+ All Categories
Home > Documents > CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1...

CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1...

Date post: 07-Mar-2018
Category:
Upload: truonglien
View: 216 times
Download: 3 times
Share this document with a friend
94
Chapter - 3 Infrastructure Roads and Bridges Transport is a vital infrastructure for rapid socio-economic growth of any country. Out of the two important modes of transport i.e. Railways and Roads the latter's share in transport has been increasing continuously due to inherent advantages of door to door service, flexibility & reliability. These qualities of road transport make it the most popular system of transport in the country. 2. Uttar Pradesh is the most populous State of India with 16.62 crore population (2001 census). The total area of the state is 2.41 lac sq km with a density of 689 persons per sq km. The decadal growth of State population during 1991-2001 has been 25.8% compared to all India growth of 21.34% over the same period. As regards population growth, UP ranks 16th among 35 States / Union territories of the country. The State rural population as per 2001 census is 13.15 crore (79.12%) and the urban population is 3.47 crore (20.87%). 3. Over the last 50 years, the volume of railway freight has increased five fold and passenger kilometers nearly seven fold. The length of surfaced roads has multiplied nine fold. The number of goods vehicles has increased 40 fold, buses 20 fold and four-wheel passenger vehicles 30 fold. Freight handling has grown more than 16 fold and airfreight has increased about 30 fold. The vehicle population has increased from 3 lac in 1950-51 to an estimated 670 lakh in 2003 i.e. 224 times in 53 years. Only seven, out of every ten habitations have been connected by either painted or BOE (Kharanja) roads. 4. The relative share of road transport has increased from 12% to 60% of the freight volume and from 32% to 80% of passenger traffic. It is [ 155 ]
Transcript
Page 1: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Chapter - 3

Infrastructure

Roads and Bridges

Transport is a vital infrastructure for rapid socio-economic growth of any country. Out of the two important modes of transport i.e. Railways and Roads the latter's share in transport has been increasing continuously due to inherent advantages of door to door service, flexibility & reliability. These qualities of road transport make it the most popular system of transport in the country.

2. Uttar Pradesh is the most populous State of India with 16.62 crore population (2001 census). The total area of the state is 2.41 lac sq km with a density of 689 persons per sq km. The decadal growth of State population during 1991-2001 has been 25.8% compared to all India growth of 21.34% over the same period. As regards population growth, UP ranks 16th among 35 States / Union territories of the country. The State rural population as per 2001 census is 13.15 crore (79.12%) and the urban population is 3.47 crore (20.87%).

3. Over the last 50 years, the volume of railway freight has increased five fold and passenger kilometers nearly seven fold. The length of surfaced roads has multiplied nine fold. The number of goods vehicles has increased 40 fold, buses 20 fold and four-wheel passenger vehicles 30 fold. Freight handling has grown more than 16 fold and airfreight has increased about 30 fold. The vehicle population has increased from 3 lac in 1950-51 to an estimated 670 lakh in 2003 i.e. 224 times in 53 years. Only seven, out of every ten habitations have been connected by either painted or BOE (Kharanja) roads.

4. The relative share of road transport has increased from 12% to 60% of the freight volume and from 32% to 80% of passenger traffic. It is therefore important that transport capacities are expended to cater to the growing future demand.

Road Development Plan – Vision 2021

5. On the basis of the assessment of the achievements of the Lucknow Plan 1981 – 2001 and keeping in view the present and the future needs of the country Indian Road Congress has formulated the Vision 2021 for the Highway development in the first two decades of the 21st century for the country as a whole.

National Highways:

6. All national highways should have a minimum of two-lane carriageway with hard shoulders. Half the network should have four/six-lanes. Strengthening of weak pavements, rehabilitation of those bridges showing signs of distress, Construction of bypasses, railway over bridges, safety engineering and drainage measures are to be provided. The present NH system will be expanded to 80,000 kms by the end of 2021.

[ 155 ]

Page 2: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

State Highways:

7. Entire length of State Highways will be of minimum two lane standard of which some segments will have additional hard shoulders and 10,000 kms. of State Highways will be four laned. The present State Highways system will be expanded to 1,60,000 kms. by the end of 2021.

Major District Roads.:

8. 40% of Major District Roads should have a minimum of two-lane carriageway and the total length of network will be expanded to 3,20,000 kms by the end of 2021.

Rural Roads:

9. All villages with population more than 1000 were to be connected by the year 2003, villages with population between 500 to 1000 were to be connected by 2007 and villages with population less than 500 will be connected by 2010. Once the basic access to all the villages is achieved in the first decade, the work of further improvements of village roads and additional links may be taken up in the subsequent years.

10. Although the vision 2021 has not laid down specific targets for the different states however the above all India National Highways, State Highways and Major District Roads targets are interpolated on the basis of the population of Uttar Pradesh in comparison to the population of the country (as per 2001 census) and the deduced targets of different categories of roads are as follows:-

S. No.

Category of Road

Population of Country (in crores)

Population of U.P. (in crores)

Target for the country as per Vision 2021 ( in kms.)

Proportionate target for U.P.for 2021 (col 4 x col 5 /col3) (in kms.)

Proportionate target for U.P.for year 2011 taking base yr. 03/06 [(col 6 – col 8)/3+ col8] (in kms.)

Existing Road length as on 3/06(in kms.)

Proposed addition/ Upgradation of roads in kms [(col 6-col 8)/3] by year 2011 (col7 – col8)

Approx. Proposed up gradation per year in kms (col9/5)

1 2 3 4 5 6 7 8 9 10

1 N.H 102.86 16.62 80,000 12,925 8030 5,583 2447 4902 S.H. 102.86 16.62 1,60,000 25,850 14542 8,888 5654 12003 M.D.R. 102.86 16.62 3,20,000 51,700 22086 7,280 14806 2960

Total 5,60,000 90,475 44658 21,751 22907 4650

Financial and Physical Achievements Xth Plan

[ 156 ]

Page 3: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Financial Achievements

11. Against an outlay of Rs.6008.16 crore, the expenditure incurred was Rs.7806.58 crore, during the 10th Plan.

Physical Achievements Roads and bridges

Sl. No. Item Unit Xth Plan Target

Xth Plan Achievement

1. New construction of new roads Kms 9236 18806

2. Strengthening/widening . of SH/MDR/ODR

Kms 1395 4094

3. Bridges Nos 216 4084. ROBS Nos 10 165. EAP

-Upgradation - Strengthening (Rehabilitation)

KmsKms

7702200

223919

Status of Village ConnectivityTotal No. of Villages (1991 census)

Villages connected as on 31.3.02

Balance unconnected at the end of IXth Plan

Xth Plan Target

Xth Plan Achievement

98248 43437 54811 3695 16647

12. During the Xth Plan period 907.275 Kms length of roads has been upgraded to NH.39.60 kms of Major District Roads were upgraded to State Highways during the year 2002-03, and 56.98 kms of Other District Roads have been up graded to MDR category in the year 2006-07.

Eleventh Plan, 2007-12

Thrust areas

All single lane and intermediate lanes of State highways will be widened to at least two lane standards and strengthened along with improvement in the riding quality.

All existing single lane and intermediate lane MDRs will be improved, i.e. strengthened and widened to two lane standards.

Existing intermediate/single lane ODRs in high traffic density zones will be improved, i.e. strengthened and widened according to traffic needs.

Existing double lane SHs will be improved by strengthening to cater to higher traffic density.

Existing double lane MDRs will be improved by strengthening in to high traffic density areas.

[ 157 ]

Page 4: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Existing double lane ODRs will be improved and strengthened.

In order to maintain the core road network of the state in the best possible riding worthy state and obtain the best possible cost benefit effects in this sector, work on introducing a road maintenance and management system along with GIS mapping will be expedited through institutional development and strengthening project.

Missing Bridges across State highways will be constructed.

Distressed bridges on State highways and important major district roads are be rehabilitated.

Narrow bridges on important state highways and major district roads will be widened.

Important Railway level crossings with traffic density above 1 lac train vehicle units (TVU) will be have replaced by road over head bridges.

Construction of flyovers in important cities of the state.

District headquarters will be provided bypasses at least for major traffic sectors or wherever major projects are coming up.

Improvement of Urban roads.

Private sector participation - Construction of overhead bridges, river bridges, bypasses and expressways to be taken up under BOT.

Maintenance of existing road network - ensuring proper level of service for road users.

Providing connectivity to rural areas i.e. villages by standard single lane width roads.

Construction of bypasses on SHs, MDRs where traffic has to pass through congested towns.

The average age of engineering staff is around 45 years. For the last 10 years no substantial technical staff has been recruited. This aspect needs immediate redressal otherwise along with the shortage of the Eng. /Tech. Staff the average age will also increase further in the coming years.

Financial Targets and Achievements of XIth PlanTotal proposed outlay of XIth Plan (Rs. Crores)

Year Outlay (Rs. Crores)

Expenditure (Rs. Crores)

24796.182007-08 3929.44 3929.44*

2008-09 (Proposed) 4793.85

Total 8723.29

*Anticipated

Physical Targets and Achievements of XIth PlanRoads and Bridges

[ 158 ]

Page 5: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Sl. No. Item Unit XI Plan Target

2007-08 2008-09Targ Anticip. Ach Targ

1. New construction of roadsReconst./Conv. to St. Single Lane

KmsKms

1233615000

4951 4951 6445

2. Strengthening/Widening of SH/MDR/ODR (incl. CRF)

Kms 18289 2032 2032 2692

3. Bridges Nos 207 40 76 634. ROB Nos 34 2 4 25. EAP

-Up gradation -Strengthening(Rehabilitation)-Major Bridges

KmsKms

Nos.

1741501

3

150500

150500

100300

Status of Village ConnectivityTotal No. of Villages (2001 census) as per diary 2006

Villages connected as on 31.3.07

XIth Plan Target

2007-08

2008-09

Target Anticip. Ach. Target

97942 60084 10960 1374 2460 2500

Status of connectivity of habitations

13. State Road Development policy was formulated in 1998 to provide impetus to the rural connectivity. On the basis of 1991 census an ambitious target of connecting all the villages of more than 1000 population by 2005 and of population less than 1000 by 2010 was targeted. On account of the practical limitations of the concept of village connectivity a new concept of connectivity of habitations was developed. PMGSY was launched in 2000 on the basis of this new concept, which envisaged a time bound programme to connect and upgrade all habitations of more than 1000 population by 2003-04 (in I Phase) and of population between 500 to 1000 by the year 2007-08 (in II Phase). However the achievement remained well below the targets and much is still left to be taken care off in the XIth Plan.

14. At the advent of the XIth Plan, out of a total of 1,70,004 habitations of the State, only 1,20,444 habitations were connected according to PMGSY standards i.e. connectivity either through painted or BOE (Kharanja) roads, thus leaving 49560 (29.15%) habitations unconnected (428 habitations of more than 1000; 4254 habitations of population between 500 to 999; 19604 habitations of population between 250 to 499 and 25274 habitations of less than 250 population). Out of these 958 habitations (428 habitations of more than 1000; 208 habitations of population between 500 to 999; 196 habitations of population between

[ 159 ]

Page 6: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

250 to 499 and 126 habitations of less than 250 population) are anticipated to be connected during 2007-08 through PMGSY. A target of connecting 1193 habitations is kept for the year 2008-09 by UPRRDA.

Construction of Railway Over Bridges

15. Construction of Railway overhead/under head bridges has also been accorded high priority along with construction of road bridges. Some important Railway overhead bridges at Lucknow (Raidas Mandir), Lucknow (Mawaiya), Fatehpur, Meerut (Partapur), Gorakhpur (Dharamshala Crossing), Lucknow (Engg. College), Lucknow (Gomti Nagar), Hathras and Hardoi were completed by March 2006. Construction of three ROBs at Aligarh, Lucknow (Sadar Bazaar) and Ambedkar nagar, and widening of Kanpur (Tat Mill) ROB was completed during 2006-07 i.e. during the last year of the Tenth Plan.

16. With further impetus during the XIth Plan construction of fly overs at Etawah, Bareilly, Allahabad (Sirsa Mandi), and widening of Ghaziabad (Mohan Nagar) ROB is likely to be completed during 2007-08.

17. Construction of overhead bridges at Railway Crossing No. 129A in Deoria and at Railway crossing No. 26B/T-2 in Jyotiba Phule Nagar is proposed during the year 2008-09.

18. During 2006-07 88 major bridges have been completed and 76 major bridges are likely to be completed during the year 2007-08.

Category wise Status of Highways and Roads in Uttar Pradesh

19. The achievements in road length of all categories, including earthen Roads corresponding to the target of Road Development Plan-Vision 2021 are as follows:-

Item Target Length for 2011 (km.)

Achievement as on 31.3.2006

% of Target

Road Dev. Plan-Vision 2021N.H. 8030 5570 (1.4.2006)* 69%S.H. 14542 8551 (1.4.2006)** 58%MDR 22086 7345 (1.4.2006)** 33%ODR&VR 255316 (1.4.2006)***Total:- 276782 #

* With PWD = 3824.775 km, With NHAI=1745.496 km.** PWD Only.

*** including 1,43,678 km of other Department Roads (excluding Local Bodies and Avas Vikas Parishad).

# Out of this Black Top length is 1,50,303 kms only.

[ 160 ]

Page 7: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

State Highways

20. As per Vision 2021, the length of State Highways in the state by the 2011 should be 14542 km against which the length of state Highways is 8551 km only as on 31.3.2006. Road Development Plan – Vision 2021 envisages the entire length of State Highways to be of minimum double lane standard.

21. Existing traffic density, on most of the State Highways, requires double laning (in some cases even four laning) and strengthening as well. However the present position is as under: -

Below Standard SL (up to 3.74 m width) 2736 kms 32%

Standard SL (3.75-6.99 m width) 1426 kms 17%

Standard DL (7.00-10.49m width) 4306 kms 50%

Standard ML (above 10.5 m width) 83 kms 1%

Total: -8551 kms

22. This clearly establishes that the existing 49% length of SHs, which is less than 7.0m in width should be double laned in the XI Plan itself. In addition to this, 30% length of the existing double lane SHs will also be strengthened. Out of which about 2000 kms are likely to be strengthened /widened during 2007-08 and a target of strengthening/widening of about 2200 kms is being kept for the year 2008-09.

Major District Roads

23. Length of Major District Roads in the State as per Road Development Plan – Vision 2021, should be 22086 km by the year 2011. Against this, the MDR length is 7345 km as on 31.03.06.

24. 40% of Major District Roads should have a double lane pavement according to Vision 2021. The present position is as given below: -

Below Standard SL (up to 3.74 m width) 5195 kms 72%

Standard SL (3.75-6.99 m width) 1518 kms 20%

Standard DL (7.00-10.49m width) 607 kms 8%

Standard ML (above 10.5 m width) 25 kms -

Total: -7345 kms

25. It is therefore important that the entire available length of MDRs of the State should be double laned and up graded to SH in the XIth Plan itself. So all the existing MDR is proposed to be double laned by 2012 and 20% of existing double lane length is proposed to be strengthened. About 500 kms of road is likely to be strengthened /widened during 2007-08 and a target of strengthening/widening of about 500 kms is being kept for the year 2008-09.

[ 161 ]

Page 8: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Other District Roads

Below Standard SL (up to 3.74 m width) 25851 kms 88%

Standard SL (3.75-6.99 m width) 2012 kms 7%

Standard DL (7.00-10.49m width) 1088 kms 4%

Standard ML (above 10.5 m width) 228 kms 1%

Total: - 29179 kms

26. To achieve the targets of the Road Development Plan – Vision 2021, widening of 20% length of 5.5m width to 7.0m width and widening of 20% length of 3.5m width to 5.5m width is proposed along with strengthening of 20% length of existing 7.0m wide roads, to cater to higher axle loads. However due to manpower/resource crunch, no specific targets have been fixed for 2007-08 and 2008-09.

Comparative Position of State in Road Length Density

27. The state lags much behind the other states of the country in road densitiy per 100 sq. km. area and per lac of population. Among the 26 major states of the country UP stands at 23rd and 11th position population and area wise respectively.

Private Sector Participation

28. In order to reduce the burden on the Public Sector, Private Sector participation in road transport has become a necessity. According to U.P. Road Development policy 1998 it has been decided to attract private sector investment for construction of rail overhead / under bridges, bypasses and construction/maintenance of roads in high density corridors. In the year1999, guidelines were framed to encourage Private Sector participation in the road and bridge projects in the state on Build-Operate-Transfer (B.O.T.) basis. U.P. State Bridge Corporation has been declared Nodal Agency for such BOT projects. Projects are to be identified on the basis of Economic Internal Rate of Return (EIRR) and Financial Internal Rate of Return (FIRR). The Government will carry out preparatory work for the projects identified for private investment and meet the cost initially but the cost for detailed feasibility study of the project and land for Right-of-way and enroute facilities will be added to the cost of the project and the entrepreneur will have to pay it back to the Government from the income from toll collection.

29. A major bridge over river Sone in Chopan has been constructed by U.P. State Bridge Corporation on B.O.T. basis. Subsequently no significant progress could be made towards private sector participation for construction of roads & bridges on account of certain unavoidable reasons.

30. A major step was taken towards boosting Private Sector participation in Road & Bridges sector by constituting U.P. State Highway Authority for the development, maintenance and management of State Highways. Executive board of the Authority identified 9 important State Highways (total length 1265 kms) for up gradation, 6 State Highways for maintenance (total length 503.60 kms) and construction of 6 important ROBs on PPP basis. The identified State Highways and ROBs are as under: -

[ 162 ]

Page 9: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

List of approved State Highways for Up gradation: -Sl No

Name of Road Category of Road

Length in Kms

1- Delhi Baghpat Saharanpur Road SH-57 200.002- Kalpi Hamirpur Road SH-90 60.003- Bareilly Baheri Kitchcha Road SH-37 64.004- Sitapur Bilgram Hardoi Road SH-21 110.005- Lumbini Duddhi Road SH-5 100.006- Badaun Bahjoi Sambhal Gajraula Bijnaur Road SH-51 195.007- Bilhaur Rasulabad Bela Etawah Road SH-40 104.008- Bahraich Balrampur Utraula Basti Road SH-26 217.009- Raibareilly Sultanpur Azamgarh Road SH-34 215.00

List of approved State Highways for Maintenance: -Sl No Name of Road Category of

RoadLength in Kms

1- Kairana Muzaffar Nagar Road SH-12 55.602- Bareilly Badaun Road SH-33 45.003- Kashipur Moradabad Road SH-41 43.004- Faizabad Akbarpur Azamgrh Road SH-30 150.005- Varanasi Azamgarh Dohrighat Road SH-73 90.006- Varanasi Shakti Nagar Road (Hathi Nala Part) SH-5A 120.00

List of approved ROBs:Sl No. Name of Road Level Crossing

No.District

1- State Highway No. 14 (Near Baghpat) 28 A Baghpat2- State Highway No. 13 (Near Raibareilly) 161 B Raibareilly3- State Highway No. 5 ( Near Mirzapur) 30 SPL Mirzapur4- State Highway No. 5 (Near Mariyahu) 7 B Mirzapur5- State Highway No. 18 (Near Bulandshahar) 13 A Bulandshahar6- State Highway No. 33 (Near Bharatpur) 342 A Mathura

Construction of Ganga Expressway project on Public Private Partnership Model

31. The Ganga Expressway Project was launched in 2007. The project aims to construct a 1047 km access controlled eight-laned expressway running along the Ganga river. This expressway will connect Greater Noida to Ballia thus ensuring high speed connectivity between the Eastern and Western boundaries of Uttar Pradesh. The construction of the expressway will be done under a Public-private partnership model entailing an investment of the order of about Rs. 40,000 crores.

[ 163 ]

Page 10: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Appraisal of some important schemes

Rural Infrastructure Development Fund Scheme Financed by NABARD

Road Works

32. Government of India has set up Rural Infrastructure Development fund (RIDF) to be operationalised by NABARD for financing the new infrastructure projects, construction of rural roads and bridges for rural connectivity have been covered under this scheme. Sanction for construction of roads and bridges was started under RIDF-II Scheme in 1996-97 and subsequently road projects under RIDF-III in 1997-98, RIDF-IV in 1998-99, RIDF-V in 1999-2000 & 2000-2001, RIDF-VI & VII in 2001-02, RIDF-X and XI in 2005-06 & RIDF-XII in 2007-08 were sanctioned.

33. Till end of 10th five year plan, 9092 road works were sanctioned under RIDF Schemes costing Rs 1411.33 (excl. estab.) crores against which 8263 works were completed up to March 2007 and expenditure of Rs. 1348.72 crore was incurred.

34. Under 10th five year plan, against an amount of Rs. 765.62 crore (excl. estab.) , Roads of 4220 km length were constructed with an expenditure of Rs. 708.98 crore (excl. estab.) and 3952 of road projects were completed.

Bridges

35. The schemewise progress of different Bridge works is as under :- Scheme No.of

sanctioned Bridges

after deletion

Sanction cost Expenditure Completed Bridges

Balance as on 30-11-07

Nabard-2 61 111.10 112.11 60 0.000Nabard-3 24 25.83 29.57 24 0.000Nabard-4 85 118.49 115.39 83 0.000Nabard-5 32 49.27 51.95 30 0.000Nabard-7 25 64.14 40.47 19 0.0628Nabard-10 34 62.45 34.29 25 0.2743Nabard-11 122 296.77 28.74 15 83.7142Total 383 728.05 412.52 256 84.0513

36. As per table shown above 01 Bridges in Nabard-2, 02 Bridges in Nabard -4, 02 Brdiges in Nabard-5, 06 Bridges in Nabard-7, 09 Bridges in Nabard-10, 107 Bridges in Nabard-11, are under construction. The amount shown in columns no.-6 is based on the amount allotted to U.P. Bridge Corporaton.

[ 164 ]

Page 11: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

37. Thus a total of 127 Bridge projects are under construction under different Nabard Schemes. An outlay of Rs.119.81 Crores has been provided and 19 Bridges are expected to be completed in the financial Year 2007-08. Total outlay for Eleventh Five Year Plan is Rs.433.87 Crores against a target of 95 Bridges. Outlay proposed for the year 2008-09 is Rs.119.81 Crores.

Likely Progress During 11 th five year plan

38. During 11th five year plan, under RIDF Scheme, against proposed outlay of about Rs. 1012 crores for road works, roads of about 2898 km length are expected to be constructed whereas for 2007-08 Rs. 143.66 crores (excl. estab.) are proposed to be spent against an outlay of Rs. 279.54 crores for road works to construct about 800 km road length. During 2008-09 against proposed outlay of Rs. 234.35 crore for road works, roads of about 671 km length are expected to be constructed.

Externally Aided Project - U.P. State Roads Project

39. World Bank sanctioned a loan to the state for Upgradation and major Maintenance of about 3500 Km. length of Core Road network. This project is being implemented in two phases –

Phase I – Upgradation of 374 Km. (4 Packages) and Major Maintenance of 808 Km. (16 Packages)

Phase II – Upgradation of 579 Km. (7 Packages) and Major Maintenance of 1766 Km. (32 Packages), Construction of 4 Bypasses of 20 Km.length and 5 Major Bridges.

40. The total cost of this project is Rs.295200.00 Lacs (USD 615 Million), out of which Loan Amount is Rs.234200.00 Lacs (USD 488 Million). The project was started in April 2003 and its duration is 5½ years. The completion date of the project is 31st December, 2008

41. Under Phase I of the project, out of 16 Major Maintenance Packages, 14 Packages have been completed (624 Km.) and work on balance 2 Packages is ongoing. Similarly works on following two Upgradation Packages, out of four packages under Phase I of the project have been completed -

Baharaich – Gonda – Faizabad Road - 109.354 Km.

Jaunpur – Mohammadpur Road - 33.873 Km.

And works on the following two Upgradation Packages, out of four packages under Phase I of the project are in progress –

Katra-Jalalabad-Allahganj-Bilgram-Bangarmau-Bilhaur Road - 171.435 Km.

Bhognipur – Ghatampur – Choudhagra Road - 82.296 Km.

42. Due to depreciation in Dollar rate, and substantial increase in cost of construction material during the construction period, the project has been modified/restructured as under:

To absorb/accomodate expected increase of Rs.649 Crores in project cost, 7 Upgradation Packages in Phase II of the project have been downgraded to Major Maintenance.

[ 165 ]

Page 12: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

A portion of 23 Km. from Madhoganj to Bangarmau Road has been included in Upgradation works on suggestion from the World Bank.

To absorb/accomodate increase of Rs.400 Crores in project cost due to unexpected increase in cost of construction material, Upgradation Package No. 9, 10 & 11 and Major Maintenance Package No. 39, 40, 41 & 53 have been deleted from the scope of the project.

Works of three Major Maintenance packages RMC-27, 28 and 29 are being done from other sources and notification has been issued declaring Raebareilly – Allahabad Road (RMC-22 & 52 ) as National Highway. Hence these packages are also out of the ambit of the project.

43. Therefore after above modifications / restructuring of the project, the length identified under Upgradation Packages has been reduced to 397 Km. and the length identified under Major Maintenance Packages has been reduced to 2420 Km.

Following Major Maintenance works of Phase I and II of the project are under progress:S.No. Package No. Name of Road Length

Km.)1. RMC-02 Muzaffarnagar-Saharanpur & Muzaffarnagar-Jansath Road 83.2872. RMC-10 Bacharawan – Fatehpur Road 72.0003. RMC-21 Lucknow – Raebareilly Road 65.3034. RMC-23 Faizabad – Raniganj Road 50.8505. RMC-24 Ranignaj – Raebareilly Road 57.0006. RMC-25 Meerut – Bulandshahar Road 55.5907. RMC-26 Bulandshahar – Narora Road 57.6278. RMC-31 Rajaganj – Sharda Bridge Road 38.0009. RMC-32 Sharda Bridge – Ghaghra Bridge Road 36.00010. RMC-33 Ghaghra Bridge – Nanpara Road 37.00011. RMC-35 Shahjahanpur – Farukhabad Road 49.64312. RMC-36 Badauyn – Kasganj Road 57.20013. RMC-37 Kasganj – Hathras Road 63.00014. RMC-38 Hathras – U.P Border Road 63.50015. RMC-42 Etah – Shikohabad Road 51.30016. RMC-43 Mathura – Naujheel Road 45.60017. RMC-44 Jagdishpur – Pratapgarh Road (0.00 – 40.00 Km.) 40.00018. RMC-45 Jagdishpur – Pratapgarh Road (40.00 – 78.50 Km.) 38.50019. RMC-46 Bela(Pratapgarh) - Patti Dhakwa Road 46.30020. RMC-47 Fatehpur – Muttor Road 35.00021. RMC-48 Muttor – Banda Road 41.50022. RMC-49 Meerut – Garhmukteshwar Road 42.00023. RMC-50 Garhmukteshwar – Bulandshahar Road 51.00024. RMC-51 Chhata – Bajna Road 42.000

[ 166 ]

Page 13: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

S.No. Package No. Name of Road Length Km.)

25. UPG-05 Pilibhit – Khutar Road 72.72626. UPG-06 Lucknow-Mohan-Bangarmau Road 75.32927. UPG-08 Azamgarh-Mau-Phephna Road 115.498

Total 1482.753

Works on following two Major Maintenance Packages under Phase – II have been completedS.No. Package No. Name of Road Length

Km.)1. RMC-30 Khutar – Rajaganj Road 42.8002. RMC-34 Nanpara – Baharaich Road 18.600

Total 61.400

Construction work on following three Major Bridges is in progress:S.No. Package No. Name of Bridge1. UPG-13 Bridge over River Ghaghra on Sitapur Baharaich Road2. UPG-16 Bridge over River Yamuna on Chata-Gomat Road3. UPG-17 Bridge over River Ganga on Badauyn – Kasganj Road

44. Besides the above following two bridges are proposed to be constructed:S.No. Package No. Name of Bridge1. UPG-14 Bridge over River Ghaghra on Gorakhpur-Shahganj Road2. UPG-15 Bridge over River Sharda on Lakhimpur-Belrayan Road

45. The work on the above two bridges could not be taken up under State Road Project due to non-availability of funds and shall be taken up under other schemes funded by State.

46. Total expenditure incurred on the project up to March 2007 is Rs.116659 Lacs and Up gradation & Major Maintenance work on 1142 Km. length of Roads has been completed.

47. During Financial Year 2007-08, Outlay for U.P. State Roads Project is Rs.70000 Lakh which islikely to be spent. During the financial year 2007-08, the target of 500 Km. of Major Maintenance and 150 Km. of Up gradation works is likely achieved.

48. During Financial Year 2008-09, an outlay of Rs.500 Crores has been proposed for this project, against which construction of 300 Km. length under Major Maintenance and 100 Km. length under up gradation works will be taken up.

Status of Institutional Development and Strengthening (IDS) Project

49. The Institutional Development and Strengthening Project has been executed in two phases. In the first phase study to develop Institutional Development and Strengthening Plan was awarded to M/s TCE

[ 167 ]

Page 14: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Consulting Engineers Limited in association with M/s Tata Consultancy Services (TCS) and Sir Owen Williams Investment. The recommendations of the Study carried out by the Consultants were discussed in the meeting held on 24.9.2001, under the Chairmanship of the Principal Secretary, PWD. The minutes of which were approved by the state Govt.

50. Based on the agreed recommendations the Consultants formulated Institutional Development and Strengthening Plan, which is the basis of the scheme “Technical Assistance for Implementation of Institutional Reforms in the Road Sector of Uttar Pradesh”

51. The Specific Institutional Development Study Plan (IDSP) includes the following issue:

Road sector Regulatory & Strategic Framework;

PWD Organization Structure & Management Capacity;

Training / Staff Development & Human Resources (HR) Management;

Accounting & Financial Management;

Project / Program Planning, Management & Operation;

Procurement & Contracting;

Road Maintenance Planning Management & Operation;

Network Condition Data & Asset Management;

Road Financing & Resource Utilization;

Private Sector Participation in UP Road Infrastructure;

Road Safety Improvement; and

Information Technology (IT) & Management Information system (MIS)

52. The Contract of Technical Assistance for Implementation of Institutional Reform in the Road Sector of Uttar Pradesh has been awarded to the joint venture company of M/S LEA Inter National Limited, Canada and M/s LEA Associates South Asia Private Limited, India at a cost of Rs. 11.76 crores. The consultants have to submit 55 Reports of which 38 have been submitted. Based on the recommendations of the Consultants six Cells have been established for the modernization of the working of PWD to enable the department to effectively plan and monitor road network. The expenditure on the project for year 2006-07 was approximately Rs. 3.50 crores and expected expenditure for year 2007-08 is approximately Rs. 4.50 crores and during 2008-09 a provision of Rs. 2.50 crores, has been made for this project.

Transport

53. The length of roads in the state is about 127108 Kms out of which about 17729 Kms route is nationalized, on which UPSRTC plies its buses and on the rest of the routes private buses numbering about 24,741 provide the transport services .There are about 91 lac vehicles registered in the State .

54. For the enforcement of the Motor Vehicle rules, the department has 75 Enforcement teams which have to take care of about 10,000 trucks entering the state from different check posts and also of 1.92 lac trucks

[ 168 ]

Page 15: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

registered with the state. The squads are also responsible for the enforcement of Motor Vehicle Rules on all public transport vehicles and private vehicles which are either registered in the state or those which enter the state from outside.The revenue earned by the department in the year 2002-03 was Rs. 85093.49 lakh which increased to Rs. 113043.51 lakh in the year 2006-07.

55. The main functions of the Transport department are as follows

Enforcement of Motor-Vehicle Rule

Issuance of Driving Licence, Permits to the Transport vehicles

Registration of vehicles

Collection of Fee on to various activities relating to vehicles

Collection of Tax and Addl. Tax from the vehicles

Enforcement of Pollution norms in respect of Vehicles

Road Safety Schemes

Planning for Urban Transport

Achievement of Xth Plan

56. Important Enforcement and other work done by the departmentYear Challans Compounded cases Fine collected

Rs in lakh2002-2003 142234 74934 2075.98 2003-2004 159149 88940 2638.77 2004-2005 133812 75926 3209.40 2005-2006 226159 127234 4588.76 2006-2007 241817 163730 8471.90

57. The total outlay provided in the Xth Plan was Rs.13851 lakh, against which the expenditure was Rs. 1884.32 lakh. During the tenth plan period the following schemes were taken up by the department

Strengthening of the District Offices

58. Offices of the department are in bad shape with the increase in the number of vehicles, records relating to them have also swelled and there has been a requirement strengthening the facilities in the offices which has been carried out under this scheme.

[ 169 ]

Page 16: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Upgradation of Check-posts

59. The survey carried out by the department reveal that about 35000 vehicles of different types enter the state through its border. As there are only 75 enforcement teams it is not possible to check all the vehicles. As a result the State is losing large amount of revenue. To overcome this, check posts are being upgraded.

Computerisation of the Department

60. In order to keep the records of the vehicles registered in the state and 35000 vehicles of different categories entering the state through the border daily, it was found necessary to get all the offices of the department computerized so that a proper check could be kept on the record of the vehicles and also the tax/ additional tax to be recovered. During the tenth plan period an amount of Rs 165.10 lac has been spent. At the end of tenth plan 39 offices of department (including the Transport commissioner office) were computerised.

Eleventh Plan and Annual plan 2008-2009

61. The department is mainly concerned with the enforcement of motor vehicle rules. The government fixes a target for the collection of revenue to support its various other schemes of the State. During the 11th plan period an increase of 10 % in revenue is envisaged by way collection of various taxes, addl. taxes and fees .In order to achieve the target the schemes proposed to be taken up during the 11 th plan period are as follows :-

Computerisation of the Department

62. The Department has 71 offices. It has been decided that all the offices will be computerized. The project was prepared by N.I.C the cost involved being Rs 7.11 Cr. During the tenth plan period 39 offices were computerized. During the Eleventh plan period an outlay of Rs 18.91 Cr. is proposed and an outlay of Rs 10.94 Cr. is proposed for the year 2008-2009.

Land and Buildings

63. Most of the offices of the department are in rented building and this is adversely affecting the Computerisation project, because of three reasons-

Offices are situated in very small building

Contract for rent is normally for 5 years. As a result House owners normally ask for premises to be vacated after the contracted period.

Computerisation involves fixing computer cables, power electrification and developing a room for keeping the computers and other equipments..All the requires expenditure once the system starts functioning it is not possible to shift it every now and then .

[ 170 ]

Page 17: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

64. The extension of Administrative building of Transport commissioner office is also proposed during Xth Plan For the Annual plan 2008-2009 an outlay of Rs.50.56 lac. is proposed

Road Safety Scheme

65. The state has a large vehicular population and a number of accidents take place because of wrong use of road and defective driving habits. There is a need to educate the public about the right use of roads and developing right road habits. This is being done by adopting different methods of awareness like organising seminars at district level, providing literature, involving children of the schools in this field through debates, sports and art competition etc. Exhibitions are also arranged subsequently for developing awareness. To check road accidents the enforcement squad requires some essential equipments like Breath Analyzer, Digital Handicam, Speed Radar etc.

Upgradation of the Check Posts

66. There are 56 transport check posts on the border of the State. Through these check posts about 10.000 goods vehicle and passenger-vehicles enter the state through these check posts. These vehicles pay taxes and fee to the Transport Department as per the rules laid down in the State. the department has only 75 enforcement teams to handle those vehicles as well as the vehicles registered in the State. Because of shortage of enforcement personnel the State is loosing its due revenue and These check posts need to be upgraded for them to be effective in enforcement and collection of revenue.

67. Under this scheme, depending upon the number of vehicles passing through the check posts multiple lanes will be developed and small cabins will be built between the roads in which computer system linked with a sensor camera will be fitted. This will also be linked with the electronic weigh-bridges which will record the correct weight of the vehicle and will communicate the reading to the cabin computer. The computer in turn will calculate the compounding fee if any and will display the reading on the digital display board. there will be electronic barriers which will open up only when all the dues are paid by the vehicle.

68. At each check post, sufficient space will also be required for parking the vehicles and certain essential facilities will also be developed. The Project is proposed to be implemented under Public Private Partnership ( PPP )

Setting up of Motor Vehicle Testing Station

69. In view of the increasing number of motor vehicles in the state, it is important to test these vehicles report issuing fitness certificates. A fully equipped workshop with modern machines and testing equipments is needed to achieve this purpose. Provisions have been made for such testing workshops under the Motor Vehicle Act 1988, schedule 56(2) and Central Motor Vehicle Rules 1989, rule 63(3). An outlay of Rs. 1028.52 Lac is proposed for this purpose during the year 2008-2009.

[ 171 ]

Page 18: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Energy

Power

70. Electricity plays an important role in improving the living standard of the people, therefore, increase in the supply of electricity and strengthening and augmentation of transmission and distribution system is a priority in the 11th Plan . In the last 55 years the growth of power sector is depicted in the following table.

Transmission & Distribution lines (Ckt.Km.)As on 800KV 400KV 220KV 132KV 66KV 33KV 11KV L.T.31.3.51 - - - - 473 1426 6620 82031.3.07 409 4259 6669 10282 3139 30226 214820 240676

Transmission & Distribution Sub-stations ( No./MVA)As on 800KV 400KV 220KV 132KV 66&33KV31.03.1951 - - - - NA31.03.2006 - 14/7930 48/12570 214/15755 1903/16277

Generating CapacityAs on Installed Capacity in MW

Thermal Hydel31.03.1951 161 2631.03.2007 3987 526.1

71. Per Capita consumption of electricity is treated as a strong indicator of development of a society. As per CEA report per capita consumption in U.P. during F.Y. 2005-06 is 208.65 Kwh against all India average of 428.57 Kwh.

Comparision of U.P.'s Datas with other States & All India 2005-06States/ Peak Peak Gen. T&D Per Capita Village PLFUTs Demand Met Capacity Loses Consumption Electrified State  (MW) (MW) (MW) % KWH Unit Nos. Sector

%Haryana 4333 3931 2560.41 30.51 715.16 6764 66.30Panjab 7731 6158 4749.68 27.56 983.58 12278 79.90Uttar Pradesh 8175 6588 4708.27 32.63 208.65 66933 57.00Delhi 3722 3600 932.47 48.61 846.40 158 46.50Madhya Pradesh 6558 5136 3795.36 40.07 344.10 50213 67.70Maharastra 16069 12360 13838.34 31.60 608.74 35541 72.70Andra Pradesh 8999 8542 8859.65 20.06 553.61 26565 80.20West Bengal 4743 4599 4726.93 24.84 266.20 32861 62.90Assam 733 679 621.52 40.34 107.57 19660 16.10All India 93255 81792 124287.18 30.42 428.57 459486 67.10

[ 172 ]

Page 19: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Power Sector Restructuring and Reforms during Tenth Plan

Uttar Pradesh is one of the first few states to embark on reform in electricity sector. The reform process started in the year 1998 with the formation of independent Electricity Regulatory Commission in September 1998 under Electricity Regulatory Commission Act, 1998 of Govt. of India.

For better accountability the erstwhile U.P. State Electricity Board was divided into three corporations namely U.P. Rajya Vidyut Utpadan Nigam Ltd. (UPRVUNL), U.P. Jal Vidyut Nigam Ltd. (UPJVNL) and U.P. Power Corporation Ltd.(UPPCL) w.e.f. 14.1.2000.

In the distribution segment Kanpur Electricity Supply Company (KESCO) and four companies were created to look after the distribution in Kanpur city and the State.

A separate State Transmission utility i.e. U.P. Power Transmission Corporation Ltd. has also been created in the State to cater to the transmission business.

Collection based franchisee scheme has been started in the villages and input based franchisee has been started in Districts.

Important steps taken

The new Power policy involves private sector in all segments of the power sector. The policy gives major fiscal concessions to new entrepreneurs . The policy also aims of 100% electrification of villages, use of bio mass for energy generation and would tap all renewable energy sources...

Anpara C of 1000 M.W. capacity has been awarded on competitive bidding basis. This is India’s first project which has been awarded on Competitive Bidding Guidelines.

The revised Power Purchase Agreement and Revised Implementation Agreement relating to Thermal Generating Stations at Rosa (2x300 MW )and Hydro Electric Project at Srinagar (4X82.5 MW ) have been executed and the work on both these projects has started.

Major steps have been taken to reduce line losses and improve collection efficiency electromechanical meters have been replaced with electronic meters. Accelerated Power Development and Reform Programme (APDRP) is being implemented in various towns of Uttar Pradesh.

Extention of Parichha Thermal Power Project by additional capacity of of 1x210MW Power Plant.

Energy accounting system has been introduced and made effective to curb theft and losses.

Renovation and modernisation of thermal Power Plants have been taken up in order to improve PLF of thermal plants. Similarly the R&M of Hydro Power plants has also been taken up and would be completed during the 11th Five Year Plan..

For implementation of Reforms activities World Bank Loan No. IN 4545 amounting to US $ 150 million was sanctioned and implemented.

[ 173 ]

Page 20: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Impact of Restructuring and Reforms

72. The study of sponsored by World Bank in March 2005 revealed the following findings:

Installation of capacitors brought improvement in voltage.

Addition of transformer capacity has resulted in reduction of tripping cases due to over loading.

Construction of new transmission lines has resulted in reduction of transmission losses and over loading of lines.

Installation of new distribution transformers has resulted in reduction in transformer damage rate which improved reliability of supply.

Generation

Thermal Generation

73. The details of Power Station-wise installed capacity and de-rated capacity of Thermal Power stations under UPRVUNL as on 01.04.2007 are as follows :-

POWER STATIONS De-rated Units De-rated Installed Capacity In MW

1. Obra 4x40 160

2. Obra Extn.-I 3x94 282

3. Obra Extn.-II&III 5x200 1000

4. Panki Extn. 2x105 210

5. Harduaganj B 2x55 110*

6. Harduaganj C 1x60+1x105 165

7. Parichha 2x110+1x210 430*

8. Anpara A 3x210 630

9. Anpara B 2x500 1000

Total 3987

Note:-* At Harduaganj TPS unit no.1 of 40 MW unit no. 6 of 60 MW have been deleted from installed capacity w.e.f 08.02.2007; Whereas one unit of 210 MW at Parichha Extension TPS has been added w.e.f. 24.11.2006

.

74. U.P. Rajya Vidyut Utpadan Nigam Ltd., had envisaged a capacity addition of 1630 MW during the 10th Plan which included 2x500 MW from Anpara 'C' Thermal Power Project and 1X210 MW from Panki extension Thermal Power Project (gas based) and 2X210 MW from Harduaganj Thermal Power Project

[ 174 ]

Page 21: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

(gas based). Later it was decided to execute the construction of 2X500 MW Anpara 'C' Thermal Power Project through private participation. Due to non-availability of gas UPRVUNL could not execute the construction of both Harduaganj and Panki gas based projects .Instead of these gas based projects, UPRVUNL has executed construction of coal based 2X210 MW Parichha Thermal Power Project extension stage-I Its 1st Unit has been taken on commercial load w.e.f. 24.11.2006 while 2nd unit has been synchronized on 28.12.2006 and is running under trial. At the end of Tenth Plan, the PLF related to thermal units was 60.15.

Hydro Generation

75. Hydro Power Generation capacity in Uttar Pradesh is very low as most of the hydro plants were located in Uttarakhand and all the plants with installed capacity of around 1000 MW have been transferred to Uttarakhand..

76. Sheetla Small Hydro Power Project(3.6 MW) on Betwa Canal in Distt. Jhansi proposed under 10th Five Year Plan has commenced generation.

Other sources of generation

In the private sector Vishnu Prayag Hydro Project has been completed and commissioned by Jai Prakash Power Ventures Ltd.After deducting 12% free power to Uttaranchal U.P. is getting 352 MW power from this project.

Revised PPA for 330 MW Srinagar Hydro Project has been signed with Alaknanda Hydro Power Company Ltd (GVK Group).The work on this project has started.

Revised PPA for Rosa power Station has also been signed for installation Roja Thermal Power Station, Earlier this power station was planned with 600 MW capacity but now the project has been taken over by Reliance Energy group and the capacity of the project has been enhanced to 1200 MW.

The joint sector 1000 MW Tehri Hydro project has been completed in which U.P.‘s Investment is 25% and share in power is 374 MW.

Co-generation

77. During 10th Five Year Plan, 150 MW capacity has been added in the state by sugar industries .

Transmission system

[ 175 ]

Page 22: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Target and Achievement of Transmission works during 10th Plan are as under :

Sl No Item Unit Target Achievement

A. Construction of Lines

  400 KV Lines CKT Km. 1076.584 720.50

  220 KV Lines CKT Km. 1883.342 1069.721

  132 KV Lines CKT Km. 1662.12 1056.247

B. Construction of New Substations

  400 KV Nos (MVA) 3/1575 3/1260

  220 KV Nos (MVA) 17/3060 11/1260

  132 KV Nos (MVA) 43/1420 29/712.5

C. Increasing Capacity

  400 KV Nos (MVA) 1/315 2/630

  220 KV Nos (MVA) 21/1540 31/2370

  132 KV Nos (MVA) 150/3390 171/3600

Distribution System Target and achievement of Distribution works during 10th Plan are as under

Item Unit Target Achievements

A. 33 KV Works      

  33 KV Lines CKT Km. 2330 2486.96

  New 33 KV S/s No./MVA 385/1975 297/1685

  Augumenation No./MVA 630/1930 586/2008.5

B. 11 KV Works      

  11 KV Lines CKT Km. 5950 18371

  New 11KV S/s No./MVA 4095/465 22267/988.79

  Augumenation No./MVA 5165/620 4891/661.14

C. L.T. Lines CKT Km. 2620 6030.58

D. Installation of 11KV Capacitors

MVAR 403 39.6

Village Electrification

[ 176 ]

Page 23: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Target and achievement Of RE Works During 10th Plan are as underItem Unit Target Achievement

1 Electrification of villages No. 42184 28609

2 Electrification of Anusuchit Basties No. 42184 29204

3 Electrification of P.T.W. No. 50000 688694 Electrification of Ambedkar

VillagesNo 2797

Village Electrification Highest In U.P.

RGGVY 2005-06 2006-07 Total

U.P. 7498 16625 24123

All India 42276

APDRP

78. In the 10th Plan, a provision of Rs. 1512.20 Crore was made for improvement of distribution system in Urban areas under the APDRP scheme of Government of India. During the 10th Plan period only 36 schemes amounting to Rs 1091 Crore for 29 Districts of U.P. have been sanctioned by the GOI. Initially 50 % share was to be provided by Government of India but later on it was revised and reduced to 25% only. Till 31st March 2007 an amount of Rs. 293 Crore was sanctioned by GOI, the remaining amount of admissible assistance would be utilised in 2007-08. A sample study of AT&C losses revealed that the implementation of the scheme has resulted in reduction of losses varying from 8 % and to 15%.

Tenth Plan Outlay & Expenditure(Rs. in crore)

Item 2006-07Approved Outlay Expenditure

UPRVUNL 640.21 873.62UPJVNL 75.67 56.19UPPCL 0.00 0.00Transmission & Distribution 2319.46 3441.92Rural Electrification 807.74 649.19APDRP 1043.00 383.62Miscellaneous 2.00 4.36Total UPPCL 4172.20 4479.09THDC 173.96 315.28Grand Total 4888.08 5408.90

Other Activities

[ 177 ]

Page 24: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

More than 25 lakh mechanical meters have been replaced by electronic meters .

Installation of meters on Distribution Transformers in Urban Area started

Double metering of Heavy Power consumers , Ice factories and Cold storage started

Automated Meter Reading of industrial consumers started as Pilot project

AT&C Losses brought down from 52.92 % in 2001-02 to 41.7% during 2006-07.

Eleventh Five Year Plan : 2007-12

79. In order to increase immediate availability of power in the state, it has been decided to invest Rs. 2000.00 crore for refurbishing the machines in power station an this has given encouraging results. An amount of about Rs. 65000.00 crore will be invested in power generation during the 11th Plan Period and 10500 MW additional power would be made available. The investment plan of 11th Five Year Plan is as under:-

Investment Plan for Eleventh Plan (2007-12)

(Rs. In crore)Name of Work Eleventh Five Year Plan

Total Investment

Through Plan Outside Plan

1 U.P. Rajya Vidyut Utpadan Nigam Ltd.a) New Project 36298.12 10485.10 25813.02b) Refurbishment 2617.55 483.25 2134.30c) R&M 990.12 314.20 675.92d) Up-rating Schemes 1502.50 450.75 1051.75e) Work under CREP 521.00 149.30 371.70Total 41929.29 11882.60 30046.69

2 U.P. Jal Vidyut Nigam Ltd.a) New Scheme 153.00 46.00 107.00b) Renovation & Modernisation 377.00 66.00 311.00Total 530.00 112.00 418.00

3 U.P. Power Corporation Ltd.i Transmission Works 10983.95 3225.15 7758.80ii Distribution Works 8971.60 8971.60 -iii APDRP Works 1000.00 1000.00 -iv Energisation of PTW 500.00 500.00 -

Total UPPCL 21455.55 13696.75 7758.804 Tehri Hydro Project 480.93 480.93 -

GRAND TOTAL 64395.77 26172.28 38223.49

Investment Plan including Private Sector during Eleventh Five Year Plan (2007-12)

[ 178 ]

Page 25: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

(Rs. in crore)

Sl. No.

Particular Thermal Generation

Hydro-generation

Transmission Distribution Village Electrification/APDRP/PTW

Total

1 State Funding 11882.60 592.93 3225.15 8971.60 1500.00 26172.282 Central Sector

Funding (Outside Plan)

- - - - 1000.00 1000.00

3 Institutional Finance

30046.69 418.00 7758.80 - - 38223.49

4 Total 41929.29 1010.93 10983.95 8971.60 2500.00 65395.775 R.G.G.V.Y.

(Central Funding)- - - - 8944.00 8944.00

6 IPP's 20600.00 1700.00 - - - 22300.00 Grand Total 62529.29 2710.93 10983.95 8971.60 16072.00 101267.77

Implementation of Franchisees Model:

80. In the area of power distribution, franchisees are being involved in a big way this has resulted on the one hand in substantial improvement in revenue collection an on the other new opportunities for employment of trained youth in the rural areas have opened up. Presentaly deployment of two models of Distribution Franchisiees for revenue collection in rural areas have been implimented as below:-

Collection Based Rural Franchisees:

81. 190 collection based franchisees have been appointed and made operational covering a total of 9169 villages including 1140 RGGVY villages. Further appointment of more franchisees is in progress, Revenue collection efficiency in rural areas allotted to franchisees has improved to 83.82% by January '2008'.

Input Based Rural Franchisees:

82. Appointment of input Based Rural Franchisees is in progress. Two input based Franchisees have been appointed, one for Shravasti district under DISCOM Lucknow, and one for Sikandra district Allahabad under DISCOM Varanasi. The above Franchisees operate in 1096 villages including 446 RGGVY villages. Franchisees for 33 KV Sikandra, Allahabad has been made operational with effect from February '2008' and Franchisees for Shravasti district will be made operational from March '2008'.

DISCOM-WISE detail of collection & input based Rural Franchisees up to January '2008.Sl. Name of DISCOM No. of Total No. of No. of No. of

[ 179 ]

Page 26: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

No. Working Franchisees

Villages Including RGGVY villages

RGGVY Villages

Villages Excluding RGGVY

Collection Based Rural Franchisees1 Agra 61 2871 273 25982 Meerut 27 1650 65 15853 Lucknow 37 2358 373 19854 Varanasi 65 2290 429 1861

Total 190 9169 1140 8029Input Based Rural Franchisees1 Agra 0 0 0 02 Meerut 0 0 0 03 Lucknow 1 576 256 3204 Varanasi 1 520 190 330

Total 2 1096 446 650

Reduction of AT & C Losses

83. The AT& C losses during Financial Year 2005-06 was 43.27% which came down to 40.68% in2006-07 and a further reduction of 4.06% is expected during 2007-08. Although the reduction the AT&C Losses to the level of 15% by the end of 11th Plan is a difficult task. However efforts will be made to achieve the target. Brief details of the actions being taken are as below.

Prevention of theft.

Checking of consumers and lodging of FIRs.

Laying of ABC Conductors- 2006-07 – 2184 KM.

2007-08 – 1578 KM

by end of 11th Plan34000 KM (Target)

Strengthening of Enforcement Squad to carry out effective raids to catch power thieves. – JEs and Inspectors have been authorised to lodge FIRs 35 squads are now in operation .

43 Sub-Divisions identified as pilot projects for .

100% Energy Accounting, Billing, Realisation, Maintenance , Consumer Service and Control of AT&C Losses

Feeder wise Accounting, Transformer level metering, Review of through rate and Energy Audit.

A proposal for issue of directives to all Government Departments to switch over to CFL lighting is under consideration of the Government.

Launching of Consumer Helpline to register complaints and grievances.

[ 180 ]

Page 27: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Guarantee Period for all transformers enhanced from 1 year to 3 years to ensure quality.

Transformers at Stores Centre are checked before accepting delivery.

All Distribution Transformers are being metered which is expected to be completed by Dec.2008. At present out of 4050999 Transformer 16200. are metered. Out of them, 10145 are electronic meters with communication facility.

Recovery per unit of input has increased by Rs. 0.12 P/U without any tariff increase.

To regularise the Katiya Connections new scheme has been launched in which initial payment for regular connection is only Rs. 250.

Appointment of Collection Franchisees in Rural Areas has been done covering approx 9100 villages which has led to collection efficiency of 79% in rural area & have also brought in 11657 new connections. The target is cover the total rural area by end of 11 th Plan, by collection franchisees. .

Appointment of two pilot Input Based Rural Franchisee in Srawasti and Sikandara.

Effective recovery of Government overdues of previous year & 100% realisation of current dues.

Increase in PLF

84. It is targeted to increase the PLF of generating units from 60% to 85% and reduce line losses to 15% by the end of 11th Five Year Plan.

(A) Thermal Generation

85. During the 11th Plan, UPRVUNL has planned to construct new Thermal Power Projects as detailed below :

Name of Thermal power project Installed/proposed

capacity in MW

Benefits in 11th

Plan(Capacity Addition)

Benefits in 12th Plan(Capacity Addition))

A IN STATE SECTOR

1 2x210 MW Parichha Thermal Power project 420 MW 210 MW2 2x250 MW Parichha Thermal Power project 500 MW 500 MW3. 2x250 MW Harduaganj Thermal Power project 500 MW 500 MW4 2x500 MW Anpara ‘D’ Thermal Power project 1000MW 1000 MW

5 2x800 MW Anpara ‘E’ Thermal Power project 1600 MW ….. 1600MW

6 2x800 MW Obra Thermal Power project 1600 MW 1600 MW7 2x500 MW Matatila Thermal Power project 1000 MW 1000

MW

8 1x250 MW Panki Thermal Power project 250 MW 250

[ 181 ]

Page 28: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Name of Thermal power project Installed/proposed

capacity in MW

Benefits in 11th

Plan(Capacity Addition)

Benefits in 12th Plan(Capacity Addition))

MW9 Meja Thermal Power Project (Joint venture with

NTPC (2x660 MW)1320MW 1320

MW10 Ultra Mega Power Project at Bundelkhand

Region4000MW

Annual Plan 2007-08

86. The energy sector still requires major reforms all over the country and U.P. is not an exception. We still need to improve our plant load factor, check on theft of electricity, reduce T&D losses, implement consumer identification through GIS, ensure proper billing and consumer services, which includes quantitative and reliable power supply & fulfillment of quantitative requirement.

Plan outlay and anticipated expenditure for the annual Plan 2007-08 is given below (Rs. in lacs)

Particulars Outlay from Budget support

Internal Resource

Total Outlay Anticipated Expenditure

UPRVUNL 100600.00 1465.00 102065.00 102065.00UPJVNL 1100.00 50.00 1150.00 1150.00UPPCL

1 Transmission 36536.52 5843.00 42379.52 42379.522 Distribution 92300.00 92300.00 92300.003 PTW 5000.00 5000.00 5000.004 APDRP 20000.00 20000.00 4087.005 Shell Company 5000.00 5000.00 5000.006 Joint Venture with NTPC 2000.00 2000.00 2000.007 Dr. Bheem Rao Ambedkar Gram

Sabha Vikas Yojna37700.00 37700.00 37700.00

8 Dr. Beem Rao Ambedkar Samajik Parivartan Sthal

770.86

  TOTAL : UPPCL 198536.52 5843.00 204379.52 250637.38THDC 10000.00 10000.00 10000.00GRAND TOTAL 310236.52 7358.00 317594.52 363852.38

Generation - Thermal

87. Fourth unit of Parichha TPS of 1x210MW has been put on trial run and will achieve commercial load.

Co-generation

[ 182 ]

Page 29: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

88. Total capacity of power arrangement from co-generation will be 850MW by March,2008 with an addition of 500MW in 2007-08.

Physical Targets and Tentative Achievements for Annual Plan 2007-08Transmission Works

Item Unit Target Anti. Achievement

A. Construction of Transmission Lines    

  400 KV Lines CKT Km.

  220 KV Lines CKT Km. 125.00 125.00

  132 KV Lines CKT Km. 1275.00 1275.00

B. Construction of New Sub-stations    

  400 KV Nos (MVA)  

  220 KV Nos (MVA) 8/1800 8/1800

  132 KV Nos (MVA) 25/800 25/800

C. Augmentation of Sub-stations      400 KV Nos (MVA)  

  220 KV Nos (MVA) 10/680 10/680

  132 KV Nos (MVA) 33/700 33/700

Distribution WorksDescription of works Unit Target Anti. Achievement

A : 33 KV Works  (i) New 33 KV Lines Ckt. Kms 1500 1500(ii) New 33 KV Sub-Stations Nos./MVA 150/900 150/900(iii) Augmentation of Sub-Station Nos./MVA 200/600 200/600

B : 11 KV & LT Works  (i) 11 KV Lines Ckt. Kms 3000 3000(ii) L.T. Lines Ckt. Kms 1000 1000(iii) Distribution S/S (New) Nos./MVA 2000/200 2000/200(iv) Distribution S/S (I/C) Nos./MVA 2000/350 2000/350(v) Installation of 11 KV Capacitors MVAR 200.00 200.00

RE works

Description of works Unit Target2007-08

AnticipatedAchievement

Electrification of villages Nos. 4720 4720Energisation of PTWs No. 20000 20000

[ 183 ]

Page 30: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Annual Plan 2008-09

89. The XI Plan places emphasis on creation of new generation capacity and reduction in T&D losses. The State has already taken steps for adding generation capacity of 10000 MW during the 11th Plan period.

Thermal Generation

State Sector

2x250 MW Parichha TPS Extn. – Work in Progress.

2x250 MW Harduaganj TPS Extn. – Work in Progress.

2x500 MW Anpara-D TPS – LOI for BOP has been issued.

Joint Sector

2x660 MW Meja Themal Power Station in Distt. Allahabad in joint venture with NTPC for which MOU has been signed.

We have planned to start activity for 2x800 MW capacity Thermal Power Station in Obra in joint venture with BHEL.

Plan to setup 4000 MW Ultra Mega Power Project in Bundelkhand region.

Private Sector

2x300 MW Roja TPS – Work in Progress.

4x82.5 MW Srinagar Hydro – Work in Progress.

2x500 MW Anpara-C TPS – Work in Progress.

3x660 MW Bara TPS – RFP being sold and LOI will be issued by March '08

2x660 MW Karchhana TPS - RFP being sold and LOI will be issued by March '08

Proposed R & M Schemes –

90. The following new Refurbishment/ R&M/ /up-rating schemes are proposed to be taken up during 11th Five year plan .

Name of the Scheme Estimated Cost (Cr.Rs )a Refurbishment Scheme

Anpara 'A' 3x210 MW 787.50

[ 184 ]

Page 31: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

b R & M Schemes(i) Anpara 'B' 2x500 MW(ii) Harduaganj (2x55 +1 x 60) MW

750.00144.00

c Up-rating Schemes(i) Panki (from 2x110 MW to 2x120 MW)(ii) Parichha (from 2x110 MW to 2x120 MW)(iii) Obra (from 3x100 MW to 3x120 MW)(iv) Harduaganj (from 1x110 MW to 1x120 MW)

440.00440.00600.00220.00

Transmission Works

Normal Development Works

91. Due to increase in demand of electricity some of the sub-stations/lines are overloaded. To meet this increasing demand it is essential to increase the capacity of the sub-stations and to create new sub-stations and lines.

Power Evacuation Works

Evacuation Of Power From Roza Thermal Power Station (2x300 Mw)

(i) 220 KV Switchyard at Roza P.H.

(ii) 220 KV DC Transmission line Roza – 220 KV S/s Shahajahanpur(25 Kms.).

(iii) 220 KV DC Transmission line Roza – 220KV S/s Hardoi (80 Kms.).

(iv) 220 KV DC Roza – Common point – 90 Kms.

220 KV SC Common point – C.B. Ganj – 2 Kms.

220 KV SC Common point – Dohna – 12 Kms.

(v) 220 KV S.C. Transmission line Roza-Badaun – (90 Kms.).

Evacuation Of Power From Anpara 'C' (2x500 Mw) & Anpara 'D' (2x500 Mw) Thermal Power Project

(i) 765 KV SC Anpara-C – Unnao line (presently charged at 400KV) to be operated at its rated voltage i.e. 765 KV

(ii) Construction of 400 KV S/s Allahabad.

(iii) LILO of existing 400 KV S/s Obra – Panki line at Allahabad 400 KV S/s.

(iv) 1x1000 MVA, 765/400 KV ICT at Anpara 'C'.

(v) 1x1000 MVA, 765/400 KV ICT at Anpara 'D'.

(vi) 400 KV SC interconnector between Anpara 'C' & Anpara 'D'.

(vii) 765 KV SC interconnector between Anpara 'C' & Anpara 'D'.

(viii) 765 KV SC Anpara 'D' – Unnao line.

(ix) 400 DC interconnector between Allahabad and Allahabad (PG).

[ 185 ]

Page 32: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

(x) 3x1000, 765/400 KV ICT at Unnao.

(xi) 400 KV Unnao – Baghpat D/C line.

Parichha (2x250 Mw) Thermal Power Station

(i) 400 KV Switchyard at Parichha P.H.

(ii) 400 KV DC transmission line

PCH-400KV Aligarh S/s (newly proposed) – 350Kms.

Harduganj Extn. (2x250 Mw) Thermal Power Station

220 KV DC Transmission line Harduaganj P.H. -400KV S/s Aligarh (30Kms).

Srinagar Hydro Power Station (IPP) (4x82.5 MW)

(i) LILO of both circuits of 400KV DC Vishnuprayag-Muzaffarnagar line at Srinagar

400KV S/s.

(ii) 2x315 MVA transformer at 400/200 KV S/s Kashipur.

(iii) LILO of 400KV SC Moradabad-Rishikesh line at Kashipur 400KV S/s.

(iv) 400 KV SC Srinagar-Kashipur line.

Evacuation System for BARA TPS (3x660 MW) Meja Road TPS (2x660MW), Karchhana TPS (2x660MW)

(i) 765 Switchyard at Meja P.H.

(ii) 765 KV Switchyard at Bara P.H.

(iii) 400 KV Switchyard at Karchhana P.H.

(iv) 765 transmission lines : (S.C.) from Meja Road – 765KV S/s Hapur S/s (newly proposed).

(v) 765KV Transmission lines (S.C.) from Bara Road – 765 KV Fatehpur S/s (proposed by PGCIL)

(vi) 400 KV D.C. Transmission line from Karchhna – Meja

(vii) 765 KV S.C. Bara – Meja

(viii) 400 KV D.C. Transmission line from Karchhna – Reewa Road Allahabad

(ix) 400 KV D.C. Rewa Road – 765 KV Unnao S/s.

(x) 765 KV Transmission Line (S.C.) Bara to Hapur

Power Evacuation System for Obra TPS Extn. (2x800 MW)

(i) 400 KV switchyard for Obra Extn.

(ii) 400 KV DC Obra – 400 KV S/s Sultanpur (240 Kms.).

92. The proposed total capacity of Obra TPS will be about 3150 MW (1600 MW future + 1550 MW present installed capacity). Hence a plan for construction of 765KV Yard at Obra TPS is being considered. For which LILO of 765 KV Sasaram – Fatehpur (PG) line is proposed.

[ 186 ]

Page 33: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Evacuation System for Tanda Extn. TPS (2x500 MW)

(i) 400 KV Switchyard at Tanda P.H.

(ii) 400 KV DC Transmission line Tanda P.H. – 400KV S/s Sohawal newly proposed (80 Kms.).

(iii) LILO of 220 KV DC Tanda – Sultanpur line at New proposed 220 KV S/s Tanda.

Secondary Transmission and Distribution Works (66 KV and below)

93. In order to provide effective and reliable power supply, development of requisite network of Secondary Transmission & Distribution is of paramount importance. It is from this network majority of electricity connections are given. This network constitutes a vital link between Extra High Voltage Transmission (132 KV & above) and the ultimate consumers. Therefore, for maintaining satisfactory supply strengthening of this vital link commensurate with the growth in load assumes importance.

94. With the introduction of 220 KV & 400 KV primary transmission the role of 66 KV network has been relegated to secondary transmission and as such with a view to optimise the system network further expansion of 66 KV & 37.5 KV network in UP Power System was discontinued and 33 KV system has come to stay as main secondary system. The 66 KV network existing in some districts is being continued but further expansion is being undertaken on 33 KV only. At present the distribution system which is heavily loaded for providing reliable & un- interrupted supply to the consumers has to be strengthened for which various works have been proposed.

Status Of Under-Construction / Proposed Thermal Power Stations

95. During the year 2008-09, the State Govt has allocated an outlay of Rs.2018.70 crores for UPRVUNL, which is inclusive of Rs 18.70 crores which are to be generated through internal resources. The status of various thermal power projects which have been planned/under construction by U.P.Rajya Vidyut Utpadan Nigam Ltd is as follows.

(1) 2x210 MW Parichha Extension Thermal Power project –

96. Two units of 210 MW each are being installed in this project. The I st unit of 210 MW has already been commissioned and is running on commercial load from 24.11.2006. The IInd unit of 210 MW has been synchronized on 28.12.2006 and is running under trial. After removing a few deficiencies it is likely to be put on commercial load shortly.

(2) 2x250 MW Parichha Thermal Power Extension Project

97. Two units of 250 MW each are being installed under this project. Letter Of Acceptance (LOA) for purchase of Boiler, Turbine and Generator including erection, testing and commissioning along with related civil works has been placed with M/s BHEL . The zero date for the project was 04.08.2006. The 1st unit is scheduled to be completed in July, 2009. The 2nd Unit is proposed to be completed in Nov., 2009.

[ 187 ]

Page 34: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

98. The balance works of Plant and chimney have also been awarded on open tender basis in Jan and June, 2007 respectively. The tender case for Switchyard work is under process. The estimated cost of the project is approximately Rs. 1900 crore., 30% of which shall be UP Govt. Equity (i.e. Rs. 570 cr). Out of this equity., Rs 307.00 cr has been allocated upto 2007-08. Out of this an amount of , Rs. 197.80 cr. is poposed during the financial year 2008-09 and Rs.10.70 cr. shall be met through internal resources.

(3) 2x250 MW Harduaganj Thermal Power Extension Project

99. Two units of 250 MW each are being installed in this project. Letter Of Acceptance (LOA) for purchase of Boiler, Turbine and Generator including erection, testing and commissioning along with related civil works for BTG have been placed with M/s BHEL . The zero date for the project was 07.09.2006. The Ist unit and IInd unit are proposed to be commissioned in October, 2009 and Feb.,2010 respectively. The work of chimney has been awarded on 01.06.2007. Regarding the balance works of Plant, the tenders for Transformer and Natural Draft Cooling Tower, CW Pump equipment, EOT Crane, water treatment plant, HT switchgear and Coal handling Plant have been opened and the process for remaining packages is under progress. The estimated cost of the project is approximately Rs. 1900 cr., 30% of which shall be State Govt. Equity (i.e. Rs. 570 cr). Out of this equity., Rs 300.00 cr has been allocated upto 2007-08. Out of above mentioned, amount Rs.142.00 cr. is proposed during the financial year 2008-09 and Rs. 8.00 cr. shall be met through internal resources.

(4) 2x500 MW Anpara ‘D’ Thermal Power project

100. Two units of 500 MW each are being installed in this project LOI has been placed by UPRVUNL on BHEL for construction of BTG package including its related civil works and part of BOP works amounting Rs. 3390.00 crore (inclusive of taxes & duties). The zero date of the work shall be the date of release of 15% advance. The time of completion of the two units is 39 & 42 months respectively from for the zero date. Long term coal-linkage from NCL for this project has also been sanctioned by Ministry of Coal , Govt. of India on 29.08.2007. The feasibility report on the MGR for coal transportation system has been submitted by the consultants M/s RITES (Railways India Technical and Economical Services) in Sept., 2007. The estimated cost of the project is approximately Rs. 5358 Cr., 30% of which shall be UP Govt. Equity (i.e. Rs. 1607.4 cr.). Out of this equity., Rs 417.90 Cr has been allocated upto 2007-08. NCL is interested in sharing the UP Govt. equity in the project on 50:50 basis in a joint venture with UPRVUNL, with overall control of the latter. A proposal in this regard is under consideration of the State Govt. Thus in case of approval of the JV proposal, the equity of UP Govt. will be only Rs 803.70 crore instead of Rs 1607.40 crore. Out of above mentioned, equity portion an outlay of Rs. 386.00 cr. is proposed during the financial year 2008-09 .

(5) 2x800 MW Anpara ‘E’ Thermal Power project

101. Two units of 800 MW each are proposed to be installed in this project The requisite land is available near Anpara thermal power Station complex. The land is in possession of UPRVUNL. The draft feasibility report has been prepared by JETRO (Japan External Trade Organization.). Water for this project

[ 188 ]

Page 35: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

is proposed to be drawn from Rihand Reservoir. The estimated cost of the project is Rs 7780.00 crore (excluding IDC). It is expected to be proposed to JBIC for funding. A proposal to this effect was put up to Energy Task Force for approval which suggested that a meeting of UP Finance Deptt., Externally Aided Projects Deptt. and UPRVUNL may be convened to work out the modalities of loaning for this project. The meeting is being convened by Finance Deptt shortly. During the financial year 2008-09 no finance is required for this project.

(6) 2x800 MW Obra Extn. Thermal Power project

102. Two units of 800 MW each are proposed to be installed in this project The required land for this project is already in possession of UPRVUNL.Coal Block (Chendipada) has been allotted for the new units of Obra Extn. by Ministry of Coal, Govt of India. Coal linkage for one unit has also been allocated by the Ministry.

103. It was decided by Energy Task Force on 07.08.2007 that instead of initially envisaged two units of 500 MW each , two units of 800 MW (supercritical) may be considered for installation. BHEL is interested in installation of the 2x800 MW units under a Joint Venture with Utpadan Nigam. A preliminary feasibility report on the layout of the proposed plant has been submitted by BHEL on 16.12.2007 The units are proposed to be installed in the 11th five year plan.

104. The process for obtaining Environmental clearance from MOEF for the new proposed 2x800 MW units is in progress.The tentative estimated cost of the project is approximately Rs. 7800 cr., 30% of which shall be UP Govt. Equity (i.e. Rs. 2340 cr.). Out of above mentioned, equity portion an outlay of Rs. 500.00 cr. is proposed during 2008-09 .

(7) 2x500 MW Matatila Thermal Power project

105. This project is in conceptual stage and its site selection is to be done for which a committee has been constituted.For preliminary expenditures like feasibility study etc., An outlay of Rs 5.00 cr is proposed during the financial year 2008-09.

(8) 1x250 MW Panki Thermal Power project (Total 250 MW)

106. Final feasibility report has been prepared by M/s NTPC. The preparation of DPR will be taken up after obtaining the clearances from UP Pollution control Board and MOEF. An outlay of Rs 5.00 cr is proposed during the financial year 2008-09 for the above project.

(9) 2x660 MW Joint Venture with NTPC

107. A 2x660 MW Thermal Power Project is being set up in tehsil Meja, Distt-Allahabad under joint venture with NTPC. The MOU for the same has been signed between UPRVUNL / U.P.Govt. and NTPC

[ 189 ]

Page 36: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

on 22 Nov.,2007. As per the decision of G.O.I. Ministry of Power, 75% of power from this project will be allocated to U.P. Meanwhile, according to a tentative programme submitted by NTPC, the activities of land acquisition, site leveling etc. would take about 20 -22 months before award of the main plant. The units would be completed and put on commercial load in 54 months after the zero date. The estimated cost of the project is Rs 7200.00 crores Out of which an outlay of Rs. 424.00 cr. is being proposed during the financial year 2008-09

Refurbishment / Renovation Of Existing Projects

108. At present the cost of construction of a new thermal power station comes to about Rs. 4 crores per MW whereas the cost of Renovation & Modernization of the old Power Station comes to Rs. 0.8 to 1.25 crore per MW depending upon the period the units have already run and the condition of the power stations. Due to acute shortage of resources for new power plants, Govt. of India encouraged the Renovation & Modernization work in all the existing plants to improve their performance. Physical status of various R&M/Refurbishment Schemes of UPRVUNL is given below :

(A) Refurbishment Schemes

1) Refurbishment of 5x50 MW Units of Obra ‘A’ TPS:

109. Refurbishment work of unit No.1 & 2 is being executed under this scheme. Unit no.2 has been put on load on 28.11.2007 and the same is likely to be stabilized shortly . Unit no.1 is expected to be completed in January, 2008. After completion of the refurbishment works of units 1 and 2, an additional generation capacity of 100 MW will be available with 15 years life extension of these units. The estimated cost of the project is approximately Rs. 486.40 cr., no finance is involved from the State Govt. during the financial year 2008-09.

2) Refurbishment Schemes of 5x200 MW units of Obra ‘B’ TPS:-

110. The Refurbishment work of units of 5x200 MW units of Obra ‘B’ TPS has been awarded to M/s BHEL in May, 2006. The contract agreement between UPRVUNL and M/s BHEL for the above work has been signed on 21.02.2007. The zero date of the work is 20.06.2006. The work is expected to be completed in 30 months from the zero date i.e. by 19 Dec., 2008. It is proposed to provide rotor of high-class design for the turbine of these units which would result in increasing the capacity of these units (each) from 200MW to 216 MW. After completion of the refurbishment work, an additional generation capacity of 1080 MW will be available with 15 years life extension of these units.The estimated cost of the project is approximately Rs. 1635 crore, The amount of State Govt. Equity is Rs. 327.00 crore. Out of this equity, Rs 245.00 cr has been allocated upto the year 2007-08. An outlay of Rs 72 Cr is proposed for the year 2008-09.

(B) Renovation & Modernisation Schemes -

Work of R&M schemes of Harduaganj TPS units No. 5&7 is being executed under the Accelerated Generation and Supply Programme of G.O.I. Work on unit no. 7 (110 MW) has

[ 190 ]

Page 37: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

been completed and Unit No. 5 (60 MW) is expected to be completed by the end of 2007-08. After re-commissioning of the unit 5, an average PLF of 53% from these units is expected to be achieved (earlier it was 31% ). No finance is involved from the State Govt during the financial year 2008-09 for this scheme.

Work on R&M scheme-II for Anpara ‘A’ TPS (3X210 MW) is under progress. Works under this Scheme are expected to be completed by 31.03.2008. After completion of the scheme, PLF of these units is expected to be sustained at 79%. No finance is required from State Govt during the financial year 2008-9 for this scheme.

Work against R&M scheme for unit no. 6 (100 MW) of Obra ‘A’ TPS is under progress. M/s PFC have sanctioned required loan and loan agreement has been signed with PFC. The Scheme is proposed to be completed shortly. After completion of this scheme, PLF of the unit is expected to improve from 35% to 60%. No finance is required from the State Govt. during the financial year 2008- 09 for this scheme.

(C) Proposed R & M Schemes –

1. Refurbishment scheme of 3x210 MWunits of Anpara A TPS

111. It is proposed to refurbish unit no. 1,2 &3 each of capacity 210 MW of Anpara 'A' TPS during 11th five year plan . This scheme is expected to completed with in 30 months from zero date . The estimated cost of the scheme is Rs. 787.50 crore , out of which 70 % is proposed to the arranged from financial institution and remaining 30 % as equity from the State Government. Out of above mentioned outlay, Rs . 23.00 crore is proposed during the financial year 2008-09 .

2. R&M scheme 2x500 MW units of Anpara B TPS

112. It is proposed to carryout R&M on unit no. 4 and 5 each of capacity 500 MW of Anpara B TPS during 11th five year plan . This scheme is expected to the completed in 30 month from the zero date. The estimated cost of the scheme is Rs. 750.00 crore , out of which 70 % is proposed to the arranged from financial institution and remaining 30 % as equity. Out of above mentioned, an outlay of Rs. 22.00 crore is being proposed during the financial year 2008-09 .

3. Uprating scheme of 2x110 MW units of Parichha TPS

113. It is proposed to uprate the capacity of Unit 1 and 2 of Parichha TPS each from 110 to 120 MW during 11th five year plan. This scheme is expected to the completed in 28 month from the zero date . The estimated cost of the scheme is Rs. 440.00 crore , out of which 70 % is proposed to the arranged from financial institution and remaining 30 % as equity. Out of above mentioned, an outlay of Rs. 60.00 crore is being proposed during the financial year 2008-09 .

4. Uprating scheme of 3x100 MW units of Obra TPS

[ 191 ]

Page 38: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

114. It is proposed to up rate the capacity of units no. 6,7 & 8 of Obra TPS each from 100 MW to 120 MW during 11th five year plan . This scheme is expected to the completed in 30 month from the zero date. The estimated cost of the scheme is Rs. 600.00 crore , out of which 70 % is proposed to the arranged from financial institution and remaining 30 % as equity. Out of above mentioned, an outlay of Rs. 60.00 crore is being proposed during the financial year 2008-09 .

5. Uprating scheme of 1x100 MW units of Harduaganj TPS

115. It is proposed to uprate the capacity of unit no. 7 of Harduaganj TPS from 110 to 120 MW during 11th five year plan. This scheme is expected to the completed in 22 month from the zero date. The estimated cost of the scheme is Rs. 220.00 crore , out of which 70 % is proposed to the arranged from financial institutions and the remaining 30 % as equity. Out of above mentioned, an outlay of Rs. 60.00 crore is being proposed during the financial year 2008-09 .

(D). Action Plan under CREP (Corporate Responsibility for Environmental Protection)

116. An action plan for various works under CREP required to be executed at Anpara, Obra, Panki, Parichha and Harduaganj Thermal Power Stations for meeting the various norms fixed by Central Pollution Control Board (CPCB), New Delhi amounting to Rs. 532.00 Crores have been approved by UPRVUNL Board of Directors. Works amounting Rs. 152.00 Crores in respect of Obra B (5X200 MW) are included in the refurbishment scheme for which approval has been given by the State Govt. This work has been awarded to BHEL The action plan includes mainly following works at all the Thermal Power Stations –

Up-gradation of ESPs for meeting the emission norms of 100 mg/Nm3 .

Installation of dry fly ash extraction plant .

Installation of opacity meter with online recording facility.

Water Recirculation System.

117. These works are proposed to be completed by Dec. 2008. Total cost of work is Rs. 532.00 Crore including the works amounting Rs 152.00 crores of Obra (5X200 MW). PFC has agreed in principle to provide 70% of the above cost. There will be indirect benefit towards improvement in the generation as the standards fixed by the Central Pollution Control Board are achieved these works. It will improve the environment of the power stations and its surrounding area.

Works Proposed Under CREP . Name of work Amount to be invested

during 2008-09 (Cr.Rs.)

1 Installation of new ESP’s of Parichha ( 2x110 MW) & Harduaganj ( 3,5,&7 units )

97

2 Installation of new ESP of ( 3x100 MW) Obra thermal power station 353 Installation of effluent treatment plant for Obra thermal power station 44 Installation of zero discharge system for Anpara thermal power station 5

[ 192 ]

Page 39: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

5 Installation of sewage treatment plant at Harduaganj 3Total 144

118. Out of this 144 crore, Rs. 43.2 crore is being proposed during 2008-09 and remaining (Rs. 100.8 crore ) will be arranged from financial Institutions .

119. The status of the said /proposed works are as under :-

Installation of new ESP’s of Parichha ( 2x110 MW) & Harduaganj ( 3,5,&7 units ). The work has already been approved and is in progress. It is proposed to be completed by April 2009.

Installation of new ESP of ( 3x100 MW) Obra thermal power station has been sent to Energy Task Force and approval is awaited.

The DPR for installation of effluent treatment plants for Obra Thermal Power Station has been received from consultant and is being examined. The work is proposed to be completed by March 2009.

Appointment of consultant is under process for installation of zero discharge system for Anpara Thermal Power Station..

Fresh offer for consultancy work is being obtained from IIT Roorkee for installation of Sewage Treatment Plant at Harduaganj.

Hydro Generation

120. During the year 2008-09, the renovation & modernization works already taken up at Rihand (300 MW), Obra (99 MW) & Matatila (30 MW) will continue. Since, State Government share for R&M works of Rihand Power Station has already been provided, no outlay is now being proposed for these works. For R&M works of Obra an outlay of Rs.200.00 lacs and for R&M works of Matatila an outlay of Rs. 100.00 lacs have been proposed. For R&M works of Power Houses situated on U.G.C. an outlay of Rs. 750.00 lacs has been proposed for initial construction activities of new power stations nearby the existing locations, with higher capacities (Nirgazini – 7 MW, Chittaura – 5.5 MW, Salawa – 4.5 MW & Bhola – 5.0 MW). Accordingly, a total outlay of Rs. 1150.00 lacs has been proposed for the year 2008-09 for above mentioned activities by U.P. Jal Vidyut Nigam Ltd.

Physical Targets for Annual Plan 2008-09Transmission Works

Item Unit TargetA. Construction of Lines    400 KV Lines CKT Km. 225.00  220 KV Lines CKT Km. 868.00

  132 KV Lines CKT Km. 502.5B. Construction of New Sub-stations   400 KV Nos (MVA)  

[ 193 ]

Page 40: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

  220 KV Nos (MVA) 8/1880  132 KV Nos (MVA) 17/740C. Augmentation of Sub-stations   400 KV Nos (MVA)  2/390  220 KV Nos (MVA) 15/930

  132 KV Nos (MVA) 49/1169.5Distribution Works

Description of works Unit Target 2008-09

A : 33 KV Works  

(i) New 33 KV Lines Ckt. Kms 1680.00

(ii) New 33 KV Sub-Stations Nos./MVA 150/750

(iii) Augmentation of Sub-Station Nos./MVA 250/750

B : 11 KV & LT Works  

(i) 11 KV Lines Ckt. Kms 1200.00

(ii) L.T. Lines Ckt. Kms 500.00

(iii) Strengthening of 11 KV Kms. 1000.00

(iv) Strengthening of L.T. lines by Aerial Bunched Conductor

Kms. 9500.00

(v) Distribution S/S (New) Nos./MVA 1000/250

(vi) Distribution S/S (I/C) Nos./MVA 3000/375

(vii) Installation of 11 KV Capacitors MVAR 42.00

(viii) Renovation and modernization of switchgear (11KV switchgear)

Nos. 2000

(ix) Sectionalizing of Rural and Urban feeder for system improvement. Segregation of rural (domestic, commercial & industrial load from PTW & state tubewell) loads in 70 districts.

No. of districts 8

APDRP

121. Restructured APDRP scheme for improvement of distribution system including reduction in AT& C loses has been framed by GOI for which an outlay of Rs 100 crores has been proposed during 2008-09. The scheme will be implemented after detailed guidelines are notified by GOI.

Investment Plan for - 2008-09

Cr. Rs. Name of Work Annual Plan 2008-09

Total Investment Through Plan Outlay

Outside Plan

[ 194 ]

Page 41: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

1 U.P. Rajya Vidyut Utpadan Nigam Ltd.10528010219000a) New Project 2994.50 1678.50 1316.00b) Refurbishment 1010.00 95.00 915.00c) R&M 101.36 22.00 79.36d)Up-rating Schemes 600.00 180.00 420.00e) Work under CREP 144.00 43.20 100.80Total 4849.86 2018.70 2831.16

2 U.P. Jal Vidyut Nigam Ltd. 10528010119000a) New Scheme - - -b) Renovation & Modernisation

110.50 11.50 99.00

Total 11.503 U.P. Power Corporation Ltd. 10528010500000i Transmission Works 1880.00 516.14 1363.86ii Distribution Works 1841.45 1841.45iii APDRP Works 100.00 100.00iv Energisation of PTW 110.00 110.00V Shell Company 20.00 20.00

Total : UPPCL 3951.45 2587.59 1363.864 Tehri Hydro Project 15.40 15.40

GRAND TOTAL : 8927.21 4633.19 4294.02

Rural Electrification

122. Under RVGGY, the work started in 2005-06 in UP and 26364 villages have been electrified against the target of 28879 villages. The DPRs sanctioned by REC for these works were on the basis of scheduled rates of 2004-05, whereas the awarded cost of works came to Rs. 3407.23 crore. Revised DPR’s have been submitted to REC . Till date only Rs. 2335 crore has been released by REC . Due to Non – Sanction of revised DPR’s the funds are not being released by REC which has affected the progress of village electrification work specially the following works are adversely affected :

Electrification of un-electrified hamlets

Strengthening of Distribution system in the villages being electrified under RGGVY for providing electricity to all BPL household

Electrification of the villages electrified as per Old CEA definition1

Conversion of villages/hamlets electrified prior to 31st March 2005 from Low Tension mains system to High Voltage Distribution System/aerial bunched conductor

1 A village will be deemed to be electrified if electricity is used in the inhabited locality within the revenue boundary of the village for any purpose whatsoever

[ 195 ]

Page 42: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Providing electricity to all rural households including free connection to Below Poverty Line households

Strengthening of Rural electricity Distribution Backbone in those villages electrified earlier and covered by RGGVY

Electrification of remote stand alone villages

Creating infrastructure for providing electric connections to common rural facilities like schools, PHC, Gram panchyats

Electrification of un-electrified hamlets

123. UP has about 1.62 lakhs of hamlets. The total cost of electrification of 0.84 lakh un-electrified hamlets works out to Rs 4,203 crores as per the following details:-

Discom Total No of Hamlets

Already Electrified

No of Hamlets to be electrified

Total cost of hamlets (Cr Rs.)

Meerut Discom 1,802 0 1,802 90

Agra Discom 20,197 15,676 4,521 226

Lucknow Discom 65,932 27,541 38,391 1,920

Varanasi Discom 74,034 34,697 39,337 1,967

UP 161,965 77,914 84,051 4,203

Strengthening of Distribution system in the villages being electrified under RGGVY for providing electricity to all BPL households

124. UP would require Rs 577 crores for electrifying all BPL households in the 28,830 villages covered under RGGVY program as per details given below:

Discom RGGVY villages Investment (Rs Crs)

Meerut Discom 1,910 38Agra Discom 5,238 105Lucknow Discom 9,903 198Varanasi Discom 11,779 236UP 28,830 577

125. At present total nos 39436 BPL households have been connected. The cost of given connection is approx Rs. 2450 per connection against Rs. 1500 per connection being provided by REC. This has resulted

[ 196 ]

Page 43: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

in uncovered expenditure of Rs. 37.01 crore. This discrepancy needs to be removed for achieving the target.

Electrification of the Villages Electrified as per Old CEA Definition2

126. As per old CEA definition there are about 9,721 villages to be electrified as per the new norms. The electrification of these villages would require about Rs 680 crores.

Discom Villages electrified as per CEA which need electrified as per

RGGVY definition

Investment(Rs Crs)

Meerut Discom 687 48 Agra Discom 358 25 Lucknow Discom 1,543 108 Varanasi Discom 7,133 499 UP 9,721 680

Conversion of villages/hamlets electrified prior to 31st March 2005 from Low Tension mains system to High Voltage Distribution System

127. In UP the total number of villages to be electrified under grid system are 97,792 out of which the village electrified prior to 31st March 2005 were 59,241. These 59,241 villages have been electrified prior to RGGVY program. In this revenue village its intervention near by one hamlet was electrified by laying LT mains. To convert from the LT system to HVDS, UP would require Rs 4,147 crores.

128. The table below depicts Discom wise investment requirement:Discom Villages Electrified

as on 31.03.05Investment for Villages +

Hamlets (Rs crs)

Meerut Discom 8,247 577Agra Discom 10,438 731Lucknow Discom 17,638 1,235Varanasi Discom 22,918 1,604UP 59,241 4,147

Providing electricity to all rural households including free connection to Below Poverty Line households

129. Total number of BPL household in UP is around 100.3 lakhs. Only 28% of the BPL household are electrified or covered under RGGVY Scheme. For providing free electricity connection to 72.2 lakh BPL households, UP would require Rs 2,166 crore.

Discom Total no of BPL Total no of BPL to be Total cost2 A village will be deemed to be electrified if electricity is used in the inhabited locality within the revenue boundary of the village for any purpose whatsoever

[ 197 ]

Page 44: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

household (Lakhs) electrified (Lakhs)Meerut Discom 6.5 5.1 152Agra Discom 17.9 13.0 391Lucknow Discom 40.4 29.0 869Varanasi Discom 35.5 25.1 754UP 100.3 72.2 2,166

Strengthening of Rural electricity Distribution backbone

130. For strengthening of rural electricity distribution backbone, UP would require Rs 1,800 Crore Discom Total cost (Rs Crs)

Meerut Discom 77Agra Discom 133Lucknow Discom 645Varanasi Discom 945UP 1,800

Electrification of Remote Stand Alone Villages

131. Solar energy and Bio fuel energy are being used for electrifying the stand alone remote villages, UP would require above Rs 30 Crores. This work is to executed thorough Non Energy Department.

Modernisation of RE Infrastructure

132. As achieve universal access to electricity for all households by 2012 and modernising the rural electricity infrastructure the total outlays for the rural electrification plan works to Rs 13, 603 crores. The task wise fund requirement is estimated as under:

Sl. No

Tasks Total Investment (Rs Crs)

1 Electrification of un-electrified hamlets 4,2032 Strengthening of Distribution system under RGGVY for providing

electricity to all BPL household577

3 Electrification of the villages electrified as per CEA 6804 Conversion of villages/hamlets electrified from LT mains to HVDS 4,147

5 Providing electricity to all rural households including free connection to BPL households

2,166

6 Strengthening of Rural electricity Distribution backbone 1,800

7 Electrification of remote villages (Stand alone) 30

[ 198 ]

Page 45: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

  Total Outlays 13,603

Work Plan:

Task 1st years

2nd years

3rd years 4th years 5th years Total Outlays

Electrification of un-electrified hamlets

841 841 1,261 1,260 - 4,203

Strengthening of Distribution system under RGGVY for providing electricity to all BPL household

- 289 288 - - 577

Electrification of the villages electrified as per CEA

- 340 340 - - 680

Conversion of villages/hamlets electrified from LT mains to HVDS

- 829 829 1,244 1,245 4,147

Providing electricity to all rural households including free connection to BPL households

- 433 433 650 650 2,166

Strengthening of Rural electricity Distribution backbone

180 540 540 540 - 1,800

Electrification of Remote Villages (Stand Alone)

6 6 6 6 6 30

Total 1,027 3,278 3,697 3,700 1,901 13,603

133. The scheme for electrification of hamlets in UP has not been included in the current programme of Government of India unless this is included, the target of providing electricity to 100% households cannot be achieved.

134. Under Rajiv Gandhi Gramin Vidyutikaran Yojna the following physical & financial target have been proposed:

Physical & Financial Targets for RE works

Task Year 2008-09Physical(Nos.) Financial(Cr.)

Electrification of un-electrified hamlets 16818 841Strengthening of Distribution system under RGGVY for providing electricity to all BPL household

14440 289

Electrification of the villages electrified as per CEA 4861 340Providing electricity to all rural households including free connection to BPL households

600000 180

[ 199 ]

Page 46: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Total 1650

Dr. Ambedker Gram Sabha Vikas Yojna

135. Government of Uttar Pradash has launched a comprehensive programme for strengthening and renovation work of the villages identified under Dr. Ambedker Gram Sabha Vikas Yojna. In the current year an outlay of Rs. 377.00 crore has been provided to the power sector and for the year 2008-09 an amount of Rs. 237.51 crore has been provided in budget.

Progress of strengthening of village electrification works. (Rs. In Lacs)

Name of Discoms Target Progress

Physical Financial Physical Financial1 PVVNL, Meerut 1655 4428 1655 45802 DVVNL, Agra 2305 4948 2248 40903 MVVNL, Lucknow 4158 7330 3798 40764 PuVVNL, Varanasi 3766 6322 3764 6206  Total 11884 23028 11465 18953

Progress of incomplete village electrification works. (Rs. In Lacs)Name of Discoms Target Progress

    Physical Financial Physical Financial1 PVVNL, Meerut 913 5586 913 47742 DVVNL, Agra 1381 8996 1373 71033 MVVNL, Lucknow 1073 4593 1059 41004 PuVVNL, Varanasi 1928 7664 1928 7587  Total 5295 26838.66 5273 23563.14

Energisation of Private Tubewells (PTWS)

136. By the end of year 2006-07, 856421 private tube wells were energized in the state. There are two schemes for providing electricity connections to PTW’s namely- “Normal scheme and Full deposit scheme”. Under the normal scheme, progress of energisation depends upon the amount released by the GoUP for this purpose, whereas under full deposit scheme, the connections are provided to all perspective consumers who apply and deposit the estimated amount, required for providing connection. During 11 th

plan it is proposed to start the work of conversion of diesel operated private tube wells into electrically operated tube wells. An investment plan of rupees 500 crore is proposed for the 11th plan period. An outlay of Rs. 50 crores has been given for energisation of tube wells for the year 2007-08 and an outlay of Rs. 110 crores has been proposed for the year 2008-09 for energization of 20000 private tube wells.

Non - Conventional Energy

[ 200 ]

Page 47: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

137. Non-conventional Energy Development Agency (NEDA) was established in 1983 in the state as a Nodal Agency to implement and execute the programmes of Non-conventional, alternate and renewable sources of energy. In order to make these programmes more viable, acceptable and known to common people in rural and urban areas, it is proposed to constitute project offices in each district of the state. So far, 55 projects offices have been established.

138. The main objectives of programmes of non-conventional energy proposed for the financial year 2008-09 are as follows:

Mobilization of financial resources through public private participation in the promotion and establishment of renewable energy systems/devices and for augmentation of electricity generatio through various renewable energy sources.

To meet the minimum energy need of the people, particularly in the rural areas through implementation of appropriate schemes.

Proposed Programmes

139. The Plan proposed for the year 2008-09 has been formulated on the basis of available resources. It is proposed to take up various programmes with & without State financial assistance.

Programmes to enlist private participation

140. It is proposed to induct private sector participation with increased inflow of financial investments in the development of renewable sources of power in the state. Following programmes are proposed to be taken up without state government's financial involvement in the financial year 2008-09.

Creation of additional power capacity

141. Creation of around 150MW additional capacity from various renewable energy projects especially, bagasse based co-generation, biomass gasifiers and biomass based generation/co-generation etc. This capacity is likely to be created through private investment. Investment of around Rs. 600.00 crores is expected to be incurred by the private developer for creation of this capacity during financial year 2008-09.

Deployment of various renewable energy systems/devices

142. Various solar energy systems/devices (solar thermal and solar photovoltic systems/devices), bio-energy systems/devices and other renewable energy based systems for various applications and energy conservation devices for saving energy are also proposed to be deployed on a large scale, with the financial assistance of various state/central government departments/institutions by adopting measure like - organizing extensive publicity compaign about the benefits of various renewable energy systems/devices.

[ 201 ]

Page 48: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Programmes with State financial assistance

143. The following programmes are proposed during 2008-09 with financial assistance from the state government.

Solar PV Street lighting Systems (CSS/DS)

144. In order to provide streetlights to the people facing power shortage in the rural areas, it is proposed to install 800. PV street lights in such villages. It is proposed to provide Rs. 7100 as state financial assistance and Rs. 9600 as central fianancial assistance for each streetlight to be installed by the community during the Eleventh Plan period. The scheme is proposed to be implemented as per the Govt. of India guidelines. The State share of Rs. 56.80 lakh is proposed during the year 2008-09 for the scheme.

Solar pump for Irrigation (CSS)

145. In order to provide additional irrigation facility to the farmers, it is proposed to deploy 135 solar PV pumps for irrigation (1.8Kwp capacity of shallow well pump/surface pump). It is proposed to provide Rs. 60000 as state financial assistance and Rs, 50000 as central fianancial assistance to individual farmer for each solar pump during the Eleventh Plan period. The scheme will be implemented as per the Govt. of India guidelines; The State share of Rs. 81.00 lakh is proposed for this scheme during the year 2008-09.

Remote Village Electrification (CSS)

146. Remote villages, which could not be covered under Rajiv Gandhi Vidhyutikarn Yojana, would be electrified with various renewable energy based systems/devices suitable to the needs of such villages, 90% funding under this scheme is provided by Government of India and 10% funding is arranged by state Government/beneficiary round 20 remote villages will be covered during financial year 2008-09. The scheme is proposed to be implemented as per the Govt. of India guidelines. An outlay of Rs. 57.70 lakh is proposed for the year 2008-09 as state share.

Wind Monitoring Stations (CSS)

147. It is proposed to establish wind monitoring stations with the assistance of Govt. of India. State share of Rs. 4.5 lakh is porposed for this programme.

Integrated Rural Energy Programme (CSS/DS)

148. This scheme is proposed to be implemented in all the 70 districts during the financial year 2008-09 as per the directions of Govt. of India Rs. 700.00 lakh is proposed as state share during 2008-09.

Urban Infrastructure, Housing, Water Supply and Sanitation

[ 202 ]

Page 49: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Urban Infrastructure

149. Urbanization is a key indicator of economic development. The increasing pace of urbanization has resulted in tremendous pressure on civic infrastructure such as, drainage, sewerage, water supply, uncollected solid waste in parks and open spaces, transport, etc. It has also led to deterioration in the quality of the city environment. Most of the cities, are facing problems like pollution, poverty, inadequate housing, inadequate water supply, traffic congestion, sanitation, etc.

150. Most of the cities in India including those in Uttar Pradesh have not been planned for development in a sustainable way. Economic development, land use planning, housing, urban infrastructure like drainage, sewerage, water supply, power, solid waste management and transportation systems are all inadequate to meet current needs. Furthermore, most of the local authorities especially Municipalities and Development Authorities do not have enough resources to provide for the growing needs of housing and infrastructure services that come with rapid urbanization. To meet this challenge, cities have to be organized and managed as efficiently as possible. Local authorities need to restructure civic services and initiate management reforms to increase productivity and efficiency. To sort out the above problems a nation wide mission mode programme "Jawaharlal Nehru National Urban Renewal Mission (JNNURM)" was launched on 3rd December, 2005 to give focused attention to integrated development of urban infrastructure and services. This programme consists of four components viz.,

Urban Infrastructure and Governance (50:20:30: center:state:urban local bodies/FIs)-UIG - For Mathura it is 80:10:10 :: center:state:urban local bodies/Financial Institutions (FIs)

Basic Services for Urban Poor (50:50::center:state urban local bodies FIs)-BSUP- For Mathura it is 80 20::center:state/ urban local bodies/ Financial Institutions

Urban Infrastructure Scheme for Small and Medium Towns (80:10:10:: center:state:urban local bodies/FIs) - UIDSSMT

Integrated Housing and Slum Development Programme (80 20::center:state/ urban local bodies/ Financial Institutions)-IHSDP

151. Components 1&2 are for cities population with more than 10 lakhs under which six Nagar Nigam cities (Kanpur, Allahabad, Varnasi, Agra, Lucknow, Meerut) and Mathura (considering its historic and touristic importance. Components 3&4 are for towns with population less than 10 lakhs under which the remaining six Nagar Nigam cities (Gaziabad, Aligarh, Bareily, Muradabad, Gorakhpur, Jhansi), 38 towns of Adarsh Janpad Yojna and 38 Class-I Municipal towns are covered.

152. UIG focuses attention on integrated development of infrastructure services in the cities. Under this sub Mission major infrastructure projects like sanitation, sewerage, solid waste management, road network, urban transport and redevelopment of inner (old) city areas are taken up.

153. BSUP focuses attention on integrated development of Basic Services to the Urban Poor in the cities. Through this sub Mission integrated development of slums through projects for providing shelter, basic services and other related civic amenities with a view to provide utilities to the urban poor are taken up.

[ 203 ]

Page 50: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

154. UIDSSMT aims at the improvement of urban infrastructure of small cities where as IHSDP aims at ameliorating the conditions of the urban slum dwellers who do not possess adequate shelter and reside in dilapidated conditions.

155. The financial assistance under this programme is provided by Govt. of India in the form of ACA (Additional Central Assistance). During the financial year 2006-07 an outlay of Rs. 86000.00 lakh has been provided against which an expenditure of Rs. 25179.95 lakh has been incurred In the 11 th Five Year Plan, an outlay of Rs. 10100.00 crore has been earmarked.

156. The total outlay provided for urban development department during the IV Plan was Rs. 5301.00 lakh.

157. The main initiatives of urban development department proposed for the 11th plan are infrastructural facilities like drainage, sewerage, water supply, power, solid waste management, transportation systems, etc.

158. Development through public-private partnership would be the main strategy during the 11 th Plan for meeting the infrastructural shortage and for providing affordable shelter for the poor in the urban areas of the state.

Efforts made for increasing Private investment through up of PPP models

The Government has issued directions to Urban Local Bodies for improving solid waste management system through private operators in the incurred areas of the cities. Under this system, contractors would provide sweepers, primary collection and transportation system. The coverage of this scheme is for 24 towns in the first phase.

Municipal laws are being amended to facilitate private partnership in various areas of urban services and management.

On the basis on Govt. of India guidelines for PFDF, State Govt has decided to create U.P. Urban Infrastructure Development Fund which would be managed by U.P. Urban Infrastructure Development Corporation.

159. The following projects are proposed to be taken up on Public Private Partnership (PPP) model.

Multi level parking cum shopping complex at Hazratganj.

Six lane Express way on Ghaziuddin Haider (GH) Canal

International Convention Center near Amar Shaheed Path.

Multi specialty Hospital near Amar Shaheed Path.

160. Project Development Special Purpose Vehicle (PDSPV) has been development and execution of constituted for the obra projects. Lucknow Development Authority (LDA) and Project Development Consultant Partner will discuss and finalize the constitution of PDSPV on mutually agreed terms and conditions.

[ 204 ]

Page 51: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

161. The PDSPV will take up project development activities till the stage of selection of developer for implementation of the projects on PPP route and may also take up post selection activities of coordination, monitoring and supervision of the project. During its implementation by the selected Developer on PPP route.

162. The Mission strategy under JNNURM Programme involves Private participation in development, management and financing of Urban Infrastructure.

Performance of the main programmes

163. For the financial year 2007-08 the total outlay provided for urban infrastructure under urban development department is Rs.162145.00 lakh against which the anticipated expenditure is Rs.116720.00 lakh. The main programmes being undertaken are:

Jawaharlal Nehru National Urban Renewal Mission (JNNURM):

164. For the financial year 2007-08 an outlay of Rs. 73688.00 lakh has been provided under JNNURM against which the anticipated expenditure is Rs. 73023.00 lakh. Consultants appointed by the Department have already prepared City Development Plans for the sever mission cities. The concerned departments are preparing Detailed Project Reports. Progress under JNNURM is as given below:

1. Urban Infrastructure and Governance

165. Under this sub mission 14 projects costing Rs. 179956.62 lakh have been approved against which central share Rs. 16013.37 lakh and state share Rs. 6350.81 lakh has been released. 13 more projects costing Rs. 336564.00 lakh are pending for approval by GOI. The works to be carried out under these projects relate to solid waste, management water supply, sewerage, drainage, relocation of industries and development of internal roads in Kanpur.

2. Basic Services for Urban Poor

166. Under this, sub mission projects for Lucknow, Allahabad, Meerut, Mathura and Kanpur relating to housing and infrastructure costing Rs. 37993.82 lakh have been approved against which central share of Rs. 17544.22 lakh and state share of Rs. 20449.61 lakh has been released. Under this programme 19576 houses including infrastructure (water supply, storm water drainage, sewerage, road, pathway, electrification, community center, park, rain water harvesting) would be constructed.

3. Urban Infrastructure Scheme for Small and Medium Towns

167. Under this scheme 49 projects costing Rs. 99545.10 lakh have been approved against which central share of Rs. 18600.2180 lakh, and state share of Rs. 2325.0248 lakh and ULB share Rs. 960.5631 lakh has been released. The works to be carried out under these projects relate to water supply, solid waste, sewerage, roads & flyover.

[ 205 ]

Page 52: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

4. Integrated Housing and Slum Development Programme

168. Under this, scheme projects of 8 commissionaries relating to housing and infrastructure costing Rs. 2901.37 lakh have been approved against which central share of Rs. 2210.21 lakh and state share of Rs. 691.17 lakh has been released. Under this programme 2032 houses including infrastructure will be constructed. For the financial year 2008-09 an outlay of Rs. 161500.00 lakh has been proposed under JNNURM programme. Component wise outlay under JNNURM is as below:

UIG - Rs. 85000.00 lakh

BSUP - Rs. 24200.00 lakh

UIDSSMT - Rs. 24100.00 lakh

IHSDP - Rs. 28200.00 lakh

Accelerated Urban Infrastructure Development Scheme

169. The objective of this scheme is to create infrastructural facilities like water supply, sewerage, drainage, solid waste management, slaughter house, roads, Street lights etc to benefit the citizens of small and medium towns. This scheme covers those Urban Local Bodies having population less than 1 Lakh as per census of 2001 but they should not be under the coverage of JNNURM and UIDSSMT schemes. 90 % of project cost is to be borne by State Govt. and 10 % cost by Urban Local Bodies. The selection of local bodies would be done by a Committee headed by Hon. Urban Development Minister. The Committee would also decide priorities of the projects.

170. Under this scheme, Local bodies would have to improve their financial capability by imposing property tax, water tax license fees etc, & aim for increasing coverage and increasing 90% collection of revenue.

171. Monitoring of this scheme would be done by the Directorate of Local Bodies. The Disbursement of funds and sanctioning of project will be done as per the guidelines approved by cabinet. During the financial year 2007-08 an outlay of Rs. 4000.00 lakh has been provided against which the anticipated expenditure is Rs. 3000.00.

172. The above programme has been restarted as Adarash Nagar Yojna and an outlay of Rs. 10000.00 lakh has been proposed in the financial year 2008-09.

Manyavar KanshiRam ji Shahari Nagar Vikas Yojna

173. The above programme has been started for providing infrastructural facilities in the urban areas. During the financial year 2007-08 Rs. 84424.59 lakh has been provided against which the anticipated expenditure is Rs. 40000.00 lakh. For the financial year 2008-09 an outlay of Rs. 50000.00 lakh has been proposed.

Manyavar Shree KanshiRam ji Shahari Samagra Vikas Yojna

[ 206 ]

Page 53: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

174. The main objective of this scheme is to saturate the urban areas in a phased and timely manner with infrastructure facilities, social security employment etc. with in a period of five years. The major works to be carried out under this programme are:

drinking water

sewerage

drainage

solid waste management

construction of C.C. roads

Electrification/street lights

Pensions for old age, widows, physically handicapped person and family benefits scheme.

Health programme and establishment of maternity and infant welfare health centers.

establishment of primary schools

Scholarship programmes

To provide ration cards to the eligible person

Housing facilities for the poor.

employment generation.

construction of community centers

beautification of parks and improvement of the environment

175. Under this programme, the urban slums of economically weaker sections are to be provided with the basic amenities so that the people of these areas join the main stream of urban development. In the first phase 4 wards and in the second, third, fourth and fifth phase 8 wards each would be selected in Municipal Corporations and 55 Municipalities of District Head quarters and one largest Nagar Panchayat each in 70 districts of the State. Similarly 70 Nagar Panchayats would be selected each year.

176. The Nodal agency for water supply, sewerage, drainage, Solid waste beautification of Parks, construction of Roads etc. is Uraban Development Department. For the financial year 2008-09 an outlay of Rs. 50000.00 lakh has been proposed.

National Urban Information System (NUIS)

177. National Urban Information System (NUIS) is a centrally sponsored scheme introduced at the end of 10th Five Year Plan. The financial assistance to be provided under this scheme is in the ratio 75% Central share and 25% State share. Its main objective is to establish a comprehensive information system in urban areas for planning, management and decentralized governance in the context of provisions of scientific planning and implementation of 74th Constitutional Amendment Act, 1992. This scheme is intended to develop spatial as well as attribute data base for various levels of urban planning and decision support to meet requirements of urban planning and management. All urban areas in India are proposed to be covered by the end of 11th Five Year Plan under this scheme. In Uttar Pradesh, Urban Development

[ 207 ]

Page 54: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Department is the administrative department for this scheme and Town and Country Planning Department has been declared as the nodal agency. In the first phase six cities viz. Lucknow, Kanpur, Varanasi, Allahabad, Meerut and Ghaziabad are covered in the state under the NUIS scheme.

178. During the financial year 2006-07, the expenditure incurred was Rs.121.41 lakh towards urban mapping of the aforesaid six cities as state share to survey of India. SOI has started the work and is expected to deliver the GIS data to concerned urban local bodies and state nodal agency by the end of second quarter of 2008-09.

179. During the 11th Five year Plan, an outlay of Rs. 162.05 lakh has been provided under this Scheme. During the financial year 2007-08, an outlay of Rs. 32.41 lakh has been provided against which the anticipated expenditure is Rs.47.00 lakh.

Housing

180. Uttar Pradesh is the most populous state of India with a total population of 16.60 crore according to Census, 2001 out of which 13.15 crore people live in rural areas and 3.45 crore in urban areas. Percentage of urban population to total population of the state stands at 20.78 as per 2001 Census whereas; this percentage was 19.68 in 1991. Thus, an increase of 1.10 percentage points has been recorded in the urban population during 1991-2001. The decadal growth of urban population during 1991-2001 is 32.88 per cent as against 30.50 per cent during 1981-91. By 2011 and 2021 the urban population of the state is estimated to be 4.49 crore (21.77%) and 5.83 crore (23.19%) showing an increase of 1.04 crore and 1.34 crore respectively, as compared to1.0 crore in 1991-2001.

181. The state has the largest urban system in the country with 628 municipalities however, it ranks 18 th

in the level of urbanization. Nearly 2/3rd (62%) of the state urban population is concentrated in 54 Class-I cities. Small towns (especially Class-5 and 6 towns) exhibited a negative rate of growth during 1991-2001 which is indicative of growing trend of population shift towards larger (5 lakh plus) cities. The numbers of metropolitan cities increased from 3 in 1991 to 6 in 2001 namely; Kanpur, Lucknow, Varanasi, Agra, Allahabad and Meerut. About 28% of the total urban population of the state is concentrated in these 6 metropolitan cities which recorded highest decadal growth rate (32%) during 1991-2001.There are marked regional imbalances in the pattern of urbanization with Western Region being the most urbanized and the Bundelkhand Region the least urbanized.

182. The urban structure is becoming more and more top heavy due to the higher demographic growth in large cities. Higher demographic growth in the class-I cities is due to both area expansion and inmigration. Further, there has been expansion in the municipal boundaries of the Class-I cities. Besides, these cities attract migrants from all over the state due to their stronger economic and infrastructural base. Thus, the spatial concentration of urban growth can be seen not only in terms of an increase in the share of urban population in class-I cities but also in that of million plus cities. The emerging trends of urbanization in the

[ 208 ]

Page 55: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

state necessitates two-pronged strategy for balanced regional urban development i.e. better management of large cities and inducing planned growth of small and medium towns.

Housing and Infrastructure Scenario

(a) Housing

183. Housing, is one of the basic necessities of life. The high urban growth entails considerable investment in housing, physical and social infrastructure. It is estimated that the housing industry in the country contributes to about 6% of the GDP. This industry itself has over 250 backward and forward linkages with ancillary industries. It is ironical that while urban population is increasing rapidly, supply of serviced land and housing units is restricted leading to creation of sub-standard and illegal housing stock.

184. Based on 2001 Census, the housing shortage in the urban areas of the state at the beginning of 10 th

Plan was 7 lakh units whereas; additional requirement during the 10 th Plan was estimated at 9 lakh units. Thus, the total housing demand during the 10th Plan was estimated at 16 lakh units which implied a provision of 3.20 lakh units per year. However, the capacity of the public sector housing agencies especially Development Authorities and Housing and Development Board has been limited to maximum of 1.0 lakh units per year. Therefore, the state government decided to formulate a strategy to meet the two-third requirement of total estimated demand of 16 lakh units during the 10 th Five Year Plan to provide 10.50 lakh units with the participation of Private and Cooperative Sectors. Targets for Public, Private and Cooperative Sectors were 4.10 lakh, 5.40 lakh and 1.0 lakh units, respectively. The total housing stock created by Development Authorities, Housing and Development Board, co-operative sector and organized private sector during the 10th Five Year Plan aggregated to 4.50 lakh dwelling units. The housing stock created by unorganized private sector is estimated to be about 1.25 times of the organized sector i.e. about 5.60 lakh units. Thus, the total estimated housing stock created during 10 th Five Year Plan was to the tune of 10 lakh dwelling units.

185. During the 10th plan period, the total outlay under housing department was Rs. 23000.00 lakh against which the expenditure was Rs. 33079.00 lakh.

186. The projected housing shortage at the beginning of 11 th Plan (2007-08) is estimated at 4.67 lakh dwelling units. Besides, an additional requirement of 11.16 lakh dwelling units is expected to be added during the 11th Plan period as per the population projections. Therefore, the total housing demand anticipated during 11th Five Year Plan (2007-12) is 15.84 lakh dwelling units.

187. Although the State Housing Policy lays special emphasis on promoting private investment in the housing sector, yet the activities of the private sector have been hapazard. With the current policy of economic liberalization and stress on privatization, the government is now resuming the role of a catalyst and “facilitator” in the housing sector rather than discharging the traditional role of being a “provider”. Therefore, during the 11th Plan efforts will be made to pursue the reform agenda further and design policies that focus on the provision of housing to weaker sections and spur private sector investment while encouraging competition by guarding against monopolistic practices.

[ 209 ]

Page 56: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

XI Plan – Strategies and Initiatives

(a) Economic Development

188. Without a strong sustainable economy, no city, state, or local authority can offer the opportunity for high quality life to its citizens. Developing a sustainable city with true economic opportunities requires a comprehensive master plan that understands and takes into account these complex interrelationships. The first step of the master planning process should be to conduct a resource assessment of the city and then to analyze these resources from an economic development perspective.

(b) Land Use

189. Building livable and sustainable cities starts with good land use policy. If land use is not planned and managed correctly then all other city functions fail. Land use decisions drive infrastructure, determine transportation systems, frame energy policy, affect economic development, and impact the quality of life in a city in immeasurable ways. Therefore, land should be treated as an economic resource while making land use decisions.

(c) Transportation

190. Perhaps nothing is as important to a city’s economic vitality as a good transportation system A truly sustainable city with a vibrant economy needs efficient and convenient mobility. To achieve this goal, cities need to take a systems approach to transportation. Transportation planning needs to be accorded top priority especially in the metropolitan cities of the state.

191. As per 2001 Census, Kanpur and Lucknow are the biggest metropolitan cities which have crossed the 2 Million population mark. The traffic and transportation conditions of these two cities are deteriorating day by day. Therefore, an efficient Mass Rapid Transit System (MRTS) i.e. Metro Rail system needs to be introduced in these cities. In this regard, an allocation of Rs. 5.00 crore (Rs. 2.50 crore each) would be required in the 11th Five Year Plan for taking up the techno-economic feasibility study for MRTS in both the cities.

(d) Urban Infrastructure

192. The quality of life in a city is greatly affected by the efficacy of its urban infrastructure. Storm-water drainage system, wastewater treatment, solid waste management and power directly impact environmental quality in a city. Local authorities need to lay special emphasis on more effective planning, operation and maintenance of its urban infrastructure. Availing maximum financial assistance and successful implementation of schemes initiated under the centrally sponsored schemes such as JNNURM, UIDSSMT and IHSDP will prove a boon during the 11 th Plan for improving and strengthening of infrastructure in the urban areas of the state.

Protection of Environment

[ 210 ]

Page 57: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

193. Erratic climatic conditions leading to prolonged periods of dry spells, flash floods, rising temperatures and pollution levels have generated a sense of urgency among the policy makers to take sincere steps to halt the degradation of global eco-systems and macro-climatic conditions. Therefore, future urban development strategy will have to be sensitive to environmental considerations to ensure overall human well being. In order to promote environmentally sustainable development of urban areas, major emphasis will be laid on effective implementation of the following measures during the 11 th Five Year Plan:-

To promote efficient land use planning based on integration of living and working areas so as to minimize traffic generation, travel distance and auto- exhaust emissions.

Conservation, augmentation & management of water through implementation of Rainwater Harvesting System.

Conservation of existing forest/green cover and provision for increase in the green space/areas through enforcement of Master Plan Guidelines and preparation of Zonal Development Plans.

Conservation of energy through promotion of non-conventional energy sources and adoption of sustainable building concepts.

Promote the use of local building materials and use of renewable materials.

Conservation of prime agricultural land and environmentally sensitive areas through rationalization of planning norms and Building Bye-laws.

To make provisions for safe disposal of solid wastes in the city Master Plans.

194. Environmental Impact Assessment of development projects and environmental clearance from Central/State departments are to be strictly adhered to before taking up the projects.

Performance of Urban Housing Sector

195. Housing schemes in the state are implemented mainly by the Development Authorities and the Housing and Development Board. At present there are 24 Development Authorities covering large cities and the Housing and Development Board is functional in 102 urban areas of the state. The schemes comprise land acquisition and development, EWS housing, sites and services scheme, low income, middle income and high income group housing. The State Government, HUDCO and other Financial Institutions have been financing such schemes.

196. The total outlay provided for the housing department in the year 2007-08 was Rs. 45547.00 lakh against which the anticipated expenditure is Rs. 83785.00 lakh. The total outlay proposed for the year 2008-09 is Rs. 70932.00 lakh. The performance of major schemes under the Urban Housing Sector are:

Indira Gandhi Pratisthan

197. This scheme is proposed on 25 acres of land situated at Gomtinagar, Lucknow. The implementation of this scheme commenced in February, 2005 and the project period is 3 years, i.e. 2005 to 2008. Under this project, construction of conference, banquet, plenary halls, library, etc. has been completed and the

[ 211 ]

Page 58: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

remaining works comprising auditorium and Stambh are expected to be completed by the year 2008. An outlay of Rs. 2000.00 lakh was provided for the financial year 2007-08 to complete the remaining works which is likely to be fully utilized. The construction agency of the project has raised a demand of Rs 87.00 lakh to complete the remaining works. Hence an outlay of Rs 87.00 lakh has been proposed for the year 2008-09.

Integrated Development of Lucknow city

198. A comprehensive development plan for Lucknow city is being prepared for its integrated development. In the aforesaid plan, there is a proposal to construct a outer ring road, urban transport system, parking, Bus stops, Railway over bridges, fly overs, sub ways, transportnagars, water supply schemes, sewage disposal works, electrification works, etc. To complete these works an outlay of Rs.20000.00 lakh has been proposed for the financial year 2008-09.

Rural Housing

Indira Awaas Yojana (IAY)

199. Under this programme houses are provided free of cost to the selected beneficiaries. 80% of the funds are utilized on the construction of new houses and the remaining 20% funds for upgradation of kutcha houses. Houses are constructed on the plots of beneficiaries. Allotment of houses under this scheme is made in the name of the female member of the beneficiary household. Alternatively, it can be allotted in the name of both husband and wife.

200. The target group for houses under the scheme are the people below poverty line living in rural areas and belonging to Scheduled Castes/Scheduled Tribes, freed bonded labourers and non-SC/ST beneficiaries to the extent of 40% of total allocation during a financial year. 3% of the funds have been earmarked for the benefit of disabled persons living below poverty line. Effective from 1.4.2004, the upper limit of new construction is Rs. 25,000 for each house in the plains and Rs. 27500 in the Bundelkhand region while cost of up gradation of each kutcha house is Rs. 12,500. Though no design is prescribed for the house, plinth area of the houses should be around 20 sq.mts.

201. On the basis of BPL Census 2002, the rural housing shortage in Uttar Pradesh is nearly 45 lakhs. To provide houses to identified BPL families is the prime priority of the State in the 11th Five Years Plan (2007-12). Thus in five years we need 45 lakhs houses to be constructed i.e. 9 lakhs houses per year. Therefore, there is a need of a new housing scheme to be implemented by the State Government apart from the IAY or to increase the outlay of IAY up to that mark.

202. Under IAY Efforts are being made to cover 20.00 lakh families during the 11th Five Year Plan subject to availability of Rs. 5000 .00 crores ( Rs. 3750 crores from Central Govt. and Rs. 1250 crores from

[ 212 ]

Page 59: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

State Govt.) State Planning Commission has provided Rs. 767.06 crores as state share for the 11th plan , hence additional outlay of Rs. 482.94 crore is required under the scheme.

203. The outlay for the year 2007- 08 under IAY is Rs 636 crores which includes state share of Rs 160 crores against which about 2.55 lakh houses can be constructed. In the year 2008-09 it has been planned to construct 4.00 lakh houses for which Rs. 1000.00 crores (Rs.750.00 crores central share and Rs. 250.00 crores state share) will be required.

204. Permanent IAY waitlist is prepared for each Gram Panchayat based on BPL census 2002. The list is displayed in each gram panchayat. The IAY waitlist is also displayed on the respective district’s NIC website in which blockwise and village wise identified households are displayed.

205. For the Eleventh Five Year Plan an outlay of Rs. 767.06 crore (State Scheme) has been approved against which a target of constructing 12.50 lakh houses has been fixed. During 2007-08 it is anticipated that 2.50 lakh houses will be constructed under the programme. An outlay of Rs 250 crore has been proposed for the Annual Plan 2008-09 against which 4.00 lakh houses will be constructed.

Maha Maya Rural Housing Scheme for BPL families –

206. The State Government floated a new scheme of rural housing for SC/ST families during 2006-07 for construction of 1.20 lakh houses. About 12.00 lakh houses are proposed to be constructed in the 11th Five Year Plan under this scheme for which Social welfare department has provided an outlay of Rs.1875.00 crores . The pattern of scheme will be the same as of Indira Awas Yojana . An outlay of Rs 200 crores has been provided for the year 2007-08 for construction of 80,000 houses. For the year 2008-09 an outlay of Rs. 200.00 crores has been earmarked by which 80,000 houses will be constructed.

Water Supply and Sanitation

207. Clean drinking water, sanitation and clean environment are vital to improve the health of our people. Provision of these basic services continues to be among the core activities of urban local bodies. Since availability of water in the country is going down, in general, with depletion of water table and the discharge of the rivers, a review of the requirements of the water is the prime need of the hour. Government of India changed the requirement levels of the rate of water supply to the individual and other users. The rate of water supply defined in the manual on water supply and treatment in May 1999 by govt. of India is as under.

Towns having no sewerage facility : 70 lpcd

Towns having sewerage facility : 135 lpcd

Metropolitan and Mega-cities : 150 lpcd

[ 213 ]

Page 60: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

208. In U.P., there are 627 local bodies out of which 12 are Nagar Nigams,194 are Nagar Palika Parishads and 421 are Nagar Panchayats whose total population according to 2001 census is 3.26 crores. This must have gone up to 3.81 crores now and is expected to increase to 12.84 crores in the year 2040. All towns are provided with piped drinking water facility except 2 Nagar Panchayats (which were among 5 towns included at a later stage). In these 2 towns piped water supply will be provided under district plan/ UIDSSMT as per needs. As per the position on 1-4-2007, drinking water availability, against norms, in towns is as follows.

100% or more availability as per norms 277 towns

More than 75% & <100% water supply 142 towns

More than 50% & <75% water supply 126 towns

More than 25% & <50% water supply 60 towns

Less than 25% water supply 20 towns

Without piped w/s 2 towns

Total 625 towns

209. Data of two towns where water supply is not maintained by Local Body or Jal Sansthan are not available

Achievements in Tenth Five Year Plan

210. The Tenth Five Year Plan emphasized provision of drinking water and sanitation facilities. The total outlay provided under Water Supply and Sanitation during the 10th Plan was Rs. 305450.00 lakh against which the expenditure was Rs. 72519.90 lakh.

211. Under Accelerated Urban Water supply Programme out of 425 towns having population less than 20,000, only schemes of 390 towns were sanctioned by GOI. 121 Towns have been provided with adequate Water supply during the Ninth Plan. 219 towns were provided with drinking water in the Tenth Plan and the rest 50 towns will be covered in year 2007-08. This Programme is now closed (March 2007) as per the decision taken by Govt. of India.

Eleventh Five Year Plan - Vision and Strategy

212. The main objectives pertaining to urban water supply and sanitation during the 11th Five Year Plan are:

Expansion and improvement of drinking water supply in every town.

Expansion and improvement of sanitation facility with other social infrastructure.

[ 214 ]

Page 61: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

213. The above objective can only be achieved through appropriate mix of central and state investments, institutional finance, strengthening of operation and maintenance system and more importantly by the involvement of local bodies/communities at various stages of planning implementation, operation and maintenance.

214. The Status of Water supply and sewerage system is not satisfactory in many of the towns as compared to the prescribed norms. For this the following strategy is proposed:-

Reorganization of water supply and Sewerage system in all the 12 Nagar Nigams. Six of them are included in JNNURM while for the remaining six Nagar Nigams, these schemes are proposed to be taken up with state resources.

Reorganization of water supply and Sewerage system of towns having Sewerage System and with population more than 1 lakh as per 2001 census.

Reorganization of water supply system of towns having water availability less than 50% of norms and not covered under AUWSP.

215. Water supply level in towns of U.P. at the end of March 2006 was 4647.94 mld per day which is expected to further improve at the end of March 2007 i.e. at the end of Tenth five year plan. With standard norms, water supply level required at the end of March 2007 is 5170.06 mld per day. The gap is proposed to be covered during Eleventh Five Year Plan.

Sewerage System

216. Out of 628 towns, partial sewerage system exists in only 55 towns. Sewerage system in most of the towns is being proposed in JNNURM and UIDSSMT Programme. Few towns will be covered in the State Sector which would be decided by State Govt. at appropriate stage.

217. The main schemes under this sector for the year 2008-09 are as follows:

Water supply schemes in towns other than AUWSP are covered under district sector:

218. This programme was approved by the State Govt. to improve the water supply conditions in 16 districts of the state. In the year 2007-08 an outlay of Rs. 9000.00lakh was provided for the improvement of water supply works such as hand pumps, extension of pipe lines, tubewells, etc. and the funds would be utilized fully. Keeping in view the increasing population and the fast improving living standards an outlay of Rs. 12000.00 lakh has been proposed for the financial year 2008-09.

Externally Aided Schemes (EAPs)

[ 215 ]

Page 62: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

219. Under EAP "Agra Water Supply Scheme (Gangajal JBIC)" has been taken up with the purpose of providing good quality water from the river Yamuna. Looking at the deteriorating conditions of river Yamuna and the water crisis being faced by the heritage city, the Government has come up with this scheme. Under this scheme it is proposed to lay a 130 km long pipe line upto Agra/Mathura. This project is assessed to be completed by the year 2014. 85% of the cost of the project will be met with loan from JBIC and 15% cost of the project will be borne by the State Government. In the year 2007-08 an outlay of Rs. 700.00 lakh was provided for the project. An outlay of Rs. 9000.00 lakh has been proposed for the financial year 2008-09.

Ganga Acton Plan - Phase- II

220. Ganga Acton Plan - Phase- II is being executed in the State under National River Conservation Programme of Government of India. Under this scheme, river pollution control works of 23 towns situated on the bank of river Ganga, Yamuna and Gomti in different components namely Ganga Action Plan (12 towns), Yamuna Action Plan (8 towns) and Gomti Action Plan (3 towns) are included.

221. Under this project, the sanctioned works in Yamuna Action Plan– Phase-I component have been completed, wherein 16 Sewage Treatment Plants of 402.25 mld capacity have been constructed and made operational. Also under Gomti Action Plan component, 1 Sewage Treatment Plant of 42.0 mld capacity in Lucknow town and 1 Sewage Treatment Plant of 1.7 mld capacity in Sultanpur town have been constructed and made operational. Under this scheme, 15 different sewage treatment plants of total 512.96 mld capacity included in sanctioned and ongoing schemes are at different stages of construction,

222. An outlay of Rs. 6535.00 lakh was provided in the year 2007-08 against which the anticipated expenditure is Rs. 2690.75 lakh. For the financial year 2008-09 an outlay of Rs. 7050.00 lakh has been proposed.

Lake Conservation Plan- Govardhan Town

223. In the 10th meeting of National River Conservation Authority (NRCA) under the chairmanship of Hon'ble Prime Minister, held on 13.03.2001, a decision was taken to the effect that “National Lake Conservation Plan (NLCP) shall receive the same priority as the rivers. As per the above decision of Government of India, the projects for 4 lakes namely, Ramgarh Tal (Gorakhpur), Laxmi Tal (Jhansi), MansiGanga Tal, Govardhan, (Mathura) and MadanSagar Tal (Mahoba) of the State were proposed under NLCP. Out of the 4 lakes, the MansiGanga Tal, Govardhan (Mathura) is the first priority by the State Government. An outlay of Rs. 450.00 lakh was provided in the year 2007-08. For the financial year 2008-09 an outlay of Rs. 300.00 lakh has been proposed under this scheme.

Rural water supply

224. The entire Rural Water Supply (RWS) programme was given a mission approach when the Technology Mission on Drinking Water and Related Water Management, also called the National Drinking

[ 216 ]

Page 63: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Water Mission (NDWM) was introduced as one of the five Social Missions in 1986. NDWM was renamed as "Rajiv Gandhi National Drinking Water Mission (RGNDWM)" in 1991.

225. As per 2004 survey, 2,33,341 Habitations were found fully covered(FC), 7993 habitations were identified as Not Covered (NC) and 18776 habitations as Partially Covered (PC) out of total 2,60,110 Habitations as on 1.4.04. Out of the above mentioned NC/PC habitations only 445 PC and 205 NC habitations are left to be covered at the end of X Five Year Plan.

226. In the rural areas of State most of the Piped Water Supply Schemes have been executed after 1970. So a 1163 Piped water Supply Schemes (PWS) covering 28996 habitations have been completed, which are under by UP Jal Nigam/ Jal Sansthan/ Gram Panchayat maintenance, District-wise status of these schemes is given in Annexure-5 At present 691 PWS are under execution in various district under diffrent programmes 95 schemes are expected to be completed by 31-3-07 and 596 schemes are expected to be carried out in the 11th Five Year Plan.

227. During the 11th Five Year Plan, the main emphasis for piped water supply schemes is to be given to bigger villages (Population more than 5000) which are not quality affected. As on 01.04.2007, the number of hand pumps installed in rural areas, is about 16.56 lakh at the end of the 10th Five Year Plan period.

Safe Drinking Water On Sustainable Basis To All Habitations

228. All Rural habitations have been covered as per norm of 40 lpcd i.e. one handpump per 250 persons. Implementation of schemes to provide safe drinking water as per revised norms of GOI (one source for a population of 150) has already been taken up during the 10th Five Year Plan period with community contribution in capital cost sharing (minimum 10%) and bearing 100% Operation & Maintenance cost. It is proposed to saturate the remaining rural habitations as per revised norms of one handpump per 150 persons during the 11th Five Year Plan.

229. In small rural habitations, only one handpump or standpost has been provided as per requirement to saturate the habitations as per revised norm. In these habitations, safe drinking water crisis emerges when existing handpump goes out of order. In all such habitations, one extra handpump is proposed to be installed during the 11th Five Year Plan period.

230. As majority of piped water supply schemes (PWS) have outlived their utility, their rejuvenation is needed. It is not possible to rejuvenate these schemes from the available O & M fund. Hence, adequate provision is required in the 11th Five Year Plan. Once these schemes get rejuvenated, the same shall be maintained on sustainable basis.

231. U.P. Jal Nigam has already sent a proposal to Govt. of U.P. for revision of the tariff, which was last revised in 1994-95. It is expected that with the rejuvenation of existing PWS the coverage will be enhanced and after revision of tariff more resources will be available from the beneficiaries.

[ 217 ]

Page 64: CHAPTER V - Planning Department(Uttar Pradesh)planning.up.nic.in/annualplan_0809/Vol-1 Part-2/Chapter-3... · Web viewA fully equipped workshop with modern machines and testing equipments

Management Information System

232. Government of India sanctioned a project in the 9th Five Year Plan for computerization of various activities related to Rural Water Supply. A separate computer centre has been set up in all the U P Jal Nigam offices. Out of the total sanctioned amount of Rs. 1166.60 lakh by State Government and GOI for this purpose, Rs. 1123.20 lakh has been utilized. Data entries for operation software are under progress. Additional demand for the 11th Five year Plan amounting to Rs. 18 Crores has also been sent to GOI after approval of State Level Committee.

[ 218 ]


Recommended