DITS Project – M. Houry 27th of april Y07
DITS PROJECT DITS PROJECT SCHEDULESCHEDULE
DITS Project – M. Houry 27th of april Y07
A Project Management Office has been established in the DITS A Project Management Office has been established in the DITS project organizationproject organization
DITS project organization.
The PMO provides a help in terms of : Schedule, Human ress., Risk, Cost, Communication, Reviewing Management
Mean Goals : Built ONE Work-Plan based on Work-Packages What you must do Periodic progression measurements
Analysis of shifts & risks anticipation Appropriate corrections or treatments
Project LeaderE. Tsitrone
Deputy Project LeaderC. Brosset
General BoardCoEx (DRFC)CCAT (DRFC)
…..
Advisory BoardEuropean Experts
EU PWI TF, CNRS, ....
WP1 – Particle Balance ExperimentsWorkPackage Leader
B. Pégourié (DRFC)
WP2 - TPL DismantlingWorkPackage Leader
F. Samaille (DRFC)
WP3 – TPL analysisWorkPackage Leader
C. Brosset (DRFC)
WP4 – Satellite ProgrammesWorkPackage Leader
E. Tsitrone (DRFC)
Erosion RedepositionE. Gauthier
IRR. Reichle
CFPJ. Schlosser
Test SATIRJ. Schlosser
DétritiationH. Roche
Management TeamProject Time & Ressource Management (M. Houry)
Project Risk, Cost & Quality Management (L. Jourd’Heuil)Project Safety Management (K. Zunino)
Management TeamProject Time & Res. Management
Project Risk, Cost & Quality ManagementProject Safety Management
DITS Project – M. Houry 27th of april Y07
The DITS schedule is made of 6 Work-Packages
WP0 - Management Time, cost, human resources, quality, risk, safety, communication, reviews
WP1 – Particle balance experiments D2 Plasma experiments for TPL loading
WP2 – TPL Dismantling Extraction – Operations – Mounting
WP3 – ANALYSIS Preparations and analysis on the TPL, fingers, tiles and samples
WP4 – SATELLITE PROGRAMS IR program (R. Reichle) PFC (J. Schlosser) Detritiation (H. Roche) DUST (S. Rosanvallon)
WP5 – CO ACTIVITIES Acoustic sensors (X. Courtois)
Tore Supra Summer Shut-down
Tore Supra Experimental program
DITS Project – M. Houry 27th of april Y07
Work Package 1 & 2 : TPL loading and Dismantling
Sept.MaiMaiMay JuinJuinJune Juil.Juil.July. AoûtAoûtAug.
Removing ICRH(Q1) & TPL(Q6A)
TPL Loading : 24/05 to 07/06
Fingers exchangeSpare Fingers validation
Qualification tests
TPL & ICRH installing
3D Cartography Meas.
WP1
WP2
WP3
Tore Supra Summer Shut-down for maintenance operationsTore Supra Summer Shut-down for maintenance operations
DITS Project – M. Houry 27th of april Y07
WP3 : Analysis
3D Cartography on fingers
TPL back in TS
Assembly - tests 18/07
April May June July Aug. Sept.
3D cartography measurements
Structure
22/06
Optics04/07
3D Cartography on sector 02/08 24/08
DITS Project – M. Houry 27th of april Y07
WP3 : Preparation for analysis WP3 : Preparation for analysis Fingers – Tiles extraction – Samples cuttingFingers – Tiles extraction – Samples cutting
Aug. Sept. Oct.
Samples characterization
Fingers activity controlSafety authority agreement 13/09
Tiles dismantling
26/09
Tiles cutting Samples 11/10
3D Cartography
Ready for analysis
22/10