+ All Categories
Home > Documents > DIRECT TESTIMONY OF ANDREW T. WOODCOCK ON BEHALF OF … · 3 1 mergers and acquisitions, and cost...

DIRECT TESTIMONY OF ANDREW T. WOODCOCK ON BEHALF OF … · 3 1 mergers and acquisitions, and cost...

Date post: 21-May-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
135
BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In Re: Application for increase in water and wastewater rates in Charlotte, Highlands, Lake, Lee, Marion, Orange, Pasco, Pinellas, Polk and Seminole Counties by Utilities, Inc. of Florida / / / / / Docket No. 160101-WS FILED: March 6, 2017 DIRECT TESTIMONY OF ANDREW T. WOODCOCK ON BEHALF OF THE CITIZENS OF THE STATE OF FLORIDA J. R. Kelly Public Counsel Erik L. Sayler Associate Public Counsel Office of Public Counsel c/o The Florida Legislature 111 West Madison Street, Room 812 Tallahassee, FL 32399-1400 (850) 488-9330 Attorneys for the Citizens of the State of Florida
Transcript

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION

In Re: Application for increase in water and wastewater rates in Charlotte, Highlands, Lake, Lee, Marion, Orange, Pasco, Pinellas, Polk and Seminole Counties by Utilities, Inc. of Florida

/ / / / /

Docket No. 160101-WS FILED: March 6, 2017

DIRECT TESTIMONY

OF

ANDREW T. WOODCOCK

ON BEHALF OF THE CITIZENS OF THE STATE OF FLORIDA

J. R. Kelly Public Counsel Erik L. Sayler Associate Public Counsel Office of Public Counsel c/o The Florida Legislature 111 West Madison Street, Room 812 Tallahassee, FL 32399-1400 (850) 488-9330 Attorneys for the Citizens of the State of Florida

FPSC Commission Clerk
FILED MAR 06, 2017 DOCUMENT NO. 03125-17 FPSC - COMMISSION CLERK

TABLE OF CONTENTS

DIRECT TESTIMONY ................................................................................................................................. 2

I. INTRODUCTION/BACKGROUND/SUMMARY ................................................................... 2

II. EXCESSIVE UNACCOUNTED FOR WATER AND

EXCESSIVE INFLOW AND INFILTRATION ........................................................................ 5

III. USED AND USEFUL ............................................................................................................. 10

IV PRO FORMA ADDITIONS TO RATE BASE ....................................................................... 31

EXHIBITS EXHIBIT__ (ATW-1) – Resume of Andrew T. Woodcock

EXHIBIT__ (ATW-2) – Excessive Unaccounted for Water Calculations

EXHIBIT__ (ATW-3) – Excessive Inflow and Infiltration Calculations

EXHIBIT__ (ATW-4) – Summary of Used and Useful Percentages

EXHIBIT__ (ATW-5) – LUSI Used and Useful Calculations

EXHIBIT__ (ATW-6) – Mid County Used and Useful Calculations

EXHIBIT__ (ATW-7) – Lake Placid Used and Useful Calculations

EXHIBIT__ (ATW-8) – Lake Placid FDEP Construction Application

EXHIBIT__ (ATW-9) – Labrador Used and Useful Calculations

EXHIBIT__ (ATW-10) – Labrador Map of Certificated Service Area and Surrounding

Property

EXHIBIT__ (ATW-11) – Eagle Ridge Used and Useful Calculations

EXHIBIT__ (ATW-12) – Crownwood Used and Useful Calculations

EXHIBIT__ (ATW-13) – Crownwood Map of Certificated Service Area and Surrounding

Property

EXHIBIT__ (ATW-14) – Sandalhaven Composite Exhibit

EXHIBIT__ (ATW-15) – Sandalhaven Used and Useful Calculations

EXHIBIT__ (ATW-16) – Summary of Pro forma projects with cost justification supporting

less than requested

EXHIBIT__ (ATW-17) – Sanlando Wekiva WWTP Rehabilitation Invoice

EXHIBIT__ (ATW-18) – Mid-County Electrical Improvements – Bid Forms

2

DIRECT TESTIMONY 1

OF 2

ANDREW T. WOODCOCK P.E., MBA 3

On Behalf of the Office of Public Counsel 4

Before the 5

Florida Public Service Commission 6

Docket No. 160101-WS 7

8

I. INTRODUCTION/BACKGROUND/SUMMARY 9

Q. PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. 10

A. My name is Andrew T. Woodcock. My business address is 201 East Pine St., Suite 11

1000, Orlando, FL 32801. 12

13

Q. PLEASE DESCRIBE YOUR EDUCATIONAL BACKGROUND AND WORK 14

EXPERIENCE. 15

A. I am a Professional Engineer licensed in the State of Florida, P.E. license No. 47118. I 16

graduated from the University of Central Florida in 1988 with a B.S. degree in 17

Environmental Engineering, and in 1989 with an M.S. degree in Environmental 18

Engineering. In 2001, I graduated from Rollins College with an MBA degree. In 1990, 19

I was hired at Dyer, Riddle, Mills and Precourt as an engineer. In May 1991, I was 20

hired at Hartman and Associates, Inc., which has since become Tetra Tech. My 21

experience has been in the planning and design of water and wastewater systems with 22

specific emphasis on utility valuation, capital planning, utility financing, utility 23

3

mergers and acquisitions, and cost of service rate studies. I have also served as utility 1

rate regulatory staff for St. Johns, Charlotte, and Collier Counties in engineering 2

matters. Exhibit ATW-1, Resume of Andrew T. Woodcock, provides additional 3

details of my work experience. 4

5

Q. HAVE YOU PREVIOUSLY FILED TESTIMONY IN UTILITY RATE CASE 6

PROCEEDINGS? 7

A. Yes. I have filed testimony in a number of proceedings before the Florida Public 8

Service Commission, on behalf of the Office of Public Counsel (OPC). In 2007, I 9

filed testimony in the Aqua Utilities Florida Rate Case (Docket No. 060368-WS). I 10

also filed testimony regarding the Used and Useful Rule for Water Treatment Systems 11

(Docket No.070183-WS), the Aqua Utilities Florida Rate Case (Docket No. 080121-12

WS), and the Water Management Services, Inc. rate case (Docket 100104-WU). I 13

have also filed testimony on behalf of OPC in two previous KW Resort Rate Cases 14

(Dockets Nos. 070293-SU and 150071-SU). 15

In addition, I have filed testimony before other agencies and in other 16

jurisdictions. In 2002, I filed testimony on behalf of the St. Johns County Regulatory 17

Authority at a special hearing in an overearnings case against Intercoastal Utilities. I 18

have also filed testimony before the Kentucky Public Service Commission in 2007 on 19

behalf of the Henry County Water District No.2 (Case No. 2006-00191) regarding 20

system development charges. In 2012, I filed testimony on behalf of Charlotte County 21

regarding a rate increase in wastewater rates filed by Utilities, Inc. of Sandalhaven. 22

4

Q. ON WHOSE BEHALF ARE YOU FILING TESTIMONY IN THIS 1

PROCEEDING? 2

A. I am testifying on behalf of the Florida Office of Public Counsel (OPC or Citizens). 3

4

Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY IN THIS PROCEEDING? 5

A. My testimony will address the excessive inflow and infiltration, excessive unaccounted 6

for water, used and useful percentages for the Utilities Inc. of Florida (UIF or 7

Company) systems, as well as, the costs and engineering aspects of the proposed post-8

test year pro forma adjustments to rate base. 9

10

Q. WHAT INFORMATION DID YOU REVIEW WHEN FORMING YOUR 11

OPINIONS AND RECOMMENDATIONS IN YOUR TESTIMONY? 12

A. I reviewed the Company’s Minimum Filing Requirements (MFRs); the Direct 13

Testimony of Frank Seidman and Jon Hoy; the Company’s filings in Docket No. 14

160101-SU; and its responses to OPC and Staff discovery. In addition, I reviewed the 15

relevant Commission rules and Statutes applicable to UIF’s request, and some 16

Commission Orders. Finally, with UIF personnel, I conducted site visits of several 17

UIF systems to inspect the plant in service and the progress of some of the major 18

proposed pro forma projects and to obtain a general understanding of the operation of 19

the systems. 20

5

Q. PLEASE SUMMARIZE YOUR RECOMMENDATIONS IN THIS CASE. 1

A. In my professional opinion, I have found excessive unaccounted for water in ten 2

systems and excessive inflow and infiltration in three systems that are a part of this 3

rate case. I conducted an analysis on and provide an opinion for the appropriate U&U 4

percentages of seven system wastewater treatment plants and two wastewater 5

collection systems. I am not providing an opinion on the U&U of the remaining 6

systems that are a part of this rate case. 7

8

Finally, I provide an opinion on UIF’s pro forma rate base additions. Of the 9

total $30,835,444 requested for approval in the original UIF filing, $21,256,538 was 10

reasonable and supported by UIF’s direct testimony and exhibits and should be 11

allowed in the rate case. The amounts unsupported by reliable documentation should 12

be considered in a subsequent proceeding, but not allowed in this rate case. 13

14

II. EXCESSIVE UNACCOUNTED FOR WATER AND EXCESSIVE INFLOW 15

AND INFILTRATION 16

Q. WHAT DID YOU FIND WITH RESPECT TO EXCESSIVE UNACCOUNTED 17

FOR WATER (EUW) IN THE SYSTEMS INCLUDED IN THIS RATE CASE? 18

A. I first reviewed and relied upon data provided by UIF in its MFRs. Utilities have to 19

account for all water pumped, purchased, or otherwise used for utility purposes. Water 20

that cannot be accounted for (i.e. sold, used for flushing, or other utility purposes) is 21

considered unaccounted for water. In determining the amount of excessive 22

unaccounted for water, I used a threshold of 10% or greater of the pumped or 23

6

purchased water, as defined by Rule 25-30.4325(1)(e) Florida Administrative Code 1

(F.A.C.), which states “Excessive unaccounted for water (EUW) is unaccounted for 2

water in excess of 10 percent of the amount produced.” Accordingly, any unaccounted 3

for water over the 10% threshold was deducted from the used and useful calculation. 4

5

Q. WHAT WERE THE RESULTS OF YOUR EUW ANALYSIS? 6

A. A summary of my analysis in provided in Exhibit ATW-2. I found excessive EUW in 7

the following systems: 8

System Excessive unaccounted for water

(expressed as a percent of total water pumped or purchased)

Labrador 4.60% Lake Placid 3.06% Pasco – Orangewood et.al. 7.66% UIF Marion 1.35% UIF Pinellas – Lake Tarpon 10.20% UIF Seminole – Ravenna Park et. al. 0.95% UIF Seminole – Little Wekiva 4.81% UIF Seminole – Oakland Shores 2.23% UIF Seminole – Phillips 1.56% UIF Seminole – Weathersfield 1.31%

9

Q. DO YOU HAVE ANY CONCERNS REGARDING OTHER WATER USES 10

FOR ANY SYSTEMS IN THE RATE CASE? 11

A. I found exceptionally high water uses in the Lake Saunders and Summertree water 12

systems. Both systems had reported “water for other uses” in excess of 47% of the 13

total water pumped. 14

7

Q. WILL YOU DESCRIBE WHAT “WATER FOR OTHER USES” IS? 1

A. Water for other uses (“WFO”) is an industry term that represents water not sold to 2

customers but can be otherwise accounted for by the utility. Some examples of this 3

are water used in the treatment process, line flushing in the system, and water used for 4

firefighting. The amount of WFO can vary greatly from system to system but in my 5

experience is usually less than 20% of the total water pumped. A utility should keep 6

WFO to a low number to conserve water resources, minimize operating costs, and 7

improve system efficiency. 8

9

Q. WHAT DID YOU FIND WITH THE WFO FOR THESE TWO SYSTEMS? 10

A. Through discovery I determined that the Lake Saunders water use is due to the 11

filtration process used to treat the water. While the WFO is still high in my opinion, I 12

can accept that filtration is a water intensive form of water treatment and adds to a 13

system’s WFO. 14

15

For Summertree, the high WFO is due to significant system flushing performed by 16

UIF to minimize the effects of the poor water quality in the system. In December 17

2016, UIF interconnected the system with Pasco County for a new water source in an 18

effort to improve water quality and reduce the flushing required to maintain water 19

quality. As of the date of this testimony, I understand UIF continues to vigorously 20

flush the Summertree system as part of the interconnection process. This is a standard 21

practice when switching water sources; it allows the chemistry in the water system to 22

adjust to the new source while minimizing short-term water quality changes. Any 23

8

costs associated with vigorously flushing the Summertree system are temporary 1

expenses. Over time, I would expect that water used for flushing the Summertree 2

system to decline to a more reasonable percentage. 3

4

Q. PLEASE DESCRIBE INFILTRATION AND INFLOW AND HOW IT 5

AFFECTS WASTEWATER SYSTEMS? 6

A. Infiltration is groundwater that seeps into a wastewater gravity collection system 7

through pipe joints or cracks. Inflow is usually stormwater that enters a wastewater 8

collection system during rain events through inappropriately connected drains or other 9

entrances to the system. Water from inflow and infiltration (I&I) entering the 10

wastewater system is treated along with customer produced wastewater, and increases 11

the cost of wastewater treatment. Further, I&I decreases the amount of available 12

capacity in a wastewater system and can compromise the ability of the system to treat 13

wastewater flows generated by a utility’s customers. Since customers are not the 14

cause of I&I, they should not be required to pay for the costs associated with treating 15

excessive I&I in a wastewater system. 16

17

Q. WHAT IS YOUR METHODOLOGY FOR DETERMINING WHETHER I&I 18

IS EXCESSIVE? 19

A. My methodology is consistent with the Commission’s conventional methodology 20

described on pages 14 and 15 of Order No. PSC-16-0013-PAA-SU. My threshold for 21

allowable infiltration are based upon 500 gallons per day (gpd) per inch-mile. My 22

threshold for excessive inflow is based on inflows of 10% or greater than the billed 23

9

water returned to the wastewater treatment plant (WWTP). In estimating the amount 1

of billed water returned to the wastewater treatment plant, I used a factor of 80% of 2

billed water for residential connections and 90% of billed water for non-residential 3

connections. If the reported flows at the WWTP exceed estimated flows returned to 4

the WWTP plus the I&I allowance, the difference is considered excessive I&I. 5

6

Q. IN THE COURSE OF THIS ANALYSIS, WAS THERE A NEED TO DEVIATE 7

FROM THIS METHODOLOGY? 8

A. Yes. Two systems, Cross Creek and Longwood, are wastewater only systems with a 9

flat rate that is billed independent of water usage. According to the MFRs, UIF was 10

unable to obtain billed water data for these two systems. As a result, the billed water 11

data necessary to implement the excessive I&I methodology was unavailable and an 12

excessive I&I number could not be calculated using this methodology. For these 13

systems, I used a more generalized approach based on an excessive wastewater 14

generation threshold of 120 gallons per capita day (gpcd). I estimated a functional 15

population served by using meter equivalents and divided the result into the reported 16

Test Year WWTP flows. In my professional opinion, any calculated amount over 120 17

gpcd is considered excessive I&I. My calculations for Cross Creek and Longwood did 18

not reveal any excessive I&I for these two wastewater only systems. 19

20

Q. WHAT ARE THE RESULTS OF YOUR EXCESSIVE I&I ANALYSIS? 21

A. Exhibit ATW-3 presents a summary of my analysis. I found excessive I&I in three 22

systems as shown in the table below: 23

10

System Test Year Excessive I&I Test Year Excessive I&I

(gallons) (as a percent of WWTP flow) Sandalhaven 4,225,819 8.37%

UIF Pasco – Wis Bar 951,518 17.22%

UIF Seminole – Lincoln Heights 8,717,900 37.41%

1

III. USED AND USEFUL 2

Q. DESCRIBE YOUR APPROACH TO USED AND USEFUL FOR THE UIF 3

SYSTEMS IN THE RATE CASE. 4

A. I limited my used and useful (U&U) analysis to utility plant assets in systems that have 5

not been previously determined to be 100% U&U by the Commission in prior rate 6

proceedings unless a settlement was involved. As a result, my analysis focuses on 7

wastewater facilities in the following systems: 8

a. Lake Utility Services, Inc. (LUSI) wastewater treatment system; 9

b. Mid County wastewater treatment and collection system; 10

c. Lake Placid wastewater treatment system; 11

d. Labrador wastewater treatment system; 12

e. Eagle Ridge wastewater system; 13

f. Crownwood wastewater treatment system; and 14

g. Sandalhaven wastewater treatment and transmission system. 15

16

The U&U percentage approved for the Sandalhaven wastewater system by Order No. 17

PSC-16-0013-PAA-SU, was protested and preserved for redetermination and 18

recalculation in this consolidated rate case by a settlement between OPC and UIF 19

11

approved by Order No. PSC-16-0151-FOF-SU. While the Commission previously 1

determined the Eagle Ridge wastewater system to be 100% U&U in Order No. PSC-2

11-0587-PAA-SU, this determination was protested and a settlement between UIF and 3

OPC approved by Order No. PSC-12-0346-FOF-SU struck the U&U language from 4

the PAA Order. 5

6

Q. DESCRIBE IN GENERAL YOUR APPROACH TO YOUR USED AND 7

USEFUL ANALYSIS FOR WASTEWATER TREATMENT SYSTEMS? 8

A. My approach to determining U&U for wastewater treatment systems follows the 9

provision set forth in Rules 25-30.431 and 25-30.432, F.A.C., (U&U Rules) and 10

Section 367.081(2) Florida Statutes (F.S.) (U&U Statute). With the exceptions that are 11

noted below in my testimony, my approach to used and useful starts with the test year 12

wastewater flow which is adjusted to reflect growth for a five-year period beyond the 13

test year and the removal of any excessive inflow and infiltration. This adjusted test 14

year flow is divided by the capacity of the treatment facilities to determine the U&U 15

percentage of the treatment facilities. Exhibit ATW-4 presents a summary of my 16

U&U analysis for each of the wastewater treatment systems. 17

18

Q. PLEASE DESCRIBE YOUR APPROACH TO YOUR U&U ANALYSIS TO 19

WASTEWATER COLLECTION SYSTEMS? 20

A. For collection systems, I based my U&U evaluation on the lot count methodology, 21

which looks at the ratio of unserved lots with access to collection lines to all lots with 22

12

access to collection lines. I applied this methodology to my evaluation of the Mid 1

County and Eagle Ridge Systems. 2

3

Q. WHAT IS YOUR OPINION OF UIF’S USED AND USEFUL 4

METHODOLOGY AND PERCENTAGES FOR THE SYSTEMS YOU 5

ANALYZED? 6

A. In many cases, I disagree with the U&U methodology and calculated U&U 7

percentages UIF has presented in this case. For the most part, my disagreements focus 8

on a few key concepts. 9

10

Q. WHAT IS YOUR FIRST POINT OF DISAGREEMENT? 11

A. I take exception to the use of prepaid connections and guaranteed revenue payments in 12

determining used and useful. UIF includes prepaid connections in the U&U 13

calculations for both the LUSI and Sandalhaven systems. 14

15

Q. WHY SHOULD PREPAID CONNECTIONS BE EXCLUDED FROM THE 16

U&U CALCULATION FOR THE LUSI AND SANDALHAVEN 17

WASTEWATER TREATMENT FACILITIES? 18

A. Prepaid ERC connections (prepaids) represent potential future connections which may 19

eventually connect to the system. With prepaid connections, there is no timing if or 20

when these connections will happen. The agreements simply say that the utility will 21

provide the service when the connections occur. In that sense, these connections are 22

13

independent of timing. The prepaids could connect in one year, two years, five years, 1

ten years or potentially never. 2

3

Section 367.081(2), F.S., already contains provisions for a growth allowance for five 4

years beyond the test year at a rate no greater than 5% per year, and prepaids are not 5

referenced in the statute. Adding the prepaid connections to the statutory growth 6

allowance creates two conflicts. First, there is the potential that the prepaids could 7

connect within that five-year growth period resulting in a double counting of growth 8

and an over statement of U&U. Second, since there is no timeframe when these 9

prepaids may actually connect, their inclusion in U&U arbitrarily extends the growth 10

period to an undefinable time period beyond the allowable five-year statutory horizon 11

that would end only when the last prepaid connects. This growth is speculative and 12

contrary to the way that Commission orders have applied Section 367.081(2), F.S. in 13

prior rate cases, including prior LUSI and Sandalhaven rate cases. Applying prepaid 14

ERCs to U&U erroneously inflates the U&U percentages and requires current rate 15

payers to indefinitely pay for unused system capacity that may never be used by future 16

customers. 17

18

Q. WHAT DOES THE U&U STATUTE AND RULES STATE ABOUT USING 19

PREPAIDS IN THE U&U CALCULATION? 20

A. They are silent. Prepaid connections are not mentioned in either Section 367.081(2), 21

F.S., or Rule 25-30.432, F.A.C., for Wastewater Treatment Plant Used and Useful 22

14

Calculations. Therefore, in my opinion, prepaid ERCs should be excluded from the 1

U&U calculation. 2

3

Q. ARE YOU AWARE OF ANY INSTANCES WHERE THE COMMISSION HAS 4

INCLUDED PREPAID CONNECTIONS IN THE U&U CALCULATION FOR 5

WATER AND WASTEWATER SYSTEMS? 6

A. Yes, in two instances. One instance occurred in Order No. PSC–16-0013-PAA-SU, in 7

Docket 150102-SU, Sandalhaven’s last rate case; however, that U&U calculation was 8

specifically protested and preserved for determination in this consolidated case. In the 9

protested order, the U&U for the system components included demand from un-built 10

guaranteed revenue agreements and prepaid ERC commitments. Including prepaids 11

was a departure from the U&U calculation in the prior Commission Sandalhaven rate 12

case (Commission Order No. PSC-07-0865-PAA-SU) and the Charlotte County rate 13

case. 14

15

Another similar but different instance occurred in Order No. PSC-09-0057-FOF-S, in 16

Docket No. 070293-SU, involving KW Resort Utilities Corp. (KWRU). In the 17

KWRU Final Order No. PSC-09-0057-FOF-SU, at page 20, the Commission mentions 18

that Monroe County reserved the remaining KWRU plant capacity so that existing 19

Stock Island residents using septic system could later connect to its wastewater system 20

and repay the county through their property taxes. In that case, the customers already 21

existed and would be required to connect to KWRU’s system. In Sandalhaven, 22

however, the future customers did not exist at the time the developers reserved 23

15

capacity. Other than these two instances, the Commission to my knowledge has not 1

included prepaid ERCs in any other U&U calculations. 2

3

Q. WHAT IS YOUR OTHER CONCEPTUAL DISAGREEMENT WITH UIF’S 4

APPROACH TO U&U? 5

A. In several instances, UIF claims that the system service area is built-out and therefore 6

the system should be considered 100% U&U. I disagree with allowing such a blanket 7

qualification to be the sole necessary justification for considering a system 100% 8

U&U. The WWTP U&U Rule 25-30.432, F.A.C., states that in determining the used 9

and useful amount, the Commission will consider “…the extent to which the area 10

served by the plant is built out…” A further refinement of this concept is provided in 11

the Commission’s rules for water treatment used and useful calculations. The water 12

treatment and storage U&U Rule 20-30.4325(4), F.A.C., states “A water treatment 13

system is considered 100 percent used and useful if the service territory the system is 14

designed to serve is built out and there is no apparent potential for expansion of the 15

service territory….” Even though this U&U rule applies to water systems, it provides 16

parallel guidance for used and useful evaluations of wastewater systems. The water 17

U&U rule lays out a two-part test for 100% U&U: (1) the design service area must be 18

built-out and; (2) there must be no apparent expansion potential the service territory. 19

Since there is no similar U&U rule for wastewater systems, my used and useful 20

evaluation of the built-out wastewater service territories, and in some cases the 21

WWTP, utilizes both parts of this two-part test. 22

16

Lake Utility Services, Inc. (LUSI) U&U 1

Q. WHAT IS YOUR OPINION OF THE U&U OF THE LUSI WASTEWATER 2

TREATMENT PLANT? 3

A. I find the U&U for the LUSI WWTP to be 53.55%. My U&U calculations for the 4

LUSI wastewater treatment plant are included in Exhibit ATW-5. My analysis differs 5

from UIF’s analysis largely because of the prepaid connections UIF adds to the U&U 6

calculation. In Schedule F-8 of the LUSI MFRs, UIF adjusts the U&U for the five-year 7

growth period using 126.22 ERCs per year at 131.2 gpd/ERC. The utility then inflates 8

the U&U number by adding an additional 187 prepaid connections at 280 gpd/ERC, 9

which increases the U&U of the facilities to 59%. As I stated previously, prepaid 10

connections should be excluded because they are not identified in any of the 11

Commission’s U&U rules or statute, and the application of these prepaid connections 12

to a U&U analysis potentially double counts connections and adds speculative 13

assumptions to the U&U calculations. 14

15

Q. IN THIS PARTICULAR CASE, HOW IS INCLUDING PREPAID 16

CONNECTIONS DOUBLE COUNTING GROWTH IN THE U&U 17

CALCULATION? 18

A. UIF’s analysis includes not only the standard allowance for growth allowed by Section 19

367.081(2), F.S., but also adds the prepaid connections. It is quite likely that at least 20

some of these prepaids could connect within the five-year statutory growth period. 21

However, if a prepaid ERC makes connection during the five-year period occurs, it is 22

already accounted for in the statutory growth allowance. If prepaids are added to the 23

17

statutory growth allowance, then current customers will be paying for these prepaid 1

connections twice in current rates. 2

3

Q. AND WHAT ARE THE SPECULATIVE ASSUMPTIONS UIF MAKES IN 4

APPLYING THESE PREPAIDS TO THE U&U CALCULATION FOR LUSI? 5

A. First, UIF assumes that the prepaid connections will someday connect to the system, 6

and this speculative assumption distorts the U&U calculation. If the prepaids do not 7

connect within the allowable growth period, UIF is extending the growth period to 8

some unidentifiable date in the future. 9

10

Second, UIF assumes the LUSI prepaid connections will use an unreasonably high 280 11

gpd/ERC, which is more than twice the 131 gpd/ERC calculated for the rest of the 12

existing LUSI system. Again, there is no way to specifically predict the exact gpd 13

contribution of these nonexistent connections and UIF did not provide any valid 14

support for how it calculated the 280/gpd/ERC number. However, if one were to 15

erroneously include prepaid connections in the U&U calculation, it would be much 16

more reasonable to use the average historical rate of 131/gpd/ERC. 17

18

Mid County U&U 19

Q. WHAT IS YOUR OPINION OF THE U&U OF THE MID COUNTY 20

WASTEWATER TREATMENT PLANT (WWTP)? 21

A. Using the statutory growth rate, I find the calculated U&U for the Mid County WWTP 22

to be 93.67%. My U&U calculations for the Mid County wastewater treatment plant 23

18

are included in Exhibit ATW-6. My analysis is slightly higher than UIF’s number of 1

91.75% largely because the Test Year Flows I obtained from the Florida Department 2

of Environmental Protection (FDEP) Discharge Monitoring Reports (DMRs). These 3

flows are greater than what UIF utilized in the MFRs. In prior Orders, the Commission 4

determined that the U&U of the WWTP to be 92%. In Order No. PSC-09-0373-PAA-5

SU, the Commission maintained the 92% U&U number in recognition that “some 6

additional capacity is available as redevelopment and some growth in the service area 7

occurs.” 8

9

Despite UIF’s U&U calculation of 91.75% for this system, UIF deems Mid County to 10

be 100% U&U. On Schedule F-6 of the Mid County MFRs, UIF “contends that the 11

limits of redevelopment in the service area appear to have been reached as evident in 12

the stability of the meter equivalent growth in Schedule F-10 and the plant should now 13

be found to be 100% U&U.” I find this statement to be at odds with the fact that UIF 14

on the same Schedule F-6 includes 52,368 gpd of projected post test year flow 15

generated by 27 new ERCs per year in the U&U calculation. It seems quite clear that 16

additional growth in the system can occur. As a result, it is my opinion that 100% 17

U&U for this system is unwarranted. 18

19

Q. WHAT IS YOUR OPINION OF THE MID COUNTY COLLECTION 20

SYSTEM? 21

A. In my review of the system maps UIF filed with the MFRs, I identified approximately 22

50 unserved lots that have access to collection lines. However, this is such a small 23

19

number compared to the total lots in the service area that the U&U of the collection 1

system is essentially 100%; therefore, I do not take exception to UIF’s proposal for 2

this system. 3

4

Lake Placid U&U 5

Q. WHAT IS YOUR OPINION OF THE U&U OF THE LAKE PLACID WWTP? 6

A. I calculated the U&U for the Lake Placid WWTP to be 29.79%. My U&U 7

calculations for the Lake Placid WWTP are included in Exhibit ATW-7. My analysis 8

is slightly higher than UIFs calculated number of 20.83% largely because UIF 9

neglected to include an adjustment for growth in the system that is supported by the 10

analysis on Schedule F-10 of the Lake Placid MFRs. Despite UIF’s U&U calculation 11

of 20.83%, on schedule F-6 for lake Placid, UIF claims this Lake Placid system should 12

be 100% U&U since “the system is not over built and the Commission has found in 13

the last rate case that there is no growth or potential for growth.” 14

15

The no-growth claim is completely refuted by the fact that the Commission has 16

historically found this WWTP to be 28.5% as stated in Order PSC-14-0335-PAA-WS. 17

The growth data UIF supplies in the Schedule F-10 of its MFRs clearly shows that 18

growth has occurred in the system. In addition, a review of the system maps of the 19

Lake Placid service area that UIF submitted as part of its filing show that there is 20

substantial area in the service territory that can accommodate new growth. 21

Furthermore, Exhibit ATW-8 presents an FDEP construction application to construct a 22

wastewater collection system for a new Dollar Store in the Lake Placid service area. 23

20

Moreover, page 10 of 13 of this exhibit shows UIF signed the FDEP application as the 1

Company that will assume ownership of the facilities after it is placed into service. 2

Clearly, growth is occurring in this service area. Therefore, the calculation for U&U 3

taking into account the five-year period for growth should be 29.79%. 4

5

Labrador U&U 6

Q. WHAT IS YOUR OPINION OF THE U&U OF THE LABRADOR WWTP? 7

A. I calculated the U&U for the Labrador WWTP to be 40.59%. My U&U calculations 8

for the Labrador WWTP are included in Exhibit ATW-9. UIF calculates the U&U to 9

be 40.27%; however, UIF contends that, since there has been no growth in the service 10

area and customer usage has actually declined since the last rate case, the system 11

should be considered 100% U&U. Nevertheless, the Company recognizes that there is 12

an 11.6 acre undeveloped parcel in the service area. In addition, a review of the area 13

around the Labrador certificated service territory shows that there is extensive 14

undeveloped land adjacent to the service territory boundary (see Exhibit ATW-10). 15

Clearly, there is potential for new customer development to occur either inside or 16

adjacent to the certificated service territory. Because the service area is not built-out 17

and there is the ability for the service area to expand, this system does not satisfy the 18

two-part test I borrowed from Rule 20-30.4325(4), F.A.C. Therefore, the unused 19

capacity in the WWTP could be used to provide service to new customers and this 20

system should not be considered 100% U&U. 21

21

Eagle Ridge U&U 1

Q. WHAT IS YOUR OPINION OF THE U&U OF THE EAGLE RIDGE WWTP? 2

A. UIF requests the WWTP be considered 100% U&U, claiming the service area is built 3

out. In evaluating UIF’s claim, I applied the two prong test mentioned above in my 4

testimony. I reviewed the system maps provided by UIF as part of the MFRs, as well 5

as aerial photographs. In addition, I conducted a site visit to the WWTP site and drove 6

through a portion of the Eagle Ridge service area. The entire service area is a planned 7

community and is located in a highly developed region of Lee County. I am of the 8

opinion that the design service area is 100% built-out and, since Eagle Ridge is a 9

planned community, there is little likelihood for redevelopment to occur. Furthermore, 10

the surrounding area is developed with centralized service provided by other utilities, 11

so there is no potential to expand the service territory of the system. Even though I 12

calculated the U&U for the Eagle Ridge WWTP to be 84.49% (My U&U calculations 13

for the Eagle Ridge WWTP are included in Exhibit ATW-11), I find both prongs of 14

my build-out test are met and that the Eagle Ridge WWTP should be considered 100% 15

U&U; I do not take exception to UIF’s U&U proposal for this system. 16

17

Q. WHAT IS YOUR OPINION OF THE U&U FOR THE EAGLE RIDGE 18

COLLECTION SYSTEM? 19

A. Based on my review of the system maps UIF provided with the MFRs and my 20

evaluation of the service area, I find that the Eagle Ridge collection system is 100% 21

U&U. 22

22

Crownwood U&U 1

Q. WHAT IS YOUR OPINION OF THE U&U OF THE CROWNWOOD WWTP? 2

A. I calculated the U&U for the Crownwood wastewater treatment plant to be 53.20%. 3

My U&U calculations for the Crownwood WWTP are included in Exhibit ATW-12. 4

In Crownwood Schedule F-6, UIF calculates the U&U to be 53.73% and then goes on 5

to say that in Docket 020071-WS the U&U for this system was previously set by the 6

Commission at 68.65%. UIF goes on to say that in Order No. PSC 14-0025-PAA-WS, 7

the Commission found all systems to be 100% U&U. However, this Order clearly 8

states that the Marion County systems, one of which is Crownwood, were not a part of 9

that rate proceeding. In reviewing this system, I found that the certificated service 10

territory is built out. However, the area around the service territory indicates that there 11

is extensive undeveloped land adjacent to the service territory boundary (see Exhibit 12

ATW-13). Only one part of my two-part test is met since the service territory is built 13

out but there is the ability for the service area to expand. There is clearly the potential 14

for new customer development to occur adjacent to the certificated service territory, 15

and for the Company to seek an expansion of its service territory to provide service to 16

any new customers. Therefore, the unused capacity in the WWTP could be used to 17

provide service to new customers and this system should not be considered 100% 18

U&U. The appropriate U&U to apply to this system is 53.20%. 19

23

Sandalhaven U&U 1

Q. WHAT IS YOUR OPINION OF THE U&U FOR SANDALHAVEN 2

WASTEWATER TREATMENT CAPACITY WITH ENGLEWOOD WATER 3

DISTRICT? 4

A. As noted above, the U&U methodology utilized by UIF in the Sandalhaven MFRs 5

overstates the amount of U&U for the wastewater treatment capacity with Englewood 6

Water District (EWD). First, UIF includes prepaid and guaranteed revenue 7

connections in lieu of including an adjustment for growth in the calculations. Second, 8

in the MFRs, UIF provides a narrative describing the conditions that led to the decision 9

to purchase the EWD capacity and construct the force main and lift station. UIF 10

claims that the EWD capacity should be considered 100% U&U because UIF was 11

prudent in its decisions with respect to purchasing capacity. Based on my review of 12

the documentation, it appears that the decision to purchase capacity and construct the 13

facilities was prudent at the time the decision was made. However, being prudent in 14

acquiring capacity is not a justification that all components should be considered 100% 15

U&U. I testified to this effect in the Sandalhaven rate proceeding before Charlotte 16

County in 2012, and the County agreed with my position. 17

18

As I previously discussed, the inclusion of prepaid connections in U&U 19

inappropriately extends the period for the growth adjustment to an indefinite period of 20

time and distorts the U&U calculation. Sandalhaven is a perfect example of how 21

adding prepaid connections in the U&U calculation forces the current customers to 22

carry the costs for growth indefinitely. Exhibit ATW-14 Sandalhaven Composite 23

24

Exhibit includes page 4 of 4 of Schedule F-6 from the Sandalhaven MFRs, UIF’s 1

responses to OPC’s 1st Request for Admission, and UIF’s responses to OPC’s 9th Set 2

of Interrogatories. 3

4

MFR Schedule F-6 in Exhibit ATW-14 shows the status of the prepaid commitments 5

for Sandalhaven as well as ERCs not built. The dates associated with these prepaids 6

go back at least as far as 1995 with one noted as “predates UI ownership.” If prepaid 7

connections were allowed in the U&U calculation in 1995, the Sandalhaven customers 8

would have been paying for that capacity for more than twenty years. The majority of 9

the remaining prepaid connection transactions occurred in the 2003 to 2006 timeframe 10

and, over ten years later, many still have not connected. 11

12

Q. WHAT IF THE PREPAID ERC COMMITMENTS WILL NEVER 13

MATERIALIZE, SHOULD THAT BE CONSIDERED? 14

A. Yes, but only if the Commission accepts UIF’s proposal for including prepaid ERC 15

connections in the U&U calculation. In response to OPC’s First Request for 16

Admissions, No. 29, UIF admits that 322 of the prepaid ERCs will never be used at the 17

Placida Commons/Coral Caye (formerly 8401 Placida Road) project. The original 18

developer prepaid for 418 ERCs, but this project was later redeveloped into a 96 lot 19

development, so 322 prepaid ERCs will never be used. It is unreasonable for current 20

customers to pay indefinitely in their rates for growth that will never happen. There 21

are two other projects on Schedule F-6 for Sandalhaven, Hammocks at Cape Haze and 22

25

Cape Haze Resort, which have 85 and 120 ERCs not built. These prepaid 1

commitments might also never be built. 2

3

On March 2, 2017, UIF updated the total prepaid commitments/ERCs not built 4

remaining. MFR Schedule F-6 showed 862 prepaid ERCs not built as of December 5

31, 2015; UIF response to OPC 9th Interrogatory No. 219 (revised) shows 847 prepaid 6

ERCs not built as of December 31, 2016. To ensure that current customers do not pay 7

for 322 ERCs that will never be used, the total 847 prepaid ERCs not built should be 8

reduced to 525 prepaid ERCs not built (847 less 322). However, I do not recommend 9

that any prepaid commitments be included in the U&U calculation. 10

11

Q. WHAT OTHER CONCERNS DO YOU HAVE REGARDING UIF’S USE OF 12

PREPAIDS IN THE SANDALHAVEN U&U ANALYSIS? 13

A. UIF uses an unreasonable gpd/ERC wastewater generation rate in its U&U calculation. 14

UIF’s U&U calculation uses a 190 gpd/ERC wastewater generation rate which is 15

almost double the average historical rate of 101 gpd/ERC for Sandalhaven. In 16

response to OPC Interrogatory No. 219 (revised), UIF updates “ERCs not built” and 17

“Prepaid Capacity Not Used” on MFR schedule F-6 page 4 of 4. The update reduces 18

prepaid connections to 847 ERCs not built and Prepaid Capacity Not Used to 160,930 19

gpd of wastewater flow. However, this update does not account for the 322 ERCs that 20

will never connect and does not use the appropriate wastewater generation rate of 101 21

gpd/ERC. If both were updated, the Prepaid Capacity Not Used would be reduced 22

further to 53,025 gpd (101 gpd x 525 ERCs not built). In my opinion, using prepaid 23

26

connections in a U&U analysis is inappropriate, but if included, the appropriate 1

wastewater flows associated with the prepaids is 53,025 gpd, which results in a 2

substantially smaller U&U percentage for Sandalhaven. 3

4

Q. WHAT OTHER CONCERNS DO YOU HAVE REGARDING UIF’S 5

SANDALHAVEN U&U ANALYSIS? 6

A. As in previous rate cases, UIF claimed “economies of scale” as a justification for a 7

100% U&U analysis of this system. While I agree in principle that there is the 8

potential for economies of scale in utility construction, the mere mention of the 9

concept is not sufficient evidence to support a 100% U&U value. It is important to 10

note that constructing larger than needed facilities adds to the operations and 11

maintenance costs of a utility which could in turn lead to higher rates. Any 12

consideration of economies of scale in the context of U&U should include specific, 13

measurable advantages, with offsets for corresponding increases in costs related to the 14

extra capacity of the utility. UIF has not provided specific evidence to document the 15

level of economies of scale associated with these facilities, and this argument should 16

be disregarded. 17

18

Q. WHAT HAS THE COMMISSION’S POSITION BEEN HISTORICALLY 19

REGARDING ECONOMIES OF SCALE IN THE U&U CALCULATION? 20

A. In Order No. PSC-16-0013-PAA-SU, the Commission recognized UIF’s argument for 21

economies of scale in prudently sizing the facilities to meet the long term needs of the 22

service area. However, in calculating the U&U for Sandalhaven, there is no mention 23

27

of economies of scale nor is there any U&U adjustment that is attributed to economies 1

of scale. 2

3

Q. HOW WAS THE ECONOMY OF SCALE ISSUE DEALT WITH IN THE 2012 4

RATE CASE BEFORE CHARLOTTE COUNTY? 5

A. There was no U&U adjustment for economies of scale in the Order adopted by 6

Charlotte County. 7

8

Q. CAN YOU DESCRIBE YOUR APPROACH TO THE U&U CALCULATION 9

FOR THE COMPONENTS OF THE SANDALHAVEN SYSTEM? 10

A. My approach to U&U for the Sandalhaven system follows the methodology I used in 11

the 2012 Rate Case under Charlotte County’s jurisdiction which was accepted by the 12

hearing officer and approved by the County Commission. The components I evaluated 13

are the EWD capacity, master lift station, pumping plants, and force main. Each 14

component is associated with providing wastewater service to the customers; however, 15

each has a different capacity and the U&U analysis should account for these 16

differences. Therefore, I evaluated each component separately for U&U which is 17

similar to the approach taken by the Commission in previous Sandalhaven rate cases. 18

See FPSC Order No. PSC-07-0865-PAA-SU and Order No. PSC-16-0013-PAA-SU. 19

In identifying the capacity of these components, I relied upon documentation provided 20

by UIF in previous rate cases including the 2004 Sandalhaven Wastewater Treatment 21

Facility Wastewater Master Plan and two letters. One letter was dated June 26, 2007 22

from CPH, an engineering company, and one letter was dated October 9, 2015 from 23

28

Kimley Horn, another engineering company, both signed by Stephen Romano, a 1

Florida Registered PE (These three documents are included in ATW-15). I also relied 2

upon the prior Sandalhaven Orders issued by the Commission and Charlotte County. 3

Based on my review of these documents, I used the following capacities in my U&U 4

analysis: 5

o Englewood Water District Capacity – 300,000 gpd 6

o Master Lift Station Structure – 665,000 gpd 7

o Pumping Plant – 275,000 gpd 8

o Force Main – 935,000 gpd 9

10

Q, ARE THESE THE SAME CAPACITIES THAT WERE USED BY THE 11

COMMISSION AND CHARLOTTE COUNTY IN PREVIOUS RATE CASES? 12

A. No. The Commission historically has considered the master lift station as having a 13

capacity of 500,000 gpd. However, in referring to the June 26, 2007 letter from CPH 14

Engineers, the engineer states that the master lift station was designed to serve 665,000 15

gpd so I have revised the capacity of the master lift station to equal this design 16

capacity. In addition from the same letter, the installed lift station pumps (pumping 17

plants) have a lower capacity of 275,000 gpd which I have also used. I make the 18

distinction between the lift station pumps and the master lift station to incorporate the 19

lower capacity of the pumps, which in turn increases the pumps’ U&U percentage. 20

21

Since the WWTP has been demolished, the force main to EWD now provides service 22

to the entire Sandalhaven service area. The 2004 Sandalhaven Master Plan identifies 23

29

the projected build out flow for the service area as 935,000 gpd, so I have used that 1

capacity for the force main U&U calculation. 2

3

Q. HOW DO YOU TREAT THE TEST YEAR FLOWS FOR THE 4

SANDALHAVEN U&U CALCULATION? 5

A. According to the flow data presented in Schedule F-2 of the Sandalhaven MFRs, both 6

the WWTP and EWD were receiving wastewater flows through October and a part of 7

November. Since the WWTP was removed from service, the entire wastewater flow 8

generated in the system has been treated by EWD. For my U&U analysis, I utilized 9

the total Test Year flows for the EWD Capacity and the Force Main. For the Master 10

Lift Station and Pumping Plant, I utilized the Test Year flow that was sent to EWD for 11

treatment as a conservative value. 12

13

Q. WHAT ARE THE U&U PERCENTAGES YOU DETERMINED FOR THE 14

SANDALHAVEN SYSTEM COMPONENTS? 15

A. My U&U calculations for the Sandalhaven system components are included in Exhibit 16

ATW-15. The results of the analysis are: 17

o Englewood Water District Capacity – 42.24% U&U 18

o Master Lift Station – 11.27% U&U 19

o Pumping Plant – 27.25% U&U 20

o Force Main – 13.55% U&U 21

30

Q. HOW WOULD YOUR U&U ANALYSIS DIFFER FROM ANALYSIS 1

PROTESTED IN ORDER NO. PSC-16-0013-PAA-SU? 2

A. As I noted before, OPC protested Order No. PSC-16-0013-PAA-SU and the U&U 3

calculation was preserved for determination in this case. I have several concerns with 4

the methodology used for the U&U calculation in that Order. First, the U&U statute 5

and Rule do not mention prepaid or guaranteed revenue connections, thus I would not 6

include prepaid connections and guaranteed revenue connections in the U&U 7

calculation for the reasons stated earlier in this testimony. 8

9

Second, I would not use peaking factors. I believe it was an error to use peaking 10

factors to adjust test year flows used in the U&U calculation which in turn overstated 11

the PAA Order U&U calculation. Both methods of calculating U&U for the 12

Sandalhaven system were substantial deviations from the Commission’s historical 13

method for calculating U&U. 14

15

Q. PLEASE EXPLAIN YOUR CONCERNS REGARDING THE USE OF 16

PEAKING FACTORS IN A U&U CALCULATION? 17

A. Wastewater flows and capacity can be expressed in a number of ways. Frequently 18

with wastewater treatment plants, capacity is expressed in terms of the average annual 19

daily flow, or AADF, which is simply the average of all of the daily flows in a year. 20

Yet, within that year there is also a maximum month (the month with the highest 21

average of daily flows), a maximum day (the day with the highest flow within the 22

year) and even a peak hour (the hour with the highest flow within a day). The 23

31

relationship between these flows is usually expressed as a ratio of the AADF. For 1

example, the maximum daily flow is typically 1.5 to 2 times the annual average daily 2

flow, and peak hour flow is typically 3 to 4 times the annual average daily flow. 3

Expressing the flows for a system in different ways is important for planning, design, 4

and proper sizing. A wastewater pipeline intended to provide service to a 1 MGD 5

AADF service area but will actually be designed to accommodate the peak hour flow 6

of 3 to 4 MGD. When doing a U&U analysis, it is crucial that the basis of flow 7

(AADF, peak hour, maximum day) be the same for both the numerator (the adjusted 8

flow) and the denominator (the facility capacity). 9

10

Q. PLEASE DESCRIBE THE ERROR OF USING PEAKING FACTORS IN THE 11

U&U CALCULATION? 12

A. The test year flows were adjusted by applying a peaking factor of 2.03; however, there 13

was no corresponding adjustment to the facility capacities which are expressed as 14

AADF. As a result, the U&U was calculated by using peak flows divided by AADF 15

capacity. This overstates U&U by a factor of 2.03 times. Therefore, to ensure an 16

apples to apples U&U analysis, the Commission should calculate using AADF flows 17

divided by the AADF capacity in order to arrive at the proper U&U calculation. 18

19

IV. PRO FORMA ADDITIONS TO RATE BASE 20

Q. WILL YOU GENERALLY DESCRIBE THE PRO FORMA ADDITIONS TO 21

RATE BASE? 22

32

A. In this rate case, UIF is requesting approval for approximately $30.8 million in post-1

test year pro forma rate base additions to be included in rate base and customer rates. 2

Of the 47 proposed projects, 44 can be characterized as renewing aging facilities, 3

replacing aging facilities, or improving operations in a number of UIF systems. There 4

are three projects which do not fit into those categories, and they are as follows: (1) 5

The Myrtle Hills Water Main is a growth related project, extending service to new 6

customers in the Sanlando system; (2) Another project is the replacement of a service 7

truck; and (3) The last project is for establishing a UIF system-wide asset database and 8

GIS mapping system. 9

10

Q. HOW DID YOU ORGANIZE YOUR REVIEW OF UIF’s REQUESTED PRO 11

FORMA ADDITIONS TO RATE BASE? 12

A. My review of the requested pro forma projects to rate base fall into four categories or 13

buckets for cost recovery in this rate case: 14

(1) Pro forma projects with adequate cost justification 15

(2) Pro forma projects with cost justification supporting less than requested 16

(3) Pro forma projects lacking adequate cost justification, and 17

(4) Pro forma projects without any cost justification 18

19

Pro forma projects in the first two categories should be included in rate base because 20

the costs appear to be reasonable and were adequately supported by the documentation 21

provided by UIF. Pro forma projects in the second two categories should not be 22

included in rate base for the reasons discussed in my testimony. Throughout my 23

33

testimony I use pro forma projects and pro forma additions synonymously to refer to 1

the almost $30.8 million in post-test year plant additions for which UIF is requesting 2

cost recovery in this rate case. 3

4

Q. DID YOU ENCOUNTER ANY DIFFICULTIES IN PERFORMING YOUR 5

ANALYSIS OF THE AMOUNTS SUPPORTING THE REQUESTED THE 6

PRO FORMA PROJECTS? 7

A. Yes. The amounts requested in the MFRs did not match the amounts supported in Mr. 8

Flynn’s written direct testimony and the supporting documentation in Mr. Flynn’s 9

testimony exhibits did not always add up to the amounts in Mr. Flynn’s written direct 10

testimony. These deficiencies create a huge problem for anyone analyzing the 11

reasonableness of costs because one does not know which amounts the Commission 12

will rely upon when making adjustments or setting prospective rates. In this case, 13

Staff’s Second Set of Interrogatories Nos. 80, 81 and Fourth Set of Interrogatories No. 14

112 recognized this problem by asking why there were discrepancies between 15

Schedule A-3 and Mr. Flynn’s direct testimony and exhibits. The information 16

contained in the MFRs and Mr. Flynn’s testimony should match; however, it does not. 17

UIF stated in each of the interrogatory responses: 18

The values in Schedule A-3 represent the cost information that was 19 available for each project when preparing the MFR’s. Where the values 20 identified for each project contained in witness Flynn’s direct testimony 21 differs from the MFR’s, the difference reflects information gathered 22 subsequently such as project bids, contract amounts, and invoices. The 23 amounts noted in either column do not include capitalized time nor 24 interest incurred during construction 25

34

While I do not agree that UIF should be allowed to provide different information in 1

testimony compared to the information contained in its MFRs, I needed a starting point 2

for my analysis; therefore, I relied on the amounts in Mr. Flynn’s direct testimony for 3

my analysis and recommended adjustments because there were no other data points 4

available. 5

6

Q. WHAT HAS BEEN THE QUALITY OF THE SUPPORTING 7

DOCUMENTATION FOR THE PRO FORMA ADDITIONS TO RATE BASE? 8

A. For the post December 31, 2015 test-year pro forma projects identified in the MFRs, 9

UIF witness Flynn provided only a part of the supporting documentation as Exhibits to 10

his August 30, 2016 testimony. Initially, the MFRs and Mr. Flynn’s testimony exhibits 11

were deemed deficient by the Commission.1 On October 31, 2016, UIF completely 12

replaced all of Mr. Flynn’s exhibits in response to Staff’s deficiency letter. On 13

November 22, 2016, almost three months after UIF’s initial rate filing, UIF’s MFR and 14

application deficiencies were deemed cured. Despite the curing of the deficiencies, 15

much of the supporting documentation provided in Mr. Flynn’s revised exhibits fall 16

short of the minimum requirements to sufficiently support an addition to rate base. 17

18

Q. WHAT DOCUMENTATION IS NECESSARY TO SUPPORT THE 19

ADDITIONS TO RATE BASE? 20

A. A rate base calculation relies upon plant-in-service amounts that are derived from the 21

actual booked costs of assets in the utility system and are supported by invoices from 22

contractors or equipment suppliers. Therefore, actual invoices that document the full 23 1 Document No.07871-16, filed September 29, 2017, in Docket No. 160101-WS.

35

scope of the projects and their final installed costs represent the best documentation to 1

support additions to rate base. That same documentary standard would apply to plant 2

additions completed during and after the test year. 3

4

Q. WOULD ANY OTHER TYPE OF INFORMATION BE SUFFICIENT? 5

A. Yes, competitive bids plus a signed contract. Competitive bids from contractors or 6

suppliers for a well-defined project scope could be considered so long as the selected 7

contractor also has a signed contract or agreement with the utility to perform the work. 8

Competitive bidding, usually from three or more bidders, is an important aspect of 9

obtaining the best cost available in the marketplace. Three competitive bids usually 10

provide the utility with a range of costs for the project. With the selected contractor 11

bound by an agreement or contract to perform the work, there is reasonable assurance 12

that the project will go forward. However, the level of information in a competitive 13

bid or executed contract is not as reliable as actual booked costs. 14

15

Q. PLEASE EXPLAIN WHY A COMPETITIVE BID ALONE IS NOT ENOUGH 16

TO JUSTIFY THE PRO FORMA PROJECT COSTS. 17

A. Competitive bids do not take into account anything that may happen during the 18

construction of the project, such as contingencies. For example, there may be an 19

unforeseen site condition that increases the overall project cost. In that case, relying 20

upon bids for adjustment to rate base could understate the actual project cost. 21

Conversely, the scope of the project may be reduced after the bids are received, 22

thereby reducing the actual cost. If competitive bids are accepted as documentation for 23

36

pro forma additions to rate base, I recommend that, a subsequent true-up should be 1

conducted to reconcile the actual project costs to rate base. In addition, to provide 2

some assurance that the project will actually proceed beyond the bidding process, 3

documentation should be provided demonstrating the contractor is under contract and 4

work on the project is proceeding. 5

6

Q. WHAT IS YOUR OPINION OF THE USE OF ESTIMATES PREPARED BY 7

ENGINEERS OR OTHERS AS SUPPORTING DOCUMENTATION FOR PRO 8

FORMA RATE BASE ADDITIONS? 9

A. Cost estimates come in various levels of detail and accuracy, depending upon the 10

amount of engineering detail and the amount of analysis conducted. One of the 11

primary purposes of an engineering cost estimate is to inform the utility of the amount 12

of funds necessary to complete the project. As a result, cost estimates are conservative 13

in nature. No engineer wants to provide a cost estimate to a utility that underestimates 14

the cost of a project, but that sometimes happens. For example, in the recent KW 15

Resorts Utilities rate case in Docket No. 150071-SU, the initial engineering estimate 16

for the 350,000 gallon treatment tank was significantly less than the competitive bids 17

for the project. If properly performed, an engineering cost estimate is routinely higher 18

than the project cost as determined from competitive bids. Therefore, I do not consider 19

engineering estimates or other estimates as sufficient supporting cost documentation 20

for pro forma rate base additions for cost recovery. 21

37

Q. WHAT WAS THE QUALITY OF THE PRO FORMA ADDITION 1

DOCUMENTATION PROVIDED IN RESPONSE TO THE COMMISSION’S 2

DEFFICIENCY NOTICE? 3

A. In some cases, it was sufficient; however, in many instances, what was provided did 4

not meet the test of valid supporting documentation, and for seven pro forma plant 5

additions, no information was provided at all. 6

7

Pro Forma projects with adequate cost justification 8

Q. WHICH PRO FORMA PLANT ADDITIONS HAVE SUFFICIENT COST 9

JUSTIFICATION? 10

A. Based on my review, UIF has provided sufficient documentation to support 11

$17,016,571 of the $30,835,444 in pro forma additions in Mr. Flynn’s testimony. 12

13

Flynn's Exhibit Number

Project

Project Amount per

Flynn’s Testimony

PCF-2 Cypress Lakes Sediment Removal $50,200

PCF-4 Labrador Sediment Removal $61,137

PCF-6 LUSI Oswalt Road WM Relocation $181,400

PCF-8 LUSI TTHM & HAA5 Study $79,250

PCF-10 LUSI US 27 Utility Relocation $1,806,000

PCF-11 Longwood Church Ave. Relocation $193,880

PCF-12 Longwood I&I Study $50,000

PCF-15 Mid County Field Office $65,000

PCF-16 Mid-County Flow Study (I&I) $80,000

38

PCF-22 Sanlando Autumn Wood Dr. WM Replacement $98,970

PCF-23 Sanlando Lift Station RTU Installation $353,200

PCF-24 Sandlando Markham Wood Utility Relocate $65,900

PCF-26 Sanlando I&I Study and Remediation $1,573,884

PCF-29 Sanlando Well 2A Lift Station Electrical Imp. $343,437

PCF-31 Tierra Verde 8th Ave. Gravity Main Replacement $84,673

PCF-32 UIF Orange Crescent Heights WM Replacement $1,806,000

PCF-35 Lake Tarpon Water Main Replacement $800,000

PCF-38 UIF Seminole Bear Lake WM Replacement $1,485,270

PCF-39 UIF Seminole Crystal Lake WM Replacement $1,585,933

PCF-40 UIF Seminole Little Wekiva WM Replacement $521,681

PCF-41 UIF Seminole Weathersfield Northwest FM $120,000

PCF-42 UIF Seminole Oakland Shores WM Replacement $1,571,701

PCF-43 UIF Seminole Phillips WM Replacement $1,188,247

PCF-44 UIF Seminole Ravenna Park WM Replacement $2,160,808

PCF-45 UIF Seminole Ravenna Park Crystal Lake Int $646,000

PCF-46 Truck Upgrade $44,000

Total $17,016,571 1

Pro forma projects with cost justification supporting less than requested 2

Q. WHICH PRO FORMA PROJECT COST LESS THAN UIF ESTIMATED? 3

A. There were 12 pro forma projects where the supporting documentation provided shows 4

the project cost less than what UIF requested in Mr. Flynn’s testimony. I have 5

summarized those projects and costs in Exhibit ATW-16. According to Mr. Flynn’s 6

testimony, these 12 projects were estimated to cost a total of $4,905,450; however, 7

after reviewing supporting documentation provided through either Flynn’s revised 8

39

testimony exhibits or discovery, I determined these 12 projects cost $4,239,967. So I 1

am recommending $655,483 in reductions from the total amount as shown in the table 2

below: 3

Flynn's Exhibit Number

Project

Project Amount per

Flynn’s Testimony

Supported Amount

PCF-1 Hydrotank Replacement $30,000 $25,732

PCF-3 WWTP EQ Tank and Headworks $350,000 $106,388

PCF-5 Sludge Dewatering Equipment $245,000 $240,000

PCF-7 SCADA $470,000 $458,902

PCF-18 Methanol Pumps and Nutrient Analyzer $102,000 $92,576

PCF-19 US Hwy 19 Relocation $230,000 $172,879

PCF-21 Placida Road Utility Relocation $250,000 $217,034

PCF-25 Myrtle Hills WM $695,450 $684,271

PCF-30 Wekiva WWTP Rehabilitation $1,803,000 $1,729,034

PCF-36 Electrical Improvements at Little Wekiva $323,000 $268,830

PCF-37 WM Replacements $57,000 $0

PCF-47 GIS Mapping Services $350,000 $244,321

Total $4,905,450 $4,239,967 4

Q. IN WHAT WAY WAS THE SUPPORTING DOCUMENTATION FOR THESE 5

PROJECTS DEFIFICIENT? 6

A. In most cases the invoices or competitive bids did not add up to the amount in Mr. 7

Flynn’s direct testimony. However, for the Eagle Ridge EQ Tank and Headworks 8

(Exhibit PCF-3), the Wekiva WWTP Rehabilitation (Exhibit PCF-30), and the WM 9

Replacements (Exhibit PCF-37) projects, there are other reasons for the reductions. 10

40

Q. WHAT IS YOUR REASON FOR THE EAGLE RIDGE EQ TANK 1

ADJUSTMENT? 2

A. Exhibit PCF-13, the Eagle Ridge EQ Tank and Headworks project, is being 3

constructed in a number of phases by different contractors. Much of the supporting 4

documentation, including the cost of the EQ Tank which is the largest component of 5

the project, did not have competitive bids or signed agreements that would adequately 6

support the costs for inclusion into rate base. 7

8

Q. WHAT IS YOUR REASON FOR THE WEKIVA WWTP REHABILITATION 9

ADJUSTMENT? 10

A. For Exhibit PCF-30, the Wekiva WWTP Rehabilitation project, I disagree with UIF’s 11

estimate for the sales tax. 12

13

Q. WHY DOES YOUR SALES TAX ESTIMATE DIFFER FROM UIF’S 14

ESTIMATE FOR THE SANLANDO WEKIVA WWTP REHABILITATION 15

PROJECT? 16

A. UIF’s contract executed with the contractor for this project does not include any sales 17

tax. Since this project is currently being constructed, there is no way of obtaining the 18

exact amount of taxes that will apply. In Mr. Flynn’s Exhibit PCF-30, he estimates the 19

taxes at 7% for the entire value of the project. However, this is clearly overestimated 20

since a large portion of this contract includes project costs that are non-taxable, such as 21

labor. 22

41

For my estimate of taxes, I looked at some of the actual contractor invoices that UIF 1

provided during discovery and found that taxes were only being paid on the equipment 2

portion of the contract at a rate of 6%. Exhibit ATW-17 shows one of the invoices I 3

considered. Therefore, I estimated total sales tax for this project at 6% on the total 4

equipment costs. 5

6

Q. WHAT IS YOUR REASON FOR THE WM REPLACMENTS ADJUSTMENT? 7

A. Documentation provided for Exhibit PCF-37, the UIF-Orange & Seminole Water 8

Main (WM) Replacements, supports engineering costs for a number of different water 9

systems costs that are also supported with the individual system projects; therefore, I 10

have removed the $57,000 amount to avoid double counting. 11

12

Pro Forma projects lacking adequate cost justification 13

Q. WHAT PRO FORMA PROJECTS ARE LACKING ADEQUATE COST 14

JUSTIFICATION? 15

A. There are two projects, the Mid-County Electrical Improvements and Sanlando 16

Shadow Hills Diversion projects, which lack adequate cost justification to be included 17

in customer rates in this rate case. 18

19

Q. WHAT ARE YOUR CONCERNS WITH THE MID-COUNTY ELECTRICAL 20

IMPROVEMENTS PROJECT (EXHIBIT PCF-14)? 21

A. The information provided in Mr. Flynn’s testimony did not include any invoices, 22

competitive bid information, contractor agreements, or invoices. To the extent that 23

42

any supporting information was provided, it was provided in discovery first provided 1

on February 25, 2017, a little more than a week before my testimony was due to be 2

filed. Based on the scant information that was provided, I have significant concerns 3

about how this project was bid. 4

5

My first concern has to do with the bid forms that were received in discovery. As I 6

explained above, competitive bids are a necessary component to ensure the 7

reasonableness of a project’s costs. Typically, the bidding process consists of a 8

number of potential contractors, usually three, submitting a binding bid price based on 9

the same set of drawings and specifications. This is important because in order to get 10

competitive prices each contractor must have access to the same information. 11

12

In response to OPC’s discovery, UIF provided two bids related to this project, one 13

from APG Electric for $1,017,000 and one that appears to be from EMS of Central 14

Florida for $1,110,000. Both bids are attached as Exhibit ATW-18. The bid from APG 15

is typical of what I would expect for a binding contractor’s bid. The bid is on a 16

standardized form signed by a representative of APG and notarized. The bid includes 17

a valid date, contract price, listing of subcontractors and other information that is 18

helpful in evaluating bids. 19

20

The “bid” from EMS of Central Florida is on a single sheet of paper, un-dated, un-21

signed, and contains none of the information that should have been included as 22

compared to APG’s bid. The full name of a representative of the company is missing 23

43

from the form. In my professional opinion, the document from EMS is not a valid bid 1

and throws into question the validity of costs for this project. This project needs to be 2

re-bid and excluded from rate base in this case. Therefore, I find that the estimated 3

costs for this project are unsupported and $900,000 should not be included in this rate 4

case. 5

6

Q. WHAT ARE YOUR CONCERNS WITH THE SHADOW HILLS DIVERSION 7

PROJECT (EXHIBIT PCF-27)? 8

A. The Shadow Hills Diversion project is the largest project in this rate case, initially 9

estimated to cost over $4.2 million. It is broken down into six phases and will have 10

five different contractors coordinating to complete the project. In UIF’s original 11

submission in its MFRs, an engineer’s estimate was provided to support the 12

$4,243,423 cost. To the extent that any supporting information was provided, it was 13

provided in discovery first provided on February 25, 2017, a little more than a week 14

before my testimony was due to be filed. Based on a preliminary review of the 15

supporting information provided, it appears that the cost for this pro forma 16

improvement has increased to approximately $7,800,000, an increase of more than 17

$3,600,000 from UIF’s original estimated cost. UIF received bids for the four most 18

expensive phases of the project in early January 2017, and contracts for the work were 19

executed on February 20, 2017. 20

21

As a professional engineer, I have a major concern with an 88% increase in project’s 22

estimated cost and feel that additional investigation and substantial vetting is required 23

44

to determine why the numbers are $3,600,000 more than UIF’s original estimate. 1

With the contracts only recently executed on February 20, 2017, there was insufficient 2

time to conduct additional discovery to fully review the prudence and reasonableness 3

of the cost numbers. Therefore, I recommend that $4,243,423 in costs be excluded 4

from the current rate case. 5

6

Pro Forma projects without any cost justification 7

Q. WHICH PRO FORMA ADDITIONS HAS UIF FAILED TO PROVIDE ANY 8

SUPPORTING DOCUMENTATION? 9

A. As of February 25, 2017, UIF has failed to provide any supporting documentation on 10

seven projects totaling approximately $3,800,000 as shown in the table below. 11

Flynn's Exhibit Number

Project

Project Amount per

Flynn’s Testimony

PCF-9 TTHM & HAA5 Study $450,000

PCF-13 Longwood Groves I&I Remediation $450,000

PCF-17 Mid-County Excess I&I Remediation $600,000

PCF-20 Pennbrooke WTP Electrical Improvements $270,000

PCF-28 Wekiva WWTP Blower Replacement $600,000

PCF-33 Orangewood, Buena Vista WM Replacement $1,200,000

PCF-34 Summertree Well Abandonment $200,000

Total $3,770,000 12

Mr. Flynn stated in his August 30, 2016 testimony that the supporting information for 13

these projects will be submitted either 60 or 90 days after filing depending upon the 14

project. The exhibit pages in his testimony that refer to these projects state: “held for 15

45

future use.” As of February 25, 2017, 179 days have passed since the filing of the rate 1

case and supporting information has not been received, 116 days since Mr. Flynn’s 2

revised exhibits were filed on October 31, 2016, and 95 days since the Commission 3

deemed UIF’s MRFs to be complete. Therefore, UIF has had more than enough time 4

to provide support for these seven projects. Since UIF failed to timely meet its burden 5

of proof for including these pro forma additions in rate base, $3,770,000 should be 6

exclude from rate base. 7

8

Q. WHAT ABOUT UIF’S RESPONSE TO STAFF’S SEVENTH SET OF 9

INTERROGATORIES, NO. 179 RECEIVED ON MARCH 2, 2017? 10

A. UIF’s response to Staff’s 7th Set of Interrogatories, No. 179, served to OPC and Staff 11

on March 2, 2017, four days before the Intervenor testimony deadline, contains eight 12

Amended Exhibits to Mr. Flynn’s testimony, Exhibits PCF-1, 9, 13, 17, 20, 27, 33, and 13

34. There is no opportunity to verify any of the information in the amended exhibits, 14

conduct discovery, or adequately review all the documents. 15

16

In order to incorporate all the requested pro forma projects into rate base and the 17

requested revenue requirement, UIF had the burden to demonstrate the reasonableness 18

of the costs when it filed its MFRs, direct testimony, and exhibits. UIF clearly failed 19

to provide the necessary support for the reasonableness of all its requested pro forma 20

projects at the time of its initial filing in August or even by the time its MFR 21

deficiencies were cured in November. It is unreasonable to inject such late 22

information into this rate case with no time for review. 23

46

Q. WHAT IS THE TOTAL AMOUNT OF YOUR ADJUSTEMENTS TO THE 1

PRO FORMA ADDITIONS? 2

A. Of the total $30,835,444 requested by UIF in its MFRs, direct testimony, and exhibits, 3

the documentation provided supports allowing up to $21,256,538 pro forma additions 4

to rate base at this time. 5

6

Q. PLEASE SUMMARIZE YOUR RECOMMENDATIONS IN THIS CASE. 7

A. Consistent with my testimony, adjustments in the following areas should be made 8

related to: (1) excessive unaccounted for water in ten systems; (2) excessive inflow 9

and infiltration in three systems; (3) recalculating the appropriate U&U percentages for 10

seven system wastewater treatment plants and two wastewater collection systems; and 11

(4) allowing no more than $21,256,538 in pro forma rate base additions. These 12

recommended adjustments are reasonable and supported by the documents provided 13

by UIF in its original filing and responses to discovery. 14

15

Q. DOES THIS CONCLUDE YOUR TESTIMONY? 16

A. Yes. 17

47

CERTIFICATE OF SERVICE

DOCKET NO. 160101-WS

I HEREBY CERTIFY that a true and correct copy of the foregoing Direct

Testimony of Andrew T. Woodcock has been furnished by electronic mail to the following

parties on this 6th day of March, 2017.

/s/ Erik L. Sayler Erik L. Sayler Associate Public Counsel

Walter Trierweiler Kyesha Mapp Danijela Janjic Wesley Taylor Florida Public Service Commission 2540 Shumard Oak Blvd., Room 110 Tallahassee, FL 32399-0850 Email: [email protected] Email: [email protected] Email: [email protected] Email: [email protected]

Martin S. Friedman, Esquire Coenson Friedman, P.A. 766 N. Sun Drive, Suite 4030 Lake Mary, FL 32746 Email: [email protected]

John Hoy Utilities, Inc. of Florida 200 Weathersfield Avenue Altamonte Springs, FL 32714-4099 Email: [email protected]

Patrick C. Flynn Utilities, Inc. of Florida 200 Weathersfield Avenue Altamonte Springs, FL 32714-4099 Email: [email protected]

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 1

General

Mr. Woodcock has been involved with many different facets of environmental engineering for 25 years. He has special expertise in utility master planning, due diligence investigations, utility valuations, financial feasibility analyses and business plans. Mr. Woodcock’s skills include assisting utilities prepare operating and capital programs and supporting those programs with a series of rates and charges to provide for their successful implementation. He is also experienced in conducting economic and feasibility analyses and serves as an expert witness on utility rate regulatory matters.

Utility Planning

Mr. Woodcock’s water and wastewater utility planning experience includes several master plans, and capital improvements programs that include water, wastewater and reclaimed water utilities. Recent planning projects include the City of Clermont Water, Wastewater and Reclaimed Water Master Plans, the City of Bartow Water Master Plan, and the City of Naples Integrated Water Supply Study. As part of the planning process, Mr. Woodcock has conducted numerous economic, present value and feasibility analyses that evaluate the financial impacts of utility programs and provide useful decision criteria for capital planning.

Mr. Woodcock has participated in over 60 water and wastewater utility valuations and acquisitions for utility systems located throughout the Southeast United States. The acquisition projects cover a wide range of utility system configurations and sizes and include engineering due diligence inspections, valuations, and financing activities associated with the transactions.

Additionally, Mr. Woodcock has experience in the review and analysis of water and wastewater utility rates, charges and impact fees. His experience also extends to providing financial feasibility documentation in support of revenue bonds and utility financial feasibility studies in support of capital funding.

International

Mr. Woodcock has been an integral team member on several infrastructure improvement programs for the US Agency for International Development (USAID). He has conducted field visits to Nigeria and Zambia to evaluate existing infrastructure; meet with prospective teaming partners to identify and recruit local designers; and interview local agency officials and stakeholders to identify project challenges, build consensus, formulate technical approaches, and secure buy-in for development programs.

Prior to his work on international development projects, Mr. Woodcock concentrated on water and wastewater utility planning in the United States. His experience includes master planning and capital improvements programs that include water, wastewater and reclaimed water utilities for major cities. As part of the planning process, Mr. Woodcock has conducted numerous economic, present value and feasibility analyses that evaluate the financial impacts of utility programs and provide useful decision criteria for capital planning. Additionally, Mr. Woodcock has experience in the review and analysis of water and wastewater utility rates, charges, and impact fees. His experience also extends to providing financial feasibility documentation in support of revenue bonds and utility financial feasibility studies in support of capital funding.

Education: MBA, Rollins College, 2001

MS, Environmental Engineering, University of Central Florida, 1989

BS, Environmental Engineering, University of Central Florida, 1988

Registrations/Certifications: Professional Engineer, Florida, No. 47118

Professional Affiliations: Water Environment Federation

American Water Works Association

Office Location: Orlando, FL

Total Years of Experience:

25

Years with Tetra Tech:

23

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 1 of 6

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 2

EXPERIENCE

Utility Planning

20-Year Reuse Water Master Plan, Daytona Beach, FL. Project Manager. The Daytona Beach 20-Year Reuse Water Master Plan evaluated the existing city reuse system and provided a listing of projects to expand the City’s use of reclaimed water over the projection period. A hydraulic model of the system was created in Innovzye software using the City’s existing CAD drawings and as-builts of recent projects. A unique feature of the modeling effort was to effectively simulate a low pressure reclaimed water transmission line that also acts as an outfall to the Halifax River. When the WWTP produces water that does not meet public reuse standards the pipeline is the sole form of effluent disposal. The model was used to develop an operational protocol for the pipeline given these two conflicting uses. Once the CIP was determined a full reclaimed water rate study was performed to demonstrate how varying levels of investment in the CIP would affect reclaimed rates.

Water, Wastewater, and Reclaimed Water Rate Study, Naples, FL. 2007. Project Manager. Performed a study for the evaluation and adjustment of the City’s rate structures for water, wastewater and reclaimed water as necessary to recover costs from capital improvement projects and to promote water conservation. The rate study recommended the development of a tiered structure to promote water conservation and also provided for lower reclaimed water rates to promote the connection to the City’s non-mandatory reclaimed water system. The project included multiple public workshops for citizen input and presentations to the City Council, with ultimate adoption of the rate structure.

Water and Wastewater Utility Master Plan, Marion County, FL. Project Manager. In the previous four years prior to initiation of the Water and Wastewater Master Plan Marion County had quadrupled its utility customer base through a series of utility acquisitions is key growth areas. The primary focus of the Water and Wastewater Master Plan was to provide a roadmap to efficiently consolidate utility systems and establish four County sub regions that would serve as the future basis for utility planning and operations. The Master Plan presented a program for systematically decommissioning small package plants and expanding sub regional facilities to accommodate the existing customer base and projected growth.

Water System Master Planning, Mapping and Modeling, City of Bartow, FL. Project Manager. Tetra Tech was contracted by the City in 1996 to perform a water master plan. In 2008 Tetra Tech updated the master plan with new projections, an expanded hydraulic model and a revised CIP. The hydraulic model was revised to include completed system improvements and projected extensions to serve growth areas. The resulting CIP was classified by three project types; pressure improvements, fire flow improvements, and growth improvements. The master plan also included an upper level financial analysis that evaluated the impact of CIP funding on the cash flows of the system.

Integrated Water Resources Plan, City of Naples, FL. Financial Evaluation. Tetra Tech developed an integrated water resources plan for the City of Naples that evaluated all water supply options for a twenty year planning period. All available water supply source were considered including brackish ground water, stormwater, and surface water from the Golden Gate Canal and Naples Bay. Mr. Woodcock performed a financial evaluation of the most technically feasible alternatives to determine the short term impact of capital and operations costs on the utility’s cash flows.

Water and Wastewater Master Plan, City of Deltona, FL. Project Engineer. The water and wastewater master plans for the City of Deltona were the first master plans prepared on the systems since the City’s acquisition in 2003. In addition the projections and capacity analysis of facilities a hydraulic model was prepared for both the water and wastewater systems to document system behavior and act as a planning tool to develop the proposed CIP. Hydraulic deficiencies in the water and wastewater systems were already well documented by City staff. The models however, were very useful in determining the magnitude of the deficiencies and the appropriate course of corrective action. The wastewater model was used to determine

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 2 of 6

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 3

force main routing to a new WWTP in the developing area of the City. The water model was field calibrated through pressure data record by the City and at remote locations as well as hydrant testing.

Water, Wastewater and Reclaimed Water Master Plan, City of Clermont, FL. 2014. Project Manager for three Master Plans for the City. The master plans were driven by near term permit limitations and accelerated growth in the City’s service area. A key component of the joint master planning effort was developing new hydraulic models for all three systems using WaterGEMSTM. Critical to the modeling effort was to simulate system changes as potable water irrigation customers are systematically converted to reclaimed service. As a result of the modeling pressure problems in the potable were alleviated once the conversions were complete allowing the City to reduce its near term CIP without compromising customer levels of service.

Water and Wastewater Connection Charge and Development Fee Study, City of Bartow, FL. Project Manager: Performed a development fee study to evaluate the impacts of projects on the City’s capital recovery charges. The study also included an analysis of the City’s connection fees for water meters and water and wastewater services. The development fee portion of the study utilized the replacement cost of the applicable portions of the water and wastewater system to establish the current system cost of capacity. The treatment and transmission components of both the water and wastewater system were evaluated separately to provide a functional component breakdown. The City’s industrial wastewater development surcharge was also reviewed. The study also evaluated the capacity definitions of an equivalent residential connection (ERC). Finally, the study updated the meter installation and water and wastewater connection fees to account inflationary changes.

Orange Tree Utilities Utility Valuation, Collier County, FL. Project Manager. Providing assistance to Collier County for the evaluation of the Orange County water and wastewater utility system to determine its condition and needs for improvement prior to acquisition by Collier County.

Series 2014 Water and Sewer Refunding Revenue Bonds, Pasco County, FL. 2014. Project Manager. Served as the Financial Feasibility Consultant for a $105 million revenue bond issue to fund capital improvement projects. Based on the financial strength of the utility and the projections performed by Tetra Tech the bonds have received a rating of AA from Fitch and AA+ from Standard and Poors.

Series 2008 Water and Sewer Refunding Revenue Bonds, Pasco County, FL. 2008. Project Manager. Served as the Financial Feasibility Consultant for a $182.5 million revenue bond issue to fund capital improvement projects. Based on the financial strength of the utility and the projections contained in Tetra Tech’s report the bonds have received an uninsured rating of AA- from Fitch.

West Virginia Planning and Development Council Regions 4 and 7

Source Water Protection Plans - Alternative Source Water Feasibility Analysis for over 20 water systems, 2015.

Deltona, FL

Consulting Engineers Report, Series 2003; Utility System Revenue Bonds, $81.72 million.

Water and Wastewater Impact Fee Study (2005)

Water and Wastewater Rate Study (2006)

Stormwater Utility Rate Study (2008, 2015)

Water and Wastewater Master Plans (2007)

Marion County, FL

Water and Wastewater Impact Fee Study (2005)

Water and Wastewater Utility Master Plan (2005)

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 3 of 6

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 4

City of Orlando, FL

Research Park Reuse Economic Impact Evaluation (2005)

Collier County, FL

Impact Fee Calculation Review (2011)

Meter Accuracy Program and Assessment (2012)

Meter Sizing Policy Review (2012)

Fire Assembly Inventory and Review (2013)

Utility Conveyance Policy Review (2014)

Orange Tree Utilities Due Diligence Investigation (2013)

St. Johns County, FL

Utility Regulatory Services – Intercoastal Utilities (2002, 2005)

Pasco County, FL

Comprehensive Water, Wastewater and Reclaimed Water Rate and Charge Study (2003, 2007, 2011, 2015)

Series 2008 Water and Sewer Revenue Bonds, $182 million

Series 2014 Water and Sewer Revenue Bonds, $104 million

City of Naples, FL

Reclaimed Water Project Assessment and Funding Program (2006)

Comprehensive Water, Wastewater and Reclaimed Water Rate Study (2007)

Stormwater Utility Financial Review (2007)

Integrated Water Supply Study (2008)

City of Minneola, FL

Water Impact Fee Update (2006)

Stormwater Utility Rate Study (2006)

State of Florida - Office of Public Counsel

Utility Regulatory Services – Aqua America Utilities (2007, 2008, 2011)

Utility Regulatory Services – Water Used and Useful Rule (2008)

Utility Regulatory Services – Water Management Services, Inc. (2010)

Utility Regulatory Services – KW Resort Utilities (2008)

City of Punta Gorda, FL

Water Treatment cost Analysis Report (2010, 2014)

City of Huntsville, AL

Alternative Water Supply Study (2008)

City of Daytona Beach, FL

20 Year Reuse System Master Plan (2012)

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 4 of 6

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 5

City of Jacksonville, AR

Acquisition of Little Rock AFB Water System (2015)

City of Clermont, FL

Water, Wastewater and Reclaimed Water Master Plans (2014)

International

USAID, Sustainable Water and Sanitation for Africa, Zambia. 2012 - 2013. Senior Technical Lead for a Cost of Service Study of the 11 utilities that serve domestic, intuitional and commercial customers to ensure that the utilities can operate as commercially viable utilities, and reliably meet the water and sanitation demand within the service areas. The project supports Zambia’s National Water Supply and Sanitation Council (NWASCO) with the overall goal to improve sustainability through promotion of cost recovery throughout Zambia’s urban water sector. Conducted initial interviews with NWASCO management and other stakeholders including USAID, MCC, and the eleven commercial utilities. Developed a comprehensive cost of service model to benchmark utility costs against known values and project future costs of service based on numerous escalation factors. The model was presented to NWASCO and representatives of the utilities in two workshops that included not only an overview of the model purpose but also specific training in the use of the model.

USAID, Sustainable Water and Sanitation for Africa, Nigeria. 2012 – 2014. Water Supply Investment Expert for development of an investment plan for urban water supply and sanitation sector of Bauchi State. The plan provides advice for improving budgeting, financial planning, and attracting external funding sources. Prepared a Water Supply Investment Plan, Long Term Business Plan, and Medium Term Business Plan for the local water service provider, Bauchi State Water Board (BSWB). The overall goal of this project is to improve the operating environment of the urban water service provider through promoting good governance, autonomy of the water service provider and promotion of sustainable financing for urban water supply and sanitation services. Conducted a field mission to Nigeria to meet with the BSWB leaders, study existing funding arrangements for capital and recurrent urban water supply expenditure, and assist in assess capital investment needs as well as operations and maintenance needs. The Water Supply Investment Plan and Business Plans will be used to attract investments from international bilateral donors.

USAID Liberia Municipal Water Project, Liberia. 2014. Team Leader for strategic and business planning development of five water supply outstations. The development consisted of two sets of workshops designed to educate and develop business plans for five water systems in Liberia. The workshops were attended by numerous utility stakeholders including system operations and management personnel, community leaders and representatives from the Liberia Water and Sanitation Corp. The first workshop introduced the concepts and components of a business plan. The audience was divided into several working groups that were guided through a number of exercises to develop the major components of a business plan. The second round of workshops introduced the business plan template and guided the working groups through the initial development of the business plan that was later finalized by the water systems.

USAID Sustainable Water and Sanitation for Africa, South Sudan. 2014. Technical Leader for the development of an Investment Plan for sanitation for the City of Juba. The goal of the investment plan is to provide a pathway for the technical, financial and institutional expansion of sanitation in a city of approximately 500,000 people. The plan expands coverage of sanitation in the city initially through the expansion of latrines, supported by a system of exhauster trucks and a treatment lagoon. In later stages the plan envisions the gradual implementation of a piped sewerage system. The plan also provides guidance on the development of an institutional framework, defining the roles of national, state and, local governing bodies. Finally the plan provides a financial plan with emphasis on the steps required to attract investment from the private and donor sectors.

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 5 of 6

Andrew T. Woodcock, PE Senior Project Manager

Woodcock, Page 6

PAPERS/PRESENTATIONS

"Water and Wastewater Impact Fees: An Overview" Alabama Water Pollution Control Association, July 28, 2008.

“Developing Multi-Year Business Plans and Infrastructure Master Plans,” Institute for Public Private Partnerships (IP3), August 2015.

Docket No. 160101‐WSResume of Andrew T. Woodcock

Exhibit ATW‐1Page 6 of 6

System Water Pumped Water Purchased Water Sold Other Uses UAW % UAW % Other UsesCypress Lakes 68.16 - 44.58 16.82 6.75 9.91% 24.68%Labrador 22.46 - 17.21 1.97 3.28 14.60% 8.77%Lake Placid 5.36 - 4.66 - 0.70 13.06% 0.00%LUSI - Main 1,393,933.00 - 1,313,905.00 9,704.00 70,324.00 5.05% 0.70%LUSI - Four Lakes 6.85 - 5.99 0.24 0.61 8.96% 3.53%LUSI Lake Saunders 4.34 - 2.28 2.07 (0.02) -0.39% 47.78%Pasco - Summertree 58.60 27.36 27.85 3.39 5.78% 47.53%Pasco - Orangewood, etc. 75.99 - 61.93 0.64 13.42 17.66% 0.84%Pennbrooke 141.73 - 130.05 1.66 10.03 7.07% 1.17%Sanlando 2,352.81 - 2,222.14 9.98 120.69 5.13% 0.42%UIF Marion 55.32 - 48.29 0.75 6.28 11.35% 1.36%UIF Orange - Davis Shores - 3.68 3.72 0.01 (0.05) -1.41% 0.33%UIF Orange - Crescent Hts - 17.86 17.44 0.00 0.42 2.34% 0.01%UIF Pinellas - Lake Tarpon 16.56 0.01 12.85 0.38 3.35 20.20% 2.27%UIF Seminole - Bear Lake 14.35 3.03 15.13 0.55 1.70 9.77% 3.16%UIF Seminole - Ravenna Park, etc. 23.86 - 20.63 0.62 2.61 10.95% 2.58%UIF Seminole - Crystal Lake - 10.70 10.67 0.12 (0.09) -0.84% 1.14%UIF Seminole - Jansen 20.60 - 19.01 0.58 1.02 4.94% 2.81%UIF Seminole - Little Wekiva 4.95 - 3.42 0.80 0.73 14.81% 16.12%UIF Seminole - Oakland Shores 24.37 0.11 21.05 0.43 2.99 12.23% 1.77%UIF Seminole - Park Ridge 6.09 - 5.82 0.22 0.06 0.95% 3.58%UIF Seminole - Phillips 5.84 0.34 5.33 0.13 0.71 11.56% 2.07%UIF Seminole - Weathersfield 73.44 6.35 69.74 1.03 9.03 11.31% 1.29%

Docket No. 160101‐WSExcessive Unaccounted for Water Calculations

Exhibit ATW‐2Page 1 of 1

System Total WW flow Water Returned to WWTP Allowable InflowAllowable Infiltration Excess I&I

Cypress Lakes 36,381,010 33,765,678 3,376,568 13,408,012 (14,169,248) Eagle Ridge 77,809,970 83,004,400 8,300,440 15,718,504 (29,213,374)

Cross Creek 21,260,885 see below see below see below see belowLabrador 20,500,225 13,553,817 1,355,382 7,694,034 (2,103,008) Lake Placid 6,843,385 5,698,896 569,890 1,148,920 (574,321) Longwood 137,344,000 see below see below see below see belowLUSI 164,655,150 295,419,535 29,541,954 25,218,113 (185,524,451) Mid-County 282,269,100 271,317,200 27,131,720 24,983,006 (41,162,826) Pennbrooke 35,914,905 84,773,128 8,477,313 12,945,333 (70,280,869) Sandalhaven 50,474,390 30,735,000 3,073,500 12,440,071 4,225,819 Sanlando 731,730,830 1,318,088,203 131,808,820 134,980,595 (853,146,788) Tierra Verde 129,033,140 116,650,200 11,665,020 13,269,167 (12,551,247) UIF Marion 6,205,000 5,328,009 532,801 773,689 (429,499) UIF Pasco

Wis Bar 5,526,330 2,986,999 298,700 1,289,114 951,518 Summertree 33,347,000 21,828,732 2,182,873 10,227,189 (891,794)

UIF SeminoleWeathersfield 48,584,209 55,678,206 5,567,821 13,285,101 (25,946,919) Lincoln Heights 23,302,461 12,124,100 1,212,410 1,248,051 8,717,900

Longwood SubscheduleBased on No of Bills Sched E2 Equivalency Factor ERUs

Res 1553 1 1,553.25 GS 5/8 51 1 50.83 GS 1 10 2.5 25.21 GS 1.5 7 5 35.42 GS 2 7 10 70.00 GS 3 4 20 80.00

Total 1,814.71 WW flow (gpd) 376,284.93 gpd/ERU 207.35 cap/ERU 2.50 gpd/cap 82.94

Longwood Subschedule Equivalency Factor ERUs Form 2015 ARRes 1 908.00 GS 5/8 1 - GS 1 2.5 - GS 1.5 5 - GS 2 10 - GS 3 20 -

Total 908.00 WW flow (gpd) 58,249.00 gpd/ERU 64.15 cap/ERU 2.50 gpd/cap 25.66

LONGWOOD

CROSS CREEK

Docket No. 160101‐WSExcessive Inflow and Infiltration Calculations

Exhibit ATW‐3Page 1 of 1

System

Wastewater

Treatment

Wastewater

Collection

Crownwood 53.20% NA

Eagle Ridge 100.00% 100%

Labrador 40.59% NA

Lake Placid 29.79% NA

LUSI 53.55% NA

Mid County 93.67% 100.00%

Sandalhaven - EWD Cap 42.24% NA

Sandalhaven - Lift Station 11.27% NA

Sandalhaven - Force Main 13.55% NA

Sandalhaven - Pumps 27.25% NA

Docket No. 160101-WSSummary of Used and Useful Percentages

Exhibit ATW-4Page 1 of 1

Docket No. 160101-WSLUSI Used and Useful Calculations

Exhibit ATW-5Page 1 of 1

LUSI

Line Description1 Test Year Flows(1)

2 Annual Average (MGD) 0.452 34 Growth Adjustment5 Test Year ERCs(2) 34416 Annual Growth Using Linear Regression (ERCs/yr)(3) 1267 Growth for Five year Period (ERCs) 6318 Test Year gpd/ERC (Line 2 /Line 5) 131 9 Growth Allowance (MGD) (Line 8*Line 7) 0.083

1011 Test year Flow Plus Growth Allowance (Line 2+line 9) 0.535 1213 Inflow/Infiltration Adjustment14 Excess I&I (gpy) - 15 Excess I&I (gpd) - 1617 Test year Flow with Growth Allowance Less I&I (Line 11-Line 15) 0.535 1819 Capacity (MGD) 0.999 2021 Used and Useful Percentage 53.55%22 Non-Used and Useful Percentage 46.45%

Notes(1) From test year DMRs(2) From MFR Schedue F-10(3) From MFR Schedue F-10

Docket No. 160101-WSMid County Used and Useful Calculations

Exhibit ATW-6Page 1 of 1

Mid County

Line Description1 Test Year Flows(1)

2 Annual Average (MGD) 0.789 34 Growth Adjustment5 Test Year ERCs(2) 20016 Annual Growth Using Linear Regression (ERCs/yr)(3) 277 Growth for Five year Period (ERCs) 1368 Test Year gpd/ERC (Line 2 /Line 5) 395 9 Growth Allowance (MGD) (Line 8*Line 7) 0.054

1011 Test year Flow Plus Growth Allowance (Line 2+line 9) 0.843 1213 Inflow/Infiltration Adjustment14 Excess I&I (gpy) - 15 Excess I&I (gpd) - 1617 Test year Flow with Growth Allowance Less I&I (Line 11-Line 15) 0.843 1819 Capacity (gpd) 0.900 2021 Used and Useful Percentage 93.67%22 Non-Used and Useful Percentage 6.33%

Notes(1) From test year DMRs(2) From MFR Schedue F-10(3) From MFR Schedue F-10

Docket No. 160101‐WSLake Placid Used and Useful Calculations

Exhibit ATW‐7Page 1 of 1

Lake Placid

Line Description

1 Test Year Flows(1)

2 Annual Average (MGD) 0.018                

3

4 Growth Adjustment

5 Test Year ERCs(2) 349

6 Annual Growth Using Linear Regression (ERCs/yr)(3) 32

7 Growth for Five year Period (ERCs) 159

8 Test Year gpd/ERC (Line 2 /Line 5) 53 

9 Growth Allowance (MGD) (Line 8*Line 7) 0.008                

10

11 Test year Flow Plus Growth Allowance (Line 2+line 9) 0.027                

12

13 Inflow/Infiltration Adjustment

14 Excess I&I (gpy) ‐ 

15 Excess I&I (gpd) ‐ 

16

17 Test year Flow with Growth Allowance Less I&I (Line 11‐Line 15) 0.027                

18

19 Capacity (gpd) 0.090                

20

21 Used and Useful Percentage 29.79%

22 Non‐Used and Useful Percentage 70.21%

Notes

(1) From test year DMRs

(2) From MFR Schedue F‐10

(3) From MFR Schedue F‐10

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 1 of 13

Florida Department d Environmental Protection

NOTIFICATION/APPLICATION FOR CONSTRUCTING A DOMESTIC WASTEWATER COLLECTION/TRANSMISSION SYSTEM

PART I- GENERAL

Subpart A: Pennit Application Type

Permit Application Type (mark one only) ED Us Application Fee* Served

Are you applying for an individual permit for a domestic wastewater collection/transmission :::_ to $500 system? Note: an EDU is equal to 3.5 persons. Criteria for an individual pcnnit are contained in Rule 62-604.600(7}, F.A.C.

< 10 $300

Is this a Notice of Intent to use the general permit for wastewater collection/transmission systems? N/A $250 Criteria for qualifying for a general permit are contained in Rule 62-604.600(6), F.A.C. Projects not meeting the criteria in Rule 62-604.600(6}, F.A.C., must apply for an individual permit.

ux"

X

*Note: Each non-contiguous project (i .e., projects that are not interconnected or are not located on adjacent streets or in the same neighborhood) requires a separate application and fee.

Subpart B: Instructions

(I) This form shall be completed for all domestic wastewater collection/transmission system construction projects as follows: • If this is a Notice of Intent to use the general permit, this notification shall be submitted to the Department at least 30 days prior to

initiating construction. • If this is an application for an individual pcnnit, the permit must be obtained prior to initiating construction.

(2) One copy of the completed form shall be submitted to the appropriate DEP district office or delegated local program along with the appropriate fee, and one copy of the following supporting documents. Checks should be made payable to the Florida Department of Environmental Protection, or the name of the appropriate delegated local program.

• If this is a Notice of Intent to use the general penn it, attach a site plan or sketch showing the size and approximate location of new or altered gravity sewers, pump stations and force mains; showing the approximate location of manholes and isolation valves; and showing how the proposed project ties into the existing or proposed wastewater facilities. The site plan or sketch shall be signed and scaled by a professional engineer registered in Florida.

• If this is an application for an individual permit, one set of plans and specifications shall be submitted with this application, or alternatively, an engineering report shall be submitted. Plans and specifications and engineering reports shall be prepared in accordance with the applicable provisions of Chapters 10 and 20 of Recommended Standards for Wastewater Facilities. The plans and specifications or engineering report shall be signed and sealed by a Professional Engineer registered in Florida.

(3) All information shall be typed or printed in ink. Where attached sheets (or other technical documentation) are utilized in lieu of the blank spaces provided, indicate appropriate cross-references on the form. For Items (I) through (4) of Part II of this application fonn, if an item is not applicable to your project, indicate ''NA" in the appropriate space provided.

DEP Fonn 62·604 300(8)(a) EITecuve November 6. 2003

Page 1 of 11

Beltran_M
date

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 2 of 13PART II- PROJECT DOCUMENTATION

(I) Collection!fransmission System Permittee

Name MR. GREG FERRELL Title PROJECT MANAGER Company Name HRES LAKE PLACID, LLC Address 5100 W. KENNEDY BOULEVARD, SUITE 100 City TAMPA State FLORIDA Zip 33609 ----------Telephone 813-289-5511 Fax ---------------- Email [email protected]

(2) General Project Information

Project Name FAMILY DOLLAR STORES -LAKE PLACID Location: County HIGHLANDS City LAKE PLACID Section 22 Township 37 Range

~~-- ----- 30 Project Description and Purpose (including pipe length, range of pipe diameter, total number of manholes, and total number of pump stations):

Sanitary sewer service for 8,352 SF Family Dollar Store including: +1-115 LF 4" PVC SDR-35; one (1) Sanitary Clean-out; +1-3 LF 2" PVC Force Main; one (1) Sanitary Lift Station; +1-1,219 LF 4" PVC Force Main

Estimated date for: Start of construction JANUARY- 2017 Completion of construction AUGUST - 2017 ----------------------Connections to existing system or treatment plant ONE ( 1 )

(3) Project Capacity

A = Type of Unit B = Number of C = Population D = Total E = Per F = Total Average G = Peak Units Per Unit Population Capita Flow Daily Flow hour flow

(Columns B x C) (Columns D x E) Single-Family Home Mobile Home Apartment Commercial, Institutional ,

8,352 SF 1 8,352 0.1 GPD/SF 835 GPD 104 GPH or Industrial Facility*

Total _,i-:L~;;;; .~·.·:.;~_ 1; .• , _'-'J."ll!t:L'" ,•f • -· 8 352 ;:,_r.;,:. .,~:,C. 835 GPD 104 GPH 0 0 0

0 •• * Descnpt10n of commercml, mstttuttonal, and mdustnal factltttes and explanatton of method used to esttmate per captta flow for these factltttes:

FAC Chapter 64E-6 [Table 1]- Shopping Center without food or laundry- 0.1 GPD I Square Foot Avg. Daily Flow: 8,352 SF x 0.1 GPDISF = 835 GPD Peak Hourly Flow: Avg. Daily Flow (835 GPD) x 1 day I 24 hours x Peak Factor (3) = 104 GPH

(4) Pump Station Data (attached additional sheets as necessary)

Estimated Flow to the Station (GPD) Location Type Maximum Average Minimum

Family Dollar 3 HP Grinder Pumo 835 835 0

(5) Collection!fransmission System Design Information

Operating Conditions [GPM @ FT (TDH)l

88 GPM @ 24 TDH

A. This information must be completed for all projects by the applicant's professional engineer, and if applicable, those professional engineers in other disciplines who assisted with the design of the project.

If this project has been designed to comply with the standards and criteria listed below, the engineer shall initial in ink before the standards or criteria. If any of the standards or criteria do not apply to this project or if this project has not been designed to comply with the standards or criteria, mark " X" before the appropriate standard or criteria and provide an explanation, including any applicable rule references, in (5)8 . below.

DEP Fonn 62·604.300(8)(a) Effective NovembeT 6. :!003

Page 2 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 3 of 13

~_£ 2.

~3.

Zk 4.

n-5. n_ 6.

13 7.

n- 8.

~9.

Note, if the project has rlllt been designed in accordance \\ilh the standards and criteria sc:t forth in Rules 62-604.400( 1) nnd (1), F.A.C., nn application for an indh idunl permit shall he submitted. Howc,·er. if Rules 62-604.400( I) nnd (2). F.A.C., specifically allow for :mother altemali\'e that will rcsull in nn equivalent level of reliability and public health protection. the project can be constructed using the general permit.

General Requirements

The project is designed based on an average daily flow of 100 gallons per capita plus wastewater flow from industrial plants and major institutional and commercial facilities unless water use data or other justification is used to better estimate the flow. The design includes an appropriate peaking factor, which covers Ill contributions and non-wastewater connections to those service lines. [RSWF 11.2431

Procedures are specified for operation of the collection/transmission system during construction. [RSWF 20.15j

The project is designed to be located on public right-of-ways, land owned by the pem1ittee, or easements and to be located no closer than I 00 feet from a public drinking water supply well and no closer than 75 feet from a private drinking water supply well; or documentation is provided in Part 11.(5)8., showing that another alternative will result in an equivalent level of reliability and public health protection. (62-604.400( I )(b) and (c), F.A.C.]

The project is designed with no physical connections between a public or private potable water supply system and a sewer or force main and with no water pipes passing through or coming into contact with any part of a sewer manhole. (RSFW 38.1 and 48.5]

The project is designed to preclude the deliberate introduction of storm water, surface water, groundwater, roof runoff, subsurface drainage, swimming pool drainage, air conditioning system condensate water, non-contact cooling water except as provided by Rule 62·61 0.668( I), F.A.C., and sources of uncontaminated wastewater, except to augment the supply of reclaimed water in accordance with Rule 62-610.472(3 )(c), F.A.C . [62-604.400( I )(d), F.A.C.]

The project is designed so that all new or relocated, buried sewers and force mains, arc located in accordance with the separation requirements from water mains and reclaimed water lines of Rules 62-604.400(2)(g)(h) and (i) and (3), F .A.C. Note, if the criteria of Rules 62-604.400(2)(g) 4. or (2)(i) 3., F.A.C., are used, describe in Part ll.(S)BG. alternative

construction features that will be provided to afford a similar level of reliability and public health protection. [62-604.400(2)(g), (h), and (i) and (3), F.A.C.]

Gravity Sewers

The project is designed with no public gravity sewer conveying raw wastewater less than 8 inches in diameter. [RSWF 33.1]

The design considers buoyancy of sewers, and appropriate construction techniques are specified to prevent flotation of the pipe where high groundwater conditions are anticipated. [RSWF 33.3}

All sewers arc designed with slopes to give mean velocities, when flowing full, of not less than 2.0 feet per second, based on Manning's formula using an "n" value of 0.0 13; or if it is not practicable to maintain these minimum slopes and the depth of flow will be 0.3 of the diameter or greater for design average flow, the owner of the system has been notified that additional sewer maintenance will be required. The pipe diameter and slope are selected to obtain the greatest practical velocities to minimize solids deposition problems. Oversized sewers are not specified to justify flatter slopes. [RSWF 33.41, 33.42, and 33.43]

te 10. Sewers arc designed with uniform slope between manholes. [RWSF 33.44]

X

X

II. Where velocities greater than I 5 fps are designed, provisions to protect against displacement by erosion and impact arc specified. [RSWF 33.45]

12. Sewers on 20% slopes or greater are designed to be anchored securely with concrete, or equal, anchors spaced as follows: not over 36 feet center to center on grades 20% and up to 35%; not over 24 feet center to center on grades 35% and up to 50%; and not over 16 feel center to center on grades 50% and over. [RSWF 33.46]

DEP Furm 6l.oo.ll00(1Kal ER'~tuve No~cn*• 6 2001

Page 3oft I

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 4 of 13

2_Pt7.

ylll.

Sewers 24. mches or less are designed with straight alignment between manholes. Where curvilinear sewers are proposed for sewers greater than 24 inches, the design specifies compression joints; ASTM or speci fie pipe manufacturer's maximum allowable pipe joint deflection limits are not exceeded; and curvilinear sewers are limited to simple curves which start and end at manholes. [RSWF 33.5]

Suitable couplings complying with ASTM specifications are required for joining dissimilar materials. [RSWF 33.7]

Sewers are designed to prevent damage from superimposed loads. [RSWF 33.7]

Appropriate specifications for the pipe and methods of bedding and backfilling are provided so as not to damage the pipe or its joints, impede cleaning operations and future tapping, nor create excessive side fill pressures and ovalation of the pipe, nor seriously impair flow capacity. [RSWF 33.81]

Appropriate deflection tests are specified for all flexible pipe. Testing is required after the final backfill has been in place at least 30 days to permit stabili7.ation of the soil-pipe system. Testing requirements specifY: I) no pipe shall exceed a deflection of 5%; 2} using a rigid ball or mandrel for the deflection test with a diameter not less than 95% of the base inside diameter or average inside diameter of the pipe, depending on which is specified in Lhe ASTM specification, including the appendix, to which the pipe is manufactured; and 3) performing the test without mechanical pulling devices. [RSWF 33.85]

Leakage tests are specified requiring that: I) the leakage exfiltration or infiltration does not exceed 200 gallons per inch of pipe diameter per mile per day for any section of the system; 2) exfiltration or infiltration tests be performed with a minimum positive head of2 feet; and 3) air tests, as a minimum, conform to the test procedure described in ASTM C-818 for clay pipe, ASTM C 924 for concrete pipe, ASTM F-14 I 7 for plastic pipe, and for other materials appropriate test procedures. [RSWF.l3.9l, 33.94, and 33.95]

X 19. If an inverted siphon is proposed, documentation of its need is provided in Pan ll.i1)J1G. Inverted siphons arc designed with: I) at least two barrels; 2) a minimum pipe size of 6 inches; 3) necessary a1>purtenances for maintenance, convenient flushing, and cleaning equipment; and 4) inlet and discharge structures having adequate clearances for cleaning equipment, inspection, and flushing. Design provides sufficient head and appropriate pipe sizes to secure velocities of nt least 3.0 fps for design average flows. The inlet and outlet nrc designed so that the design average tlow may be diverted to one barrel, and that either barrel may be cut out of service for cleaning. [RSWF 35)

Manholes

X 20. The project is designed with manholes at the end of each line; at all changes in grade, size, or alignment; at all intersections; and at distances not greater than 400 feet for sewers 15 inches or less and 500 feet for sewers 18 inches to 30 inches, except in the case where adequate modem cleaning equipment is available at distances not greater than 600 feet. [RSWF 34.1)

X 21. Design requires drop pipes to be provided for sewers entering manholes at elevations of 24 inches or more above the manhole invert. Where the difference in elevation between the incoming sewer and the manhole invert is less than 24 inches, the invert is designed with a fillet to prevent solids deposition. Inside drop connections (when necessary) arc designed to be secured to the interior wall of the manhole and provide access for cleaning. Design requires the entire outside drop connection be encased in concrete. [RSWF 34.2]

X 22. Manholes are designed with a minimum diameter of 48 inches and a minimum access diameter of 22 inches. [RSWF 34.3]

X 23. Design requires that a bench be provided on each side of any manhole channel when the pipe diameter(s) are less than the manhole diameter and that no lateral sewer, service connection, or drop manhole pipe discharges onto the surface of the bench. [RSWF 34.5]

X 24. Design requires: I) manhole lift holes and grade adjustment rings be sealed with non-shrinking mortar or other appropriate material: 2) inlet and outlet pipes be joined to the manhole with a gasketed flexible watertight connection or another watertight connection arrangement that allows differential settlement of the pipe and manhole wall; and 3) watenight manhole covers be used wherever the manhole lops may be flooded by street runofTor high water. [RSWF 34.6]

X 25. Manhole inspection and testing for watertightness or damage prior to placing into service arc specified Air testing, if specified for concrete sewer manholes, conforms to the test procedures described in ASTM C-1244 [RSWF 34. 7]

X 26. Electrical equipment specified for use in manholes is consistent with Item 46 of this checklist. [RSWF 34.9)

DEr FarmGl-60J lOO(IM•I Elfccu•• NO\·cmbo:r 6, 1001

Pagc4 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 5 of 13

X

X

X

X

X

Stream Crossings

27. Sewers and force mains entering or crossing streams are designed to be constructed of ductile iron pipe with mechanical joints or so they will remain watertight and free from changes in alignment or grade. Appropriate materials which will not readily erode, cause siltation, damage pipe during placement, or corrode the pipe are specified to backfill the trench. [RSWF 36.21 and 48.5]

28. Stream crossings are designed to incorporate valves or other flow regulating devices (which may include pump stations) on the shoreline or at such distances .fuwl.feml the shoreline to prevent discharge in the event the line is damaged. [62-604.400(2)(1\)5., F.A.C.]

29. Sewers and force mains entering or crossing streams are designed at a sufficient depth below the natural bottom of the stream bed to protect the line. At a minimum, the project is designed with subaqueous lines to be buried at least three feet below the design or actual bottom, whichever is deeper, of a canal and other dredged waterway or the natural bottom of streams, rivers, estuaries, bays, and other natural water bodies; or if it is not practicable to design the project with less than three-foot minimum cover, alternative construction features (e.g. a concrete cap, sleeve, or some other properly engineered device to insure adequate protection of the line) arc described in Part II. C. [62-604.400(2)(k) 1., F.A.C., and RSWF 36.11)

30. Specifications require permanent warning signs be placed on the banks of canals, streams, and rivers clearly identifying the nature and location (including depths below design or natural bottom) of subaqueous crossings and suitably fixed signs be placed at the shore, for subaqueous crossings of lakes, bays, and other large bodies of water, and in any area where anchoring is normally expected. [62-604.400(2)(k)2., F.A.C.]

31. Provisions for testing the integrity of subaqueous lines are specified. [62-604 .400(2)(k)4 , F. A C.]

X 32. Supports are designed for all joints in pipes utilized for aerial crossings and to prevent overturning and settlemenl.

X

Expansion jointing is specified between above ground and below ground sewers and force mains. The design considers the impact of floodwaters and debris. [RSWF 37 and 48.5]

33. Aerial crossings are designed to maintain existing or required navigational capabilities within the watenvay and to reserve riparian rights of adjacent property owners. [62-604.400(2)(k)J., F.A.C.)

Pump Stations

;J} 34. In areas with high water tables, pump stations are designed to withstand flotation forces when empty. When siting the pump station, the design considers the potential for damage or interruption of operation because of flooding. Pump station structures and electrical and mechanical equipment are designed to be protected from physical damage by the I 00-yenr flood. Pump stations are designed to remain fully operational and accessible during the 25-year flood unless lesser flood levels are appropriate based on local considerations, but not less than the I 0-year flood. [62-604.400(2)(e), F.A.C.]

~5. Pump stations are designed to be readily accessible by maintenance vehicles during all weather conditions. [RSWF 41.2]

~ 36. Wet well and pump station piping is designed to avoid operational problems from the accumulation of grit. [RSWF 41.31

X 37. Dry wells, including their superstructure, are designed to be completely separated from the wet well. Common walls nrc designed to be gas tight. [RSWF 42.21]

X 38. The design includes provisions to facilitate removing pumps, motors, and other mechanical and electrical equipmenl. [RSWF 42.22}

DEr l'orm 62-60ol lOOIIM•l Eft'ea•'-r No,·rmbct 6. 2001

Page 5 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 6 of 13

X 39.

:JP4o. ~41 .

The design includes provisions for: I) suitable and safe means of access for persons wearing self-contained breathing apparatus are provided to dry wells, and to wet wells; 2) stairway access to wet wells more than 4 feet deep containing either bar screens or mechanical equipment requiring inspection or maintenance; 3) for built-in-place pump stations, a stairway to the dry well with rest landings at vertical intervals not to exceed 12 feet; 4) for factory-built pump stations over 15 feet deep, a rigidly fixed landing at vertical intervals not to exceed 10 feet unless a man lift or elevator is provided; and 5) where a landing is used, a suitable and rigidly fixed barrier to prevent an individual from falling past the intennediate landing to a lower level. If n manlift or elevator is provided, emergency access is included in the design. [RSWF 42.23)

Specified construction materials arc appropriate under conditions of exposure to hydrogen sulfide and other corrosive gases, greases, oils, and other constituents frequently present in wastewater. [RSWF 42.25]

Except for low-pressure grinder or STEP systems, multiple pumps are specified, and each pump has an individual intake. Where only two units are specified, they are of the same size. Specified units have capacity such that, with any unit out

of service, the remaining units will have capacity to handle the design peak hourly flow. [RSWF 42.31 and 42.36} X 42. Bar racks arc specified for pumps handling wastewater from 30 inch or larger diameter sewers. Where a bar rack is

specified, a mechanical hoist is also provided. The design includes provisions for appropriate protection from clogging for small pump stations. [RSWF 42.322)

X 43. Pumps handling raw wastewater are designed to pass spheres of at least 3 inches in diameter. Pump suction and discharge openings are designed to be atleast4 inches in diameter. [RSWF 42.33] (Note, this provision is not applicable to grinder pumps.)

7l} 44.

J!P4s. The design requires pumps be placed such that under normal operating conditions they will operate under a positive suction head, unless pumps are suction-lift pumps. [RSWF 42.34]

The design requires: I) pump stations be protected from lightning and transient voltage surges; and 2) pump stations be equipped with lighting arrestors, surge capacitors, or other similar protection devices and phase protection. Note, pump stations serving a single building are not required to provide surge protection devices if not necessary to protect the pump station. [62-604.400(2)(b), F.A.C.]

The design requires I) electrical systems and components (e.g., motors, lights, cables, conduits, switch boxes, control circuits, etc.) in raw wastewater wet wells, or in enclosed or partially enclosed spaces where ha7.ardous concentrations of flammable gases or vapors may be present, comply with the National Electrical Code requirements for Class I Group D, Division I locations; 2) electrical equipment located in wet wells be suitable for use under corrosive conditions; 3) each nexible cable be provided with a watertight seal and separate strain relief; 4) a fused disconnect switch located above ground be provided for the main power feed for all pump stations; 5) electrical equipment exposed to weather to meet the requirements of weatherproof equipment NEMA 3R or 4; 6) a II 0 volt power receptacle to facilitate maintenance be provided inside the control panel for pump stations that have control panels outdoors; and 7) ground fault interruption protection be provided for all outdoor outlets. [RSWF 42.35]

X 47. The design requires a sump pump equipped with dual check valves be provided in dry wells to remove leakage or drainage with discharge above the maximum high water level of the wet well. [RSWF 42.37]

1[}48.

_:n 49.

_il35o.

j[B 51.

~52.

Pump station design capacities arc based on the peak hourly flow and are adequate to maintain a minimum velocity of2 feet per second in the force main. [RSWF 42.38]

The design includes provisions to automatically alternate the pumps in use. [RSWF 42.4]

The design requires: I) suitable shutoff valves be placed on the suction line or dry pit pumps; 2) suitable shutoff and check valves be placed on the discharge line of each pump (except on screw pumps); 3) a check valve be located between the shutoff valve and the pump; 4) check valves be suitable for the material being handled; 5) check valves be placed on the horizontal portion of discharge piping (except for ball checks, which may be plnced in the vertical run); 6) all valves be capable of withstanding normal pressure and water hammer; and 7) all shutoff and check valves be operable from the floor level and accessible for maintenance. [RSWF 42.5]

The effective volume of wet wells is based on design average flows and a filling time not to exceed 30 minutes unless the facility is designed to provide flow equalization The pump manufacturer's duty cycle recommendations were utilized in selecting the minimum cycle time [RSWF 42.62]

The design requires wet well noors have a minimum slope of I to I to the hopper bottom and the horizontal area of hopper bottoms be no greater than necessary for proper ~nstallation and function of the inlet. [RSWF 42.63]

DEr Form 62·6GI lOO(IKol Elf«ll•c No--cmll<r 6 lOOJ

l'agc 6 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 7 of 13

X

X

X

X

X

53. For covered wet wells, the design provides for air displacement to the atmosphere, such as an inverted "j" tube or other means. [RSWF 42.64]

54. The design provides for adequate ventilation all pump stations; mechanical ventilation where the dry well is below the ground surface; permanently installed ventilation if screens or mechanical equipment requiring maintenance or inspection are located in the wet well. Pump stations are designed with no interconnection between the wet well and dry well ventilation systems. [RSWF 42.71]

55. The design requires all intermittently operated ventilation equipment to be interconnected with the respective pit lighting system and the manual lighting/ventilation switch to override the automatic controls. [RSWF 42. 73]

56. The design requires the fan wheels of ventilation systems be fabricated from non-sparking material and automatic heating and dehumidification equipment be provided in all dry wells. [RSWF 42.74]

57. If wet well ventilation is continuous, design provides for at least 12 complete 100% fresh air changes per hour; if wet well ventilation is intermittent, design provides for at least 30 complete I 00% fresh air changes per hour; and design requires air to be forced into wet wells by mechanical means rather than solely exhausted from the wet well. [RSWF 42.75)

58. If dry well ventilation is continuous, design provides at least 6 complete 100% fresh air changes per hour; and dry well ventilation is intermittent, design provides for at least 30 complete 100% fresh air changes per hour, unless a system of two speed ventilation with an initial ventilation rate of 30 changes per hour for I 0 minutes and automatic switch over to 6 changes per hour is used to conserve heat. [RSWF 42.76)

~59.

1!} 60.

Pump stations are designed and located on the site to minimize adverse effects from odors, noise, and lighting. [62-604.400(2)(c), F.A.C.)

The design requires pump stations be enclosed with a fence or otherwise designed with appropriate features to discourage the entry of animals and unauthorized persons. Posting of an unobstructed sign made of durable weather resistant material at a location visible to the public with a telephone number for a point of contact in case of emergency is specified. [62-604.400(2)(d), F.A.C.]

X

X

61. The design requires suitable devices for measuring wastewater flow at all pump stations. Indicating, totalizing, and recording flow measurement are specified for pump stations with a 1200 gpm or greater design peak flow. [RS WF 42.8]

62. The project is designed with no physical connections between any potable water supplies and pump stations. If a potable water supply is brought to a station, reduced-pressure principle backflow-prevention assemblies are specified. [RSWF 42.9 and 62-555.30(4), F.A.C.]

Additional Items to be Completed for Suction-Lift Pump Statjons

63. The design requires all suction-lift pumps to be either self-priming or vacuum-priming and the combined total of dynamic suction-lift at the "pump ofr' elevation and required net positive suction head at design operating conditions not to exceed 22 feet For self-priming pumps, the design requires: I) pumps be capable of rapid priming and repriming at the "lead pump on" elevation with self-priming and repriming accomplished automatically under design operating conditions; 2) suction piping not to exceed the size of the pump suction or 25 feet in total length; and 3) priming lift at the "lead pump on" elevation to include a safety factor of at least 4 feel from the maximum allowable priming lift for the specific equipment at design operating conditions. For vacuum-priming pump stations, the design requires dual vacuum pumps capable of automatically and completely removing air from the suction-lift pumps and the vacuum pumps be adequately protected from damage due to wastewater. [RSWF 43.1]

64. The design requires: I) suction-lift pump equipment compartments to be above grade or offset and to be effectively isolated from the wet well to prevent a hazardous and corrosive sewer atmosphere from entering the equipment compartment; 2) wet well access not to be through the equipment compartment and to be at least 24 inches in diameter; 3) gaskcted replacement plates be provided to cover the opening to the wet well for pump units to be remove for service; and 4) no valving be located in the wet well. [RSWF 43.2]

DEl' Form62·6G4100(ftWo) Efftcu"-r Nn\c:ntbn 6, 1001

Page: 7 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 8 of 13

n65. Additional Items to be Completed for Submersible Pump Stations

Submersible pumps and motors are designed specifically for raw wastewater use, including totally submerged operation during a portion of each pump cycle and to meet the requirements of the National Electrical Code for such units. Provisions for detecting shaft seal failure or potential seal failure arc included in the design. [RSWF 44.1] .D 66. The design requires submersible pumps be readily removable and replaceable without dewatering the wet well or disconnecting any piping in the wet well. [RSWF 44.2)

67. In submersible pump stations, electrical supply, control, and alarm circuits are designed to provide strain relief; to allow disconnection from outside the wet well; and to protect terminals and connectors from corrosion by location outside the wet well or through use of watertight seals. [RSWF 44.31]

~ 68.

71-69.

11- 70.

'}Z71.

~72.

/}1 73 .

In submersible pump stations, the design requires the motor control center to be located outside the wet well, readily accessible, and protected by a conduit seal or other appropriate measures meeting the requirements of the National Electrical Code, to prevent the atmosphere of the wet well from gaining access to the control center. If a seal is specified, the motor can be removed and electrically disconnected without disturbing the seal. The design requires control equipment exposed to weather to meet the requirements of weatherproof equipment NEMA 3R or 4. [RSWF 44.32]

In submersible pump stations, the design requires: I) pump motor power cords be Ocxiblc and serviceable under conditions of extra hard usage and to meet the requirements of the National Electrical Code standards for flexible cords in wastewater pump stations; 2) ground fault interruption protection be used to de-energize the circuit in the event of any failure in the electrical integrity of the cable; and 3) power cord tenninal fittings be corrosion-resistant and constructed in a manner to prevent the entry of moisture into the cable, provided with strain relief appurtenances, and designed to facilitate field connecting. [RSWF 44.33]

In submersible pump stations, the design requires all shut-off and check valves be located in a separate valve pit. Provisions to remove or drain accumulated water from the valve pit are included in the design. [RSWF 44.4]

Emergency Operations for Pump Stations

Pump stations are designed with nn alarm system which activates in cases of power failure, sump pump f.1ilurc, pump failure, unauthorized entry, or any cause of pump station malfunction. Pump station alarms arc designed to be telemetered to a facility that is manned 24 hours a day. If such a facility is not available and a 24-hour holding capacity is not provided, the alarm is designed to be tclemetered to utility offices during nomtal working hours and to the home of the responsible person(s) in charge of the lift station during off-duty hours. Note, if an audio-visual alarm system with a self-contained power supply is provided in lieu of a tclemetered system, documentation is provided in Part II.( 5 )BG. showing an equivalent level of reliability and public health protection. [RSWF 45}

The design requires emergency pumping capability be provided for all pump stations. For pump stations that receive now from one or more pump stations through a force main or pump stations discharging through pipes 12 inches or larger, the design requires uninterrupted pumping capability be provided, including an in-place emergency generator. Where portable pumping andfor generating equipment or manual transfer is used, the design includes sufficient storage capacity with an alarm system to allow time for detection of pump station failure nnd transportation and connection of emergency equipment. (62-604.400(2)(a) I. and 2., F.A.C., and RSWF 46.423 and 46.433]

The design requires: I) emergency standby systems to have sufficient capacity to start up and maintain the total rated running capacity of the station, including lighting, ventilation, and other auxiliary equipment necessary for safety and proper operation; 2) special sequencing controls be provided to start pump motors unless the generating equipment has capacity to start all pumps simultaneously with auxiliary equipment operating; 3) a riser from the force main with rapid connection capabilities and appropriate valving be provided for all pump stations to hook up portable pumps; and 4) all pump station reliability design features be compatible with the available temporary service power generating and pumping equipment of the authority responsible for operation and maintenance of the collection/transmission system. [62-604.400(2)(a)3 ., F.A.C., and RSWF 46.4311

;i}P 74. The design provides for emergency equipment to be protected from operation conditions that would result in damage to the equipment and from damage at the restoration of regular electrical power. [RSWF 46.411, 46.417, and 46 .432]

DEP Form~-~ l!JOtiX>l Ell"ectr\1! NoW11'1brr 6 2001

Page 8 or t I

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 9 of 13

X

X

X

X

X

75. For permanentl)"'mstfllled internal combustion engines. underground fuel storage and piping facilities arc dcs'1gncd ·m accordance with appli cubic state and fcderdl regulai•ons-, and the design requires engines to be located above grade \<ith adequate vcntit.ttio~ of fuel vapors and c\hausl gases. [RSWF 46.414 and 46.415)

76. F'or pcrmnncnll}•installcd or portable engine-driven pumps nrc used, the design 'mcludcs plovisions for malual .~lart-up. [RSWF 46.422]

77. Where independent substnlP ns arc used for emergency po\<er, each separnte substation and its associnted tmrei miss ion line~ is designed to he capable of'.~tarting af d operating th= p 1mp .r;tation at il'i rated cnfY!city. [RSWF 46.441

Force Mains

78. Force mains nrc designed to maintain, at design pumping rntes, il cleansing velocity nf ill least 2 feet per second. The minimum Ioree mnin diameter specified for rnw wastewater is not less than 4 inches. [RSWP 48.1]

79. The design requires· I) branches of intersecting force mains be provided with npproprintc valves such that one branch may be shut down f<>r maintenance nnd repair without interrupting the now c>f other branches; nnd 2) stubouts on force mains, placed in nnticipution of future connections, be equipped with a valve to nil ow such connection without interruption of service. [62-604.400(2)(f), F.A.C.]

HO. · r he design requires air relief valves be placed at high points in the force main to prevent air locking. LRSWP 48.2)

7f 81. Specified force mnin pipe and jo'mts arc equal to water nulrn strength materiaL'. suitable f{)r design conditions The Ioree main, reaction bloct..ing. and station pip'mg nrc designed to withstand wntcr hammer pressures nnd stresses associated with the c.ycling of w3i tcwatcr pump stations. [RSWF 48.4]

.:9-82.

UsJ. ~114.

When the tt.tzcn nnd Willium!. formula is used to calculate fr1ction lo!.~c~ th1m1gh force muins, the value for "C" is I 00 for unlined iron ol .~ted pipe for design. f-or other snt>olh pipe. nutcri·.,l~. 9-Jch as PVC, polycthylc·• e, l'rncd ductile irm~ the vnlue for C' docs not exceed 120 for design. [RSWF 48.61]

Where fotcc mains ole constructed of material, which nirght cuuse the lo1·cc main to he confused with potable wntct mains, specifications require the force main to be clearly identified. [RS\Vf •18.7)

l.cnkngc tests for force mains are specified 'mclud'mg testing n-,;•thodlt nnd lcat..agc limits. [RSWF 48.8]

•nsWF"' llN'CJ/1/IIII!IUII!dStcrmlcrtrll'/m· Wu.wwater full ft i t•.l' (1997) n~ uduplcd hr rule (V.(,()~ .l011(5)(1,1). f. A (.

n £.\pl.tfll l'Jin lill Rtl(llircmenls or Stund mls Murkctl "X'' inii(5)A Ahute (A linch ml!' r'nmnl ~heel~ ·.r. ~'( CSSRI)' ):

SEEATIACHED

PAirf Ill- Ct:l(flFICA'fiONS (I) Collection/Transmission System Pcnnittcc

I, rhc undersigned owner ur ·o~uiiJlrltcd rcprco;cntnfll't • uf _ H_R_E_S_L-:A_K_E_ P_L-:-A_C_ ID_ , _L_L_c ________________ _ IIIII fully aware thntthc SIDICiliCIIIS mmJe .Ill tli1s DJlf rlcn!ion rot n (UIIStrucl intl pcrmil ore true, COrTCCI Dlld C0111plclc lo the best of Ill)' knowledge 1111tl

hclid lngrcc to relainlhc c.l~:sign eng' or nnothcr pmrcssiunul engineer rcg·lslcred in f-lorida, to condncl on·sllc ohscnaliun ul cun~truct'um, to pre pure II ccrtiliention or complct' If i Ull'.lrue(lon, nnd In rcvicl< rccnnl dm\\ ings ror ndequncy. ruflhcf. I ngrcc tu Jllm ii.Jo.: 1111 IIJIJIIIIJll inlc opemlion nnd muinten cc mn or 1l1c r~ ililics pursunnl 111 lhtle 62-604.500(4}, F.A.C, and tu rctuin u prufcss·I(IIHII engineer rcgislcrtd in Huidn 10 c\anime 'r t.' • c!c:fuL•d) ll c numunl. I nm rully nwurc lhnl Ucpurtment upprovulmust be ohlrlmcd hcfnrc tli1s pcoJ~ci .IS pl.1tcll

I / Jir.l• t.:.\ling lin tcnk~ nmltcMing ctJuipmcnl upcroli<m

Signed Name

~~~~~~===-----------------------------------------------

Date ' l'tde

I :H f oton b2·h0~ JUOfl M•l I' lrctl\ c 1\11\Cn.O.:t f 2CJUI

I' age 9 ul' II

VICE PRESIDENT OF CONSTRUCTION

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 10 of 13

(2) Owner of Collectionffransmission System

I, the undersigned owner or authorized representative* of UTILITIES, INC. OF FLORIDA certify that we will be the Owner of this project after it is placed into service. I agree that we will operate and maintain this project in a manner that will comply with applicable Department rules. Also I agree that we will promptly notify the Department if we sell or legally transfer ownership of this project.

Signed ~L:~ Date 2/7/20 17 Name PATRICK C. FLYNN Title VICE PRESIDENT Company Name UTILITIES, INC. OF FLORIDA Address 200 WEATHERSFIELD AVENUE City ALTAMONTE SPRINGS State FLORIDA Zip 32714-4027 Telephone 866-842-8432 ---------------- Fax 407-869-6961 Email PCFL [email protected] *Attach a letter of authorizatioll.

(3) Wastewater Facility Serving Collectionffransmission System**

If this is a Notice of Intent to use a general permit, check here:

~The undersigned owner or authorized representative* of the Sun 'n Lakes of Lake Placid wastewater facility hereby certifies that the above referenced facility has the capacity to receive the wastewater generated by the proposed collection system; is in compliance with the capacity analysis report requirements of Rule 62-600.405, F.A.C.; is not under a Department order associated with effluent violations or the ability to treat wastewater adequately; and will provide the necessary treatment and disposal as required by Chapter 403, F.S., and applicable Department rules.

If this is an application for an individual permit, check one:

DThe undersigned owner or authorized representative* of the wastewater facility hereby certifies that the above referenced facility has and will have adequate reserve capacity to accept the flow from this project and will provide the necessary treatment and disposal as required by Chapter 403, F.S., and applicable Department rules.

0The undersigned owner or authorized representative* of the wastewater facility hereby certifies that the above referenced facility currently does not have, but will have prior to placing the proposed project into operation, adequate reserve capacity to accept the flow from this project and will provide the necessary treatment and disposal as required by Chapter 403, F.S., and applicable Department rules.

Name of Treatment Plant Serving Project

County Highlands Sun 'n Lakes of Lake Placid

DEP permit number FL A014386 Maximum monthly average daily flow over the last I 2 month period Maximum three-month average daily flow over the last 12 month period Current permitted capacity

City

Expiration Date 6/18/2025 --~-------------------0.0165 MOD Month(s) used Jan-Dec16

0.0212 MOD Month(s) used Jan-Mar16 0.090 MOD ~AADF QiADF 0TMADF

Signed ~.:::: ~ Date 2/7/2017 ---------------Name PATRICK C. FLYNN Title VICE PRESIDENT Address 200 WEATHERSFIELD AVENUE City ALTAMONTE SPRINGS State FLORIDA Zip 32714-4027 Telephone 866-842-8432 Fax 407-869-6961 Email [email protected]

--~------------

.Attach a letter of authorization. **If there is an intennediate collection system, a letter shall be a/lac/red certifying tlrattlre inten11ediate dow11stream collecti01r system lras adequate reserve capacity to accepttlreflowjimn tlris project.

DEP Fonn 62·604.300(8)(a) Effective November 6, ::!003

Page 10 of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 11 of 13(4) Professional Engineer Registered in Florida

I, the undersigned professional engineer registered in Florida, certify that I am in responsible charge of the preparation and production of engineering documents for this project; that plans and specifications for this project have been completed; that I have expertise in the design of wastewater coll~ction/transmission systems; and that, to the best of my knowledge and belief, the engineering design for thi\~il~~P~Jc~ith the requtrements of Chapter 62-604, F.A.C. \.,. ,..l- P.,, ••. , . .: .r-. · •:· ..

Name BRIAN A. BARKER, PE Company Name DEUEL & ASSOCIATES Address 565 S. HERCULES AVENUE City CLEARWATER Telephone 727-822-4151 Fax ------------------Portion of Project for Which Responsible 100%

Name

Company Name Address City

Email

- -------------------------------------

,,~ ,~.· ,..o .. ~. ' ' "' , ... ;.lr~:· . "J..n ..._~~ ... )f'O ~~-:\ ~: • ~ _>.. J :.~; ~ ... : ... :·;~ .. ;.~ ~ ~ ,,~. "'-· . . .. ,~ ..... , ........ ( ;~ww· 5~J~t-l2:-J \ \

- ~~: - ~ - _,.._ ... -- : ::: = ;; "{: ~<i~ ; • .. /'' Lllpe",.

0._ . ,,~. , .:~··

~ ~"' ·"' .· .,..· ,. .... ~~-·~· ... ~ 0 P. \ ?.-··,0:- ~· ~~~ ~-l~ ~~ ... . r:• ..... ~ ....... . :... -~ etc ' v , •

56728 ..,,..t., . ,N ~\ ~- . ·' ·.:" S:n"' ~: . .. ~ ... · ··

Florida Registration No.

State FLORIDA Zip 33764 ~~~----------

[email protected]

Florida Registration No.

State

Signed ---------------­Date

Zip -----------------Telephone Fax Email ------------------Portion of Project for Which Responsible

Name -------------------------------------Company Name Address City Telephone Fax -----------------Portion of Project for Which Responsible

Email

Signed ______________ _ Date

Florida Registration No.

State Zip ----------

DEP Fonn 62-604 300(8)(a) Effecll\e NO\ ember 6. 2003

Page ll of II

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 12 of 13

fAMILY DOLLAR STORES- LAKE PLACID, FLORIDA

ADDRESS: 116 SUN 'N FUN LAKE BOULEVARD, LAKE PLACID, FLORIDA 33852

[D&A#2015-96]

FDEP NOTIFICATION/ APPLICATION FOR CONSTRUCTING A DOMESTIC WASTEWATER COLLECTION/TRANSMISSION SYSTEM FDEP FORM 62-604.300(8)(a)

ADDITIONAL SHEET(S) FOR ITEM (5)8. EXPLANATION FOR REQUIREMENTS OR STANDARDS MARKED "X" IN II(S)A.

GRAVITY SEWERS:

• NUMBER-11

• NUMBER -12 • NUMBER -14 • NUMBER -19

MANHOLES:

• NUMBERS 20 • 26

STREAM CROSSINGS:

• NUMBERS 27 • 33

PUMP STATIONS:

• NUMBER37

a NUMBER 38

• NUMBER39

• NUMBER42

a NUMBER43

• NUMBER47

• NUMBERS 54- 58

No velocities greater 15 FPS are proposed for this project. No Sewers with slopes greater than 20% are proposed for this project. No joining of dissimilar materials proposed for this project. No inverted siphon proposed for this project.

No manholes are proposed for this project.

No stream crossings are proposed for this project.

This pertains to a "Wet Well/ Dry Well" configuration, which the subject Pump Station is not.

Proposed Ebara Sewage Grinder Pump system contains a Guide Rail system that allows for pulling the pumps without having to enter the wet well. This pertains to a "Wet Well/ Dry Well" configuration, which the subject Pump Station is not. In addition, the proposed wet well is less than fifteen feet (15) feet deep. Proposed setup is approximately 8.6 feet deep. Not Applicable - there is no 30-inch or larger diameter sewer. Grinder pumps are to be used.

Not Applicable.

Not Applicable -These pertain to a "Wet Well/ Dry Well" configuration, which the subject Pump Station is not.

ADDITIONAL ITEMS TO BE COMPLETE FOR SUCTION-liFT PUMP STATIONS: • NUMBERS 63 • 64 Not Applicable.

EMERGENCY OPERATIONS FOR PUMP STATIONS: • NUMBERS 75-77 Not Applicable.

fORCE MAINS:

• NUMBER 79 Not Applicable -The design does not include branches of intersecting force mains. • NUMBER 80 Not Applicable -The design does not require air relief valves to be placed at high points.

X:\CAD Projec:ts\Projects\201S\2015·96E Family Dollar ·1.3ke Placid\Englneerinc\Correspondence\Permittin&\FDEP\Orah\Additlonal Sheets FDEP.Wastewater.Applicalloi'\._Form 62·604 300 Ba FamllyOollarStore LP.clocx

Docket No. 160101-WSLake Placid FDEP Construction Application

Exhibit ATW-8Page 13 of 13

5100 W. Kennedy B lvd. Suite 225 Tampa, FL 33609

Tel: 8 13.289.55 11 Fax: 8 13.289.4800

January 5, 2017

Reference: Family Dollar Store US27 and Sun N Lakes Blvd Lal'e Placid, FL

To Whom It May Concern:

\ \

\

Please accept this letter as authorization for Greg Ferrell of Hunt Real Estate to act on behalf of Hunt Real Estate Services, aka Hunt Re Acquisitions, LLC and HRES Lake Placid, LLC regarding correspondence and representation of all notices, approvals and pe1mitting matters required for the above referenced project. If you have any questions, please contact me at 813-289-5511.

of Hunt Real Es,. te Services Inc., Manager

STATE OF FLORIDA COUNTY OF HILLSBOROUGH

Before me personally appeared Hamilton E Hunt Jr who being duly sworn, swears and affirms that the above information is true to the best of his knowledge.

Signed and sworn to before me this 5111 day of January 2017, who I personally know.

NICOLE LACY

\ \

\

I

Notary Public _ _ ___ =--- -----'""-"----'<--------+---?'o;J

My Commission Expires: 0:; \ 80\ \\ (407J '39a:~153 MY COMMISSION #FF029717

EXPIRES J~ne 20, 201?

Florida,NGiaryService.com

I

\ \

I

\

\ \

\

I I

I

Docket No. 160101-WSLabrador Used and Useful Calculations

Exhibit ATW-9Page 1 of 1

Labrador

Line Description1 Test Year Flows(1)

2 Max Three Month (MGD) 0.088 34 Growth Adjustment5 Test Year ERCs(2) 10816 Annual Growth Using Linear Regression (ERCs/yr)(3) 07 Growth for Five year Period (ERCs) 08 Test Year gpd/ERC (Line 2 /Line 5) 81 9 Growth Allowance (MGD) (Line 8*Line 7) -

1011 Test year Flow Plus Growth Allowance (Line 2+line 9) 0.088 1213 Inflow/Infiltration Adjustment14 Excess I&I (gpy) - 15 Excess I&I (gpd) - 1617 Test year Flow with Growth Allowance Less I&I (Line 11-Line 15) 0.088 1819 Capacity (gpd) 0.216 2021 Used and Useful Percentage 40.59%22 Non-Used and Useful Percentage 59.41%

Notes(1) From test year DMRs(2) From MFR Schedue F-10(3) Linear regression results in negtive growth

LEGE

ND

Source: Pasco County, FL; BING imagery

LABRADOR SERVICE TERRITORY0 2,000

Feet

´

P:\

IER

\08

46

5\2

00

-08

46

5-1

60

03

\GIS

\ma

ps\P

asco

_A

PL

ab

rad

orW

SA

.mxd

[be

tty.

mo

rris

3/1

/20

17

]

Labrador Service Territory

Parcels

Docket No. 160101-WS Labrador Map of Certificated Service

Territory and Surrounding Property Exhibit ATW-10

Page 1 of 1

CJ D

~ TETRA TECH

SAYLER.ERIK
Text Box
Docket No. 160101-WS Labrador Map of Certificated Service Territory and Surrounding Property Exhibit ATW-10 Page 1 of 1

Docket No. 160101-WSEagle Ridge Used and Useful Calculations

Exhibit ATW-11Page 1 of 1

Eagle Ridge

Line Description Plant1 Test Year Flows(1)

2 Max Three Month (MGD) 0.239 34 Growth Adjustment5 Test Year ERCs(2) 13126 Annual Growth Using Linear Regression (ERCs/yr)(3) 337 Growth for Five year Period (ERCs) 1658 Test Year gpd/ERC (Line 2 /Line 5) 182 9 Growth Allowance (MGD) (Line 8*Line 7) 0.030

1011 Test year Flow Plus Growth Allowance (Line 2+line 9) 0.269 1213 Inflow/Infiltration Adjustment14 Excess I&I (gpy) - 15 Excess I&I (gpd) - 1617 Test year Flow with Growth Allowance Less I&I (Line 11-Line 15) 0.269 1819 Capacity (gpd) 0.318 2021 Used and Useful Percentage 84.49%22 Non-Used and Useful Percentage 15.51%

Notes(1) From test year DMRs(2) From MFR Schedue F-10(3) Linear regression results in negtive growth

Docket No. 160101-WSCrownwood Used and Useful Calculations

Exhibit ATW-12Page 1 of 1

Crownwood

Line Description1 Test Year Flows(1)

2 Max Three Month (gpd) 20,667 34 Growth Adjustment5 Test Year ERCs(2) 5736 Annual Growth Using Linear Regression (ERCs/yr)(3) 37 Growth for Five year Period (ERCs) 178 Test Year gpd/ERC (Line 2 /Line 5) 36 9 Growth Allowance (gpd) (Line 8*Line 7) 613

1011 Test year Flow Plus Growth Allowance (Line 2+line 9) 21,280 1213 Inflow/Infiltration Adjustment14 Excess I&I (gpy) - 15 Excess I&I (gpd) - 1617 Test year Flow with Growth Allowance Less I&I (Line 11-Line 15) 21,280 1819 Capacity (gpd) 40,000 2021 Used and Useful Percentage 53.20%22 Non-Used and Useful Percentage 46.80%

Notes(1) From test year DMRs(2) From MFR Schedue F-10(3) From MFR Schedue F-10

LEG

END

Source: Pasco County, FL; BING imagery

CROWNWOOD SERVICE TERRITORY0 1,000

Feet

´

P:\IE

R\0

8465

\200

-084

65-1

6003

\GIS

\map

s\M

ario

n_A

PCro

wnw

oodW

SA

.mxd

[bet

ty.m

orris

3/6/

2017

]

Crownwood Service Territory

Parcels

Docket No. 160101-WS Crownwood Map of Certificated Service Territory

and Surrounding Property Exhibit ATW-13

Page 1 of 1

Cl D

~ TETRA TECH

SAYLER.ERIK
Text Box
Docket No. 160101-WS Crownwood Map of Certificated Service Territory and Surrounding Property Exhibit ATW-13 Page 1 of 1

Used and Useful Calculations Wastewater Tre.'ltment Plant

Utilities, Inc. of Florida - Sandalhaven (256-446) Docket No. 160101-WS Test Year Ended: December 31,2015

Florida Public Service Commission

Schedule F-6 Pnge4 of4 Preparer: Seidman, F.

Explanation: Provide all calculations, analyses and governmental requirements used to determine the used and useful percentages for the wastewater treatment plant(s) for the historical test year and the projected test year (if applicable).

Schedule of Commitments and Capacity

COMMITMENTS

Current Annual Average Flow (12 Month RAA) to Sandalhaven WWTP

Additional Prepaid Commitments:

52 lots 60 lots 4Siots 105 condos 48 rooms 234 condos Commer'l 264 apts

422 condos

Eagles Preserve Shamrock Shores Cape Haze Marina, in bankruptcy Hacienda Del Mar, under constr. Ship's Lantern Hotel, no activity Hammocks at Cape Haze, under constr. Cape Haze Plaza Addition, under constr. Cape Haze Resort-under constr. SUBTOTAL 2006

Placida Commons/Coral Caye (formerly 8401 Placida Road} Total Prepaid Commitments through 2006

Prepaid Commitments added after 2006 Placida Plaza Egret Real Estate

Total Prepaid Commitments

(a)

CIAC Paid?

No Yes Yes Yes Yes Yes Yes Yes

Yes

Yes Yes

Total Capacity Committed including flows diverted from WWTP

(b) (C) (d) (e) (9

Calculation of Committed EWD Capacity for Docket No. 160101 Prepaid

ERCs@ Flow ERCS capacity Date 190 gpd/ERC (gpd) not built Not Used Paid

138,285

68 12,920 68 12,920 Guaranteed Rev. Payments 57 10,830 56 10,640 Predates UI ownership 59 11,290 45 8,550 6/12/95

112 21,280 2/24/03 51 9,600 51 9,690 1/15/03

234 44,460 85 16,150 10/1/04 28 5,260 3/31/05

264 50£160 120 22!800 2/24/06 873 165,800 425 80,750

418 79,420 408 77,520 9/11/06 1,291 245,220 833 158,270

26 4,922 26 4,940 10/19/08 3 619 3 570 3/17/09

22 515~1 22 51510 1,320 250,761 862 163,780

I 389L046 I

1

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In Re: Application for increase in water and wastewater rates in Charlotte, Highlands, DOCKET NO. 160101-WS Lake, Lee, Marion, Orange, Pasco, Pinellas, Polk, and Seminole Counties by Utilities, Inc. of Florida /

UTILITIES, INC OF FLORIDA’S RESPONSES TO OPC’S FIRST

REQUEST FOR ADMISSIONS (Nos. 1 – 29)

Utilities, Inc. of Florida (“UIF”), by and through its undersigned counsel, hereby responds

to Office of Public Counsel’s (“OPC”) First Request for Admissions, and states as follows:

Quality of Service

1) UI shareholders earn a return on plant investment to produce, treat, and distribute water. Admit.

2) UI shareholders earn a return on plant investment to collect and treat wastewater. Admit.

3) UI shareholders do not earn a return on bulk water costs passed through to the customer. Admit.

4) UI shareholders do not earn a return on bulk wastewater costs passed through to the

customer. Deny.

5) UI shareholders earn a greater return on plant investments than on passing through

purchased water and wastewater costs to the customer. Deny.

6) UIF works hard to resolve primary water quality issues if and when they occur in any of

its Florida water systems. Admit.

7) The Department of Environmental Protection (DEP) mandates that UIF resolve primary

water quality issues and customers pay for that in their water rates. Deny.

8) UIF is aware of secondary water quality complaints at the following systems:

2

a. Cypress Lakes

b. Labrador

c. Lake Utility Services, Inc. (LUSI)

d. Pennbrooke

e. Sanlando

f. UIF-Marion

g. UIF-Pasco – Summertree

h. UIF-Pasco – Orangewood

i. UIF-Pinellas

j. UIF-Seminole

Admit.

9) The following water systems are out of compliance with DEP secondary water quality

standards:

a. Cypress Lakes

b. Labrador

c. Lake Utility Services, Inc. (LUSI)

d. Pennbrooke

e. Sanlando

f. UIF-Marion

g. UIF-Pasco – Summertree

h. UIF-Pasco – Orangewood

i. UIF-Pinellas

j. UIF-Seminole

3

Deny.

10) Other than resolving the secondary water complaints in the Summertree water system, UIF

has not resolved any secondary water quality complaints in any of its other Florida systems.

Deny.

11) Having failed to resolve the secondary water quality complaints in its other Florida

systems, UIF has sought a rate increase affecting all UIF systems in Florida. Deny.

12) UIF’s current rate increase does not include any programs to resolve secondary water

complaints in its Florida systems. Deny.

13) At the time UIF filed its petition seeking a rate increase (August 30, 2016), UIF did not

have any plans to resolve the secondary water quality complaints in any of UIF’s systems

which currently have secondary water quality complaints. Deny.

14) If the Commission grants UIF’s request for consolidated rates, customers of Pennbrooke,

Sanlando, and UIF-Marion will each see rate increases without resolution to their

secondary water quality complaints. Deny.

15) If the Commission does not grant UIF’s request for consolidated rates, all customers of the

systems with secondary water quality complaints will see rate increases. Deny.

16) When UIF acquired the Summertree water system, UIF knew there were secondary water

quality complaints. UIF has made reasonable inquiry and the information known or

readily obtainable by UIF is insufficient to enable it to admit or deny.

17) UIF waited almost 25 years (1991-2016) to resolve the secondary water quality complaints

in the Summertree water system (i.e. – the interconnection with Pasco Utilities was not

completed until 2016). Deny.

4

18) UIF could have interconnected with Pasco County Utilities in the early 1990s, and have

resolved Summertree’s secondary water quality complaints. UIF has made reasonable

inquiry and the information known or readily obtainable by UIF is insufficient to

enable it to admit or deny.

19) Instead of solving those secondary water quality complaints in the early 1990s, UIF chose

to make additional water treatment plant investments. Deny.

20) When UIF-Summertree had problems complying with the primary water quality standards

in the early 2000s, UIF could have interconnected to Pasco County Utilities which would

have resolved both the primary and secondary water quality complaints. Deny.

21) Instead of solving those primary and secondary water quality complaints in the early 2000s,

UIF chose to make additional water treatment plant investments. Deny.

22) UIF’s shareholders have earned a return on and return of the additional water treatment

plant investments made in Summertree from 1991 to 2016 even though those investments

did not resolve the secondary water quality complaints. Deny.

23) Regarding many of the major projects identified in UIF’s MFRs, UIF delayed starting

major infrastructure improvement projects in its various water and wastewater systems

until it planned to file for its 2016 rate case. Deny.

Sandalhaven

24) After losing the Wildflower Golf Course as a reuse customer, UI did not seek to find any

additional reuse customers for the reuse water produced by the Sandalhaven wastewater

treatment plant. Admit.

5

25) In 2005, UI Sandalhaven knew that development projects in the Sandalhaven service

territory had stalled. Deny.

26) In 2006, UI Sandalhaven knew that development projects in the Sandalhaven service

territory had stalled. Deny.

27) Despite the slowdown in development, UI Sandalhaven entered into two capacity

agreements with the Englewood Water District (EWD) for 100,000 and 200,000 gpd.

Deny.

28) Despite purchasing too much capacity from the Englewood District, UI Sandalhaven has

not sought a refund from EWD for capacity payments. Deny.

29) Please refer to Schedule A-12, page 3 of 3 (attached hereto) which was provided to the

Commission Docket No. 060285-SU, and which was updated in response to staff’s fourth

data request in Docket No. 150102-SU, dated October 15, 2015:

a. Schedule A-12 is a list of developments in the Sandalhaven service territory for which

developers pre-paid CIAC / plant capacity charges to reserve capacity on

Sandalhaven’s system. Admit.

b. The list of 11 developer projects on Schedule A-12 which prepaid CIAC to

Sandalhaven (or its predecessor) has not changed since the December 31, 2014 test

year. Deny. [The ERCs not built count has decreased if houses have been built]

c. Eagles Preserve prepaid CIAC for 68 ERCs, currently pays BFCs to Sandalhaven, but

has not connected to Sandalhaven. Deny. [We collect guaranteed revenue from lot

owners because the Eagles Preserve developer did not pre-pay CIAC]

6

d. Shamrock Shores prepaid CIAC for 57 ERCs, and 57 ERCs have connected to

Sandalhaven. Deny. [The utility seller did not provide any documentation

regarding prepayment of CIAC for Shamrock Shores.]

e. Cape Haze Marina has 45 lots, prepaid CIAC for 59 ERCs, and 45 ERCs not built.

Admit. [I need to double check, but I believe the marina owner paid the CIAC

eventually. We have not been collecting guaranteed revenue thereafter]

f. Sandalhaven is currently collecting payments from Cape Haze Marina customers

connected to the system. Deny.

g. Hammocks at Cape Haze had planned for 234 condos, prepaid CIAC for 253 in 2004

and that number of prepaid CIAC decreased to 234 ERCs by 10/15/16. Deny. [I have

no record of the developer paying for anything other than the 234 condos’ CIAC]

h. Hammocks at Cape Haze has developed approximately 149 condos. Admit.

i. Hammocks at Cape Haze has indicated it will not develop the remaining condos, even

though it has prepaid CIAC for 234 ERCs. Deny. [I have had no communication with

Hammocks at Cape Haze regarding their future development plans.]

j. Sandalhaven has not refunded any of the unused CIAC back to Hammocks at Cape

Haze. Admit. [We don’t refund CIAC]

k. Cape Haze Resort planned for 264 apartments and prepaid CIAC for 264 ERCs but has

not developed or used of its prepaid CIAC? […all of its prepaid CIAC? If so.] Admit.

l. Cape Haze Resort has indicated it will not develop the remaining apartments, even

though it prepaid CIAC for 264 ERCs. Deny. [Don’t know their plans]

m. Sandalhaven has not refunded any of the unused CIAC back to Cape Haze Resort.

Admit.

7

n. In 2006, 422 unit condominium project was under design, and Sandalhaven collected

prepaid CIAC for 418 ERCs. Admit.

o. This 422 unit condominium project went bankrupt and was never built. Admit.

p. Another developer bought this 422 unit condominium project out of bankruptcy, and

redeveloped it to be about 100 units meaning that 322 units will never be built. Admit.

[A 96-lot s/d was developed; some lots now have homes built, 418-96=322.]

q. When this 422 unit condominium was redeveloped, Sandalhaven attempted to collect

from the developer even though Sandalhaven had previously collected CIAC on this

property. Admit. [As I recall, there was some confusion about whether the new

developer was developing some other parcel, not the one planned for the condos.

This confusion was cleared up before any CIAC was paid.]

r. As the successor in interest to the 422 unit condominium project, this developer could

request a refund of approximately 322 ERCs of prepaid CIAC. Deny. [We don’t

refund CIAC]

s. Based on changes to the character of these developments which prepaid CIAC,

Sandalhaven knows that about 300 ERCs worth of prepaid capacity will never be used.

Admit. [As it relates to the 8401 Placida Rd project payment only, 322 units]

COENSON FRIEDMAN, P.A. 766 North Sun Drive, Suite 4030 Lake Mary, FL 32746 Telephone: (407) 322-8000 Fax: (407) 878-2178 [email protected] /s/ Martin S. Friedman Martin S. Friedman, Esquire For the Firm

1

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In Re: Application for increase in water and wastewater rates in Charlotte, Highlands, DOCKET NO. 160101-WS Lake, Lee, Marion, Orange, Pasco, Pinellas, Polk, and Seminole Counties by Utilities, Inc. of Florida /

UTILITIES, INC OF FLORIDA’S RESPONSES TO OPC’S NINTH

INTERROGATORIES (Nos. 217 – 222)

Utilities, Inc. of Florida (“UIF”), by and through its undersigned counsel, hereby responds

to Office of Public Counsel’s (“OPC”) Eighth Interrogatories, and states as follows:

PRELIMINARY STATEMENT

These responses represent UIF’s diligent and best effort to respond to OPC’s written discovery based on investigation which UIF has thus far been able to undertake into the facts relative to this litigation. There may exist further information responsive to this discovery request which is not within UIF’s present knowledge or reasonably available. There may exist persons with knowledge relating to the subject matter of this discovery request of whom UIF is not presently aware of or who has not yet been interviewed. These responses are based on the facts and information now known to UIF as well as a present analysis of the litigation, and do not constitute an admission or representation that additional facts, documents, or witnesses having knowledge relevant to the subject matter of this discovery request do or do not exist. As this matter proceeds, UIF anticipates that other facts and witnesses having knowledge relevant to this request may be identified. Without in any way obligating itself to do so, UIF reserves the right to alter, supplement, amend or otherwise modify the responses herein in any way at any time.

GENERAL OBJECTIONS

1. UIF objects to any Interrogatory that seeks information that was prepared for or in anticipation of litigation and is protected from disclosure by the attorney/client, accountant/client, work product, joint defense or other applicable privileges. To the extent that an interrogatory may be construed as seeking such privileged or protected information, UIF hereby claims such privilege and invokes such protections and will not intentionally provide such information. To the extent that such information is inadvertently provided, it is to be disregarded upon notification by the undersigned. 2. UIF objects to any interrogatory to the extent that it seeks information that is protected from disclosure by Statute, regulation, Administrative Order or case law. 3. UIF objects to any interrogatory to the extent that it seeks confidential business or proprietary information or trade secrets (absent the entry of an appropriate Protective Order or

2

agreement between the Parties) or information, which is subject to the terms of any Confidentiality Agreement(s). 4. UIF objects to any interrogatory that is overly broad, unduly burdensome or seeks information available from other sources that are more convenient and less burdensome and expensive (and/or equally available to OPC). UIF further objects to any interrogatory to the extent that it seeks information that is immaterial and unnecessary to the prosecution or defense of this action. 5. UIF objects to any interrogatory which is not reasonably calculated to lead to the discovery of admissible evidence or which seeks information that is irrelevant and is, therefore, beyond the permissible scope of discovery. 6. UIF objects to any instruction or definition contained in the Ninth Interrogatories to the extent that any such instruction or definition seeks to impose upon UIF any greater obligation than is required by applicable law or any Order entered in this proceeding. UIF further objects to any instructions and/or definitions which call for UIF to provide information that is not in UIF’s possession, custody or purport to require UIF to search the files of other individuals or entities to cull responsive information, are overly broad and unduly burdensome and seek to elicit information that is wholly irrelevant to this proceeding and therefore beyond the permissible scope of discovery. UIF’s provision of an answer in response to any numbered Request is not intended, nor should it be construed, as an acceptance of, or agreement with any of the instructions, definitions, characterizations or descriptions of transactions or events contained in the Request. 7. In providing these answers, UIF does not in any way waive or intend to waive, but rather, to the contrary intends to preserve and is preserving, the following:

A. All objections as to competency, relevance, materiality and admissibility of the discovery and these answers to that discovery, or the subject matter thereof and any aspect of this proceeding or any other court action or judicial or administrative proceeding or investigation;

B. All objections as to vagueness, ambiguity and undue burden; C. All rights to object on any ground to the use of any of these responses to

interrogatories to the subject matter thereof in any subsequent proceeding, including the final hearing in this proceeding or trial in any other action;

D. All rights to object on any ground to any interrogatory for further responses to these or other Requests or any discovery involving or related to the subject matter of the Request; and

E. The right to amend or supplement the interrogatory responses and objections contained herein at a later time.

8. Unless otherwise stated, each of these general objections applies to each of the numbered interrogatory response set forth below and should be deemed related for each numbered Request. All interrogatory responses are made subject to and without waiver of these general objections. Where specific objections are raised, those objections are raised in addition and not to the exclusion of these general objections.

3

9. All interrogatory responses are made subject to and without waiver of these General Objections. Where specific objections are raised, those specific objections are raised in addition to these General Objections.

RESPONSES TO OPC’S NINTH INTERROGATORIES

217. Employee Benefits Expense. Please refer to the attachment provided for the response to

OPC ROG 91, specifically line 549 pertaining to the Health Insurance Claims subaccount.

Please respond to the following:

a. Explain, in detail, why the health insurance reserves adjustment of $110,000

booked on December 31, 2015 was made.

b. Please explain and show, in detail, how the amount of the reserve adjustment was

determined.

c. Please describe the Company's policy of reserving health insurance claims and

indicate when the policy was implemented.

d. Please provide the amount of health insurance reserves adjustments booked in

2013, 2014 and 2016, by month.

RESPONSE: Attached is a breakdown of monthly bills when the services were performed. Using the history in the spreadsheet UIF tries to estimate the amount that is not yet billed, therefore, UIF makes a reserve adjustment for year end. See attached spreadsheet for the health insurance reserve adjustments for 2013-16. These are year- end adjustments; they are not made each month.

218. Employee Benefits Expense. Please refer to the response to OPC ROG 172. Based on the

information provided in the attachment, the health insurance claim expense was $926,599

in 2014, $1,153,840 in 2015 and $1,034,444 in 2016. Please explain, in detail, what factors

caused the mount of health insurance claims expense to decline by approximately $120,000

between the 2015 test year and 2016.

4

RESPONSE: The number of claims vary from year to year. 2016 had fewer claims than 2015.

219. For each of the 10 development projects identified on this Schedule A-12 (attached to the

request for admissions) and shown as having paid CIAC, please describe how the company

verified or determined that the number of “ERCs not built” were in fact not built.

RESPONSE: See document “Sandalhaven ERC’s not built”.

220. For each of these 10 development projects shown on Schedule A-12 (attached to the request

for admissions) that are shown as having paid CIAC, but have “ERCs not built”:

a. has the company contacted the developer to ascertain whether any of those “ERCs

not built” can or will ever be built (For example, has the developer changed the

scope of the project to reduce the number of ERCs that will connect to UI-

Sandalhaven?);

b. and if not, why not;

c. and if so, what did the company learn?

RESPONSE:

a. The Utility has been in contact with the developer of the Ship’s Lantern Hotel, now known as Lemon Bay Resort, periodically over the last few years to request an updated construction schedule but none has been forthcoming even when the developer promised to provide it and after the developer had started construction on the structure.

None of the other developers has provided a construction schedule to the Utility nor informed the Utility of any change in the size or scope of their project. The Utility has not asked any developers to confirm their intentions to construct their projects as originally designed.

b. The developer agreements do not specify a deadline to complete construction. The pace of development is totally up to the project developer. The Utility is obligated, by virtue of the terms of the developer agreement, to reserve capacity in perpetuity for the benefit of the developer or his successors. The Utility must have adequate capacity in its

5

facilities, including the bulk wastewater service agreement, sufficient to provide wastewater service to each development, in whole or in part, when it is connected to the Utility’s infrastructure irrespective of the time lag between execution of the agreement and making connection.

c. See above.

221. For any of the prepaid CIAC development projects shown on Schedule A-12 (attached to

the request for admissions), please explain the differences in ERCs in 2006 and ERCs in

2015.

RESPONSE: One house was built in Shamrock Shores since 2006, fourteen units were built in Cape Haze Marina. Phase 1 of Hammocks at Cape Haze, containing 149 units and the clubhouse/pool facility, was completed. Phase 1 of Cape Haze Resort, containing 144 units and the clubhouse/pool facility, was completed. Placida Commons, a 95-lot subdivision including a clubhouse/pool, was developed and eight homes started. The Cape Haze Plaza Addition was completed. Hacienda del Mar’s 112 condos in seven high rise buildings were completed.

222. Please refer to Schedule A-12 (attached to the request for admissions), please update the

number of “ERCs not built” and “Prepaid Capacity Not Used” and explain the reasons for

the update.

RESPONSE-REVISED: The developer of Coral Caye (formerly known as Placida Commons) continues to construct new single family homes. In 2015, eight homes and the clubhouse/pool were built. In 2016, 16 additional homes have been built. Therefore, the empty lot count is 71. There was no building activity in 2016 in the other developments listed on the referenced schedule. See “Sandalhaven ERCs not built” referenced in Interrogatory No. 219.

COENSON FRIEDMAN, P.A. 766 North Sun Drive, Suite 4030 Lake Mary, FL 32746 Telephone: (407) 322-8000 Fax: (407) 878-2178 [email protected] /s/ Martin S. Friedman Martin S. Friedman, Esquire For the Firm

Utilities, Inc. of Florida - Sandalhaven (256-446)

Docket No. 160101-WS

Test Year Ended: December 31, 2015

Preparer: Flynn, P.

Calculation of Committed EWD Capacity

Response to OPC 9th ROG, 219

CIAC Paid

ERCs @ 190

gpd/ERC

Flow

(gpd)

ERCs not

built as of

12/31/16

Prepaid

Capacity Not

Yet Used Verification Method

All Flows to EWD, TY 2015 138,285

Prepaid Commitments

Eagles Preserve No 68 12,920 68 12,920 Counted empty lots in s/d

Shamrock Shores Yes 57 10,830 56 10,640 Counted empty lots in s/d

Cape Haze Marina Yes 59 11,290 45 8,550 No construction has occurred

Hacienda Del Mar Yes 112 21,280 -

Ship's Lantern Hotel, under constr. Yes 51 9,600 51 9,690 Hotel construction stopped

Hammocks at Cape Haze, Ph. 1 of 2 built Yes 234 44,460 85 16,150 County tax records

Cape Haze Plaza Addition Yes 28 5,260 -

Cape Haze Resort, Ph. 1 of 2 built Yes 264 50,160 120 22,800 County tax records

SUBTOTAL 2006 873 165,800 425 80,750

Coral Caye (fka 8401 Placida Road) Yes 418 79,420 393 74,670 96-lot s/d developed

Total Prepaid Commitments through 2006 1,291 245,220 818 155,420

Prepaid Commitments added after 2006

Placida Plaza Yes 26 4,922 26 4,940 Developer-supplied info

Egret Real Estate Yes 3 619 3 570 Developer-supplied info

29 5,541 29 5,510

Total Prepaid Commitments 1,320 250,761 847 160,930

Total Capacity Committed including

flows diverted from WWTP 389,046

Note: Coral Caye log of sewer taps includes 8 homes and clubhouse in 2015, 16 homes in 2016.

Utilities, Inc, of Florida

Docket No. 160101-WS

Coral Caye subdivision, log of sewer connections by date

2015 Premise Id Address Install Date1 7714169881 10407 COQUINA CT 3/25/20152 8168788272 8881 CONCH AVE CLUB HOUSE 4/1/20153 8289579026 10391 COQUINA CT 6/3/20154 7533161289 10454 COQUINA CT 6/17/20155 0425524790 8816 CONCH AVE 6/19/20156 1731273203 10399 COQUINA CT 6/19/20157 9524616477 8825 CONCH AVE 7/31/20158 7328864940 8897 SCALLOP WAY 12/23/20159 3283470043 8976 SCALLOP WAY 12/23/2015

2016 Premise Id Address Install Date1 4703767795 8785 CONCH AVE 1/14/20162 4395075072 10438 COQUINA CT 1/14/20163 1648073586 10446 COQUINA CT 1/14/20164 6246670171 10500 COQUINA CT 1/14/20165 7634482325 8793 CONCH AVE 1/18/20166 8707557151 8857 CONCH AVE 1/19/20167 7831711261 8873 CONCH AVE 1/19/20168 8103417965 8760 CONCH AVE 1/22/20169 5581122546 8824 CONCH AVE 1/22/2016

10 5695983721 8848 CONCH AVE 1/22/201611 7580175225 9000 SCALLOP WAY 1/22/201612 6317116260 10382 COQUINA CT 4/1/201613 6933537222 8833 CONCH AVE 4/20/201614 8247396948 8944 SCALLOP WAY 7/22/201615 4297536398 8817 CONCH AVE 10/21/201616 3426949060 8912 SCALLOP WAY 11/22/2016

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 1 of 27

Sandalhaven

Line Description

Capacity Fees 

Paid to EWD

Master Lift 

Station

Pumping 

Plant Force Main

1 Test Year Flows(1)

2 from Schedule F‐2 50.474                29.847             29.847           50.474             

3 gallons per day (gpd) 138,285              81,773             81,773           138,285          

4

5 Growth Adjustment

6 Test Year ERCs(2) 1365 xx xx 1365

7 Annual Growth Using Linear Regression (ERCs/yr)(3) 0 0 0 0

8 Growth for Five year Period (ERCs) 0 0 0 0

9 Test Year gpd/ERC (Line 3 /Line 6) 101.31                xx xx 101.31             

10 Growth Allowance (gpd) (Line 8*Line 9) ‐ xx xx ‐

11

12 Test year Flow Plus Growth Allowance (Line 3+line 10) 138,285              81,773             81,773           138,285          

13

14 Inflow/Infiltration Adjustment

15 Excess I&I (gpy)(4) 4,225,819             2,498,871         2,498,871     4,225,819         

16 Excess I&I (gpd) 11,578                6,846               6,846             11,578             

17

18

Test year Flow with Growth Allowance Less I&I (Line 12 ‐ Line 

16) 126,707                74,926               74,926           126,707            

19

20 Capacity (gpd) 300,000              665,000          275,000         935,000          

21

22 Used and Useful Percentage 42.24% 11.27% 27.25% 13.55%

23 Non‐Used and Useful Percentage 57.76% 88.73% 72.75% 86.45%

Notes

(1) Since the decomissioning of the WWTP all Sandalhaven flow pass through the force main and is treated by EWD

(2) From MFR Schedue F‐10

(3) Linear regression results in negtive growth

(4) Excess I&I for Master Lift Station and Pumping Plant calculated as follows.

Total Lift Station Pumps

Test Year Flow 50,474,000     29,847,000   29,847,000     

Ratio to Total 100% 59% 59%

Total Excess I&I 4,225,819       4,225,819     4,225,819       

Allocated I&I 4,225,819       2,498,871     2,498,871       

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 2 of 27

·--[

[

I c I [

[

[

[

[

[

[

[

[

[

[

[

[

[

[

SANDALHA VEN WASTEWATER TREATMENT FACILITY

WASTEWATER MASTER PLAN

FOR:

UTILITIES, INC. OF S~"lDALIL\ VEN 200 \VEATHERSFIELD AVE~l.iE

ALTAMONTE SPRINGS, FL 32714

September 2004

PREPARED BY:

CPR ENGINEERS INC. 101 NORTH \VOODLAND BOULEY ARD, SUITE 100

DELA1~D, FL 32720 PHONE: (386) 736-4142 FAX: (386) 736-8412

CPII Job No.: U0746

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 3 of 27

[

[

[

[

[

[

[

[

[

[ .r L

[

[

[

[

[

[

[

[

1.0 INTRODUCTION

2

Sandolhaven Wastewater Treatment Faci ity is located in eastern Charlotte County east of County Road 775 and south of Gnspnrillo Pines Boulevard. A location mop can be seen in Figure 1-1 .. Titc Facility trcaunc:nt capacity is currently rated at lSOtOOO gallons per day (gpd). The Facility experiences significant seasonal variation in flows primarily due to an increase in the population during the winter months (November through March).

This rnnstcr phm wns prepared to express the future needs of the Facility nnd \\iJl attempt to project the ultimate wastewater demands in the existing service orca by nnnlyzing zoning and future land use maps. This wastewater projection was used to analyze the Utility's future options regarding the wastewater treatment and disposal. The options considered in meeting the flow projections CU'C:

I. E.xpnnd the Facility to trent all current and future flo\\'S. 2. Abandon the Facility nnd convert it into a master pumping station nnd send nll the

flow cWTCnt nnd future to Englewood Water District. 3. Abandon the Facility and con,•crt it into n master pumping station and send all the

flow current and future to Charlotte County. 4. Enter into a bulk agreement with Englewood \Vater District to treat only future flo\\1'"5. S. Enter into n bulk agreement with Charlotte County to treat only future flows.

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 4 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

2.0

2.1

2.2

3

EXISTING

SERVICE AREA

The Snndulhnven \Vastcwntcr Treatment Facility's service area is Jocnted in eastern Charlotte County. The service area is bounded by the lnterconstul Waterway on the west, Buck Creek on the north, Arlington Drive nnd the Rotonda West in the cast, nnd the south end of Don Pedro State Park. There are two golf courses nnd two parks \\ithin the service nren, which comprise approximately 33% of the service oren. The golf courses, Lemon Bny nnd Wildflower, ore located in the northern portion of the service tll'en. One park is Joented in the enst-centrol portiont nnd Don Pedro State Pork makes up the southern most boundary point of the service arcn. The remaining nrcns consist of high, medium, nnd low-density residential areas (developed nnd undeveloped), commercial areas, and industrial areas. There are minimnl amounts of wetlands located within the scr\'ice area; therefore, much of the remaining area could be developed. Figure 2-1 illustrates the zoning in the service area.

The orcas of development primruily consist of single-family nnd multi·frunily residential homes. Approximately 189 acres of the service area (74%) is undeveloped \\ith the ability to be developed.

The service nren hns four areas that are zoned commercial, and they nrc located along County Road 775, as sbO\\n in Figure 2-1. There is n smnll section of nren zoned industrial on the Intcrconstnl where the Mruinn is located.

\V\VTF DF..SCRIPTION

Snndnlhnven Wastewater Treatment Facility is located in the Fiddlers Green community. The Facility operates under Florida Department of Environmentnl Protection Pcnnit # FLA014053. The treatment plant has a rated capacity of 150,000-gallons per day, nnnunl nvcmgc daily Dow. The facility site plan is sho\\11 in Figure 2-2.

The collcclion/tmnsmission system is comprised of approximately 5.25-miles of gravity sewer, approximately 3.7-miles of force mnin, and 12 lift stntions. The Facility does not conlnin a master pump station. Locations of the lift stations are sho\\11 in Figure 3·1. There arc seven (7) lift stations associated with the northern portion of the service area. These lift stations nrc 4, S, 6, 7, 8, 9 and 11. Lift stations 8, 9, and 11 serve the Lemon Buy Golf and Country Club Estates. Lift stntions 9 and 11 feed into lift station 8. Lift station 8 then pumps rnw wastcwntcr across County Road 775 to lift station 4. Lift station 4 nlso receives flow from lift station 7. Lift station 4 then pumps directly into lift station 5. Lift stationS then pumps to the WWTP through n 6-inch force main. Lift stntion 6 also pumps directly to the wnstcwater plant by manifolding into the 6-inch force mnin from lift stntion 5.

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 5 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

l

2.3

4

The southern portion of the service area is comprised of five (5) lift stations. These lift stations EU"C 1, 2, 3, 10 and 12. Lift stations 3, 10 and 12 nll feed a 4·inch force main that runs nlong County Road 775. This 4·inch force moin dumps into n manhole that ultimately feeds lift station 2. Lift station 2 pumps to a mo.nhole thnt is connected with lift station 1. Then lift station 1 pumps directly to the WWTP through a 4·inch force main.

The influent flow c:nlers the plant through 4-inch and 6·inch force mains: directly from lift stations 1 and 5/6, respectively. The influent flow enters inlo the circuhtt steel plant through n manual bar-screen nnd then into the surse chnmbcr. The surge chamber and mnnunl bar-screen arc the only pre-treatment processes for the plant. The steel plant also provides extended aeration nnd clarification. Treated water then enters into one of two sand filters for final filtration. The fihcrcd water then enters one of two chlorine contact chambers for disinfection.

The Facility has two pcnnitted disposal sites (R-001 and R-002) for effluent water. Disposal site R·OOI consists of three rapid infiltration basins (RIBS) with a permitted capacity of 0.150 MOD annuol average doily flow. These rapid infiltration basins are located on site and contain a bottom aren of approximately 32,670 square feet.

Disposal site R4 002 is considered a slow-rotc public access disposal site for golf course irrigation at the Wildflower golf course. The finished wnter is stored in a lined stomgc pond on the \\-nstewnter facility site. R-002 has a pcnnittcd capacity of 0.1 00 MGD annual average daily flow. The reuse water is transferred from the Facility's on site storage pond to either one of two off site: storage ponds located at the Wildflower Country Club & Golf Course. Both off site holding ponds are isolated from the public. The reuse wntcr cnn be introduced into the golf course irrigation system from either of the two off site stomge ponds. TI1c golf course irrigation system can be supplemented by n mnin irrigation lake which is supplied by the on site storm water management system.

EXISTING DEMAl"'mS

The Snndnlhnven Wastewater Treatment Facility experiences seasonal flow vnritltions. The Facility usually mnintnins its peak flows in the months ofNovember through March, due to increases in sensonnl residences. As of December 2003, Snndnlhavcn Wastewater Treatment Facility has 889 service connection!!. This would produce a flow of 102 gallons per service connection, based on the nnnunl average daily flow (AADF) for 2003 of 0.091 MGD. In 2003, the monthly flow vnricd from 0.116 MGD in March to 0.073 MGD in May. The service area's large seasonal population accounts for this variation. The flows per connection runge from 82-130 gpd. For the purpose of flo''' projection in this analysis, the water usnge chart proyided by the Utility was utilized for all future flows.

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 6 of 27

[

[ 3.0 FUTURE

[ 3.1 FUTURE DEVELOPMENT

Throughout the Sandalhaven Wastewater Treatment Facility's service nrea, there nre nine

[ (9) main residential areas that are not developed. Four of the areas nre zoned for High Density Residential (i.e., apartment homes and condominiums). Two arc zoned for Low Density residential (i.e., single family residential homes) and three nrc zoned for Medium

[ Density Residential (i.e •• duplexes or single family residcntinl homes \\oith small lots). Figure 3·1 shows the potcntilll future development of the area. Further, Wildflower Counuy Club is considering selling hnlfofthcir golf course for development.

[ The kn0\\11 and IUlticipated development in the nren includes a 73 unit mobile home

[ community (Pines at Sandalhnvcn) in the northern portion of the service arcn. a 48 unit hotel (Ships Lnntem) nenr the marina. a 112 unit high-rise condominium (Hncicndn Del Mar) in the southwest portion of the service arc~ a 200 unit development (Mnngrove

[ Point) south of the WWTP, a 100 unit development in the medium density area south of Hacienda Del Mar, ond nn expansion to the Cape Haze Plnza (commercial). These five kno\\11 residcntinl developments arc anticipated to ndd 533 connections. The addition to

[ the Cape Haze Plnzn is projected to add 4-ncrcs of development, which is nppro:<imntcly equivalent to 10 more connections.

[ In order to detcnnine the approximate build-out for the service nrcn, the nine residential areas were compared to similar areas that have already been developed. The potentinl amount of units that can be developed in the four High Density Residential areas is

[ approximately 2,105. The 2, lOS units, assumes half the golf course would be de\'clopcd as high-density residential. Redeveloping the golf course area could potentinlly provide 465 service coMcctions. The two low density areas arc located along Counly Road 775

[ and cast of the Wildflower Golf Course, respectively. The Utility is awnre that approximately three 5-ncre rcsidcntinl lots were developed in the low density residential area, cast of the Wildflower golf course. By taking into account the three 5·ncre Jots, the

[ potential amount of connections projected for the low density residential are 150. The three medium density areas nrc along County Road 775, contnin approximately 33.5· acres. These arcns could potentially add 340 connections. Combined, these nine (9)

[ undeveloped areas could potentially ndd 2,595 service connections.

Within the service area there are six (6) non-residential areas that enn be further

[ developed, including the Cape Haze Plazn. These nrens include five (5) commercial areas and one light-intensity industrial arcn, nil of which ore located along County Rond 775. Combined, the five commercial areas contain npproximotely 74·acres. Taking a

[ conservntive estimate thnt 30% of the commercial areas remain to be developed leaves approximately 23-ncrcs of building space in the five commercial nrens. Since these areas are along County Rend 775, we could assume that these areas will be developed into

[ restaurants, offices, hotels, and retail stores. Assuming there could potentially be fi\'e (S) restaurants, 720,000 square feet (st) of store frontage and 250,000 sf of offices, could incrensc the amount of cquivnlent connections by 50. The Utility is aware that a

[

f s

I

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 7 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

f

developer is interested in the light density industrial area. The Utility was infonnc:d that the developer wants to construct n hotel nnd other runcnitics in this area. Currently, the developer is estimating 100,000 gpd of \\nstewater, which is equivalent to 500 connections.

Table 1: Future Dc,•elopmcmt

Name or De,·elopment Number of Units

Pines nt SandBlhaven 73

Mangrove Point 250 Ships Lantern Hotel 48

Mnrinn Redevelopment -Hacienda Del Mar 112 Wild Flower Golf

465 Course Redevelopment Cape Haze Plaza -

Low Intensity Residential (cast of Wild 100

Flower) Low Intensity residential 50 (west of Fiddlers Green)

·~cdium Density Residential (south of 100 Hacienda Del Mar)

High Density Rcsidenti11l Areas 1,640

Surrounding the Pnrk Medium Density

Residential Arens Along 340 County Road 775

Undeveloped Commercial Arens -

TOTAL •3.178

•No~ including the commercial COMcctions • .. ~Ot including the CUJTeflt WDStCWlltCr nows.

Estimaled Known/ TJmc Flow (~pd) Potential

14,600 Kn0\\11 Currently Accepting

Residents 47,500 Known December 2006 9,600 Kno\\11 Unknown

t5o.ooo Potcntinl September 2006 17.400 Known Under Construction

I 93,000 Potentinl Property for Sale

I 5,260 Kno\\11 Under Design

20,000 Potential UnknO\vn

1 10,000 Potential Unknown

20,000 Known Under Design

328t000 Potential Unknown

68,000 Potential Unkno\\11

10,000 Potential Unkno\\11

'"'793,360

At build·out the Facility could have approximately 4.937 service coMections. Since the service nrea contains n minimal amount of wetlands, it is feasible the remaining undeveloped nrcas could be developed.

3.2 FUTURE DEMANDS

6

• ------------------------------------------------------------------------------·

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 8 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

r ._

[

[ r-

L

t 7

Future demands on the Facility arc dependent upon development \\ithin the service orca. The known development consists of the Pines at Snndnlhaven development (14,600 gpd), the Mangrove point development (40,830 gpd), the Ships Lontcm Hotel (9,600 gpd), Hacienda Del Mar (17.400 gpd)~ the Cope Haze Plaza addition (5,260 gpd), the 100 unit development south of Hacienda Del .Mnr (20,000 gpd), and the development in the light density industrial nrcn (150,000 gpd). Combined, these additions to the service area would increase the row wastewater flow by 257,690 gpd. These seven known and onticipated demwtds potcntinlly place the Facility's seasonal high influent flow at a 357,690 brpd, which is 207,690 gpd over the existing desiGJl capacity.

The anticipated development in the area includes the undeveloped residential and commercial nrcas in the service an:a. According to the projection, potentially 2,480 residential coMections can be added to the service area. By applying a per coMection flow of200 gpd per connection, from the water usage chart, these 2,480 connections can odd approximately 496,000 gpd of mw wnstewntcr. This is dependent upon development of the undeveloped nreas. That wouJd bring the Treatment Plants influent flow to approximately 853,690 gpd, not including commercial and industrlnl areas. This flow would necessitate a recommended residential buildout treatment capacity of approximntely 900,000 _gpd.

The remaining orcas, \\hich ore comprised of four commercial areas and one industrial nrca, ore dependent upon whnt type of development occurs. The Utility is D\\1ll'C that n developer is interested in developing the light intensity industrial oren and expanding the Cape Hnze Plnza. Since, both. of these developments arc known, their flows hnve been accounted for. Jt can be assumed thnt the four commercial orcas will either be stores, offices or rcstnumnts. Appro~i~J]nlcly 23-ncrcs of the four (4) commercial sites can be developed. Based on the \\ater usage chort, stores wiJI produce approximately S gpd per I 00 square foot (sf)t offices \\ill produce approximately 1 0 gpd per 1,000 sf, and restaurants will produce approximntcly 50 gpd per scat. A conservative estimate \\ill approximate 5 restnumnts, each with a seating capacity of 150, approximately 720,000 sf of store frontage and 250,000 sf of offices. Combined. these areas could increase the rnw wastewater flow by 81.000 gpdt which would increase the overaJl plant capacity to 935,000 gpd.

t --------------------------------------------------------------------------------------·

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 9 of 27

[

[

[

[

r L

[

[

[

[

[

[

[

[ ,_

L

[

[

[

[

f

ALTERNATIVES

4.1

8

Based on the circumstances the Facility could face in the future, five options have been considered. Currently there are seven projects \\ithin the sen•ice nren that nrc scheduled for development or anticipated for development. These areas 3J'c proposed to increase the wastewater flow by approximately 203,190 gallons per doy (based on projected flows in the pennit application). Based on zoning nnd undeveloped areas, build out would require the Facility to hove a treatment capacity of approximately 896,190 gpd, nearly five nod 11

halftimes the existing capacity. A design cnpncity of at least 1.0 MOD is recommended for any expansions to the facility. Five options have been evnJuoted based on future development to dc:tenninc which best suits the Utility's intentions.

The five options arc as follows:

1. The fll'St option is to cxpllDd the capacity of the existing wastewater treatment fncility and disposal sites.

2. The second option is to abandon the Snndalhoven W\V11' and construct n master pump station \\ith force main and add additional infmstructure requirements needed to transport all the sewage to the Englewood Water District through a bulk agreement.

3. The third option is to abandon the existing facility ru1d construct a mnstcr pump station with force main and odd additional infrastructure requirements needed to transport o.Jl the sewage to the Charlotte County through a bulk agreement.

4. The founh option is to maintain the existing treatment plant at the existing capacity of 0.1 S MGD and pump the excess flo\'fs to Englewood Water District through n bulk agreement.

S. The fifth option is to maintain the existing treatment plant at the existing cupncity of 0.1 S MGD and pump all excess flows to Charlotte County through a bulk nsrcement.

OPTION lA & lB

Option I modifies the existing \VWTP in order to increase the capncity to treat all future flows. In order to increase the design treatment capacity of the Facility to 1.0 MGD, other plant modifications must be done us well. These modifications include increasing the design capacity of the existing percolation ponds and/or increasing the capacity of the reclaimed water disposal sites.

Treatment

The first step expands the existing treatment plant to obtain a higher treatment cnpncity. While the build-out treatment capacity is estimated nt 935,000 gpd, it is recommended thot 11 treatment capacity of 1.0 MGD be pursued. This puts the facility at 93% of capacity at build·out. Further, this allows for excessive nows due to high rains, equipment maintenance, etc.

The expansion of the wastewater facility could be pcrfonned in two different wnys. Option 1 A includes the construction of two (2) 0.500 MGD treatment facilities, which

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 10 of 27

[

[

[

[

[

[

[

[

[

r L

[

[

[

[

[

[

[

[

l 9

could be pcrfonned in two stngcs. Option 1 B includes the construction of three (3) 0.333 MGD treatment plants, which could be performed in three pbnses. Both of these scenarios are dependent upon available land.

Option lA includes the expansion of the S3Ddallinven Wastewater Treatment Facility by constructing two (2) 0.500 MGD wastewater package plants. This option could be pcrfonncd in two stages. The first stage would be the construction of a 0.500 MOD plant, which would give the facility n treatment capacity of 0.650 MGD. As part of the first pbnse, the UtHity would hnvc to construct a new filter, chlorine cootnct chllltlbcr (CCC), transfer pump station, n 1.5 MG reclaimed water ground stomge tank, and n high service pumping station. The second phnse includes the construction of a second 0.500 MGD treatment plant IU1d modifying the existing 0.150 MGD plant into a surge tank for the fncility. This phase also includes modifying the proposed filter nnd CCC to 1.0 MGD each. The two (2) O.SOO MGD plnnts would provide the required amount of treatment capacity and the existing 0.1 SO MGD plnnt contains enough volume to be sufficient for the surge tank. TI1crc ore two possible locations for constructing the proposed 0.500 MGD plnnts. Since Pond #4 hns historicnlly hod problems percolating, the pond could be decommissioned and the proposed O.SOO MOD plants could be constructed inside Pond #4. Decommissioning Pond #4 to place both \V\VfP's inside would decrcosc the cnpncity of the disposal site R-OO I (0.150 MGD nnnual average daily flow rapid rotc infiltration basin) by 56,000 gpd, len,ing less than 100,000 gpd available for disposal. The ground stomge tanks would hnve to be constructed in Pond #1, which would further decrease disposal site R-001. Figure 4·1, illustrates the locations of each structure for option t. The other possible location is nn undeveloped areu south of the \V\VfP site. The Utility may have the ability to acquire this piece of land through a developer's agreement. This area is approximately 1.5-acrcs, which is sufficient enough to accommodate both 0.500 MGD plnnts. This area would provide the Utility the lnnd necessary for expansion, without having to make ony site modifications to the existing \V\VTP site. Figure 4-2A depicts the proposed site layout. If the Utility can acquire this land through impact fees, it should be more feasible than constructing inside Pond #4, depending upon the site conditions. The costs associated with constructing two (2) 0.500 MOD W\VTP ond associated equipment capable of producing public access effluent arc approximately S8,500,000

Option 1 B includes the expansion of the Snndalhavcn Wastewater Treatment Facility by constructing three (3) 0.333 MGD packngc plonts. This option could be constructed in three (3) phases. The first phase would include the construction if a 0.333 MGD package plant. This initial phase would place the treatment capacity of the plnnt 11t 0.483 MGD. Along with the initial 0.333 MGD pacJmgc plnnt, the Utility would have to construct a 1.0 MG ground storage tank to accommodate for the three days wet weather stomge, n transfer pump station, high service pumping station, new tertiary filter, nnd chlorine contact chamber (CCC). The Utility would be able to utilize its existing ponds for one days reject stomgc. The second phase would include the construction of a second 0.333 ~IGD package plnnt, which would increase the treatment capacity to 0.816 MGD. A1ong with the package plant the Utility would lu1''C to increase its storage, pumping and filtrotion capacities. In the second phase the Utility must have ot least 2.0 MG of wet

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 11 of 27

[

[

[

[

[

[

[

[

[

[

r L

[

[

[

[

[ r I ._

[

r 10

weather sComge. The fiHcr and high service pumps will have to be increased to meet the plant capacity (0.816 MOD). The third phase v.ill provide enough capacity for buildout. This phase includes a third 0.333 MGD package phutt llJld modifYing the existing 0.150 MGD plant to a surge tank. A third 1.0 MG ground storage \\~11 be required to meet the FDEP storage requirement for wet weather stomge. The high service pumping ond filtmtion capacities will ho'\ e to be increased as well to meet the treatment capacity. The third package plnnt will provide n treatment capacity of 1.0 MGD. Along with the third plant, the filters and pumps would have to be increased to 1.0 MGD. Figure 4-28 illustrates the possible locations for this option. The totnl costs nssociotcd with three (3) 0.333 MGD package plants llJld nllassocinted equipment is approximately $10,000,000

Disnosnl

Along with treatment capacity, the disposal capacity ,,,.ould need to be increased to 0.900 MGD. Currently, the design capacity of the existing mpid infiltration basins (R-001) is rntcd for 0.150 ·~00. R-002 is mtcd for 0.100 MOD nt the Wildflower Golf Course. This yields a totnl permitted disposnl copncity of 0.250 MOD. If half the golf course is redeveloped, the overall disposal capacity should be reduced to 0.200 MOD. Therefore, a capacity incl'CBse of0.800 MGD is required.

The nrea required for a new percolation pond was anal,yzed at three (3} different flow mtcs. The soil infonnntion used· for this analysis wns taken from n geotech report written by The ColinllS Group. This report WllS \\'Iitten ns part of an cvnluution of the existing percolation ponds onsitc. It wns detennined thnt the infiltration rate wns 5 feet per day and tbc ground water table was two feet below the pond bottom. It was assumed that these same conditions would apply at a new percd ntion pond site. The frrst flow mtc annlyzcd \\115 300,000 gallons per day (gpd). This flow rotc gcncrotcs a pond area of approximately 12 acres. The other two flow rntcs annlyzcd were 600,000 gpd and 1.0 •\'IGD. These flow mtes genemted a pond area of 25 and 41 acres, respectively. Another percolation pond site can be acquired, however, due to the typically poor percolation cnpacity in the an:a, this is not recommended.

The reuse system {R-002) can be expanded to account for some of the flow. If all future single·family homes (approximately 223) were connected, n reclaimed capacity of npproximntcly 0.100 MGD could be added. This expands the disposal capacity of the facility to onl~ 0.300 MOD. Common area irrigation can be added as \\o'Cll to increase capacity, ho\vcver, there mny not be cnougb common nren to mnke it either technically or finnnein11y feasible.

The reclaimed s}stcm can also be expanded to deliver reuse to either Charlotte County or Engle\~ood Water District. This nllows the facility full disposal capabilities. Part of the cost of nny reuse expansion will include the mandatory 3-dnys wet weather storage nnd one-day reject stomgc. Preliminary discussions ha\'e been initiated \\ith both Charlotte County o.nd Englewood and both Utilities are \\1llins to accept odditiomll reclaimed water. This solution can be considerably Jess expensive thllJl trying to expand the reclaimed system \\ithin the service area. The mnin cost for this expansion would be the

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 12 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[ r

L

[

L 11

construction of a reclaimed pipeline to the neighboring utility and the required storage. At buildout, the required wet weather and reject storage shall be 3.0 MG nnd 1.0 MG, respectively. However, if the expansion of the facility is kept onsite, the avnilablc reject storage is approximately 466,250 gallons, assuming a 3-fec:t pond depth. That is 533,750 gallons short of the required nmount. The wet weather storage can be accommodated by the construction of two (2) 1.5 MG ground storage tanks. The tanks cnn either be constructed in pcn:olalion Pond #4, or on the land south of the existing WWTP site. Currently, the ponds 1, 2, nnd 3 have an ovoiloble pond capacity of approximately 742,000 gallons, BSswning n 3-fcet depth. If pond 1 can be converted from n holding pond to n percolation pond, it \\ill provide the necessary amount of volume required for reject storage, combined \\1th the other ponds.

Of the: options for effiuent disposo.J, delivering public access reclaimed water to n neighboring Utility is the most desirable and is the recommended means of disposnl. This recommendation would require the Utility to construct n stomge tonk nnd high service pumping. According to the preliminary meeting with Englewood \Voter District, they nrc willing to accept reclaimed ,, .. otcr from Sandalb11\'en. This option would include the constrUction of a reclaimed water main along with stomge and high service pumping. The major cost ossocinted with tltis option will be the construction of o reclaimed water mnin from the Sandalhaven WWTF to Englewood's \\'WTF. This 1 0-inch transmission mnin \\ill opproximntcly be 13,000 feet in length. The cost nssocinted \\ith the construction of the pipe is approximately S325,000. The representatives from Englewood stated that if an agreement were rcnchcd, they would like Sandalhaven's recJnimed water main to directly manifold into their clearwell. There is no precedent on which to base nn impact fee for the connection of the reclaimed system into the Englewood system. However, Englewood has constructed an 8.0 MGD deep injection well, which cost approximately $4,000,000. Therefore, we can conservnti\•cly estimate thnt the impact fee ,..,;n be based on Englewood recovering n respective portion of this construction cost. This yields nn estimated impact fee of $500,000 per 1.0 MG. According to this report, nt buildout tlte Sandalhavcn W\VfP will require approximately 1.0 MGD of disposnl capacity. This impact fcc can likely be spread out over time with the incremental increases to the \\11Stcwater facility capacity. In the first phase of construction (0.500 MGD plnnt) Sandalhavcn should require 0.500 MGD of reclnimcd disposal. This anticipated disposal flow gencmtcs an estimated impact fcc of S250,000. The other hnlf of the impact fee (S250,000) could be paid when the second phBSe of construction (0.500 MGD plant) is complete.

If this option is considered Snndalh11ven and EWD together would hove to hire n third pnrty consultant to generate a base rate (impact fee) and a per thousnnd gallon rote. The base rnte would cover 1111y costs associotcd with capacity. The per thous1111d gallon rate would cover any costs associated with pumping nnd distribution of the reclaimed water. The representatives from EWD stated n preliminary per thousand gallon mte of $2.00. At buildout this best guess mte would costs Sondalhavcn Sl,625 per day ($600,000 per ycnr) to send EWD rcclnimcd water. The estimated total cost for Option lA (2 • 0.500 MGD plants) for phases 1 and 2, including the reclaimed tmnsmission main arc $4,750,000.00 nnd $4,250,000.00. A combined cost for constructing a 1.0 MOD extended aeration plant

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 13 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

l

4.2

12

with 3.0 MG of stomge capacity is approximately ·S9,000,000.00t plus the costs per yenr to send Englewood reclaimed ·water. The estimated cost for Option 1 B (3 - 0.300 MGD plants) for phBScs 1-3, including the reclaimed trnnsmission main is approximately $10,500,000.

OPTIONS2&3

Options 2 and 3 both entail abandoning the existing wastewater plnnt nnd sending all sewer flows through a bulk agreement to either Englewood (Option 2) or Charlotte County (Option 3}. These options include the abandonment of the existing wastewater plant nnd the construction of a mnstc:r pump station and associated force moin.

The construction of the master pump station allov."S the Utility to still operate and maintain the collection/transmission system within their service area. The master pump station can be constructed on the W3Stewatcr plant site. The capacity of this station should be designed to handle the peak flo\\'S through the system. The buildout flows were esdmnted to be 935,000 gpd or 650 gpm. Peak flows can be approximated ot 3 to 4 times the ovemge flows. This yields a pump station capacity of up to 2,600 gpm. A triplex submersible pump station is recommended. The cost to construct the lift station is estimated to be $500,000.00

The Englewood connection point is estimated nt approximately 13,000 ft from the plant. The force main would be constructed ns shown in Figure 4-3. This force main should be 10-12 inches in diameter to minimize pressure losses in the pipe while maintaining 11

velocity above two feet per second. The cost to construct this force main is estimated to be S325,000. The total estimated cost of Option 2 is approximately S 1,000,000

The actual size and model of the pumps should be funher analyzed if this option is chosen. An analysis of the lift station pumping system can be completed to more accurately size the master lift station pumps. This analysis would determine the peak flows based on the pumping rates of the existing and proposed lift stations. lnfonnation regarding the connection point to determine the head condition placed on the master lift station pumps would nlso need to be dctcnnincd prior to design.

The Charlotte County connection point is approximately 5,000 ft from the plant. The force main would be constructed as shown in Figure 4-4. This force main should be 10-12 inches in diameter to minimize pressure losses in the pipe while maintaining a velocity above two feet per second. The estimated cost to construct this force mnin is npproximatcl)• $250,000. The total cost of Option 3 is $550,000. However, ChW"lotte County stated that they would be hesitant in taking rnw wnstewntcr.

i i

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 14 of 27

[

[

[

[

[

[

[

[

[

[

[

[

The Utility may be able to transfer raw wnstewuter to EnglC\'r"Dod by redirecting their existing lift stations. This would entail modifying SC\'crallift stations and installing new force mains. This option was briefly re\•icwcd and is not expected to greatly differ in cost from the proposed option. Further, sufficient infonnation is not nvoilnble Co properly model the system to detennine the feasibility of this alternative.

The major drawback to either Option 2 or 3 is the potential loss of rc\•cnuc. Depending on the bulk treatment rate, these options may not be the best long-range nltemotive. However, due to the low capitol cost the Utility should investigate the bulk mtes that EngJC\\>"'od \\>"'uJd charge and perform n cost·benefit analysis compared to the other options. In the initinl conversations \'tith Charlotte County, they nre very hesitant on treating row wastewater. From n meeting \\ith E\VD, they would accept rBw wastewater from Sandnlhavcn. They also stated to us, that they were currently working with a consultant to generate new impact fees for bulk agreements. The representatives from E\VD stnted that they would prefer Sondalhavcn pump their raw wastewater directly to the Englewood's WWTF.

If this option were considered Sondolhnven would hBve to purchase capacity in EngJcv.'Ood's WWTF. The preliminary costs associated with purchasing capacity in Englewood's W\VTF is approximately $1,000,000 for 200,000-gallons of raw wastewater. At buildout, Sandalhaven would have purchnsc approximately 1.0 MG of capacity. This flow generates a cost of npproximntely SS,OOO,OOO. The per thousand gallon treatment chllfgc gcnemted by PRMG, the third party consultant for Englewood Water District is $7.28 per thousand galJons. At buildout, a flow of 1.0 MGD would cost Sanda.lhavcn approximately $7,280 per day (S2,657,000 per yenr). The length force main that would coruu:ct Sandalhaven's service oren to Englewood's WWTF would be opproximBtely 13,000 linear feet. The costs to construct this length of force mBin nnd a master lift station '"·ould be approximately $1,000,000. The total costs adding the impact fees and per thousand gallon roles for Englewood would be approximately S6,900~000t plus $7.28 per thoUSMd gallon.

[ 4.3 OPTIONS 4 & 5

[

[

[

[

[

f 13

Options 4 and 5 both involve maintaining the existing plo.nt at the design capacity of 0.150 MGD, and entering into a bulk agreement Y.ith Englcm:ood Water District (Option 4) or Ch11rlotte County (Option 5) to treat the additional flO\\i'S. TI1csc options '''Ould entail the construction of a new force mBin to the connection point with the neighboring utility. These options can be pursued in two wnys. The first wny is to construct a master lift station and force main very similar to Options 2 and 3 with similar costs (maybe slightly less due to lower pumping requirements). The second way is to divert flows from c:~tisting lift stations ns detailed below.

In order to ensure the plant maintains a flow of 0.150 MGD cel'Ulin lift stations throughout the service area would hove to be directed to either Englev .. 'Ood Water District or Charlotte County. Currently, there arc twelve (12) lift stations throughout the service

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 15 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[ 14

area. Lift stations 8, 9, nnd 11 operate and maintnin the Lemon Bay Golf & Country Club Estntcs. At buildout this community will hnve approximately 93 single-family homes, which constitutes n raw wastewater flow of approximately 19,000 gpd. Lift stations 1, ~ 4, S, 6, nnd 7 operate and maintain the northeast portion of the service nren. Currently, this nrc:a generates the majority of the raw wnstewnter flow. These lift stations alone account for approximately 70% or 81,000 gpd of the current mw wastewater. This Ql'ca hilS little room for gro\\1h. Potentially 200 more single family connections could be made, which would increase the raw wastewater to npproximately 150,000 gpd from these six lift stations. If half of the golf course is developed into high density residential, it should increase the number of service connections by 465. These 465 connections should produce approximately 93,000 gpd of rnw wastewater, which would place the influent flow from the northern portion of the service area at approximately 230,000 gpd at buildout. Lift sto.tions 3, 10, and 12 opcmte and maintain the southern portion of the service orea. This is the Dl'Ca that should experience the majority of the growth. Currently, these three lift stations account for 30% or 35,000 gpd of the raw wastewater. At buildout this area could potentially generate 665,000 Qpd of raw wastewater flow, nearly 70% of buildout flow. HO\\--ever, not enough information is kno\\n about the existing lifi stations. For this report we assumed the construction of a master lifi station onsitc, similar to option2.

To connect \\ith Englewood Water District nnd ensure thnt the Facility maintains a flow of 0.150 MGD, the Utility would hnve to construct a new force main. Since, the southern portion of the service nrea should experience the majority of the snl\\1h, it may be easier to tmnspon that flow to Englewood Water District. That would involve transferring lift stations 3, 10, nnd 12. In order to trnnspon the row wastewater flow, pump modifications ,,;n be required for lift stations 3, 10, and 12. This can be performed by constructing a new force main nlong County Road 775, which would connect with the existing force main on County Road 775. This force main should be 8-10 inches nnd would run north along County Road 775 to the connection point \\ith Englewood, which is approximately 13,000 fcc:t north of the Sandolhnven's service area. Adequate valves would be placed wong the force mn.in to ensure that Snndnlhaven's opcmtors could vnry the flo\\' during the non-peak season.

As stated earlier, the representatives from EWD noted that they would prefer Snndalhavcn to pump their raw wastewater directly to their WWTF. This option would include construction of a dedicated force main directly to Englewood's WWTF, approximately 13,000 feet in length. The costs associated to modify the existing lift stations to pump directly to Englewood ore unknown, due to the Jack of informntion. For this option it wns assumed that a master lift station could be constructed onsite to transfer the excess mw wastewater to Englewood. To ensure that the existing plant rnnintnins n flow of 0.1 SO MGD, modifications to the hcad\\'Orks mny be required. The force main would be constructed as shown in Figure 4·5. To construct n new master lift station, make modifications to the hcndworks, nnd construct a force main is estimated at approximately Sl,IOO,OOO. The capacity purchase charge for this option will be Jess than option 2, since the existing WWTF will be maintained. To purchase 850,000-saHons of capacity (buildout) will approximately cost $4,250,000, plus S7.28 per thousnnd gallon

• •

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 16 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

r 15

sent to Englewood. The total estimnted cost for option 4 is appro:dmntely SS,3SO,OOO, plus the per thousand gllllon fee ofS7.28.

The Utility has two options to connect \\ith CbElflotte County nnd gulll'lUltce the Facility maintains a flow of O.lSO MOD. The Utility would have to construct a force mnin to connect \\ith Charlotte County. Charlotte County's service nrcn borders Sandalhaven's service aren in the cnst. This can be perfonncd by constructing n new force main from the \VWTP to the connection point with Charlotte County. It would be more feasible to tmnsfer the rnw wastewater flow from the northern portion of the scn·ice orca, but this Dow could not ensure the plnnt operates at 0.1 SO MGD during pcnk season. By constructing a force main to connect with the influent line from lift station 1 would o.llow the utility to tmnsfer the flow from the southern portion of the service area to Charlotte County. The proposed force main would run enst, adjacent to the 6-inch force main from lift station 5. Sufficient vnlves would be installed at the WWTP to ensure the plant operates at 0.1 50 MOD. This option is illustrated in Figure 4-6. The Utility mny have the ability to redirect the force main along County Road 775. If the Utility hos this option, it may require fewer modifications to the existing force main. The Utility mentioned that they might hove the capability of acquiring the ownership of lift station 12 (Cope Haze Plaza). If the Utility ncquircs this lift station, it might be feasible to modify this lifi station into 11 master lift station. From lift station 12, the Utility could run n force mnin north along the park, to the connection point \\ith Charlotte County. This option would require the Utility to purchase an casement to construct the force mnin from lift station 12. This option is illustrated in Figure 4-7. The totnl estimated cost of Option 5 is 5750,000. Since Charlotte County is not interested in treating Sandnlhnvcn's raw waste\\-ater, this option should not be considered.

These Options appear to be the most cost effective to pursue, capitally. The mnin operating difference between Options 4 and 5, and Options 2 IUld 3 is that Options 4 nnd 5 would incur higher operating costs due to manning and maintaining the treatment facility.

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 17 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

S,O RECOMMEI\llATIONS

16

The Options outlined in this repon provide only 11 guide for moking future decisions on the treatment of future wastewater flows. There nrc several other issues to consider, such as the bulk sewer rates, the bulk reuse rates (if any), nnd the timing of development. The timing of the development of the area could have the greatest impact. The main factor in detcnnining a potenti£11 timing problem is the current available capacity in the Charlotte County and Engle\\'ood systems.

It was detc:nnincd that any agreement \\ith Charlotte County would not be feasible, since they nrc not cap11ble of boodling Sandolhnven' s needs. To our knowledge, at this time Charlotte County docs not have the capacity to receive mw or reclaimed flows. However, Englewood stated to us in o meeting on August 30, 2004 tbnt the timing was good for either n mw wastewater or reclaimed wntcr interconnect. Englewood is scheduled to increase the copncity in their \V\VTP nnd their rcclnimed disposal system. Englewood's treatment plant expansion has given them the ability to receive over 0.5 MOD in the short tenn. Englewood funhcr stnted that they would give Snndalhaven first refusal when the time came to enter into the bulk agreement. Englewood is in the final stages of permitting their ASR well (aquifer storage 110d recovery). This '"ill enable them to commit to accepting oil of Sondnlhnvcn's reclaimed effluent. Further, Eng]cwood's ASR well mny be sufficient to sntisfy the wet weather requirements for the Sandalhaven facility, thereby reducing the cost to construct future treatment capacity.

Therefore, the two most feasible options are tabulated below for your reference.

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 18 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[ 17

Table 2: Options

*OPTIONS EQUIPMENT COST lA: E.""pansion of the

plant by adding two (2) . 0.500 MGD olo.nts

One (1) 0.500 MGD pncknge plant, l.S MG

Phase I: ground stomgc tank, high service pumps, 4.75 million (plus CCC, tcttiary filler, transmission main (for S2/J 000 gallon)

disposal). Impacl fcc One (I) 0,500 MGD package plant, 1.5 MG

4.25 million (plus Phnse II: ground storngc, O.S MOD filter copncity, high service pumps, CCC, Impact fcc $2/1000 gallon)

I B: Expansion of the phml by adding three (3) -

0.300 MGD plants One (I) 0.333 MGO packnge plant, 1.0 MG

Phase 1: stomgc trutk, CCC, tertiary filter. high 4.16 million service pumps, trnnsmission main

One (1) 0.333 MGD plant, 1.0 MG stomge Phase IJ: 1ank, expansion to filter and high service 3.16 million

pumps One (1) 0.333 MGD plant, 1,0 MG storage

Phase ill: tank, expansion to high service pumps and 3.16 million filter

Option 2: Tronsfer aH Master lift station, associated components, 6.9million (plus S7.28/1000 flow to Englewood force main, and impact fees _MUon)

Option 3: Transfer all Master lift station, associated components, Not Applicable flow to ChPrlottc County force main Option 4: MDintnin Master lift station, associated components, 5.4 million existing plant IUid send force main, modifications lo hcndworks, (plus 57.28/1000 future flows to

Enwewood and impact fees gallon)

Option 5: Maintnin Master lift station, associated components, existing plant and send all force main, modifications to headworks, Not Applicable future flows to Ch11rlonc

County and impact fees

Due to the impact fees, option 1 rnny be the best solution. Option 1 entElils the construction of 1.0 MGD of treatment capacity. This option cnn be pcrfonncd in two phases. Phase 1, \\ill consists of a 0.50 MGD extended nemlion plnnt, tertiary filter, lltld chlorine contact chamber (CCC}. This phase ,,;u also include n 1.5 MG ground storage tnnk, high service pumping and electrical building. Phase 2, will consist of a second 0.50 MGD c.'<tcnded aeration plant nnd n 1.5 MG ground stomsc tD.nk. The filter nnd CCC will ha\'C to be modified for the phase 2 e:<pllllSion. The proposed locutions for the treatment structures can be observed in Fisures 4-1 nnd 4·2A. Ho\\'C\'cr, this option is dependent upon disposal.

!

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 19 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

l \

18

Option lA is recommended over option lB, due to the lower cost. It will be less expensive to construct two (2) 0.500 MGD plonts instead of three (3) 0.333 MGD plants. Option I is the recommended option due to the costs associated \\ith sending Englewood reclaimed water compared to mw wastewater. Table 3 illustrntcs the costs comparing the two alternatives.

Tobie 3: 10 Yenr Scennrio I Numberof Total Estimated Disposal Option 4 Option 1A Year Connections Number of Flow Added Connections (MGD} {MGD} (Millions of S) (Millions of S)

2006 I 1050 2050 0.390 0.390 53.74 54.92 2007 I 288 2338 0.444 0.444 S0.7B 50.21 2008 I 288 2626 I 0.499 0.499 50.93 50.25 2009 288 2914 0.554 0.554 52.07 50.29 2010 268 3202 0.608 0.608 51.22 50.33 2011 268 3490 0.663 0.663 51 .36 54.62 2012 288 3778 0.718 0.718 51 .51 50.41 2013 288 I 4066 0.773 0.773 52,65 50.45 2014 288 I 4354 0.827 0.827 51.80 50.49 2015 288 4642 0.882 0.882 $1.95 $0.53 2016 288 4937 0.938 0.938 52.09 I so.se Total 3 930 4.937 0.938 0.938 $20.10 t $13.12

Table 3 demonstrates n IO·yeor scenario comparing option lA and option 4. Option lA includes the construction of n 1.0 MGD plnnt (in two phases) cnpablc of producing reclaimed effiucnt. Option 4 includes mnintnining the existing plant at 0.150 MGD and tmnsfcrring all future mw \\'Dstcwnter flows to Englewood for treatment. For this scenario we assumed an aggressive gro\\1h. The assumptions for the scenario include buildout of the service oren in ten years. By 2006 Mangrove Point and the Marina Redevelopment \\ill be complete, and after 2006, the senice arcn \\ill grow nt n mtc of 288 connections per year.

Option 4 assumes that Snndolhnvcn would buy capacity in Englewood's \VWTF in 2006 (0.400 MGD), 2009 (0.200 .MGD), and 2013 (0.200 MGD). The upfront costs of 3.74 million in 2006 include the construction of the master lift station, mw transmission mnin, capacity charge, nnd the per thousand gallon charge. For the years 2007 through 2016 include only the per thousand gn1lon chnrgc, except for 2009 and 2013, which also include the cost to purchase additional capacity. The costs for Option 4 nrc adjusted to account for the flow treated at the Snndalbavcn WWTF is 0.1 SO MOD. Option l A assumes that in 2006, Sandnlhnven should have to construct the first phBSe. The upfront costs illustmted in Table 3, include the construction of a 0.500 MGD pucknge plant, all nssocinted components to produce reclaimed water, and the construction of the reclaimed transmission main to Englewood. According to this sccnnriot by 2011 Sandalhaven will have to construct the second phase in order to meet the nssumed gro\\1h. Table 3 illustmtc:s that it \\ill be nn estimated 7 minion dollars Jess expensive to construct a plant to treat all future flows and transfer the reclaimed water to Englewood. This scenario

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 20 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

t 19

llSSWllcs that Snndnlhaven will hove to pay Englewood to nccept the rcclnimed for the next ten yenrs. However, the rcclnimcd wnter mny become an nsset instead of a liltbility to Sondalhnven. Englewood "ill likely be willing to pay Snndalhavcn for their reclaimed water in the future.

It should be noted that as the development starts to occur in the southern portion of the service nrca, modifications should be pcrfolltlcd on the collectionltronsmission system. Currently, lift stations 3, 10, and 12 feed the force main along County Road 775. This force main evcntunlly feeds a gravity system in the Fiddlers Green Community, which limits the nmount of raw wastc\'w'Dter that can be transported. As development occurs in the southern portion of the service orca, this section of the collcction/tronsmission system will become undersized. No matter whnt option is selected, the Utility ,.,;u have to modify this portion of the coUcction/trnnsmission system. lf the Utility cno obtain lift station 12, they may WIUlt to investigate the means of constructing n force mnin adjacent to the park to deliver mw wastewater to the \VWTP. If the Utility cnn tmnsfollll this lift -station into a mllSter lift station, it may be the best method to convey raw waste\\'Dtcr to the \VWTP. Since the majority of the gro\\1h is planned for the southern portion of the service area, it warrants n collection/transmission system analysis to determine the most feasible method to transport raw wnstewntc:r.

• • I

I I

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 21 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

l

FIGURES

20

Docket No. 160101-WS Sandalhaven Used and Useful Calculations

Exhibit ATW-15 Page 22 of 27

LOCATION MAP

SANOALHAVEN UTILITIES

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[ <D ucu.IIIINirrr JUaC(Nf"'-

® I'MICI Ale M:IISA'TC'N

CD ·~ ~~CN

® II~DCNim' PEIIDf:h-:tAI.

r.piHrn ,.,._, '-"'"'~ Alrilllm. s_,..,. OINtrlllf'" ,\Caot~t ,.,,,. ~ ....

® ~ CONI-

@ I.ONOU.8W lttlctHTM.

Scale :NlS

Dato:J-31·2004

Job No.~ U07-48.0

®

Docket No. 160101-WS Sandalhaven Used and Usefu l Calcu lations

Exh ibit ATW-15 Page 23 of 27

SERVICE AREA ZONING MAP

UTILITIES INC. OF SANDALHAVEN

I

N

I

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 24 of 27

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[ Scale: NTS

SITE PLAN 1-c-•_te:_·l-_3_1·2004----+-------------tFIGURE

Job No.: UD?4S.o UTILITIES INC. OF 2•2

SANDALHAVEN

. •

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 25 of 27

Kim ley>» Horn October 9, 2015

Patrick Fly11n VIce President

· Utilities Inc. of Sandalhaven 200 Weathersfleld Ave Altamonte Springs, FL 32714C

Re: Sandallaven Master Lift Statton and fon::e main clarlflcatlon

Patrick:

As requested, thlaleUer Is to provide a c::larlnca~on of the June 28, 2007 Sandalhaven Master Uft Stallon and Force Main Project Summary tetter. In the second paragraph of the letter the following was asserted:

.-,e 12-lnch pfpellns was setecled beCIJuse II reduces the head condition down to approJCimatefy 125 feet at 950 gpm, and 105 feet at 750 gpm. This equates to a power requirement of BB Horsepower for each pump. Had a smaller pipe size been aelected to maximize velocity through the pfpslln8 In order to minimize 50/Ids deposition, the pump horsepawer would have been slgnlf1cantly higher- an estimated 300 Horsepower. •

The pump design points ere associated with the specific pump c::urve for each pump. To achieve the peak design point of 1850 gpm, the design point With a 12-lnch pipeline caiJed for a bfplex pump station with each pump's design point being at 950 gpm al125 feet TDH. This ytelds three Be-Hp pumps, wtth two operating and one as a standby. This Is a total of 176-Hp with two pumps operating. The reduction of the pipeline to a 1o-tnch increases lhe pump design point ID 950 gpm at approximately 275 feet TDH. Thla yfelde e horsepower per pump of approximately 15~Hp for a Ictal 300-Hp with two pumps operating.

The comparison made In the June 26, 2007 letter was based on two pumps operating with a rated horsepower of 178 as compared to 300, e 70% Increase In required motor size.

I hope this dariflcatlon provldee you with the Information you needed. If you need any additional Information please contact me any time.

Very truly ~S)Evt/~. ~NT'AID../4.SSOCIATES,INC.

By· Stephan N. Romano, PE Sr. Project Manager

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 26 of 27

............ ----------------------------•

June 26, 2007

Mr. Pabiclc Flynn Regional Director Utilities, Inc. of SandaJhaven 200 Wcathersfietd Avenue A!tarnonte Springs, FL 32714

RE: Sandalhaven Master Lift Station and Force Main Project Summary

Dear Mr. Flynn:

101 NCIItJI Woodland 11•11. Safte.al

'De~4, floddli S27:IO nonr. MU3~au

Jax: 316.'736.1411

lllllfW.qrllllt;tiiN--

Pursuant to your request, this letter is intended to summarize the lift station and force main project ~ntly completed in the Utilities, Inc. ofSandalhavcn•s (Sandalbavcn) service area. The lift station aod force main were constructed to divert a portion of the Saodalhavcm service area's flows to the Englewood Water District's (EWD) Wastewater Treabnent Facility. Saudalbavcn's c:umnt waste\\-ater treabnent fact1ity is rated at 0.150 million gallons per day (MOO), an4 flows during peak season exceed 0.135 MOD. Instead of expanding the wastewater treatment facility to meet fUture growth requirementSt Sandalhavea opted to install approximately three miles of 12·inch force main and ccnstruct a master lift station to divert flow to EWD.

As detailed in the Master Plaa developed in 2004, the service area's flow at buildout Is projected to be approximately 900,000 gallons per day (gpd). The new force main and master lift station were desi~r~ed to deliver all of the flow from the southern portion of the service area. This ultimately equates to approximately 665,000 gpd (or 462 pllons per minute), about 70% of the total seniee uea flow. To handle this expected flow, the lift station design must allow for a peaking fac:tor of 4.0, yielding a Dow rate of2.660 MOO or 1,850 gpm. The lift station is setup as a triplex (three pump) station to ultimately pump the peak rate to the EWD wastewater facility. The pipcUoe was modeled to determine the most efficient pipeline size based on the need to produce velocity sufficient to carry solids through the pipe as well as well as meet the total bead condition (pressure) on the pwnp. The 12·fncb pipeline was selected because it reduces the head condition down to approximately 125 feet at 950 gpm, and 1 OS feet at 750 gpm. This equates to a power requirement of 88 Horsepower for each pump. Had & smaller pipe size been selected to maximize velocity throu&h the pipeline in order to minimize solids deposition. the pump boncpower would bave been significantly higher-an estimated 300 Horsepower. This would have drastically increased the operating cast of the station. This would also have required installation of a larger wet well and a larger emergency generator for backup power. Therefore. the smaller 1 O·ineh pipeline was not considered feasible based on the increased pumping and power requirements compared to the relatively small gain in capital cosL

While the plDilp station was desi,ned and sized f9r ultimate capacity. the project was cousnuctccl to meet the Utility•s more immediate needs. Two 45 Horsepower pumps

Docket No. 160101‐WSSandalhaven Used and Useful Calculations

Exhibit ATW‐15Page 27 of 27

I

I

I

I I I

were installed initially to provide an interim pumping capacity o£760 gpm or 1.0 MOD peak flow. This equates to an average dany flow nte of0.27S MOD. The current Oow generated by the e~sting customers in the southern portion of the Sandalhaven service area is estimated to be approximately 0.050 MOD. While lhis initial flow rate wiD require periodic maintenance of the pjpdine due to possible solids deposition caused by low velocities, the low head condition made this interim size feasible and more cost effective.

If you bave any further questions or need any additional clarifications, please let me know. Thank you.

.. ,.

Docket No. 160101‐WS

Summary of Pro forma projects with cost

justification supporting less than requested

Exhibit ATW‐16

Page 1 of 1

Flynn Exhibit

Number System Project

Cost per Flynn's

Testimony

Recommended

Costs Reason

PCF-1 Cypress Lakes Hydro Tank Replacement $ 30,000 $ 25,732 Remainder unsupported

PCF-3 Eagle Ridge

WWTP EQ tank and

headworks $ 350,000 $ 106,388

Unsigned agreement with

contractor

PCF-5 LUSI

Sludge Dewatering

Equipment $ 245,000 $ 240,000 Remainder unsupported

PCF-7 LUSI SCADA $ 470,000 $ 458,902 Remainder unsupported

PCF-18 Mid-County

Methonal Pumps and

Nutrient Analyzer $ 102,000 $ 92,576 Remainder unsupported

PCF-19 Mid-County

US Hwy 19 Relocation; 525

ft 6" FM and 190 ft 8" GM $ 230,000 $ 172,879 Remainder unsupported

PCF-21 Sandalhaven Placida Rd. Utility Relocatio $ 250,000 $ 217,034 Remainder unsupported

PCF-25 Sanlando Myrtle Lake Hills WM $ 695,450 $ 684,271 Remainder unsupported

PCF-30 Sanlando

Wekive WWTP

Rehabilitation $ 1,803,000 $ 1,729,034

Adjusted for taxes on equipment

only

PCF-36 UIF - Seminole

Electrical Imp. At Little

Wekiva and Jansen WTPs $ 323,000 $ 268,830 Remainder unsupported

PCF-37

UIF - Seminole &

Orange WM Replacements $ 57,000 $ - Included elsewhere

PCF-47 GIS Mapping Services $ 350,000 $ 244,321 Remainder unsupported

Totals $ 4,905,450 $ 4,239,967

Docket No. 160101‐WSSanlando Wekiva WWTP Rehabilitation Invoice

Exhibit ATW‐17Page 1 of 1

8VOQUA

Evoqua Water Technologies LLC 2607 N. Grandview Blvd, Ste 130 Waukesha, WI 53188

RECEIVED OCT 3 1 2016

~<X>S1b~ P& J I~1Coic

Bill To: UTILITIES INC OF FLORIDA- SAN LANDO ~ 1.. j 15'"g (;, l ATTN: ACCOUNTS PAYABLE

200 WEATHERSFIELD AVE

ALTAMONTE SPRINGS, FL 32714

INVOICE Tax Scheduled

Agreed Invoicing Mi lesto nes Y/N Value Previous Tax

Equipment

10 With Signed Agreement y $56,083.50 $56,083.50 $3,415.01 Plant Ill y $182,912.40 $0.00 Plant 112 y $150,811.20 $0.00 Plant 113 y $171,027.90 $0.00

Installat ion

10 With Signed Agreement N $51,046.40 $51,046.00 $0.00 Plant Ill N $165,35S.20 $0.00 Plant 112 N $137,178.90 $0.00 Plant 113 N $156,883.50 $0.00

Field Paint

10 With Signed Agreement N $45,470.10 $45,470.10 $0.00 Plant 111 N $137,953.80 $0.00 Plant 112 N $119,823.30 $0.00 Plan t 113 N $137,953.80 $0.00

Startup

Plant Ill N $4,500.00 $0.00 Plant 112 N $4,500.00 $0.00 Plant 113 N $4,500.00 $0.00

TOTALS $1,526,000.00 $152,599.60 $3,415.01

Terms: Balance due in 30 days.

NEW REMITIANCE ·CHECK New REMITTANCE - ACH/WIRE

EVOQUA WATER TECHNOLOGIES J.P. Morgan Chase Bank, N.A. 28563 Network Place Account: Evoquqa Water Technologies Chicago, IL 60673-1285 New York, NY 10004

Acctll 603148011 Amount Due: $181,289.57 ABA# 044000037

Swift Code: CHASU$33

These commodittei are sold for domestic consumption. Any eJCport o f these commodltres must be m411dc In com pliance with applkablc U.S. l aws.

lhese commodities, technolosv or software (items) were exported from the United Sutes in accordance with the Export Administration

Phone: 262-547-0141 Fax: 262-521-8586 E-mail: [email protected]

Invoice# 902844050 Date: 10/26/ 2016 PO# Signed Proposall60124-Al Customer ID: 1010924 Evoqua # 2033/ 000739 Tax Rate 6.00%

1% on first 55,000

SHIP TO: WEKIVA WWTP

144 LEDBURY DRIVE

LONGWOOD, FL 32779

Th is Per iod Tax

-. -

$171,027.90 10,261.67

----

----

---

$171,027.90 $10,261.67

Total $181,289.57 I

Rctulatlons Diversion cont roary to US law is prohibited. These It ems 1re not to be used dlrectlvor lndlrectlv In prohibited nuclear chemical/biological or missile w e.1pons act iv1tics.

Balance

To Fin ish

$0.00

$182,912.40

$150,811.20

$0.00

$0.40

$165,355.20

$137,178.90

$156,883.50

$0.00 $137,953.80

$119,823.30

$137,953.80

$4,500.00

$4,500.00

$4,500.00

$1,202,372.50

Bid Form

RFP #2016085

Utilities Inc. of Florida – Mid County

Mid County Electrical Service & 500 Kw Generator Improvements

Item Quanty Item Total Price

01 Lump Sum Mobilization and Permitting $60,000.00

02 Lump Sum Electrical Service Upgrade $60,000.00

03 Lump Sum Electrical Controls and

Program Upgrade $600,000.00

04 Lump Sum Engineered Slab and

Construction $30,000.00

05 Lump Sum Generator Package $250,000.00

06 Lump Sum Mechanical Contractor $50,000.00

07 Lump Sum Demolition and Removal $30,000.00

08 Lump Sum Testing and Training $10,000.00

09 Lump Sum As Built and Close-out

Documentation $20,000.00

Total Proposed Price $1,110,000.00

FROM: EMS of Central Florida Inc.

7906 Clark Moody Blvd

Port Richey, Fl 34668

Office 727-847-3722, Allen Cell 727-243-0878, Frank Cell 727-234-5265

Email: [email protected]

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 1 of 13

SAYLER.ERIK
Text Box
EMS of Centra Florida, Inc.

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 2 of 13

EXHIBIT B BID FORM

RFP # 2016085 Utilities Inc. of Florida - Mid County

Mid County Electrical Service & 500 Kw Generator Improvements

The following bid, for the Mid County Electrical Service and 500 Kw Generator Improvements, is hereby made to Utilities Inc. of Florida, hereafter called the Owner. This Bid is submitted by

APG ELECTRIC, INC -- 4825 140th Avenue North -- Clearwater, FL 33762 (727-530-0077)

The undersigned declares that they have familiarized themselves with the nature and extent of this work by examining carefully the Project Manual, Specifications and Drawings, Bid Documents Issue date of September 15, 2016 included in this Request for Proposal (RFP), and project site survey as deemed necessary.

The bidder agrees to furnish all shop drawings, products, materials, equipment, and preform all labor necessary to complete the scope of work. The bidder further attest that the bid proposal amount herein-proposed represents and includes the entirety of the work, fees, taxes, profit, overhead, general requirements, and general conditions of the project as per the bid documents. The bid also includes the following addenda:

Addenda Number: __ N..:...../A __ Dated: ____ _ Addenda Number: ____ _ Dated: ____ _ Addenda Number: ----- Dated: ____ _

The bidder may withdraw their proposal at any time prior to the date of the RFP opening. All Bid Proposals shall be irrevocable for a period of ninety (90) days from the date of the RFP opening.

The undersigned further certifies that the pricing reflected on this bid form is valid through January 31, 2017.

ITEM QUANITY ITEM TOTAL PRICE # 01 Lump Sum Mobilization and Permitting $42,000.00

02 Lump Sum Electrical Service Upgrade 1 Generator Installation $ 487,000.00

03 Lump Sum Electrical Controls and ProQramminQ Upgrade $ 149,000.00

04 Lump Sum Engineered Slab and Construction $19,000.00

05 Lump Sum Generator Package $ 246,000.00

06 Lump Sum Mechanical Contractor $15,000.00

07 Lump Sum Demolition and Removal $33,000.00

08 Lump Sum Testing and Training $12,000.00

09 Lump Sum As-Built and Close-out Documentation $14,000.00

TOTAL PROPOSAL PRICE $ 1,017,000.00

NOTE: See APG proposal letter for clarifications.

SAYLER.ERIK
Text Box
APG Electric, Inc.

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 3 of 13EXHIBIT B

Continued BID FORM

RFP # 2016085 Utilities Inc. of Florida- Mid County

Mid County Electrical Service & 500 Kw Generator Improvements

The bidder has verified and included the following items in the sealed bid:

[ •1 Exhibit B Bid Form for RFP # 2016085 [ •I Exhibit C Subcontractor Vendor List [ •I Exhibit D Trench Safety Statement [ •I Inserted all above into the sealed envelope address to:

Utilities Inc. of Florida 200 Weathersfield Avenue Altamonte Springs, FL 32714 Mid County Electrical Service and 500 Kw Generator Improvements RFP # 2016085 Bid Proposal

Bid Security Form is not required for this RFP.

APG Electric, Inc. Company Name

~~c.;;p~.,__ _ ____ 0_at-e ...:1:.~.1/-=2.:J9/~..:2:.::..0:..:16::.._

Notary Public

-

Alida N. Flculoy NOTARY PU8Uc STATE OF FLORIDA Cornmt FF188780 Explrea 10/1512018

Terry Ryan -- Preconstruction Special Projects Printed Name and Title

4825 140th Avenue North Company Address

Clearwater FL 33762 City State Z1p Code

727-530-0077 727-530-0045 Telephone No . Facsimile No.

[email protected] E-mail Address

Signature of Notary

STATE OF FLORIDA COUNTY OF Pinellas

The foregoing instrument was acknowledge before me this 29th day of November 2016, by Terry Ryan

• Personally Known Produced Identification

Type of ID: ----------

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 4 of 13

EXHIBIT C SUBCONTRACTOR VENDOR LIST

RFP # 2016085 Utilities Inc. of Florida- Mid County

Mid County Electrical Service & 500 Kw Generator Improvements

Bidder's Name: ___ ....;A...;.;.P_.;;G;....;E=Ie=c=tr=ic.c...;, l~nc=·----- Date: November 29, 2016

Address: ______ 4=8=25=-=-14..:.:0=th:..:..:A;..:.v:..:e:.:.;.n=ue;;..:N=o=rt=h.;....__ Phone#: 727-530-0077

City, State, Zip Code: _....;;C;.;.;;Ie=a.;..;rw..:.:a;;..=.;te;:;.;..r~....:., F...;;;L~3.=..;37;...;:6=2 ___ _ FEIN# 34-1412413

e-mail: ------~es=t=im..:.:a;.;.:ti.:...:.lng.....::@_a=p=g=.c=om~pa:;;.;.n;..&..y __

SubcontractorNendor Work Subject Subcontract Amount FEIN# Status CONTROL SOLUTIONS

RUARK CONSTRUCTION

ALL SOUTH LIGHTNING PROT.

UL TESTING AGENCY

t/b/d

SubcontractorNendor Provide Business Name

Control cabinets

Demo building, new slab

Lightning protection

UL inspections

Rigger

Work Description Contractor-Type Vendor-Supplying

INCLUDED

INCLUDED

INCLUDED

INCLUDED

INCLUDED

Status Submitted - Submitted w/ Bid Added - Submitted after bid Removed - No longer using Canceled - No Contract!PO issued

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 5 of 13

EXHIBIT D TRENCH SAFETY STATEMENT

RFP # 2016085 Utilities Inc. of Florida - Mid County

Mid County Electrical Service & 500 Kw Generator Improvements

Bidder acknowledges that included in the various items of the proposal contained on the Bid Form are costs for complying with the Florida Trench Safety Act (FS 553.60-553.64 ). The Bidder further identifies the cost of compliance with the applicable trench safety standards for the project as follows (Bidder to attach additional sheets as necessary to identify all costs):

Trench Safety Measure Units of Measure Unit Unit Cost Extended (Description) (LF, SF, SY) Quantity Cost

A t/b/d INCLUDED

B c D E F TOTAL $

I NOTE: All excavating and backfill is included in Electrical Service Upgrade cost. I

The total cost shown herein is already included in the various items on the Bid Form and is not additional to the pricing shown on the Bid Form.

Bidder, by signature below, assures that the contractor performing trench excavating will comply with the applicable Trench Safety Standards.

Submitted, signed and sealed this 29th day of ____ N_o_ve_m_b_e_r _____ 20_1_6 __

APG Electric, Inc. Company Name

11/29/2016 Date

Terry Ryan-- Preconstruction Special Projects Printed Name and Title

ATTE$l: _ ..

~~16

Notary Public

G) Alk:la N. Flounoy NOTARY PUBliC STATE OF FLORIDA Com"'* FF181780 Expires 10/15f2018

(SEAL)

(THIS PAGE WAS INTENTIONALLY LEFT BLANK)

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 6 of 13

November 29, 2016

Utilities, Inc. of Florida 200 Weathersfield Ave. Altamonte Springs, FL 32714-4027

Attn: Michael Wilson (via email: [email protected])

RE: Mid-County Electrical Service and 500 kW Generator Improvements Dunedin, FL

Dear Michael,

The following is our cost proposal for electrical work as shown on Electrical Drawings E0 through E5 dated September 16, 2016 – in full accordance with project specifications, local codes and ordinances.

BID AMOUNT ............................................................ $ SEE BID FORM

SCOPE OF WORK

MOBILIZATION AND PERMITTING

ELECTRICAL SERVICE UPGRADE

• Method of procedures / master plan• Two (2) 4-inch PVC conduits for Duke primary• Pad for Duke transformer• Furnish and install new panels and transformers• Furnish and install surge protection devices• Stainless steel racks for service locations• Hand dig excavation for new feeders• Compaction and shell replacement• Copper feeders utilizing PVC or aluminum conduit• Feeder tie-ins to existing panels / equipment• Grounding with test wells and reports• Megger testing of all feeders

ELECTRICAL CONTROLS AND PROGRAMMING UPGRADE

• Blower Control Cabinet #1 (Sheet E2-A, Notes 6-12) New Panel UL 508 • Blower Control Cabinet #2 (Sheet E2-A, Notes 13-19) Field Modified UL Evaluation • Surge Tank Blower Control Cabinet (Sheet E2-A, Notes 20-22) Field Modified UL Evaluation

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 7 of 13

Page 2 of 5

• Surge Pumps Control Cabinet (Sheet E2-A, Notes 23-32) Field Modified UL Evaluation • Master Lift Station Control Cabinet (Sheet E2-A, Notes 33-37) New Panel UL 508 • Odor Control Cabinet (Sheet E2-A, Notes 38-43) Field Modified UL Evaluation • Blowers Timer Control Cabinet (Sheet E2-B, Notes 9-11) New Panel UL 508 • Backwash Blower #1 Control Cabinet (Sheet E2-C, Notes 5-10) Field Modified UL Evaluation • Backwash Blower #2 Control Cabinet (Sheet E2-C, Notes 5-10) Field Modified UL Evaluation • Backwash Pump #1 Control Cabinet (Sheet E2-C, Notes 13-17) Field Modified No UL Evaluation • Backwash Pump #2 Control Cabinet (Sheet E2-C, Notes 13-17) Field Modified No UL Evaluation • Plant Water Pump Control Cabinet (Sheet E2-C, Notes 18-24) Field Modified UL Evaluation • Instrument Air Compressor Control Cab. (Sheet E2-C, Notes 30-33) Field Modified UL Evaluation • SOMAT Control Cabinet (Sheet E2-D, Notes 5-10) Field Modified UL Evaluation • Filter Feed Control Cabinet #1 (Sheet E2-D, Notes 11-20) Field Modified UL Evaluation

Notes:

o Each panel provided with CAD drawings listing manufacturer catalog numbers and wiring diagram.o All new panels are NEMA 4X type 304 stainless steel.o All panels are programmed and tested.o Required field wiring.

ENGINEERED SLAB AND CONSTRUCTION

• 20’ x 20’ x 2’ deep concrete slab with double mat of reinforcing steel• Engineered (stamped) drawings

GENERATOR PACKAGE

• 480 volt, 3-phase, 500 kW, tier-4, diesel generator• Weather proof, sound attenuated aluminum enclosure• Enclosure PE certified at 200 mph wind load• 2000 gallon sub-base tank• 100 amp load center• Four (4) light fixtures• Service receptacles• Annunciator panel• Two (2) remote emergency shunt trip reset buttons• 1000 amp, 480 volt, 3-phase, service entrance rated automatic transfer switch• Start-up load bank testing

GENERATOR INSTALLATION (cost of this work is with Electrical Service Upgrades)

• Rigging / setting generator on pad• Installation of gen set, tank, enclosure• Wire terminations of feeders, start circuits, miscellaneous power & control circuits, annunciator wiring• Lightning protection on generator• Installation of automatic transfer switch• Installation of remote shunt trip devices• Diesel fuel fill-up of tank after testing

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 8 of 13

SAYLER.ERIK
Line

Page 3 of 5

MECHANICAL CONTRACTOR (APG)

• Re-wiring of motor leads to 480 volt (in lieu of 240 volt hi-leg) if multi-leads exist• Testing of motor rotation• New seal tight electrical connections• Report and coordination for re-wiring or replacement of motors (if required)• Owner to provide allowance (cover cost) of any motor re-wiring or replacement

Note:

o APG will track all activity on Motor Matrix spreadsheet (see attachment).

DEMOLITION AND REMOVAL

• Disconnect and rigging out of existing generator. Generator to be placed on site for ownerremoval (sell?)

• Disconnect and remove all existing panels, transformers, and control equipment as called foron documents

• Remove all existing wiring as required• Demolish and remove existing building which houses existing generator (this work is permitted)

Note:

o Trash materials will be placed in dumpster on site (dumpster is to be provided by others).o Removal of demolished generator building from site is included.

TESTING AND TRAINING

• Megger test on all feeders (recorded)• Ground resistant testing (recorded)• All control panels tested and UL Certified• Motor rotation• Owner commissioning

AS-BUILT AND CLOSE-OUT DOCUMENTS

• As-Built drawings on CAD

ALTERNATES

1) Provide alternate enclosures for the gear (panels, transformers) in lieu of standard NEMA 3Renclosures as specified.

A) Power coating

ADD .......................................................................... $ 3,800.00

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 9 of 13

Page 4 of 5

B) NEMA 4X stainless steel

ADD .......................................................................... $ 43,000.00

Note: Item 1A or 1B may be taken, not both.

2) Provide NEMA 4X stainless steel enclosure for 1000 amp transfer switch in lieu of standard NEMA 3Rtype as specified.

ADD .......................................................................... $ 9,800.00

3) Provide (qty. 3) site lighting (LED) fixtures mounted on owner-furnished poles.

ADD .......................................................................... $ 5,400.00

Note: To be controlled via photo cell.

4) Provide extended warranty and maintenance agreements for the generator as follows:

A) Warranty for 5 years

ADD .......................................................................... $ 2,300.00

B) Warranty for 10 years

ADD .......................................................................... $ 8,400.00

Note: Item 4A or 4B may be taken, not both.

C) Maintenance for 5 years

ADD .......................................................................... $ 3,700.00 / per year

D) Maintenance for 10 years

ADD .......................................................................... $ 4,600.00 / per year

Note: Item 4C or 4D may be taken, not both.

5) Provide extended warranty on automatic transfer switch as follows:

A) Warranty for 5 years

ADD .......................................................................... $ 2,500.00

B) Warranty for 10 years

ADD .......................................................................... $ 9,800.00

Note: Item 5A or 5B may be taken, not both.

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 10 of 13

Page 5 of 5

CLARIFICATIONS

The following costs are EXCLUDED from our bid proposal:

1) Payment and Performance Bond.2) Utility company service charges for permanent and/or temporary electrical service.3) Utility company energy consumption charges.4) Off-site parking and lay down areas for material storage.5) Electrical Engineering.

Note: This contract is direct with APG Engineering and Utilities, Inc. of Florida.6) Re-building or replacement of existing motors.

Note: As discussed, these motors will be addressed on a one-by-one evaluation and paid for by owner.7) Methanol control cabinet (by owner, see Note #25 on Drawing E2-C).

Note: Installation is included.

The following costs are INCLUDED in our bid proposal in addition to what is shown on bid documents:

1) Permit cost (an allowance of $15,000).Note: Cost has not been verified yet.

2) Removal of trash from site.3) State and County sales tax on all materials.

We want to thank you for the opportunity to present our proposal, and look forward to working with you on this project.

Sincerely, APG Electric, Inc.

Terry Ryan Preconstruction Special Projects

TR/anf

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 11 of 13

(THIS PAGE WAS INTENTIONALLY LEFT BLANK)

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 12 of 13

MID‐COUNTY MOTOR MATRIX

MOTORHORSEPOWER 

RATINGNEW 

VOLTAGEACCEPTS NEW 

VOLTAGEREQUIRES FIELD MODIFICATIONS

REQUIRES REPLACEMENT

DATE

1 Methanol Pumps 0.5 480

2 Backwash Blower #1 40 480

3 Backwash Blower #2 40 480

4 Air Compressor 3 480

5 Air Compressor 3 480

6 Backwash Water Pump #1 7.5 480

7 Backwash Water Pump #2 7.5 480

8 Plant Water Pump 7.5 480

9 Blower #1 40 480

10 Blower #2 40 480

11 Blower #3 40 480

12 Blower #4 40 480

13 Clarifier Drive 0.75 208

14 Clarifier Drive 0.75 208

15 Master Lift Station 20 480

16 Master Lift Station 20 480

17 Odor Control Scrubber 5 480

18 Screw Conveyor 0.75 208

19 Surge Pump 15.5 480

20 Surge Pump 10 480

21 Filter Blower #1 75 480

22 Filter Blower #2 75 480

23 Surge Tank Blower 15 480

24 Filter Feed Pumps 7.5 480

25 Sludge Transfer Pumps 3 480

26 SOMAT Presses 5 480

27 Flocculator Mixer 0.5 480

28 Sludge Pump West 1 480

November 29, 2016

Docket No. 160101-WSMid-County Electrical Improvements - Bid Forms

Exhibit ATW-18Page 13 of 13


Recommended