+ All Categories
Home > Documents > Dholpur Waste Water Subproject since sewer line will be laid in the middle of road and on both sides...

Dholpur Waste Water Subproject since sewer line will be laid in the middle of road and on both sides...

Date post: 20-Apr-2018
Category:
Upload: doankhue
View: 212 times
Download: 0 times
Share this document with a friend
76
Resettlement Planning Document The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Project Number: 40031 Revised July 2013. India: Rajasthan Urban Sector Development Investment Program – Project 2 Loan 2506 Dholpur Waste Water Subproject Prepared by Local Self Government Department
Transcript

Resettlement Planning Document

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Project Number: 40031 Revised July 2013.

India: Rajasthan Urban Sector Development Investment Program – Project 2 Loan 2506

Dholpur Waste Water Subproject Prepared by Local Self Government Department

Resettlement Planning Document

Draft Short Resettlement Plan for Dholpur Waste Water Sub-project Project Number: 40031 February 2009 Revised: June 2013

India: Rajasthan Urban Sector Development Investment Program

Prepared by Local Self Government Department The Resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

ABBREVIATIONS

ADB Asian Development Bank

AP Affected Person

BDO Block Development Officer

DBPL Below Poverty Line

CBO Community Based Organization

CPR Common Property Resources

DOI Department of Irrigation

DPR Detailed Project Report

DPEP District Primary Education Program

DRDA District Rural Development Agency

EH Entitled Household

EMAP Environmental Management Action Plan

EWS Economically Weaker Section

GoI Government of India

GoR Government of Rajasthan

GRC Grievance Redress Committee

IA Implementing Agency

IP Indigenous People

IPIU Investment Program Implementation Unit

IPMC The Investment Program Management Consultant

IPMU Investment Program Management Unit

IR Income Restoration

ISA Initial Social Assessment

LA Land Acquisition

LAA Land Acquisition Act

LIG Lower Income Group

LSGD Local Self Government Department

MFF Multi-Tranche Financing Facility

M&E Monitoring and Evaluation

NGO Non-Government Organization

NH National Highway

NRRP National Resettlement & Rehabilitation Policy

OMG Operations and Maintenance Contractors

PAF Project Affected Family

PAH Project Affected Household

PAP Project Affected Person

PIU Project Implementation Unit

PMU Project Management Unit

PRI Panchayati Raj Institution

PWD Public Works Department

RCC Reinforced Cement Concrete

RF Resettlement Framework

RP Resettlement Plan

ROR Record of Rights

RoW Right of Way

R&R Resettlement and Rehabilitation

RS Resettlement Specialist

RUIDP Rajasthan Urban Infrastructure Development Project

RUSDIP Rajasthan Urban Sector Development Investment Programme

SC Supervision Consultant

SDM Sub Divisional Magistrate

SES Socio-Economic Survey

SHG Self Help Group

SJSRY Swarn Jayanti Gram Rojgar Yojna

ST Scheduled Tribe

UDD Urban Development Department

ULB Urban Local Body

WTP Water Treatment Plant

1

SHORT RESETTLEMENT PLAN

A. Scope of Land acquisition and resettlement 1. The Investment Program will optimize social and economic development in 15 selected towns1 in Rajasthan through investments in urban infrastructure (water supply, sewerage and sanitation, solid waste management, urban drainage, and urban transport and roads), social infrastructure, and infrastructure support to cultural heritage. The Program will also provide policy reforms to strengthen urban governance, management, and support for urban infrastructure and services.2 This short resettlement plan (RP) is prepared for the waste water sub-project in Dholpur. 2. The infrastructure will extend throughout many parts of the town, where pipes for new secondary and tertiary sewer networks will be buried within or alongside roadways. It has been proposed to construct 10 MLD sewage treatment plant-1 with up flow anaerobic sludge blanket process, laying of 3.2 Km outfall sewer line, trunk and laterals sewer of 75.7 km total length and construction of 10,000 house service connection, construction of sewage pumping station, laying of outfall sewer line of 1000mm dia, trunk and laterals sewers of 93km total length and construction of 10,000 house service connection. Appendix 1 shows each sub-project component and expected resettlement impacts. The balance works of sewer lines along with house service connections and sewage pumping station-2 is taken under Phase II The location of sub-project components is provided in Map 1, 2 and 3. 3. This Resettlement Plan is in continuation of the SRP earlier prepared for the detailed sewerage system design for whole city. The entire city was divided in three parts under the system defined as a) Western Zone, b) Eastern Zone Part ‘A’ (package: RUSDIP/DLP/TR-02/WW/04 and 05) and Eastern Zone Part ‘B’(package: RUSDIP/DLP/TR-02/WW/08). The design was made for the full city but the sanction done under Phase I included a) Western Zone and b) Eastern Zone Part ‘A’. These zones did not involve any pumping but the Eastern Zone Part ‘B’ required pumping and was left for Phase II. 4. This Resettlement Plan has been prepared in tune with the ADB Handbook on Resettlement and the agreed Resettlement Framework (RF). The Methodology prescribed by ADB was scrupulously adhered to, to find out any adverse or Involuntary Resettlement impact in the project area. Since the same areas as defined with the design population and flows for the Eastern Part B – Dholpur City as adopted in the original design are adopted, the coverage of present package (RUSDIP/DLP/TR-02/WW/08) are area near Ghanta ghar (ward no 10); Gurudwara and Sitaram Colony (ward no 11); Hanuman Tiraha, halwai Khan, Kharanja Road and jail gali (ward no 16); Radha Bihari Mandir, Tallyya, Durga colony (ward no 17); Nagar Palika, Hardev Nagar (ward no 18); Civil Hospital Area (ward no 19); Glass Factory Road Area, Purani Sarai area(ward no 27); Naya pura basti, Harijan Basti, Narani Mata Tirah(ward no 29); Modi tiraha and Punjab National Bank nearby area(ward no 30); Niahal ganj and Lal Bazar area and Jagan Chowraha(ward no 31); Nihaleshwar Mandir , Purani Sabji Mandi and Topwala park area and Bajaria Road(ward no 32); Garadpura Road (ward no 33); Panchamukhi hanuman Tiraha, Grandil Mohalla(ward no 34); Purana Bijali Ghar, Bhamtipura, Post office area, Gir-raj Colony(ward no 35); Kela Colony & Bhamtipura Road(ward no 36); Bag Babasa Civil Line area(ward no 38) 5. The works of the sub-project will not have any resettlement impacts given that the STP will be constructed on vacant government land at Tagawali village (2.64 ha) and sewer

1 Particularly district headquarters and towns with significant tourism potential. 2 The assistance will be based on the State-level framework for urban reforms, and institutional and governance reforms recommended by the Government of India through the Jawaharlal Nehru National Urban Renewal Mission and Urban Infrastructure Development Scheme for Small and Medium Towns.

2

mains will not have resettlement impacts since all 96 Km of pipe lines will pass through the main road which is open road with sufficient government land (RoW). Temporary disturbance in normal life due to trenching for laying of the Sewer lines however cannot be avoided. Only one temporarily affected person comes under the stretch in the Western Zone and Eastern Zone (part-A). The scope of land acquisition and identified temporary resettlement impact is presented in the Table 1. Whereas, Eastern Zone Part (B) have no affected person and public consultations were conducted throughout the stretch where likely inconvenience is expected (Appendix 6). The width of the commercial/ Market street where trenching will be undertaken for laying of sewer line are approx 5.5 meter to 12 meter in which 200 mm dia to 300 mm dia sewer line will be laid down . Less than 1 meter wide trench having depth of minimum 1 meter to 4.5 meter will be made to lay the sewer line. A significant portion of proposed area area where sewer line is to be laid has small commercial activities. During site verification and survey it is found that there might be short term temporary inconvenience but no major impact on commercial activities can be perceived. Therefore, no affected person was found, the accessibility of the shops will not be hampered since sewer line will be laid in the middle of road and on both sides minimum 2 -4 meter wide passages will be still available during construction time . Possibility of minor traffic diversion exists for which there are alternative streets available where traffic can be diverted easily in almost all of the project area.

6. The work of Phase-I (RUSDIP/TR-02/DLP/WW/04&05) is under execution in which 25 Km sewer line laid & civil work of STP is in progress. Phase II (RUSDIP/TR-02/DLP/WW/08) works include supply, Laying, Jointing & commissioning of branch sewers, lateral sewer etc. covering ward nos. 10, 11, 16-19, 27, 29-36 and 38. The work is under implementation. In Phase III (RUSDIP/TR-02/DLP/WW/10) it is proposed to provide sewerage network, sewage treatment facilities for left out areas of Dholpur town. This area includes ward no 7,8,9,20,21,22,23,24,25 and a part area of ward No 10 & 26 to provide a comprehensive sewerage related facilities for whole of the town. Earlier this area was left out as it was not feasible to drain it with the major northern part of city as a ridge line passing through near the Govt. Hospital separating the Slope of the city in North & Southern direction. The areas proposed to be benefitted by these proposal are

S.No. Ward No % Area proposed to be covered

1 Ward No 7 100%

2 Ward No 8 100%

3 Ward No 9 100%

4 Ward No 10 55%

5 Ward No 20 100%

6 Ward No 21 100%

7 Ward No 22 100%

8 Ward No 23 100%

9 Ward No 24 100%

10 Ward No 25 100%

11 Ward No 26 55%

7. The proposed project area flow is to be to discharged at single location at Shekhupura, south of Radha Vihar Colony, in south east direction of city and the treated

3

effluent will be discharged in a local drain nearby from where it will discharge in river Chambal. It is proposed to develop Sewage Treatment Plant in modular way with present capacity to be developed is 3.00 MLD.

8. There will be no permanent temporary impact in package RUSDIP/DLP/TR-02/WW/10, but there will be minor inconvenience as the area covered under this package are mostly narrow road of 2.5- 3.5m width. Though most of them are residential areas, few small shops were also found as adjoining parts of their respective residences. As there will be minor temporary inconvenience with regard to mobility community at large were consulted and were informed about the benefits of the project through various public consultations. Special emphasis was made to hold such ward meetings with not only ward members but with other stake holders as well. It has been also decided that all who were residing or having residential cum commercial structures along the project road stretches which are covered under sewerage network would be enlisted and informed about the project and likely inconveniences that might occur during implementation. Consequently, all the ward members of respective wards took the initiative in bringing awareness among the people and in each ward a written consent (Resolution or Sankalp) was taken from the Ward member or Parshad along with other participants. All the ward members of respective wards were disclosed of the proposed RUIDSP works who then took the initiative in bringing awareness among the people and as a concurrence their consent was also takenin the form of “sankalps” . They have stated no objection with the sewer work to be taken up by RIUDP in Dholpur. A written consent was also taken from all the ward members/councilors i.e., the Parshad along with some of the important decision makers (stakeholders) in the community. ( Refer appendix 7)

B. Socio-Economic Background

9. As the Project will not acquire any private land, social Impacts are confined to movable structures placed on RoW. Affected mobile vendors will be assisted in moving temporarily to the other side of the road and re-establish their structures as soon as construction is over. Where moving is not required, access will be ensured by the contractor. The construction period is estimated to be 14 day per section of work and all the affected business establishments and vendors will be given 14 day income loss as per the policy framework and entitlements for the Program. To assess the temporary social impacts a series of transect walks were conducted in the city; this was followed by a 100 percent census and a socio-economic survey conducted in the areas, where the works are to be done. This was conducted with the help of a predesigned tool. The Census was conducted using a two page questionnaire. 10. A Socio-economic Survey on 20% of the occupants of the affected structures was Conducted. as per the requirements after the completion of Census survey in the stretches of impact of the proposed construction package. This was done with the aid of a structured close ended (for ease of information processing ).

Table 1: Summary of Resettlement Impacts

Impact

Permanent Land Acquisition (ha) 0

Temporary land Acquisition (ha) 0

Affected Households (Ahs) 1

Titled Ahs 1

Non-titled Ahs 0

Female AH 0

IP/STAH 0

4

BPL AH 0

Affected Trees/Crops 0

Affected Common Structures 0

Average Family Size 5.0

Affected Household Income (per month) 3000

Income Sources Affected Residential cum Commercial Source: Consultant’s Census and Socio – Economic Survey conducted on June 2008 (for package: RUSDIP/DLP/TR-02/WW/04 and 05) January 2012 (for package: RUSDIP/DLP/TR-02/WW/08) and on June 2012 (for package: RUSDIP/DLP/TR-02/WW/10)

11. The only AP is having a residence-cum-business establishment within the RoW. He has a nuclear family with 5 members. The affected structure is semi-pucca, temporary in nature and the income from this structure is Rs 100 per day3. However, as per decisions, It was ensured that the AP was paid minimum wage of Rs. 100/- per day as in 2010 against loss of livelihood. The detail socio-economic data is presented in Appendix 2. C. Policy Framework and Entitlements

12. The Policy Framework and entitlements for the program are based on national laws:

The Land Acquisition Act, 1894 (LLA, amended in 1984), and the National Resettlement and

Rehabilitation Policy, 2007 (NRRP); ADB’s Policy on Involuntary Resettlement, 1995; and

the agreed Resettlement Framework (RF). Based on these, the following core involuntary

resettlement principles applicable are:

(i) land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative sub-Project designs;

(ii) where unavoidable, time-bound RPs will be prepared and affected persons (APs) will be assisted in improving or at least regaining their pre-program standard of living;

(iii) consultation with APs on compensation, disclosure of resettlement information to APs, and participation of APs in planning and implementing sub-Projects will be ensured;

(iv) vulnerable groups will be provided special assistance4; (v) payment of compensation to APs including non-titled persons (e.g., informal

dwellers/squatters, and encroachers) for acquired assets at replacement rates;

(vi) payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities;

(vii) provision of income restoration and rehabilitation; and (viii) establishment of appropriate grievance redress mechanisms.

13. Policy framework and entitlements are further discussed in Appendix 3. The entitlement matrix5 for the sub-Project based on the above policies of this RP are in Table 2.

3 Minimum wage in Rajasthan was Rs.73 per day (2009), since the income of the AP was Rs. 100 during socio economic

survey June 2008, the question of minimum wages did not arise, when the SRP was prepared in February 2009 for the first

time. Subsequently due to change of scope, SRP was revised for the second time in January 2012. The present SRP is the

third revision for incorporating the scope of new package. However, the no. of AP remains 01 as in the first submission. The AP

was paid Rs 100 per day as compensation on 04.10.2010 as per the minimum wage rate applicable at that time i.e. Rs. 100/-

per day. . 4 Including poor households, households headed by women, the elderly, the disabled scheduled tribes &

Scheduled Caste considered vulnerable based on the agreed Indigenous People Development Framework

(IDPF) 5 While no impacts are noted on common resources, such row is included in the entitlement matrix as there is a

probability of impacts on common resources should alignment change after detailed design

5

Table 2: Entitlement Matrix

Sl. No

Type of Loss Application Definition of Entitled Person

Compensation Policy Implementation Issues

Responsible Agency

1 Temporary disruption of livelihood

Legal titleholders, non-titled displaced persons

• 30 days advance notice regarding construction activities, including duration and type of disruption

• Contractor’s actions to ensure there is no income/access loss consistent with the IEE.6

• Assistance to mobile vendors/hawkers to temporarily shift for continued economic activity.7

• For construction activities involving unavoidable livelihood disruption, compensation for lost income or a transitional allowance for the period of disruption, whichever is greater

• Identification of alternative temporary sites to continue economic activity

• Valuation Committee will determine income loss.

• Contractors will perform actions to minimize income/access loss.

2 Any other loss not identified

• Unanticipated involuntary impacts will be documented and mitigated based on the principle of the Resettlement Framework (RF)

• NGO will ascertain the nature and extent of such loss. IPMU will finalize the entitlements in line with the RF

6 This includes: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time.

7 For example assistance to shift to the other side of the road where there is no construction.

6

D. Consultation, Information Dissemination, Disclosure, and Grievance Redress

14. The RP was prepared in consultation with stakeholders. Meetings and individual interviews were held involving stakeholders, particularly potentially temporarily affected persons; and transect walks, census, survey and interviews were conducted to determine the potential impacts of sub-Project construction to prepare the sample sub-Project RP. Following the model developed for the MFF, a town-wide stakeholder consultation workshop was conducted which provided an overview of the Program and sub-Projects to be undertaken in Dholpur; and discussed the Government and ADB’s resettlement policies and potential resettlement impacts of the sub-Projects in Dholpur. During the workshop, Hindi versions of the RF were provided to ensure stakeholders understood the objectives, policy principles and procedures for any land acquisition, compensation and other assistance measures for any AP. During consultations, key issues raised were: (i) participants expressed satisfaction that there was a sub-Project taking care of their needs which they have waited for 25-30 years; (ii) they are not hesitant to move or shift if necessary to accommodate the work; (iii) they are willing to provide labor for the sub-Project; and (iv) they raised that it is important to repair the roads after sub-Project construction. Consultation records are in Appendix 4.

15. Information continues to be disseminated to APs and beneficiaries through various10. media. English and Hindi versions of the RF and RP are placed in the Urban Local Body (ULB) office and APs have accesses to RPs. The NGO engaged to implement the RP will continue consultations, information dissemination, and disclosure. A strategy for continued consultations and participation is in the RF. The RP is available in the ULB office, Investment Program Project Management Unit and Implementation Unit (IPMU and IPIU) offices, and the town library. The finalized RP will also be disclosed in ADB’s website, the State Government website, the local government website, and the IPMU and IPIU websites. ADB review and approval of the RP is required prior to award of civil works contracts; and compensation/assistance of APs is required prior to commencement of civil works. Consultation and disclosure activities to be followed are in Appendix 5. 16. Grievances of APs will first be brought to the attention of the implementing NGO or Social Development Specialist (SDS). Grievances not redressed by the NGO or SDS will be brought to the City Level Committees (CLC) set up to monitor project implementation in each town. The CLC, acting as a grievance redress committee (GRC) is chaired by the District Collector with representatives from the ULB, state government agencies, IPIU, community-based organizations (CBOs) and NGOs. As GRC, the CLC will meet every month. The GRC will determine the merit of each grievance, and resolve grievances within a month of receiving the complaint, failing which the grievance will be addressed by the inter-ministerial Empowered Committee (EC). The Committee will be chaired by the Minister of Urban Development and Local Self Government Department (LSGD), and members will include Ministers, Directors and/or representatives of other relevant Government Ministries and Departments. Further grievances will be referred by APs to the appropriate courts of law. The IPIU will keep records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The grievance redress process is shown in Figure 1.

7

Figure 1: Grievance Redress process

CLC = City Level Committee, GRC = Grievance Redress Committee, IPIU=Investment Program Implementation Unit, IPMU = Investment Program Management Unit, NGO = nongovernmental organization, SDS = Social Development Specialist

All costs involved in resolving the complaints will be borne by the IPMU. The GRCs will continue to function throughout the project duration

E. Compensation and Income Restoration 17. APs will be provided 30 days advance notice to ensure no or minimal disruption in livelihood. If required, they will also be assisted to temporarily shift for continued economic activity. For example they will be assisted to shift to the other side of the road where there is no construction. Ensuring there is no income or access loss during sub-Project construction is the responsibility of contractors. Consistent with the initial environmental examination, contractors will ensure: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time.

NGO/SDS

Not Addressed

Affected Persons

IPMU

Grievance

Addressed

GRC/CLC

Grievance

Addressed

Court of Law

Grievances

Grievances

Not Addressed

Grievance

Addressed

Not Addressed

8

18. Should construction activities result in unavoidable livelihood disruption, compensation for lost income or a transitional allowance for the period of disruption whichever is greater will be provided. Vulnerable APs will be given priority in project construction employment. 19. Compensation and assistance to APs must be made prior to possession of land/assets and prior to the award of civil works contracts.

F. Institutional Framework, Resettlement Costs, and implementation Schedule 20. The LSGD is the Executing Agency (EA) responsible for overall technical supervision and execution of all sub-Projects funded under the Program. The Implementing Agency (IA) is the Project Management Unit of the ongoing RUIDP, which has been expanded and assigned as the IPMU, to coordinate construction of sub-Projects and ensure consistency across the towns. The EC provides LSGD with central policy guidance and coordination. The IPMU is assisted by: Investment Program Management Consultants (IPMC) who manages the Program and assure technical quality of the design and construction; and Design and Supervision Consultants (DSC), who are designing the infrastructure, managing the tendering of Contractors, and supervising construction. 21. IPIUs have already been established in the project towns to manage implementation of sub Projects in their areas. CLCs will monitor sub-Project implementation in each town. They will appoint Construction Contractors (CC) to build elements of the infrastructure in a particular town (supervised by DSC). Once the infrastructure begins to operate, responsibility will be transferred to the appropriate state or local Government Agency (GA), who will be given training, support and financial assistance through the Program where necessary to enable them to fulfill their responsibilities. They will employ local Operations and Maintenance Contractors (OMC) to maintain and repair the infrastructure as required. 22. Resettlement issues are coordinated by a Social Development Specialist (IPMU SDS) within the IPMU, who ensures that all sub-Projects comply with involuntary resettlement safeguards. A Resettlement Specialist (RS) who is part of the IPMC team assists the SDS. SDS, as part of the DSC, have been appointed to work with each IPIU to update the RP in the detailed design stage, and to prepare RPs for new subprojects, where required to comply with Government and ADB policies. NGO is appointed to implement RPs. The responsible agencies, resettlement costs, and implementation schedules are provided in Tables 3, 4, and 5, respectively.

Table 3: Institutional Roles and Responsibilities

Activities Agency Responsible

Sub-project Initiation Stage

Finalization of sites/alignments for sub-projects IPMU Disclosure of proposed land acquisition and sub-project details by issuing Public Notice Meetings at community/household level with APs of land/property Formation of Valuation Committees

IPMU NGO IPMU

RP Preparation Stage Conducting Census of all APs IPMU/IPIU/NGO Conducting FGDs/meetings/workshops during SIA surveys IPIU/NGO Computation of replacement values of land/properties proposed for acquisition and for associated assets

VC/IPIU

Categorization of APs for finalizing entitlements IPIU/IPMU Formulating compensation and rehabilitation measures Conducting discussions/meetings/workshops with all APs and other

IPIU/IPMU IPIU/NGO

9

Activities Agency Responsible

stakeholders Fixing compensation for land/property with titleholders VC/IPMU Finalizing entitlements and rehabilitation packages IPIU/IPMU Disclosure of final entitlements and rehabilitation packages IPIU/NGO Approval of RP IPMU/ADB Sale Deed execution and payment Taking possession of land

IPMU

Resettlement Plan Implementation Stage Implementation of proposed rehabilitation measures NGO/SDS Consultations with APs during rehabilitation activities NGO/SDS Grievances redressal NGO/SDS/GRC Monitoring IPIU/IPMU ADB = Asian Development Bank, FGD = focus group discussions, GRC = Grievance Redress Committee, LSGD= Local Self Government Department, NGO = nongovernmental organization, IPMU = investment program management unit, IPIU = investment program implementation unit, SDS = Social Development Specialist, SIA = social impact assessment, VC = Valuation Committee.

Table 4: Summary of Land acquisition and Resettlement Costs

Item Unit APs Rate Costs

1. Relocation & Transfer

Loss of Income Livelihood 14 days 1 100 1400

Shifting Assistance (estimated at Rs. 200) Once 1 200 200

Sub Total item 1 1600

2 Administrative & Implementation costs

Implementing NGO covering NGO engagement, cost of census and survey of APs and inventory of assets, cost of information and consultations, training and monitoring (including evaluation by independent agency), and rental of office space and required physical facilities and materials

Lump Sum 100000

3 Contingencies

Price (5%) of Project Cost 5080

Physical (20%) for unanticipated impacts such as temporary impacts on structures or temporary loss of land

20320

Total 1,27,000 Source: Consultant’s Census and Socio – Economic Survey conducted on June 2008 (for package: RUSDIP/DLP/TR-02/WW/04 and 05) on January 2012 (for package: RUSDIP/DLP/TR-02/WW/08) and on June 2012 (for package: RUSDIP/DLP/TR-02/WW/10)

10

Table 5: Schedule of Resettlement Implementation Activity Months

i. Appointment of NGOs 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 ii. Briefing of the CLC on GRC functions

iii. Census and socio-economic surveys(issuance of ID cards)*

iv. Consultations and disclosure v. Confirmation of government land to be used and transfer from other departments

vi. RP updating** vii. RP review and approval (PMU and ADB) ***

viii.Issue notice to APs ix. Compensation and resettlement assistance

x. Relocation as required xi. Skills training as required xii. Takeover possession of acquired property

xiii.Internal monitoring xiv. Handover land to contractors xv. Start of civil works xvi. External monitoring xvii. Rehabilitation of temporarily occupied lands

Immediately after construction

*The census will be the cut-off date for non-titled APs. For titles APs, the cut-off date is the date of notification. **The RP will be updated based on the final detailed design and AP census and surveys ***Endorsement and disclosure of finalized RPs consistent with the RF to be undertaken.

G. Monitoring and Evaluation

23. RP implementation will be closely monitored to provide the IPMU with an effective basis for assessing resettlement progress and identifying potential difficulties and problems. Internal monitoring will be undertaken by the IPIU with assistance from the IPMU. Internal monitoring will involve: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after any resettlement impact utilizing baseline information established through the socio-economic survey of APs undertaken during project sub-preparation, and (iii) overall monitoring to assess AP status. Job charts will be given to the SDS. The job charts will indicate the targets to be achieved during the month. Monthly progress report will be prepared and submitted to the IPMU, reporting actual achievements against the targets fixed in their respective job charts and reasons for shortfalls, if any. The IPIU will be responsible for managing and maintaining AP databases, documenting results of AP census, and verifying asset and socio-economic survey data which will be used as the baseline for assessing RP implementation impacts. The EA will appoint an independent agency to undertake external monitoring to document: (i) restoration of income levels; (ii) changes and shifts in occupation pattern; (iii) changes in AP type of housing; (iv) assessment of APs access to amenities, such as water, electricity, and transportation; and (v) performance of NGO, IPIU, and IPMU in resettlement implementation. The independent agency will monitor sub-Projects twice a year and submit reports directly to the EA (IPMU). The EA will submit all external monitoring reports to ADB for review. Further details are in the RF.

11

Map 1. PROPOSED NETWORK OF DHOLPUR WASTE WATER (Phase I)

12

Map 2. PROPOSED NETWORK OF DHOLPUR WASTE WATER (Phase II)

13

Map 3. PROPOSED NETWORK OF DHOLPUR WASTE WATER (Phase III)

WARDS MARKED IN WW/10

14

15

Appendix 1

COMPONENTS AND RESETTLEMENT IMPACTS

WESTERN ZONE AND EASTERN ZONE ( PART-A) Package: RUSDIP/DLP/TR-02/WW/04 & 05

Sl. No. Components IR Impact

i 10 MLD sewerage treatment plant with up flow anaerobic sludge blanket process

No Impact as on vacant government land

ii Laying of 3.2 km outfall sewer line No Impact as on vacant government land

Iii Laying of trunk and laterals sewers of 75.7km total length

Only temporary impacts on livelihood of one residential cum commercial structure work will be done in road RoW

iv Construction of 10000 house service connection No Impact as on vacant government land

ADDITIONAL COMPONENTS OF EASTERN ZONE (PART-B) Package: RUSDIP/DLP/TR-02/WW/08

v Providing, Laying, Jointing, Testing and Commissioning of Sanitary Sewers along with all necessary manholes, appurtenances etc. and restoration of roads including Pumping main.

No Impact with probability of minor temporary inconvenience to small commercial activities

vi Construction of Intermediate sewage pumping station (SPS) in eastern Part-B

No Impact

vii Construction of treated sewage pumping station (TSPS) at outlet of STP to Pump treated effluent from SPS to Node-9 incl. pipeline work

No Impact

COMPONENTS OF Package: RUSDIP/DLP/TR-02/WW/10

viii 1. Provide sewerage network, sewage treatment facilities for left out areas of Dholpur town. This area includes ward no 7,8,9,20,21,22,23,24,25 and a part area of ward No 10 & 26 and also to develop a Sewage Treatment Plant in modular way with present capacity of 3.00 MLD.

Though there will be minor inconvenience along the lateral connections, there will be no permanent or temporary impact in areas proposed for sewerage network as well as in the proposed STP site.

16

Appendix 2

Socio-economic Survey Summary

Location Name of Establishment/vendor

Type of structure

Social Category

Daily income (in Rs.)

Shiv Nagar, Nursery Road

Keshav Singh Residential cum

commercial

OBC 100

Source: Consultant’s Census and Socio – Economic Survey conducted on June 2008 (for package: RUSDIP/DLP/TR-02/WW/04 and 05) Category of AP change after site verification/preparation of Microplan

17

APPENDIX 3:

POLICY FRAMEWORK AND ENTITLEMENTS

A. Policy and Legal Framework The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) the National Resettlement and Rehabilitation Policy, 2007 (NRRP); and ADB’s Policy on Involuntary Resettlement, 1995. The salient features of Government and ADB polices are summarized below.

1. Government Policy

a. National Resettlement and Rehabilitation Policy, 2007 The NRRP stipulates the minimum facilities to be ensured for persons displaced due to the acquisition of land for public purposes. The objectives of the Policy are:

(i) to minimize displacement and to identify non-displacing or least displacing alternatives;

(ii) to plan resettlement and rehabilitation of project affected families (PAFs) or project affected households (PAHs), including tribal and vulnerable households;

(iii) to provide improved standard of living to PAFs or PAHs; and (iv) to facilitate a harmonious relationship between the requiring body and PAFs.

Though NRRP is applicable for projects where over 400 PAFs in the plains or 200 PAFs in hilly or tribal areas are displaced, the basic principles can be applied to resettling and rehabilitating PAFs regardless of the number affected. NRRP’s provisions are intended to mitigate adverse impacts on PAFs. While key principles of NRRP are similar, and for some items go beyond ADB’s Policy on Involuntary Resettlement (1995), NRRP excludes linear projects (which acquire only narrow strips of land). Linear impacts and temporary linear impacts (which is the likely impact of the Program) are not covered by NRRP. Further, there is no law on resettlement in the country. The law relating to the acquisition of privately owned immoveable property is the Land Acquisition Act of 1894 (LAA, amended 1984) discussed in the following section.

b. Land Acquisition Act, 1894 The LAA provides a framework for facilitating land acquisition in India. LAA enables the State Government to acquire private land for public purposes. LAA ensures that no person is deprived of land except under LAA and entitles APs to a hearing before acquisition. The main elements of LAA are:

(i) Land identified for the purpose of a project is placed under Section 4 of the LAA. This constitutes notification. Objections must be made within 50 days to the District Collector (DC, the highest administrative officer of the concerned District).

(ii) The land is then placed under Section 6 of the LAA. This is a declaration that the Government intends to acquire the land. The DC is directed to take steps for the acquisition, and the land is placed under Section 9. Interested parties are then invited to state their interest in the land and the price. Under Section 11, the DC will make an award within one year of the date of publication of the declarations. Otherwise, the acquisition proceedings shall lapse.

18

(iii) In case of disagreement on the price awarded, within 6 weeks of the award, the parties (under Section 18) can request the DC to refer the matter to the Courts to make a final ruling on the amount of compensation.

(iv) Once the land has been placed under Section 4, no further sale or transfer is allowed.

(v) Compensation for land and improvements (such as houses, wells, trees, etc.) is paid in cash by the project authorities to the State Government, which in turn compensates landowners.

(vi) The price to be paid for the acquisition of agricultural land is based on sale prices recorded in the District Registrar's office averaged over the three years preceding notification under Section 4. The compensation is paid after the area is acquired, with actual payment by the State taking about two or three years. An additional 30 percent is added to the award as well as an escalation of 12 percent per year from the date of notification to the final placement under Section 9. For delayed payments, after placement under Section 9, an additional 9 percent per annum is paid for the first year and 15 percent for subsequent years.

2. ADB’s Policy on Involuntary Resettlement, 1995 The three important elements of ADB’s involuntary resettlement policy are (i) compensation to replace lost assets, livelihood, and income; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same level of well-being with the project as without it. For any ADB operation requiring involuntary resettlement, resettlement planning is an integral part of project design, to be dealt with from the earliest stages of the project cycle, taking into account the following basic principles:

(i) Involuntary resettlement will be avoided whenever feasible. (ii) Where population displacement is unavoidable, it should be minimized. (iii) All lost assets acquired or affected will be compensated. Compensation is

based on the principle of replacement cost. (iv) Each involuntary resettlement is conceived and executed as part of a

development project or program. APs need to be provided with sufficient resources to re-establish their livelihoods and homes with time-bound action in co-ordination with civil works.

(v) APs are to be fully informed and closely consulted. (vi) APs are to be assisted to integrate economically and socially into host

communities so that adverse impacts on the host communities are minimized and social harmony is promoted.

(vii) The absence of a formal title to land is not a bar to ADB policy entitlements. (viii) APs are to be identified and recorded as early as possible to establish their

eligibility, through a census which serves as a cut-off date, and prevents subsequent influx of encroachers.

(ix) Particular attention will be paid to vulnerable groups including those with out legal title to land or other assets; households headed by women; the elderly or disabled; and indigenous groups. Assistance must be provided to help them improve their socio-economic status.

(x) The full resettlement costs will be included in the presentation of project costs and benefits.

19

C. Comparison of Borrower’s Policy with the RF The NRRP represents a significant milestone in the development of a systematic approach to address resettlement issues in India. LAA, 1894 however gives directives for acquisition of land in public interest and provides benefits only to titleholders. Table 1 presents a comparison of Government polices (LAA and NRRP) in comparison with the RF which is consistent with ADB’s involuntary resettlement policy.

Table 1: Comparison Between the Borrower’s and ADB’s Involuntary Resettlement

Policy

Policy Principles LAA NRRP Remarks Compliance of proposed RF with ADB’s IR Policy

1. Involuntary resettlement should be avoided where feasible.

r� a�

LAA is applicable wherever private land is to be acquired by Government for public purpose.

This is addressed in the RF. The locations for project components have been identified in such a manner that IR is avoided to the extent possible. These IR impacts shall be further minimized during detailed designs.

2. Where population displacement is unavoidable, it should be minimized by exploring viable project options.

r� a�

LAA is applicable wherever private land is to be acquired by Government for public purpose.

This is addressed in the RF. The locations for project components have been identified in such a manner that IR is avoided to the extent possible. These IR impacts shall be further minimized during detailed designs.

3. If individuals or a community must lose their land, means of livelihood, social support systems, or way of life in order that a project might proceed, they should be compensated and assisted so that their economic and social future will generally be at least as favorable with the project as without it. Appropriate land, housing, infrastructure, and other compensation, comparable to the without project situation, should be provided to the adversely affected population, including indigenous groups, ethnic minorities, and pastoralists who may have usufruct or customary rights to the land or other resources taken for the project.

r� a�

According to the ADB’s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more than 500 families (roughly about 2,000 persons) in plain areas and 200 families (roughly about 1,000 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India.

The RF addresses the IR impacts. The entitlements to the APs are outlined in the Entitlement Matrix.

4. Any involuntary resettlement should, as far as possible, be conceived and executed as a part of a development project or program and resettlement plans

r� a�

According to the ADB’s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is

The RF addresses the IR impacts. The entitlements to the APs are outlined in the Entitlement Matrix.

20

Policy Principles LAA NRRP Remarks Compliance of proposed RF with ADB’s IR Policy

should be prepared with appropriate timebound actions and budgets. Resettlers should be provided sufficient resources and opportunities to reestablish their homes and livelihoods as soon as possible.

required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more than 400 families (roughly about 2,500 persons) in plain areas and 250 families (roughly about 1,250 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India.

� �

LAA does not provide for resettlement. However, it specifies the time limit for acquisition, though the project / program for which it is conceived need not necessarily be time-bound.

A time-bound action plan and implementation schedule for the IR activities is outlined. The key RP activities are identified and the responsibilities for the same outlined.

5. The affected people should be fully informed and closely consulted on resettlement and compensation options. Where adversely affected people are particularly vulnerable, resettlement and compensation decisions should be preceded by a social preparation phase to build up the capacity of the vulnerable people to deal with the issues.

r� a�

LAA recognizes only titleholders, who are to be notified prior to acquisition.

Consultations have been carried out with APs. This will be further consolidated by the RP implementing NGO. The plan for information disclosure in the project, including the RF.

6. Appropriate patterns of social organization should be promoted, and existing social and cultural institutions of resettlers and their hosts should be supported and used to the greatest extent possible. Resettlers should be integrated economically and socially into host communities so that adverse impacts on host communities are minimized. One of the effective ways of achieving this integration may be by extending development benefits to host communities.

r� a�-

This is addressed in the Entitlement Matrix.

7. The absence of formal legal title to land some affected groups should not be a bar to

r� a�

LAA provides for every affected person to receive a notification prior to

The process for verification of impacts and establishing the eligibility

21

Policy Principles LAA NRRP Remarks Compliance of proposed RF with ADB’s IR Policy

compensation. Affected persons entitled to compensation and rehabilitation should be identified and recorded as early as possible, preferably at the project identification stage, in order to prevent an influx of illegal encroachers, squatters, and other nonresidents who wish to take advantage of such benefits. Particular attention should be paid to the needs of the poorest affected persons including those without legal title to assets,, female-headed households and other vulnerable groups, such as indigenous peoples, and appropriate assistance provided to help them improve their status.

acquisition and for a hearing in case of any objection. Acquisition under the Act is permitted within one year from the date of declaration of intent to acquire, failing which, the process has to start again. LAA does not regard non-titleholders as APs. The Rajasthan Urban Housing and Habitat

Policy, 2006 aims to provide tenurial rights to urban slum dwellers with special emphasis on persons belonging to scheduled castes, scheduled tribes, weaker sections, physically handicapped and widows. This is consistent with recognizing those without legal titles and the vulnerable.

of the APs is outlined in the RF.

8. The full costs of resettlement and compensation, including the costs of social preparation and livelihood programs as well as the incremental benefits over the “without project” situation, should be included in the presentation of Project costs and benefits.

r� a�

According to the ADB’s IR policy full RP is required when 200 or more people will experience major impacts. A Short RP is required when resettlement is insignificant when less than 200 people will experience major impacts. According to the NRRP, RP should be prepared when it involves resettlement of more than 500 families (roughly about 2,500 persons) in plain areas and 250 families (roughly about 1,250 people) in hilly areas, Desert Development Programme (DDP) blocks, areas mentioned in Schedule V and Schedule VI of the Constitution of India.

The RF addresses the IR impacts. The entitlements to the APs are outlined in the Entitlement Matrix.

� �

The NRRP’s concept of replacement cost is not clearly defined. However, the NRRP does consider various compensation packages to substitute the losses of APs.

This is addressed in the Entitlement Matrix

22

Policy Principles LAA NRRP Remarks Compliance of proposed RF with ADB’s IR Policy

9. To better assure timely availability of required resources and to ensure compliance with involuntary resettlement procedures during implementation, eligible cots of resettlement and compensation may be considered for inclusion in Bank loan financing for the project, if requested.

r� a�-

The impacts have been assessed and RP costs according to the entitlement matrix have been worked out. These costs are included in the Project Costs.

.

23

APPENDIX 4: PUBLIC CONSULTATIONS

24

25

Issues Discussed

1. The proposed Sewer line are aimed to cover 75% of all wards and area of the city 2. Livelihood affected households shall be given assistance in the mode of cash

compensation 3. As far as possible local people shall be employed by the contractor during

construction work 4. Due safety measures shall be taken during actual construction work 5. Sewarage work to be confined within existing ROW 6. Compensation package to be determined at the local market price in the event of

land acquisition (if any) 7. Willingness to shift in nearby places of Mobile kiosk/vendors

People’s Perception about the project

The overall benefits of the Project as per the local residents recorded during public

consultation and field survey are:

1. This Project will ensure smooth canalization and discharge of domestic liquid effluents

2. This in turn stop or reduce to significant level of the accumulation of waste and fecal matters on surface

3. The Project would ensure reduction in the incidence of waterborne diseases such as diarrhea and hepatitis

4. This Project will ensure hygienic conditions in the city and save the water bodies from, pollution.

26

APPENDIX 5

CONSULTATION AND DISCLOSURE

A. Consultation

Consultations will be held with special emphasis on vulnerable groups. Encouraging public participation in consultations informs the public of the Program and serves as a venue for the public to express their opinion on priorities which the Program should address.

The key stakeholders to be consulted during RP implementation and Program implementation includes:

(i) all APs, including vulnerable households; (ii) program beneficiaries; (iii) host populations in resettlement sites; (iv) elected representatives, community leaders, and representatives of community-

based organizations; (v) local NGOs; (vi) local government and relevant government agency representatives; and (vii) Program staff, IPMU, IPIU, and consultants.

Consultations conducted during RP implementation will identify help required by APs during rehabilitation. Continuing involvement of those affected by sub-Projects is necessary in the resettlement process. The IPIU will ensure that APs and other stakeholders are informed and consulted about the sub-Project, its impact, their entitlements and options, and allowed to participate actively in the development of the sub-Project. This will be done particularly in the case of vulnerable APs, who will be encouraged to choose options that entail the lowest risk. This exercise will be conducted throughout the sub-Project—during preparation, implementation, and monitoring of sub-Project results and impacts.

The implementing NGOs will ensure that views of APs, particularly those who are vulnerable, related to the resettlement process are looked into and addressed. The NGOs will ensure that APs consulted are informed of the outcome of the decision-making process, and will confirm how their views were incorporated. Since resettlement is a continuous process and baseline data/information will be collected, the implementing NGO will regularly update the baseline information.

B. Disclosure

Information was and continues to be disseminated to APs for the sample sub- Projects. Finalized RPs will be disclosed in ADB’s website, IPMU websites, and IPIU or town websites; and information dissemination and consultation will continue throughout program implementation.

The IPIU SDS will conduct consultations and disseminate information to all APs. RPs will be translated into the local language and made available at offices of the: (i) Urban Local Bodies (ULBs); (ii) relevant local government line agencies; and (iii) IPMU and IPIUs. RPs will also be kept in the public libraries, accessible to citizens as a means to disclose the document and at the same time creating wider public awareness.

The RF and RPs will be disclosed in the following websites: IPMU, IPIU, State Government, local governments, and ADB. The IPMU will issue notification of implementation start dates for each sub-Project. The notice will be issued by the IPMU in local newspapers one month ahead of implementation. This will create awareness of project implementation. The IPMU and IPIUs will provide information on IR policies and features of the RP. Basic information such as sub-Project location, impact estimates, entitlements, and implementation schedule will be presented in the form of a brochure that will be circulated among APs. Posters

27

containing basic RP information will also be posted in different localities to increase awareness. Copies of RP summaries will be kept in the IPMU and IPIU offices and will be distributed to any AP consulting on resettlement issues. The RF will be made available in local language during public meetings. This will enable stakeholders to provide inputs on the resettlement process, prior to award of civil work contracts.

An intensive information dissemination campaign for APs will be conducted by the IPIU with assistance from the implementing NGO at the outset of RP implementation. All the comments made by the APs will be documented in the sub-Project records and summarized in sub-Project monitoring reports. A summary of consultation and disclosure activities to be followed for each sub-Project are in Table 1.

Table 1. Consultation and Disclosure Activities

Program phase Activities Details Responsible Agency

Investment Program Bridging Phase

Mapping of the Program areas

Area to be mapped, clearly showing survey numbers of titleholders of land/property proposed for acquisition

IPMU in coordination with DC’s offices and other local bodies.

Stakeholder identification Cross section of stakeholders to be identified in order to facilitate their participation in the program

IPMU and IPIUs in consultation with stakeholders.

Program/sub-project information dissemination; Disclosure of proposed land acquisition

Leaflets containing information on the Program and sub-project to be prepared. Public notice issued in local newspapers (and disclosed on IPMU /IPIU website) including survey numbers and names of titleholders for land to be acquired concurrent with consultancy with title holders.

SDS and RS from IPMU. IPMU may seek the assistance of CAPP consultants for leaflet Preparation. Notice will be issued from the DC’s office. SDS IPMU and SDS IPIU to disclose on the web.

Stakeholder consultation Further consultations with affected titleholders and households. Consultations with non-titled APs and other stakeholders during sub project scoping

SDS IPIU and NGO.

RP Preparation Phase

SIA surveys Surveys to be conducted. Summary RF to be disclosed in local language through printed materials to APs particularly those who are vulnerable and other stakeholders.

IPIU to conduct surveys. SDS IPIU to disclose RF to stakeholders (including making it available in IPMU/IPIU offices and government

28

Program phase Activities Details Responsible Agency

agency offices), SDS IPMU to disclose on the web.

Formulating compensation and resettlement assistance measures

Conducting stakeholders consultations particularly APs in and reflecting issues raised in revised RP

SDS IPIU and NGO

Disclosure of final entitlements and rehabilitation packages

Provision of RPs to stakeholders particularly APs. Conducting consultations and distributing local language version of the summary RP

SDS IPMU, and SDS IPIU to disclose on the web. SDS IPIU and NGO to conduct consultations.

RP Implementation Stage

Disclosure of RP Review and approval; of RP by EA. Review and approval of RP by ADB. Web disclosure of the RP

EA to provide ADB with RP for review and approval. SDS IPMU and SDS IPIU to disclose on the web

Consultation with APs during RP implementation

Consultation with APs NGO with monitoring from IPIU and external agency

29

APPENDIX 6

PUBLIC CONSULTATIONS

For Waste Water Eastern Zone (part B)

The proposed project area for which consultation has been done is of Sewerage System in Dholpur Town Eastern Zone Part B. The width of the commercial/ Market street where trenching will be made for laying of sewer line are approx 5.5 meter to 12 meter in which 200 mm dia to 300 mm dia sewerline will be laid down . Less than 1 meter wide trench having depth of minimum 1 meter to 4.5 meter will be made to lay the sewer line.

A significant portion of proposed area where sewer line is to be laid have small commercial activities. During Site survey it is found that there might be be short term temporary inconvience but no major impact on commercial activities. Therefore, no affected person was found, the accesibbility of the shops will not be hampered since sewerline will be laid in the middle of road and on both side minimum 2 -4 meter wide passes will be still available during construction time . Possibility of minor traffic diversion exists for which there are alternative streets available where traffic can be diverted easily in almost all of the project area.

The consultation has been done to know the opinion/suggesion of public and information dissemenation about the project. At 8 place consultation has been done where inconvenience is likey during construction. Addition to that at many place informal consultation has been done mainly in small residential streets where lateral sewer will be laid. At most of the places people are ready to extend their cooperation but at the same time they are also concerned that when construction takes a longer time it causes trouble as trenches are left opened for many days as witnessed in other part of town where construction work is already in progress.

PUBLIC CONSULTATION. 8 Nos. – SOCIAL

SUBPROJECT: Dholpur Waste Water Sub project Eastern Zone Part-B

DURATION: 45 min to 1hr

LOCATION: Jagan Chauraha, Batashe wali Gali, Meat Wali Gali, Hanuman Tiraha, Hardev Nagar, Saray Gajra Road, Nagar Palika Road, Raneli Mohalla

NUMBER OF PARTICIPANTS: 6-11 on average (Attendance Sheet is attached)

Sl. No.

Key issues / demands

Perception of Community Action to be taken

1. Awareness of the Project- including coverage area

One third of them appeared to be aware of the Project but not clearly about the coverage area,

The Implementing Agency, ULB, NGOs, Media should inform the public.

2 In what way they may be associated with the Project

Other than the welfare of the community temporary affect out of the project were not considered problematic. A stretch of one and a half km road is more densely affected otherwise.

IPIU, DSC to ensure least affect during implementation

3 Perception of people- they might face during construction and

Since it is a work to be undertaken inside the town and covers a major market area during implementation and

Should be regularly monitored by Executing Agency, Implementing Agency, IPIU,

30

Sl. No.

Key issues / demands

Perception of Community Action to be taken

their requirement/demand with respect to noise, accessibility to various places and others

construction phase IPIU and Contractors should keep noise and accessibility factor in check

4 Impact on livelihood due to construction of project

There will be no impact on livelihood and they have no objection

IPIU, DSC to ensure

5 Willingness to work in the project work

People are willing to work in the project

The IPIU, DSC, ULB, Construction Contractors to ensure engagement of locals in the Project work

6 What kind of facilities they would like so that their movement remains unaffected during laying of pipes

They expect that access and movement remains Unhindered.

IPIU, DSC, ULB and Construction Contractors to ensure that access and movement remain open.

7 What kind of R&R assistance they would require

Since there will be no displacement, this point was not discussed

No action needed

31

Consultation at Jagan Chauraha

32

English Translation of Performa of Public Consultation

Name of Project/Package

Town

Area/Locality

Date

Description of Project and Activities

1. Waste Water sub-project of RUSDIP is funded by a loan via the Multitranche Financing Facility (MFF) of the ADB.

2. In this project area sewerage pipe line of 200 mm to 300 mm will be laid down. 3. To lay down 200 mm to 300 mm pipe line one meter wide trench will be dig out. 4. The depth of tranch will depend on the level of ground; it should in between 1 meter

to 4.5 meter. 5. In one day not more than 100-150m pipe line will be laid down. 6. Most of the tranch will be refilled on same day or next day. 7. During lying of pipe line traffic route will be diverted or changed for a short period of

time. 8. 2 meter space will be provided to pedestrians for access to their residents and shops. 9. For a certain period little inconvenience will be caused. 10. Every possible precaution will be taken to avoid inconvenience to the Community. 11. Public will be informed 30 days prior to starting of construction work in all the

proposed project areas. Benefits of waste water project Construction of sewer line will not allow waste water from the public toilets and residents to fall in the open drains and will help get rid of foul smell, decrease mosquito breeding, improve health of the people and avoid occurrence of various water borne diseases. Public view / Problem

33

34

35

Consultation at Hanuman Tiraha

36

37

38

Consultation at Nagarpalika Road

39

40

41

Consultation at Batashe Wale Gale & Meat Wale Gale

42

43

44

45

46

Consultation at Hardev Nagar & Saray Gagra Road

47

48

49

50

51

Consultation at Raneli Mohalla

52

53

54

APPENDIX 7

PUBLIC CONSULTATIONS

DLP/WW/10

55

56

Date & time of Consultation :- 05.10.2012 at 02.15 pm and 9.10.2012 at 1 pm

Location: - STP (3MLD) site near Poultry farm, Agriculture land and Temple Sekhupura Village, Mahatma Nand Ke Bagiche, Near Sekhupura Chunabhatti ,Near STP Site

Ref:- As per instructions of ADB vide email dated: - 21 September 2012

Table-: Issues of the Public Consultation- Design phase

Sr.No. Key Issues/Demands Perception of community

1. Awareness of the project – including coverage area

People are aware of the location of STP site.

2. In what way they may Associate with the project

They demand that labour of the village should get employment on the S.T.P site and during operation local people should be given priority for employment.

3. Presence of historical/ cultural/ religious sites nearby

There is a small temple situated approx 200 meter away from site few people come for worship occasionally in temple. However, consulted people do not think that there will be any adverse impact except odor as the connecting path/tract is away from STP site.

4. Drainage and sewerage problem facing

There is a good natural drainage system as the topography around the site is ravine, however at present there is no sewerage system are available.

5. Availability of labour during construction time

Unskilled labour are available in plenty in locality.

6. Access road to project site

At present STP site is accessible thorough dirt road. The all weather road is proposed to be constructed.

7. Perception of villagers on tree felling and afforestation

At present no trees are there however plantation is proposed along the boundary of STP site. Consulted people also expressed their positive view on green belt generation.

8. Disturbances during construction work

Route, time and Vehicles movement will be controlled & appropriate measure will be taken to minimize the negative impact.

9. Whether local people agreed to sacrifice their lands (cultivable or not) for beneficial project after getting proper compensation

Since, S.T.P site has been proposed to be constructed in Government land. Any land acquisition from private owner is not required.

Summary of Consultation: Most of the consulted people are known about the project. As the project does not require any land acquisition and there is no permanent impact on the livelihood but they are concerns about the problems have to face bad odors from the STP near areas. People are ready to extend all types of support to during execution of the project. They want development like proper Solid Waste Management and drinking water facility, Road and School (school is very far away because of that most of the girls or children don’t send to school by their parents). During monsoon period villagers take their cattle’s for grazing in nearby lands however they do not anticipate much impact regarding grazing as much land will be available around the STP.

57

Priest of nearby temple are also aware about the project and they also not anticipate much impact due to project except odor. The project will help irrigation and manure for growth for crops. Give employment to local people.

Most of the consulted People are known of the proposed project as well as proposed location of STP. The proposed project does not involve any private land as the land belong to Line Agency (Municipal Council) and has been allotted for project development . The local community are known and accepted that there will be no permanent livelihood lose. Few of the consulted people are worried about odors, generated from STP. Some of the consulted people also raise their voice regarding possible unwanted mosquito and other microbes. Local community also wanted to get their sewerage connection as early as possible. Most of the consulted People are ready to extend their all support during construction and operation of the project. They also want Solid waste management project should be taken up as early as possible.

Name of Persons Consulted:-

Sl. No. Name S/O Occupation

1 Madhav Singh C/o Jamil Khan Farmer worker

2 Manju Khan Gani Khan Poultry farm owner /Land owner

3 Munna Khan Gani Khan Land owner

4 Salim Khan Gani Khan Land owner

5 Sahesh Khan Gani Khan Land owner

6 Jamil Khan Gani Khan Poultry farm / Land owner

7 Hamib Khan Gani Khan Land owner

8 Papu Khan Gani Khan Land owner

9 Gherulal Priest

10 Rambhagan Malha S/O Waman Singh Labour

11 Bamalish W/O Uday Singh Housewife

12 Sunita W/O Bashuden Singh Housewife

13 Rekha W/O Veer Singh Housewife

14 Sanker S/O Anter Ram Labour

15 Bangali S/O Papu Truck Driver

16 Shikadai W/O Ramkhilardi Housewife

17 Guddi W/O Ramnarish Housewife

18 Ramish S/O Antram Labour

19 Bashu Dev --- Shop

20 Udile Singh --- labour

21 Vimal Hotam Singh Shop

22 Chanden Singh Pati Ram Labour

23 Samaram Rambhorasa Shop

24 Banshlal Ramswroop labour

25 Gulphan D/O Farahdeen Khan Home staying Girl

26 Sammi D/O Farahdeen Khan Home staying Girl

27 Phul singh Narayan singh Labour

28 Kalpana W/O Ramveer Housewife

29 Shukhi Late Kurmodi House wife

30 Ramshukhi W/O Vimal House wife

58

Demarcation Process of STP Land

Public Consultation

59

English Translation of Performa of Sankalp (consensus)

Ward N0. --------

We the resident of Dholpur town, have discussed today with the Executive engineer, RUIDP,

Dholpur; ACM of DSC-I and assistant community officer of CAPP regarding Sewerage

project of RUIDP.

1. We are agreeing that the project is useful for all of us and all citizens.

2. We have been assured by the Executive engineer, RUIDP, Dholpur that construction

work will not hindered in our day to day activities, the construction work will be

completed in minimum possible time, there will be no resettlement and work will not be

commissioned during the festivals to maintain traffic movement smoothly.

3. We are determined to co-operate with the implementing agency and the contractor

during construction and we are ready to bear inconvenience during the construction

work.

4. We will not expect any kind of financial and other assistance from government and

other agencies to compensate inconvenience during the construction work

SR. NO. NAME OF

PARTICIPANT

OCCUPATION SIGNATURE

60

61

62

63

64

65

66

67

68

69

70

71

The schedule for resettlement plan

S.

No

Short resettlement Plan for

Start dates of public consultation/dissemination of information

Start dates of RP disclosure to the entitled APs

Close dates of public consultation/dissemination of information

1 RUSDIP/ TR-02/ DLP/WW/04 & 05

(re tendered of WW/01 , WW-02 & WW-03 Lot-1 & Lot2)

June 2008

Within 15 days after approval

2 RUSDIP/ TR-02/ DLP/WW/08 (Re-tendered for DLP/WW/06)

Jan 2012

Within 15 days after approval

3 RUSDIP/ TR-02/ DLP/WW/010

(Re-tendered for DLP/WW/07)

June 2012 Within 15 days after approval

2. Authors name: DSC I

3. Consultant Firm name: M/s Gherzi Eastern Limited.

4. Government ministry: Rajasthan Urban Infrastructure development Project (RUIDP).


Recommended