+ All Categories
Home > Documents > District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB...

District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB...

Date post: 23-Jan-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
42
Always there to help you User manual 2 GC4511 Specifications are subject to change without notice © 2014 Koninklijke Philips N.V. All rights reserved. 4239 000 95691
Transcript
Page 1: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

District Energy SystemProgram Options Report

August 16th 2018

Page 2: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

DES Project Summary� FVB responded to, and was hired after a Request for

Proposal (RFP) issuance in 2017

� FVB prepared a comprehensive evaluation report for Metro to summarize the in-depth assessment of the economic viability of the DES

� Options/recommendations are provided for the future of the system

� Four scenarios are developed and compared

Page 3: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

DES Project Scenarios� FVB developed and analyzed four primary DES scenarios:

� No Growth (Business as Usual (BaU)) scenario� Based on existing operations with little or no growth

� Growth scenario� Based on expanding the system capabilities and customer base� Two different and not mutually exclusive expansion options explored

� Internal management and operations option� Metro retains ownership and internally manages and operates DES

� Business Exit case� Valuations if Metro exits the business

Page 4: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

DES Project Scenarios Overview� FVB evaluated options for the future of the DES, but

no specific option is favored or recommendation explicitly given

Page 5: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

DES Project Key Takeaways� Regardless of the ownership of DES, an active management

structure that takes ownership, has accountability, and encourages growth will need to be put in place

� It will be necessary to incorporate an effective marketing scheme into the management structure to successfully capture growth opportunities

� New customers should sign contracts that do not tie debt service to customer revenues, and existing customer contracts need to be revisited and restructured to allow additional capital to flow to the DES to allow for system growth, Energy Generation Facility (EGF) maintenance and improvements, and additional capital expenditure (CAPEX) needs

Page 6: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Scenario Overview� DES currently receives a yearly subsidy from Metro in

the form of the Metro Funding Amount (MFA) – Fiscal

Year (FY) 2019 MFA is $1,640,300

� The MFA will go down over time in any scenario, but at

different rates

� NPV (Net Present Value) is the difference between the

present value of the benefits of a project and its costs.

Page 7: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

BaU Scenario:Takeaways

� NPV of future MFAs discounted at 4.33%:� $4.9 MM without additional CAPEX� $10.4 MM with additional CAPEX

� Sales value will decrease over time:� Energy Generation Facility (EGF) equipment will age

and require additional CAPEX� Contracts will move towards expiration� Potential additional growth opportunities will be missed

Page 8: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

BaU Scenario:CAPEX Requirements

$3,292,300

$687,500 $577,500

$2,142,800

$495,000

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

$3,500,000

2019 2020 2021 2022 2023

CA

PEX

Req

uire

men

ts

Fiscal Year

CAPEX requirements are estimated and subject to revision. $495,000/year is assumed after starting in 2023.

Page 9: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

BaU Scenario:The Metro Funding Amount (MFA) Over Time

-

500

1,000

1,500

2,000

2,500

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

USD

(in 0

00's)

Year

MFA MFA with CAPEX

A 10% reduction in System Operator (SO) costs beginning in Fiscal Year 2019 is assumed.

Page 10: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Growth Scenario:Energy Generation Facility (EGF) Expansion

� Expand the existing EGF to its maximum site capacity by serving additional customers in the growing SoBro area

Page 11: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Growth Scenario:Thermal Energy Storage (TES) Tank

� Construct a TES to serve additional customers in the downtown area

Page 12: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Growth Scenario:Takeaways

� Promising option� Will require substantial upfront capital investment

� Energy Generation Facility (EGF) Expansion� Present day capital cost: $52.7 MM� Investment has a positive return but negative cash flows would

need to be funded for the first eight years� Thermal Energy Storage (TES) Expansion

� Present day capital cost: $38.5 MM� Investment has a positive return but negative cash flows would

need to be funded for the first five years

Page 13: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Growth Scenario:The MFA Over Time

� The Growth scenario generates a sustained cash surplus starting in 2031, consequently:� Contributes to the value of the DES in the long run and

demonstrates promise to a potential acquirer.� Does not contribute to a more rapid decline of the MFA.

Page 14: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Internal Management and Operations Option:Takeaways

� Possible cost savings and operational efficiencies to be gained could yield a 19% reduction in annual operations & maintenance (O&M) costs enabling the MFA to be eliminated faster

� A well-defined transition plan, management structure, and capital plan are needed

Page 15: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Internal Management and Operations Option:The MFA Over Time

-

500

1,000

1,500

2,000

2,500

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

USD

(in 0

00's)

Year

MFA MFA with CAPEX

Page 16: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Business Exit Case:Takeaways

� Sale of the DES is likely to repay all existing debt obligations

� The MFA will no longer be required

Page 17: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Business Exit Case:Valuation Metrics

� Potential growth� CAPEX requirements (based on the age and condition

of the system)� Customer contracts (structure and term)� Commodity risk (mitigated by pass-through contract

provisions)

Page 18: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Business Exit Case:DES Market Valuation Range with Reduced System Operator Costs

and System Growth

Valuation* Valuation Net of Debt*

$46.7 MM -$4.9 MM

$56.1 MM $4.5 MM

$65.4 MM $13.8 MM

*DES net debt as of the end of FY 2017 is $51.6 MM.

An active market for DE assets and strong market participants suggest that the higher valuation range may be achieved.

Page 19: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

DES Project Summary� FVB developed and analyzed four primary DES scenarios:

� No Growth (Business as Usual (BaU)) scenario� Based on existing operations with little or no growth

� Growth scenario� Based on expanding the system capabilities and customer base

� Internal management and operations option� Metro retains ownership and internally manages and operates DES

� Business Exit case� Valuations if Metro exits the business

Page 20: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Summary of ScenariosBaU Scenario

• CAPEX funding not adequate• Sales value will decrease over time• Will continue to require

subsidization through FY 2021

Growth Scenario• Two promising and not mutually

exclusive growth options• Will require substantial upfront

capital investment

Internal Management and Operations Option

• Possible cost savings and operational efficiencies to be gained could yield a 19% reduction in annual operations & maintenance (O&M) costs

• A well-defined transition plan, management structure, and capital plan are needed

Business Exit Case• Sale of the DES is likely to repay all

existing debt obligations• The MFA will no longer be required

Page 21: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario

Questions?


Recommended