Diglycolamine® Solvent Quality Improvement with Thermal Reclaiming
Don DaughtonSuncor Energy Inc.
Bob VerobaHuntsman Corporation
2
OutlinePlant OverviewOperations Prior to Thermal ReclaimingMerchant ReclaimingThermal Reclaimer DesignOperations After Thermal ReclaimerInstallationConclusionsRecommendations
3
Suncor Plant Location
4
Oilsands Mining/Extraction
5
Millennium Upgrader
6
Plant OverviewMillennium Amine Unit (Plant 53) Start up in 2001Main Fuel Gas Absorber, Primarily Coker Gas, 77 MMSCFD, 15% H2S, 1% CO23 Hydrotreater Absorbers, 540 MMSCFD Total, 0.4 to 1.8% H2S, no CO21 Liquid C4 Treater, 30 gpm, 100 ppm H2SCommon Regenerator for all AbsorbersTotal Circulation Rate 2500 gpm DGA® at 35 to 40 weight percent
7
Plant OverviewDEA For Original Plant DesignDGA® Chosen to Achieve Future Expansion Capacity, Fuel Gas Total Sulfur at Low Operating PressureExisting DEA Unit Has High HSS and CO2/COS DegradationExpected Need to Reclaim - Tie in Points Added
8
Operations Prior to Thermal ReclaimerAmine Degradation Did OccurBHEEU Formation at 2 WT%/Month due to COS Removal, Maximum Over 20 WT%Heat Stable Salts Were < 2 WT%No Significant Operating Problems Due to BHEEUMerchant Reclaiming Used to Maintain Amine Quality
9
BHEEU HistorySuncor BHEEU
-5
0
5
10
15
20
25
30
35
April 19,2001
November5, 2001
May 24,2002
December10, 2002
June 28,2003
January 14,2004
August 1,2004
February17, 2005
September5, 2005
March 24,2006
October 10,2006
April 28,2007
Date
Wei
ght P
erce
nt
BHEEU
Reclaimer Start upFebruary 2006
10
Heat Stable Salt HistorySuncor Heat Stable Salts
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
April 19,2001
November5, 2001
May 24,2002
December10, 2002
June 28,2003
January 14,2004
August 1,2004
February17, 2005
September5, 2005
March 24,2006
October 10,2006
April 28,2007
Date
HSS
WT%
HSS
Reclaimer Start upFebruary 2006
11
Merchant ReclaimingMerchant Reclaiming Needed 2 Times per YearBHEEU Content Range 10 to 25 Weight %Minimal BHEEU Conversion50 MT of 80% Nitrogen Waste per Reclaim –Environmental Concern Expansion Capacity Needed 50 Weight % DGA®
High Viscosity Issues at High Amine WT%Permanent Operation With < 10% Degradation Needed
12
Thermal Reclaimer DesignBHEEU Reversed/Recovered In Thermal Reclaimerat 360oF2*DGA® + (CO2 or COS)<-> BHEEU + (H2O or H2S)2 Control Loops
Temperature Control at 360oF Using Water FeedLevel Control With Lean Amine Feed
Vapor Returned to Regenerator Reclaimer Heat Input = Regenerator Reboiler Reduction
300 Day Cycle Time, Depending on Solids/Non-Volatile Accumulation
13
Thermal Reclaimer DesignDesign for Current DGA® Unit (Plant 53) and Future Plant 68Maximum Heat Duty 41 MMBtu/hrMaximum Amine Feed Rate 49 gpm Total
27 gpm Plant 53 and 22 gpm Plant 68 (2008 Start up)
12’ ID X 24’ T/T, 15,000 Gallon CapacityTarget BHEEU 3 WT%
14
Suncor Reclaimer Schematic
16
Operations After Thermal ReclaimerInstallation
Start Up February, 2006Steam Trap/Condensate Return ProblemsTemperature Controller Calibration IssuesLevel Control Range Conflicts
BHEEU Reduced from 17 WT% to 3 WT% in 3 MonthsAmine Consumption Reduced Due to Conversion of BHEEU to DGA®
17
18
BHEEU After Reclaimer Start upBHEEU After Reclaimer
-5
0
5
10
15
20
December 14,2005
February 2,2006
March 24, 2006 May 13, 2006 July 2, 2006 August 21,2006
October 10,2006
November 29,2006
January 18,2007
Date
Wei
ght %
BHEEU
19
Operations After Thermal ReclaimerInstallation
Particulate Filter Replacement Reduced by 50%2:1 Length to Diameter Ratio was Effective in Eliminating Carryover Out of ReclaimerRegenerator Reboiler Temperature Reduced Due to Higher Water Content in Amine SolutionFirst Reclaim Cycle was 9 Months
Steam Coil Leak Was Found – Vibration Was Main Cause, Possibly Due to Changes to Inlet Distributor
20
Amine Feed Rate To ReclaimerAmine Feed to Reclaimer
0
5
10
15
20
25
30
35
40
45
22/0
2/20
06
08/0
3/20
06
22/0
3/20
06
05/0
4/20
06
19/0
4/20
06
03/0
5/20
06
17/0
5/20
06
31/0
5/20
06
14/0
6/20
06
28/0
6/20
06
12/0
7/20
06
26/0
7/20
06
09/0
8/20
06
23/0
8/20
06
06/0
9/20
06
20/0
9/20
06
04/1
0/20
06
18/1
0/20
06
01/1
1/20
06
Date
Flow
(USG
PM)
USGPM
21
Steam Rate To ReclaimerReclaimer Steam Rate
0
2000
4000
6000
8000
10000
12000
14000
16000
14/12/2005 02/02/2006 24/03/2006 13/05/2006 02/07/2006 21/08/2006 10/10/2006 29/11/2006
Date
Stea
m (l
b/hr
)
Steam (lb/hr)
22
Reboiler TemperatureReboiler Temperature
245
250
255
260
265
270
275
280
05/09/2005
25/10/2005
14/12/2005
02/02/2006
24/03/2006
13/05/2006
02/07/2006
21/08/2006
10/10/2006
29/11/2006
Date
Deg
rees
F
Reboiler Temperature (F)
Reclaimer Start upFebruary 2006
23
ConclusionsBHEEU and Degradation Targets Met with New Thermal ReclaimerIncrease in Amine Strength is Now Possible for Capacity IncreaseWaste Volume and Nitrogen Content Has Been ReducedAmine Losses ReducedMerchant Reclaiming Costs Eliminated
24
RecommendationsReclaimer Design for Future Voyageur Expansion Project Will Be Based on Plant 53/68 DesignImprovements to Level and Temperature Indication Will Be ImplementedCondensate Drum Should be Considered for Future DesignsVibration Analysis and Inlet Design Are Important in Future Designs2:1 L:D Ratio is Effective in Reducing Liquid Carryover