1
Fixed Cost Category Applicability Cost (including GST) Partially-Serviced Power line exists on the road adjacent to property and was installed by a developer. Required construction includes only low voltage overhead power line. $0 Small Required construction includes 0–35m of high-voltage overhead power line. $2,350 Small with Road Crossing Required construction includes 0–35m of high-voltage overhead power line and the line crosses a roadway. $4,150 Large Required construction includes 36– 300m of high-voltage overhead power line. $6,150 Large with Road Crossing Required construction includes 36– 300m of high-voltage overhead power line and the line crosses a roadway. $7,950 * Calculations based on estimated 2019 transmission and distribution rates and the one year average RRO cost per kWh RESIDENTIAL CONSTRUCTION COSTS ESTIMATED 2019 MONTHLY POWER BILL* DO YOU NEED POWER FOR YOUR NEW ACREAGE? At FortisAlberta we believe that turning the power on should be simple, easy, and affordable! Our fixed cost options provide you the certainty needed to power your home. $200 $150 $50 $100 $63.33 0kWh 600kWh $114 1000kWh $169 1500kWh $239 Total Monthly Bill Consumption $30 Pole mounted metering is available upon request Connect with us today. Call 310-WIRE (9473) or 1-866-717-3113 (toll-free) B37 Sept 2019
Transcript

Fixed Cost Category

ApplicabilityCost

(including GST)

Partially-Serviced

Power line exists on the road adjacent to property and was installed by a developer. Required construction includes only low voltage overhead power line.

$0

SmallRequired construction includes 0–35m of high-voltage overhead power line.

$2,350

Small with Road Crossing

Required construction includes 0–35m of high-voltage overhead power line and the line crosses a roadway.

$4,150

LargeRequired construction includes 36–300m of high-voltage overhead power line.

$6,150

Large with Road Crossing

Required construction includes 36–300m of high-voltage overhead power line and the line crosses a roadway.

$7,950

* Calculations based on estimated 2019 transmission

and distribution rates and the one year average RRO

cost per kWh

RESIDENTIAL CONSTRUCTION COSTSESTIMATED 2019 MONTHLY POWER BILL*

DO YOU NEED POWER FOR YOUR NEW ACREAGE?At FortisAlberta we believe that turning the power on should be simple, easy, and affordable! Our fixed cost options provide you the certainty needed to power your home.

$200

$150

$50

$100

$63.33

0kWh 600kWh

$114

1000kWh

$169

1500kWh

$239To

tal M

on

thly

Bill

Consumption

$30

Pole mounted metering is available upon request

Connect with us today. Call 310-WIRE (9473) or 1-866-717-3113 (toll-free)