agreement ENRON had serious cash flow problems with DPC Furthermore, if the project was terminated, Enron’s goal of
sourcing a large supply of consumers for its LNG facilities over a long period of time would never materialize
Enron had little choice but to negotiate with the Governments of India and Maharashtra instead of lobbying for policy, judicial and economic reform since there is no unified consortium of private investors or businesses in India with which a multinational could join forces and lobby
Specifically, Enron’s efforts to lobby the GOI to exert pressure on the GOM and the MSEB on the issue of default payments, quickly deteriorated vis-à-vis external events influencing American foreign policy
RENEGOTIATED DEAL ENRON was ready to renegotiate the deal,
after having realized that it would have to work with local politicians in order to move ahead
After review of the modified agreement, the government had reversed its position and accepted the renegotiated deal
Although elected to office based on cancellation of deal, GoM still had to solve problem of inadequate supply in energy sector
ENRON agreed to change from distillate fuel to Indian Naphtha fuel and made MSEB a 15% equity partner
IMMEDIATE POLICY CHANGES Revised project documents were immediately
made public so that the cost base of the project was transparent
As a result of the controversy over corruption, the government ruled that future power sector contracts would no longer follow the MOU process as with Enron, but would be replaced with mandatory competitive bidding
TRANSFER OF RISK FROM ENRON TO GOI, GOM Given the tenuous nature of the MSEB’s
financial position, the project lenders and Enron required a counter-guarantee of payment from the state government
The solvency of the state government was questionable, so Enron required that this insurance be further backed by a guarantee from the central government
This sovereign guarantee was controversial because the credit rating of the whole of India became dependent on non-payment by one state, on one project
Deal not signed until Atal Bihari Vajpayee’s13-day government came to power marking shift in risk
ENRON INFLUENCE ON GOM, GOI Combination of a take-or-pay contract and a
sovereign guarantee meant that Enron would be paid for the electricity without taking on the risk of reduced market demand or nonpayment by the MSEB
When ENRON came to India there was little regulatory structure for project approval process
Enron made many recommendations to the GoI as to how it could improve the process for foreign investors
Laws were passed as a result of Enron’s experience with Dabhol
All other projects in the country were benchmarked against the Dabhol tariff
THE ARBITRATION STORY After the MSEB failed to remit payment
government paid the MSEB’s arrears MSEB argued that the central government
should not pay the latest arrears because the bills needed correction, and Enron claimed that the MSEB was trying to renege on its contractual obligations
Enron invoked the political force majeure clause for non fulfillment of the MSEB’s contractual obligations and issued arbitration notice to the central government to collect the December bill
MSEB stopped payment on electricity from Dabhol, and issued notice to scrap the PPA
THE ARBITRATION STORY First, the dispute under the Power Purchase Agreement
was referred by the DPC to arbitration in London Second, Bechtel, as a co-owner of the DPC, referred a
claim under the DPC Shareholders Agreement to the ICC Arbitration in New York
Third, claims for about $1.3 billion in compensation were reportedly launched by Bechtel and General Electric under India’s bilateral investment treaties with Mauritius and the Netherlands
Fourth, in a state-to-state arbitration, the U.S. government brought a claim against India after OPIC was required, in an American Arbitration Association proceeding in the U.S., to pay about $110 million to Enron, Bechtel, General Electric, and Bank of America in risk insurance for the Dabhol project
THE ARBITRATION STORY Of these four arbitrations, only the ICC
Arbitration led to a known and publicly available award. This is partly because, in 2005, an overall settlement was reached between the U.S. and Indian governments, as well as U.S. firms, which terminated outstanding arbitrations and court actions
The ICC arbitration allowed tribunal’s decisions to expand the arbitration beyond the parties to the relevant contract and apply a variety of legal sources besides that contract, offered reasons to suspect regime bias and was indicative of wider conflict between Western and Third World interests
LEARNING FROM THE EPISODE A surplus of power is as harmful as a shortage of power It is imperative to examine the tariff implications DSM must be included as an option with Integrated
Resource Planning (Least Cost Planning) to arrive at the cheapest mix of supply and saving options.
Competitive bidding procedures rather than MoUs and counter-guarantees
The sector must pursue the goal of universal access to affordable electricity
Protection against exchange rate volatility and strengthening of BHEL
Not only competitive bidding but transparency, accountability and participation
The right to information
POSSIBLE MEASURES FOR FUTURE Technical advisers must be appointed NGOs may act to ensure that peoples’ views
reach policymakers Consumers need to be more vocal so as to
play a part in decision making View of opposition party must be taken into
consideration Renegotiation of agreement, though not
advisable, but could have been done in this case
To conclude, trust and relationship and perhaps some initiative and flexible contracts might
have been more successful than relying purely on contract