+ All Categories
Home > Documents > Document of The World Bank...Bodri Kuto) In 3 basins the Balai PSDAs plan basin operations and...

Document of The World Bank...Bodri Kuto) In 3 basins the Balai PSDAs plan basin operations and...

Date post: 03-Feb-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
81
Document of The World Bank Report No: ICR00001861 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47110, IBRD-77570, IDA-38070, TF-52124, TF55997) ON A LOAN/CREDIT/GRANT IN THE AMOUNT OF US$45.0 MILLION (LOAN), SDR17.9 MILLION (CREDIT), US$14.0 MILLION (GOVERNMENT OF NETHERLANDS GRANT) AND EURO 9.5 MILLION (EC GRANT) RESPECTIVELY TO THE REPUBLIC OF INDONESIA FOR A WATER RESOURCES AND IRRIGATION SECTOR MANAGEMENT PROGRAM PHASE I PROJECT AND NUSA TENGGARA BARAT WATER RESOURCE MANAGEMENT PROJECT March 30, 2012 Indonesia Sustainable Development Unit Sustainable Development Department East Asia and Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • Document of

    The World Bank

    Report No: ICR00001861

    IMPLEMENTATION COMPLETION AND RESULTS REPORT

    (IBRD-47110, IBRD-77570, IDA-38070, TF-52124, TF55997)

    ON A

    LOAN/CREDIT/GRANT

    IN THE AMOUNT OF US$45.0 MILLION (LOAN), SDR17.9 MILLION

    (CREDIT), US$14.0 MILLION (GOVERNMENT OF NETHERLANDS GRANT)

    AND EURO 9.5 MILLION (EC GRANT) RESPECTIVELY

    TO

    THE REPUBLIC OF INDONESIA

    FOR A

    WATER RESOURCES AND IRRIGATION SECTOR MANAGEMENT PROGRAM

    PHASE I PROJECT AND

    NUSA TENGGARA BARAT WATER RESOURCE MANAGEMENT PROJECT

    March 30, 2012

    Indonesia Sustainable Development Unit

    Sustainable Development Department

    East Asia and Pacific Region

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    (Exchange Rate Effective December 31, 2011)

    Currency Unit = Indonesian Rupiah

    IDR = US$0.00011236

    US$* = IDR 8,900 *All $ in this document refer to US currency unless otherwise noted.

    GOI FISCAL YEAR

    January 1 – December 31

    ABBREVIATIONS AND ACRONYMS

    ADB

    AMDAL

    APBD(K)

    APBD(P)

    APBN

    APL

    AWP

    Balai PSDA

    Bangda

    Bapedalda

    Asian Development Bank

    Full Environmental Assessment

    Kabupaten Government Budget

    Provincial Government Budget

    Central Government Budget

    Adaptable Program Loan

    Annual Work Plan

    Provincial River Basin Management Organization

    DG Regional Development, MoHA

    Local Environmental Management Office

    Bappeda

    Bappenas

    B (B)WS

    BPKP

    BWRC

    BWRM

    BWRMP

    CAS

    CDD

    CDP

    CDMU

    CPS

    CSO

    DA

    DAS

    DGWR

    DGAIF

    Dinas Pertanian

    Dinas PUP

    Dinas SDA

    DPRD

    DSC

    EMP

    FMR

    GOI

    GP3A/IP3A

    IAIP

    IBRD

    ICR

    IFR

    IMEU

    IMF

    JBIC

    JIWMP

    Kabupaten

    Local Government Development Planning Board

    National Development Planning Board

    National River Basin Management Organization

    Central Government Audit Agency

    Basin Water Resources Council (Committee)

    Basin Water Resources Management

    Basin Water Resources Management Plan/Planning

    Country Assistance Strategy

    Community-driven development

    Community Development Plan

    Central Dam Monitoring Unit within MPW

    Country Partnership Strategy

    Civil Society Organization

    Designated Account

    River Basin

    Directorate General of Water Resources, MPW

    Directorate General of Agriculture Infrastructure and Facilities

    Local Government Agriculture Services

    Local Government Public Works Services (Department)

    Local Government Water Resources Services (Department)

    Local Government Legislative Assembly

    Dam Safety Commission

    Environmental Management Plan

    Financial Monitoring Report

    Government of Indonesia

    Federation/Apex Body of Water Users Associations (WUAF)

    Kabupaten Irrigated Agriculture Improvement Program

    International Bank for Reconstruction and Development

    Implementation Completion Report

    Interim Financial Reports

    Impact Monitoring and Evaluation Unit

    Irrigation Management Fund

    Japan Bank for International Cooperation

    Java Irrigation and Water Resources Management Project

    District

  • KIIF

    KLH

    KOMIR

    KPIU

    KPMU

    MIS

    MoA

    MoEnv

    MOF

    MoHA

    MPW

    MOU

    NPIU

    NPMU

    NSCWR

    NWC

    O&M

    PAD

    PDO

    Perda

    PIM

    PIU

    PJT I/II

    PKPI

    PMU

    PMM

    PPISP

    PPIU

    PPMU

    PPTPA

    PTPA

    PWRC

    SRI

    RBC

    RIM

    TA

    UPTD

    WISMP

    WS

    WUA

    WUAF

    WUR

    Kabupaten Irrigation Improvement Facility (DPI-K)

    State Ministry of Environment

    Irrigation Commission (Committee)

    Kabupaten Project Implementation Unit

    Kabupaten Project Management Unit

    Management Information System

    Ministry of Agriculture

    Ministry of Environment

    Ministry of Finance

    Ministry of Home Affairs

    Ministry of Public Works

    Memorandum of Understanding

    National Project Implementation Unit

    National Project Management Unit

    National Steering Committee for Water Resources

    National Water Council

    Operation and Maintenance

    Project Appraisal Document

    Project Development Objectives

    Local Government Regulation

    Participatory Irrigation Management

    Project Implementation Unit

    Basin Management Corporation I/II

    Irrigation Management Reform Policy

    Project Management Unit

    Project Management Manual

    National Policy on Irrigation

    Provincial Project Implementation Unit

    Provincial Project Management Unit

    River Basin Water Management Committee

    Provincial Water Management Committee

    Provincial Water Resources Management Council

    System of Rice Intensification

    River Basin Corporation

    River Infrastructure Maintenance and Rehabilitation

    Technical Assistance

    An Operational Unit within Dinas PUP

    Water Resources and Irrigation Sector Management Program

    River Territory

    Water User Associations

    Water User Association Federation (GP3A/IP3A)

    Water Use Right

    Vice President:

    Pamela Cox, EAPVP

    Country Director: Stefan Koeberle, EACIF

    Sector Director: John Roome, EASSD

    Sector Manager: Franz Drees-Gross, EASIS

    Task Team Leader: Xiaokai Li, EASIN

  • INDONESIA

    Water Resources and Irrigation Sector Management Program Phase I Project

    (WISMP1) and

    Nusa Tenggara Barat Water Resource Management Project (NTB-WRMP)

    CONTENTS

    Water Resources and Irrigation Sector Management Program Phase I Project Data Sheet…………………………………………………………………………………….i

    A. Basic Information

    B. Key Dates

    C. Ratings Summary D. Sector and Theme Codes

    E. Bank Staff

    F. Results Framework Analysis

    G. Ratings of Project Performance in ISRs H. Restructuring

    I. Disbursement Graph

    Nusa Tenggara Barat Water Resource Management Project (NTB-WRMP)

    Data Sheet…………………………………………………………………………………….xi

    A. Basic Information B. Key Dates

    C. Ratings Summary

    D. Sector and Theme Codes

    E. Bank Staff F. Results Framework Analysis

    G. Ratings of Project Performance in ISRs

    H. Restructuring

    I. Disbursement Graph

    1. Project Context, Development Objectives and Design…………………………..1

    2. Key Factors Affecting Implementation and Outcomes …………………………7

    3. Assessment of Outcomes ………………………………………………………15

    4. Assessment of Risk to Development Outcome ……………………………….. 24

    5. Assessment of Bank and Borrower Performance ………………………………26

    6. Lessons Learned ………………………………………………………………..29

    7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ….29

    Annex 1. Project Costs and Financing ……………………………………………31

    Annex 2. Outputs by Component …………………………………………………34

    Annex 3. Economic and Financial Analysis ……………………………………...41

    Annex 4. Bank Lending and Implementation Support/Supervision Processes …...45

    Annex 5. Beneficiary Survey Results …………………………………………….48

    Annex 6. Stakeholder Workshop Report and Results …………………………….49

    Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR…………50

    Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ………….55

    Annex 9. List of Supporting Documents ………………………………………….56

    MAP: IBRD 39248

  • i

    For WISMP 1 (Phase I of the WISMP APL):

    A. Basic Information

    Country: Indonesia Project Name:

    Water Resources &

    Irrigation Sector

    Management Program

    Project ID: P059931 L/C/TF Number(s):

    IBRD-47110, IBRD-

    77570, IDA-

    38070,TF-52124

    ICR Date: 03/29/2012 ICR Type: Core ICR

    Lending Instrument: APL Borrower: REPUBLIC OF

    INDONESIA

    Original Total

    Commitment: USD 84.00M Disbursed Amount: USD 86.00M

    Revised Amount: USD 84.00M

    Environmental Category: B

    Implementing Agencies:

    Directorate General Water Resources of Ministry of Public Works (DGWR-MOPW)

    Directorate General Regional Development of Ministry of Home Affairs (DGRD-MOHA)

    Directorate General Land and Water of Ministry of Agriculture (MOA)

    Co-financiers and Other External Partners: Government of Netherlands (USD 14 Million)

    B. Key Dates

    Process Date Process Original Date Revised / Actual

    Date(s)

    Concept Review: 12/17/2001 Effectiveness: 11/24/2005 11/24/2005

    Appraisal: 03/17/2003 Restructuring(s):

    Approval: 06/26/2003 Mid-term Review: 03/17/2008 03/28/2008

    Closing: 12/31/2009 12/31/2010

    C. Ratings Summary

    C.1 Performance Rating by ICR

    Outcomes: Moderately satisfactory

    Risk to Development Outcome: Moderate

    Bank Performance: Moderately Satisfactory

    Borrower Performance: Moderately Satisfactory

    C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

    Bank Ratings Borrower Ratings

    Quality at Entry: Moderately

    Satisfactory Government:

    Moderately

    Satisfactory

    Quality of

    Supervision: Satisfactory

    Implementing

    Agency/Agencies: Satisfactory

  • ii

    Overall Bank

    Performance: Moderately

    Satisfactory Overall Borrower

    Performance: Moderately

    Satisfactory

    C.3 Quality at Entry and Implementation Performance Indicators

    Implementation

    Performance Indicators

    QAG Assessments

    (if any) Rating

    Potential Problem

    Project at any time

    (Yes/No):

    No Quality at Entry

    (QEA): Satisfactory

    Problem Project at any

    time (Yes/No): Yes

    Quality of

    Supervision (QSA): None

    DO rating before

    Closing/Inactive status: Satisfactory

    D. Sector and Theme Codes

    Original Actual

    Sector Code (as % of total Bank financing)

    General water, sanitation and flood protection sector 50 30

    Irrigation and drainage 50 70

    Theme Code (as % of total Bank financing)

    Rural services and infrastructure 50 50

    Water resource management 50 50

    E. Bank Staff

    Positions At ICR At Approval

    Vice President: Pamela Cox Jemal-ud-din Kassum,

    Country Director: Stefan G. Koeberle Andrew Steer

    Sector Manager: Franz R. Drees-Gross Mark D. Wilson

    Project Team Leader: Xiaokai Li Guy Alaerts

    ICR Team Leader: Xiaokai Li

    ICR Primary Author: Xueming Liu &

    John Weatherhogg ( FAO/CP)

    F. Results Framework Analysis

    Project Development Objectives (from Project Appraisal Document)

    (a) Water allocation, water quality and water conservation improved in Project basins, and

    river infrastructure better maintained, through strengthened capacity for planning and

    management; and investments;

    (b) Sector governance enhanced, and sector fiscal sustainability strengthened, nationally,

    and in Project basins, through setting up Water Resources Councils; ensuring stakeholder‟s

  • iii

    involvement; unbundling of operational tasks, and Private Sector Participation; and improved

    cost recovery; and

    (c) Increased agricultural productivity and improved performance of irrigation, based on

    participatory irrigation management, through setting up and strengthening WUAFs;

    strengthening restructured Dinas PUP of local government; financing rehabilitation and

    improvement of existing irrigation schemes; and facilitating access to agricultural support

    services and micro-credit.

    The project development objective stated in the Development Credit Agreement (DCA) is as

    follows: The objective of the Project is to assist the Borrower in attaining a strengthened

    water resources sector by improving the performance of its water resources and irrigation

    sector, and rehabilitating and upgrading the infrastructure of the said sector.

    Revised Project Development Objectives (as approved by original approving authority)

    There is no revision of project development objectives in the course of project

    implementation. There are some discrepancies between the monitoring indicators of the DCA

    and those of the PAD. As per advice of the Operations Support Team of the EAP Sustainable

    Development Department, the indicators from the PAD were used for reporting below.

  • iv

    Indicator Baseline Value

    Original Target

    Values Formally Revised

    Target Values Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 Allocation of deliverable water more equitable for all competing uses and needs (incl.

    environmental).

    Value

    quantitative

    or

    Qualitative

    No

    participatory

    water allocation

    planning

    practiced

    >75% of demand being

    met in each sub-sector,

    in 5 project Basins

    Participatory allocation

    planning was piloted in 5

    river basins and is being

    practiced in 9 river

    basins, enabling more

    equitable water

    allocation for all uses.

    However, no information

    is available on the exact

    percentage of sub-sector

    water demand met.

    Date

    achieved

    31-May-2003 31-December-2006 31-December-2010

    Comments

    Achievement: Virtually achieved based on the number of river basins practicing

    participatory water allocation planning

    Indicator 2 System of water pollution monitoring and control effective

    Value

    quantitative

    or

    Qualitative

    No basin

    oriented water

    pollution

    monitoring and

    control system

    in place

    System of water

    pollution monitoring

    and control, incl.

    discharge permits and

    fees, effective in 1

    Project Basin

    Water quality monitoring

    is practiced in 27

    participating basins and

    water quality databases

    established. The data

    collected was shared

    with the respective

    environmental agency

    responsible for water

    pollution control,

    discharge permit, and

    fees, for further action.

    Date

    achieved

    31-May-2003 31-December-2006 31-December-2010

    Comments

    Achievement: partially achieved. Water quality/pollution monitoring target fully achieved

    while there is no data available on the effectiveness of water pollution control (discharge

    permit and fees, etc)

    Indicator 3 Economic losses reduced as river infrastructure development and O&M are better geared

    to regional priorities and sustained cost recovery.

    Value

    quantitative

    or

    Qualitative

    River

    infrastructure

    development

    and O&M were

    carried out

    without public

    consultation

    Economic losses

    reduced as river

    infrastructure

    development and O&M

    are better geared to

    regional priorities and

    sustained cost recovery.

    Priority maintenance of

    key river infrastructure

    in 54 Balai PSDA is

    based on public

    consultation and

    participation. O&M cost

    is met through

    government budget as

    cost recovery through

    service fees was

    precluded by Law No.

    7/2004.

    Date

    achieved

    31-May-2003 31-December-2006 31 December-2010

  • v

    Comments Achievement: largely achieved, based on the fact that river infrastructure development and

    O&M are better aligned with regional priorities and needs through consultation and

    participation.

    Indicator 4 Balai PSDA plan basin operations and investments based on BWRMPs

    Value

    quantitative

    or

    Qualitative

    BWRMP

    prepared for 2

    basins (Pekalen

    Sampean and

    Bodri Kuto)

    In 3 basins the Balai

    PSDAs plan basin

    operations and

    investments based on

    Basin Water Resource

    Management Plans

    (BWRMPs)

    In 20 project basins the

    BWRMPs were prepared

    and six of these plans

    were legalized and are

    being used as the basis

    for basin operations and

    investments.

    Date

    achieved

    31-May-2003 31-December-2006 31 December-2010

    Comments Achievement: over 100% by the number of basins where basin operations and investments

    are based on BWRMPs.

    Indicator 5 Demonstrable improvement in construction quality and contract management, annual

    work programs based on cost-effectiveness, improved inter-agency coordination.

    Value

    quantitative

    or

    Qualitative

    Construction

    work program

    was prepared

    through top-

    down approach,

    with little inter-

    agency

    coordination

    Demonstrable

    improvement in

    construction quality and

    contract management;

    annual work programs

    based on cost-

    effectiveness;

    Improved inter-agency

    coordination.

    Construction quality and

    contract management

    improved through

    beneficiary participation;

    Work program more cost

    effective because of end

    user participation in

    investment prioritization;

    Inter-agency

    coordination established

    and strengthened through

    river basin councils

    Date

    achieved

    31-May-2003 31-December-2006 31 December-2010

    Comments

    Contract management follows established procedures but more transparent with better

    quality results by involving beneficiaries. Achievement: largely achieved

    Indicator 6 A National Water Council and its Secretariat develop policies for fiscal sustainability and

    sector governance and resolve inter-agency conflict

    Value

    quantitative

    or

    Qualitative

    There was no

    dedicated

    multi-

    stakeholder

    coordination

    setup for water

    sector.

    A National Water

    Council has appropriate

    stakeholders

    representation,

    reflecting gender

    sensitivity, and has its

    Secretariat fully

    established, staffed,

    funded and operational

    as evidenced by policy

    decisions made.

    Target remained the

    same, and achievement

    date amended to

    become December 31,

    2010.

    A National Water

    Council (NWC)

    established with multi-

    stakeholder

    representation in 2009,

    and its secretariat fully

    functional with adequate

    staff and funding from

    National Budget

    (APBN); A National

    Water Resources Policy

    was prepared by NWC in

    2010 and enacted in

    2011.

    Date

    achieved

    31-May-2003 31-December-2006 31-December-2010 31-December-2010

    Comments Achievement: 100% based on establishment of a NWC with a fully functional Secretariat

    Indicator 7 Number of Participating Provinces that have established Provincial and Basin Water

  • vi

    Resources Councils (PWRC and BWRC ) with appropriate stakeholder representation

    Value

    quantitative

    or

    Qualitative

    Provincial

    Water

    Resources

    Management

    Committees

    (PTPA) existed

    in a small

    number of

    provinces,

    without

    stakeholder

    participation.

    In 12 Provinces and 15

    basins multi-

    stakeholder Water

    Resources Councils

    reflecting sensitivity

    towards gender

    sensitivity and

    vulnerable groups are

    established, and

    demonstrably influence

    regulations, water

    allocation investments

    and budgets.

    50% of the Participating

    Provinces establish

    PWRCs with proper

    stakeholder

    representation, and 50%

    of these provinces in

    process of establishing

    BWRCs.

    Target achievement

    date amended to be

    December 31, 2010.

    13 out of 14 provinces

    established PWRCs, with

    9 fully functional and 5

    out of the 9 PWRCs

    finalizing the provincial

    water resources policy.

    9 out of the 14 provinces

    established a total of 16

    BWRCs that were

    engaged in basin

    strategic plan review and

    water use conflict

    resolution.

    Date

    achieved

    31-May-2003 31-December-2006 31-December-2010 31-December-2010

    Comments

    Achievement: over 100% based on the number of total PWRCs and BWRCs established

    (against amended targets)

    Indicator 8 Basin Water Resources Management Plans (BWRMP)adopted by the local parliament

    (DPRD) and the Provincial Water Resources Council

    Value

    quantitative

    or

    Qualitative

    2 Basin Water

    Resources

    Management

    Plan are

    prepared, have

    not been

    discussed in

    PPTPA.

    3 BWRMPs adopted by

    DPRD and Provincial

    Water Resources

    Councils.

    9 basin strategic plans /

    BWRMP have been

    reviewed and adopted by

    the Provincial Water

    Resources Councils/local

    parliament (DPRD).

    Date

    achieved

    31-May-2003 31-December-2006 31 December-2010

    Comments

    Achievement: over 100% based on the number of BWRMPs adopted

    Indicator 9

    Local Government (Pemda) budget allocation covers 50% of Balai PSDA operating cost;

    abstraction and effluent discharge fee revenue covers 25% of operational expenditures of

    a new river basin corporation (RBC)

    Value

    quantitative

    or

    Qualitative

    In Balai PSDAs

    established

    prior to the

    project, major

    part of the

    budget

    originated

    from central

    government

    In 3 basins, earmarked

    Pemda budget

    allocation covers 50%

    of Balai PSDA

    operating costs;

    Abstraction and effluent

    discharge fee revenue

    covers 25% of

    operational

    expenditures of a new

    basin organization

    (RBC)

    In each of the 14 Participating Provinces

    for each basin under their

    authority, a Balai PSDA

    established in each of 14

    provinces for every

    provincial basin with

    100% funding

    (structural) from

    provincial budget

    (APBD). Effluent

    discharge fee not

    allowed by the Water

    Law No. 7/2004.

    Date

    achieved

    31-May-2003 31-December-2006 31 December-2010

    Comments

    Achievement: fully achieved if measured by the number of basins where the Balai PSDAs

    get 50% of their operating costs from APBD.

    Indicator10 Operational Framework prepared to pilot more commercial approach in APL II

    Value Operational Operational Framework Operational framework

  • vii

    quantitative

    or

    Qualitative

    framework not

    available

    prepared to pilot more

    commercial approach in

    APLII

    based on public service

    corporation (BLU)

    concept developed but

    not yet accepted by the

    National Government.

    Date

    achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments

    Financial administrative regulations require a full separation of management entities of

    BLU and Balai WS. This issue was not resolved during WISMP2 (APLII) negotiations so

    the BLU could not be officially included in WISMP2. Achievement: partially achieved

    Indicator11 Public irrigation schemes in kabupaten are governed by WUAFs in partnership with

    kabupaten government.

    Value

    quantitative

    or

    Qualitative

    493,540 ha

    irrigation area

    adopted joint

    management;

    166,173 ha

    rehabilitated

    and managed

    by WUAF with

    technical and

    matching grant

    financial

    support;

    Irrigation

    commissions

    established in

    50 Kabupatens

    50% of public irrigation

    schemes in 70

    kabupaten (690,000 ha)

    managed by WUAFs in

    partnership with

    Kabupaten government;

    At least 25% of

    secondary canal

    services (345,000 ha)

    managed by WUAFs

    with technical and

    matching grant financial

    support;

    Kabupaten Irrigation

    Commissions

    operational in 70

    Kabupaten

    A total of 1,027,194 ha

    of public irrigation areas

    governed by WUAFs in

    partnership with

    kabupaten or provincial

    government agencies

    (>100%);

    Secondary canals serving

    354,464 ha rehabilitated

    and managed by WUAFs

    jointly with Kabupaten

    irrigation agencies

    providing technical and

    financial support

    (>100%); and 12

    Provincial and 95

    Kabupaten Irrigation

    Commissions operational

    (>100%).

    Date

    Achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments Achievement: over 100% (See above)

    Indicator 12 Active participation of women farmers in WUAs and WUAFs enhanced

    Value

    quantitative

    or

    Qualitative

    Women were

    rarely active in

    the WUAs and

    WUAFs.

    Active participation of

    women farmers in

    WUAs and WUAFs

    enhanced

    Women‟s participation in

    WUAs and WUAFs is

    stimulated through their

    inclusion in training and

    provision of female

    community organizers or

    facilitators (30%),

    resulting in increased

    active women

    participation in many

    WUA/WUAF boards,

    now accounting for 5%-

    7% of total board

    members.

    Date

    achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments Achievement: fully achieved, based on qualitative assessment of women‟s participation in

    WUAs and WUAFs

    Indicator 13 Capacity of 70 Kabupaten Irrigation Departments Improved

    Value

    quantitative

    Participatory

    irrigation

    Capacity of 70

    Kabupaten Irrigation

    99 Kabupaten and 12

    provinces restructured

  • viii

    or

    Qualitative

    management

    newly

    introduced

    Departments Improved their irrigation

    departments, issued

    Regulations on

    Irrigation, and trained

    their staff (about 7,000)

    in participatory irrigation

    management, rapid

    assessments, and

    supporting user

    communities.

    Date

    achieved

    31-May-2003 31-December-2006 31 December 2010

    Comments: Achievement: over 100% measured by the number of Kabupaten irrigation departments the

    capacity of which has been improved under the project

    Indicator 14 Reduction in Government rehabilitation investment expenditures by 10% by transfer of

    tasks and budgets to WUAFs

    Value

    quantitative

    or

    Qualitative

    Contribution of

    the WUAFs to

    rehabilitation

    cost piloted in

    the irrigation

    systems under

    previous

    IWIRP project.

    Reduction in

    Government

    rehabilitation

    investment expenditures

    by 10% by transfer of

    tasks and budgets to

    WUAFs

    Participatory

    construction enabled

    WUAF contributions in

    form of labor, materials

    and sometimes cash, and

    related budget transfer to

    them. WUAFs‟

    contributions reached

    10% of rehabilitation

    cost, and led to better

    quality and longer use

    life of project works

    Date

    achieved

    31-December-2006 31- December-2010

    Comments Achievement : 100% by percentage of WUAF contribution to government system

    rehabilitation investment expenditures

    Indicator 15 Matching contributions from WUAFs for O&M of schemes are at least 20% of expenditure

    in half of the schemes and increase in all schemes.

    Value

    quantitative

    or

    Qualitative

    There was no

    mechanism for

    WUAF to

    participate in

    the O&M

    activities. If

    any, it was

    done in an ad

    hoc manner.

    Matching contributions

    from WUAFs for O&M

    of irrigation schemes

    are at least 20% of

    expenditure in half of

    the schemes and

    increase in all schemes.

    For O&M of public

    systems the WUAF

    contributed in form of

    labor amounting to 20%

    or more of the O&M

    cost. In general,

    WUAFs‟ contributions to

    O&M of all the project

    schemes have increased.

    Date

    Achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments: Achievement: full achieved

    Indicator 16 Irrigation O&M budgets of 11 provinces and 70 kabupaten reach a satisfactory and

    sustainable level.

    Value

    quantitative

    or

    Qualitative

    The local

    budget (APBD)

    allocated for

    irrigation

    system O&M is

    erratic and

    marginal, well

    below the level

    of 60,000Rp/ha

    level.

    Irrigation O&M budgets

    of 11 provinces and 70

    Kabupaten reach a

    satisfactory and

    sustainable level.

    At least15 Participating

    Kabupaten provide

    from their APBD at

    least Rp60,000/ha per

    year for O&M over the

    total irrigated areas.

    Target achievement

    date amended to be

    December 31, 2010.

    9 Provinces and

    71Kabupaten,

    representing a total of

    1,387,000 ha of irrigated

    areas, allocated O&M

    budgets of over 60,000

    Rp/ha(average 130,000

    Rp/ha). About 30% of

    these provinces and

    Kabupatens in 2010

  • ix

    matched or exceeded

    150,000 Rp/ha.

    Date

    achieved

    31-May-2003 31-December-2006 31-December-2010 31- December-2010

    Comments: Achievement: 99% against original target and 500% against amended target of total

    number of provinces and Kabupatens that provided satisfactory level of O&M budget

    Indicator 17 No decrease in average and median farm income in 30 irrigated kabupaten, and

    mechanisms in place that will increase income over WISMP2

    Before the

    project the

    irrigation water

    efficiency tends

    to decline,

    causing

    decrease in

    production and

    farm income.

    No decrease in average

    median farm income in

    30 irrigated Kabupaten,

    and mechanisms in

    place that will increase

    income during

    WISMP2

    Government statistics

    showed significant

    increase in farm income

    in all Participating

    Kabupaten, especially in

    18 Kabupaten where

    agricultural support was

    piloted, although no

    project specific

    monitoring data

    available. Investments in

    capacity building in all

    99 Kabupaten

    contributed to better

    water management and

    to increasing farm

    income under WISMP

    Date

    Achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments: Achievement: fully achieved, based on the qualitative assessment

    Indicator 18 Increase in ERR of benefits based on income from higher rice yield and higher value

    crops; and improved farm gate prices.

    Crop yield was

    generally

    decreasing due

    to declining

    irrigation

    system

    performance.

    Most farmers

    sell their

    products to the

    mediators /

    collectors at

    low price for

    quick cash.

    Increase in ERR of

    benefits based on

    income from higher rice

    yield and higher value

    crops; and improved

    farm gate prices.

    Crop production

    increased in project areas

    due to improved

    irrigation system

    performance leading to

    increase in both crop

    intensity and

    diversification, which

    was reflected in a re-

    calculated overall ERR

    of 23% (See Annex 3).

    Many WUAFs signed

    farming contracts with

    the private companies,

    enabling better prices of

    farm products although

    systematic record on

    farm gate prices are not

    available.

    Date

    Achieved

    31-May-2003 31-December-2006 31- December-2010

    Comments: Achievement: fully achieved based on economic analysis results

  • x

    G. Ratings of Project Performance in ISRs

    No. Date ISR Archived

    DO IP Actual

    Disbursements (USD millions)

    1 12/30/2003 Satisfactory Satisfactory 0.00

    2 06/25/2004 Satisfactory Unsatisfactory 0.00

    3 12/20/2004 Satisfactory Unsatisfactory 0.00

    4 06/01/2005 Moderately Satisfactory Unsatisfactory 0.00

    5 06/27/2005 Moderately Satisfactory Satisfactory 0.00

    6 06/27/2005 Moderately Satisfactory Satisfactory 0.00

    7 06/07/2006 Moderately Satisfactory Moderately Satisfactory 6.15

    8 06/25/2007 Moderately Satisfactory Moderately Satisfactory 7.20

    9 06/23/2008 Satisfactory Satisfactory 18.76

    10 06/26/2009 Satisfactory Satisfactory 37.90

    11 12/24/2009 Satisfactory Satisfactory 42.16

    H. Restructuring (if any)

    N/A

    I. Disbursement Profile

    The actual disbursement is the total of credit, loan and grant while the original and

    formally revised amounts do not include the grant amount.

  • xi

    For NTB-WRMP:

    A. Basic Information

    Country: Indonesia Project Name:

    EC GRANT - ID

    NTB-River Basin

    Water Resources

    Management Program

    Project ID: P095128 L/C/TF Number(s): TF-55997

    ICR Date: 03/29/2012 ICR Type: Core ICR

    Lending Instrument: SIL Grantee: REPUBLIC OF

    INDONESIA

    Original Total

    Commitment:

    Euro 9.05 M

    (USD 12.00 M

    equivalent)

    Disbursed Amount: N/A

    Revised Amount:

    Euro 9.50M

    (USD 11.36M

    equivalent)

    Disbursed Amount

    Euro 9.46M

    (USD11.31M

    equivalent)

    Environmental Category: U

    Implementing Agencies:

    Directorate General Water Resources of Ministry of Public Works (DGWR-MOPW)

    Directorate General Regional Development of Ministry of Home Affairs (DGRD-MOHA)

    Directorate General Land and Water of Ministry of Agriculture (MOA)

    Co-financiers and Other External Partners: European Commission(EC)

    B. Key Dates

    Process Date Process Original Date Revised / Actual

    Date(s)

    Concept Review: * Effectiveness: 12/27/2005 12/27/2005

    Appraisal: * Restructuring(s): N/A N/A

    Approval: * Mid-term Review: 03/28/2008 02/19/2008

    Closing: 06/30/2011 06/30/2011

    * There was no formal concept review, appraisal and Board approval.

    C. Ratings Summary

    C.1 Performance Rating by ICR

    Outcomes: Moderately satisfactory

    Risk to Development Outcome: Moderate

    Bank Performance: Moderately satisfactory

    Grantee Performance: Moderately Satisfactory

    C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

    Bank Ratings Borrower Ratings

    Quality at Entry: Moderately

    Satisfactory Government:

    Moderately

    Satisfactory

  • xii

    Quality of

    Supervision: Satisfactory

    Implementing

    Agency/Agencies: Satisfactory

    Overall Bank

    Performance: Moderately

    Satisfactory Overall Borrower

    Performance: Moderately

    Satisfactory

    C.3 Quality at Entry and Implementation Performance Indicators

    Implementation

    Performance Indicators

    QAG Assessments

    (if any) Rating

    Potential Problem

    Project at any time

    (Yes/No):

    No Quality at Entry

    (QEA): None

    Problem Project at any

    time (Yes/No): No

    Quality of

    Supervision (QSA): None

    DO rating before

    Closing/Inactive status: Satisfactory

    D. Sector and Theme Codes

    Original Actual

    Sector Code (as % of total Bank financing)

    General water, sanitation and flood protection sector 50 30

    Irrigation and drainage 50 70

    Theme Code (as % of total Bank financing)

    Rural services and infrastructure 67 67

    Water resource management 33 33

    E. Bank Staff

    Positions At ICR At Approval

    Vice President: Pamela Cox Jemal-ud-din Kassum

    Country Director: Stefan G. Koeberle Andrew Steer

    Sector Manager: Franz R. Drees-Gross Mark D. Wilson

    Project Team Leader: Xiaokai Li Guy Alaerts

    ICR Team Leader: Xiaokai Li

    ICR Primary Author: Xueming Liu &

    John Weatherhogg ( FAO/CP)

    F. Results Framework Analysis

    Project Development Objectives (from Grant Agreement)

    The objective of the Grant is to assist the Recipient in strengthening the water

    resources and irrigation sector in the Province of Nusa Tenggara Barat and in the

    Kabupatens of the said province by improving the performance of the Province's and

  • xiii

    the Kabupatens' water resources and irrigation sector, and rehabilitating and

    upgrading its infrastructure of the said sector.

    Revised Project Development Objectives (as approved by original approving authority)

    There is no revision of the project development objective in the course of project

    implementation.

    There is no PAD for this project, therefore the performance indicators in the 2005

    Grant Agreement (amended in 2009) are used for the analysis.

    Indicator Baseline

    Value

    Original Target

    Values (from

    approval

    documents)

    Formally Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1

    A Provincial Water Resources Council (PWRC) with appropriate stakeholder

    representation and its Secretariat established and functional.

    Value

    quantitative or

    Qualitative

    No provincial

    water resources

    council exists.

    A PWRC, with

    Secretariat,

    established with

    representative

    stakeholder

    representation,

    reflecting gender

    sensitivity established

    and functional with

    evidence

    A PWRC established

    with a fully staffed and

    funded secretariat in

    2009. PWRC includes

    women and

    vulnerable group

    representatives. It is

    functional, and has

    discussed provincial

    policy on climate

    change adaptation, and

    resolved water use

    conflicts.

    Date achieved 20-December-

    2005 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    The PWRC and its Secretariat established with appropriate representation and fully

    functional. Achievement: fully achieved

    Indicator 2 Basin Water Resources Councils (BWRCs) established with appropriate stakeholder

    representation and functional.

    Value

    quantitative or

    Qualitative

    No provincial

    basin water

    resources

    council exists.

    All BWRCs

    established covering

    the whole territory of

    the Province and each

    BWRC has

    representative

    stakeholder

    representation.

    Two BWRCs are

    established in Sumbawa

    and Bima-Dompu

    covering the whole

    Island of the province,

    each with representative

    stakeholder

    representation.

    Two BWRCs

    established with

    required representation

    in NTB. BWRC

    Lombok established in

    2009 and functional -

    discussed strategic

    plan and basin

    management issues;

    BWRC Bima -Dompu

    established in 2010,

    and BWRC Sumbawa

    in 2011

    Date achieved 20-December-

    2005 30-June-2011 30-June-2011 30-June-2011

    Comments

    (incl. %

    Achievement: 100% by number of BWRCs established (According to Water Law

    No.7/2004, BWRC establishment is based on need).

  • xiv

    achievement)

    Indicator 3 Balai PSDA covering entire provincial territory established and operational with

    trained staff.

    Value

    quantitative or

    Qualitative

    No formal basin

    unit or Balai

    PSDA exists.

    All UPTD/ Balai

    PSDA established,

    covering the entire

    Province, adequately

    staffed and

    operational, and at

    least half of such

    entities are receiving

    50% of their

    operational budget

    form the Province

    Government

    Three Balai PSDAs

    and one Balai ISDA

    established and

    functional. Necessary

    training carried out

    with over 100

    personnel trained.

    These entities are

    receiving over 50% of

    their budgets for

    operations, from

    Provincial

    Government.

    Date achieved 20-December-

    2005 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    All Balai PSDA established covering the whole territory of the Province, and

    appropriately staffed and fully operational. Achievement: 100% by number of Balai

    PSDA.

    Indicator 4

    A decree of Dinas PUP has been issued for role sharing in hydrometeorology between

    the relevant Dinas PUP and UPTD or Balai PSDA, and the hydromet network is

    operational.

    Value

    quantitative or

    Qualitative

    There were no

    dedicated funds

    for hydromet

    work in the

    Balai, although

    limited funds

    available in

    Dinas for this

    purpose.

    A Dinas PUP Surat

    Keputusan has been

    issued for role

    sharing in

    hydrometeorology

    between the relevant

    Dinas PUP and

    UPTD or Balai PSDA

    in the Province.

    Hydromet asset mgt

    fully transferred from

    the Dinas PUP to the

    relevant UPTD or

    Balai PSDA and

    hydromet network

    fully operational

    A decree of Dinas

    PUP issued, 4 Joint

    Operation Agreements

    between Dinas PUP

    and Balai PSDA

    Lombok, Balai PSDA

    Sumbawa,

    Balai PSDA Bima-

    Dompu and Balai

    ISDA signed in 2007.

    Hydromet asset mgt.

    transferred; and and

    hydrometric data being

    collected and

    managed by Balai

    ISDA.

    Date achieved 20-December-

    2005 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: largely achieved.

    Indicator 5 The provincial planning unit in Dinas PUP appropriately staffed and funded, and

    producing basin water resources management plans.

    Value

    quantitative or

    Qualitative

    There was no

    planning unit in

    the Dinas PUP.

    The provincial

    planning unit in

    Dinas PUP

    appropriately staffed

    and funded, and

    producing basin

    water resources

    management plans.

    The Provincial

    Planning Team in Dinas

    PUP established,

    appropriately staffed

    and funded and capacity

    developed to prepare

    strategic and master

    plans for river basins

    under the authority of

    the Province.

    The planning function

    integrated into the

    structural functions of

    Dinas PUP. A

    provincial planning

    team established

    supervising outsourced

    planning services;

    strategic plans for

    Lombok and Bima

  • xv

    Dompu basins

    completed and

    legalized.

    Date achieved 20-December-

    2005

    30-June-2011 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: virtually achieved based on the number of basin plans completed.

    Indicator 6 : Quality assurance plans and infrastructure maintenance plans produced and being

    implemented.

    Value

    quantitative or

    Qualitative

    There was no

    Quality

    Assurance Plans

    in existence.

    Quality Assurance

    Plans and river

    infrastructure

    maintenance plans

    produced and being

    implemented.

    Quality Assurance

    Plans and irrigation

    infrastructure

    maintenance plans

    produced and being

    implemented.

    Quality Assurance

    Core team established,

    quality assurance and

    maintenance plans

    produced and being

    implemented, and

    annual river

    infrastructure

    maintenance plans

    prepared in

    consultation with

    stakeholder and

    implemented.

    Date achieved 20-December-

    2005

    30-June-2011 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: fully achieved.

    Indicator 7 : Area of irrigation system is co-managed by WUAFs.

    Value

    quantitative or

    Qualitative

    There was no

    co-management

    arrangements

    for irrigation

    system

    At least 60,000 ha of

    irrigation system is

    co-managed by

    WUAFs, resulting in

    demonstrable

    operation and

    maintenance, crop

    productivity, water

    use efficiency, and

    reduced levels of

    infrastructure

    deterioration.

    145,000 ha of

    irrigation schemes co-

    managed with

    WUAFs;

    crop productivity

    increased 4.4% and

    harvested areas

    increased 24.5%; and

    infrastructure

    improved with longer

    life expected.

    Date achieved 20-December-

    2005 30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: 225% by number of hectare co-managed by WUAFs.

    Indicator 8 Number of WUAFs established in 7 Participating Kabupatens.

    Value

    quantitative

    or

    Qualitative

    No WUAF

    request

    mechanism

    was in

    At least 160

    WUAFs in 7

    Kabupatens

    established,

    presented to

    respective

    The Province and 7

    Kabupatens issued

    Perdas and

    established

    Irrigation

    Commissions; A

  • xvi

    existence.

    Irrigation

    Commissions IMF

    funding proposals

    endorsed by the

    relevant Dinas

    PUP.

    total of 214 WUAFs

    established;

    WUAFs‟ proposals

    presented to

    Irrigation

    Commissions.

    Date

    achieved

    20-

    December-

    2005

    30-June-2011 30-June-2011

    Comments

    (incl.%

    achievement)

    Achievement: 135% by number of WUAFs established.

    Indicator 9 Number of IMF funding proposals received by the Irrigation Commissions from

    WUAFs in the 7 Participating Kabupaten.

    Value

    quantitative

    or

    Qualitative

    Neither

    WUAF

    request

    mechanism

    nor Irrigation

    Commission

    exists.

    In 7 Participating

    Kabupaten, the

    Irrigation

    Commissions

    received, reviewed,

    evaluated and

    recommended at

    least 100 WUAFs‟

    proposals for IMF

    funding endorsed

    by the relevant

    Dinas PUP.

    The Irrigation

    Commission

    received and

    evaluated over 100

    proposals endorsed

    by the Dinas PUP,

    and 91 proposals

    were recommended

    for IMF funding.

    Date

    achieved

    20-

    December-

    2005

    30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: 100% by number of proposals received by the Irrigation

    Commissions and endorsed by Dinas PUP.

    Indicator 10 Number of Participating Kabupaten that provide from APBD at least 60,000 Rp/ha

    O&M budget for their project schemes.

    Value

    quantitative

    or

    Qualitative

    Local budget

    (APBD)

    allocated for

    irrigation

    system O&M

    was erratic

    and marginal,

    well below

    the level of

    60,000Rp/ha

    level.

    At least 3

    Kabupaten

    supplied from their

    APBD, at least

    60,000 Rp/ha per

    year of IMF funds

    over the total

    irrigated area in

    their respective

    Kabupatens,

    besides required

    counterpart budget

    The Province and 4

    Kabupatens

    allocated over

    60,000 Rp/ha O&M

    budget through

    APBD. All 7

    Participating

    Kabupatens

    provided required

    counterparts budgets

    for project

    implementation.

    Date

    achieved

    20-

    December-

    2005

    30-June-2011 30-June-2011

    Comments

    (incl. %

    achievement)

    Achievement: 100% by number of Kabupaten providing the required O&M budget.

  • xvii

    G. Ratings of Project Performance in ISRs

    No. Date ISR Archived

    DO IP Actual

    Disbursements (USD millions)

    1 06/25/2008 Satisfactory Moderately Satisfactory 3.79

    2 06/24/2009 Satisfactory Satisfactory 5.63

    3 02/13/2010 Satisfactory Satisfactory 8.97

    4 06/27/2011 Satisfactory Highly Satisfactory 12.21

    H. Restructuring (if any)

    N/A

    I. Disbursement Profile

    The Grant has been fully disbursed. Disbursement Profile for NTB-WRMP is not

    available in the system because it is not treated as a separate project due to its special

    relation with the WISMP 1 project, although NTB-WRMP has its own project

    number.

  • 1

    1. Project Context, Development Objectives and Design

    1.1 Context at Appraisal

    1.1.1 Country and sector background: Water resources and irrigation management plays an

    important role in Indonesia‟s socio-economic development in terms of food security since

    most grain production is from irrigated areas. Development of water resources and irrigation

    between the 1970s and mid 1980s focused on achieving and maintaining self sufficiency in

    rice after a period of serious food shortages. During five consecutive five-year plan periods

    starting in 1969, some 2.5 million hectares of irrigation areas were rehabilitated and 1.7

    million hectares of new areas were developed. River basin management was mainly seen as a

    requirement for securing irrigation supply and flood protection. Such efforts were supported

    by massive expansion and farm input programs leading to self sufficiency in rice in 1984.

    1.1.2 However, the government could not maintain rice self-sufficiency after that. One of

    the main reasons was the lack of attention to and funding for operation and maintenance

    (O&M) of the newly rehabilitated and developed irrigation systems. The subsequent rapid

    deterioration of the physical systems resulted in frequent and premature rehabilitation or

    deferred maintenance of the infrastructure. In the late 1990s it became clear that such a supply

    driven approach led to unsustainable use of water resources and poor cost recovery.

    1.1.3 In response to the financial crisis, the government embarked in 1998 on a process of

    democratization and decentralization. This also involved reform of the water resources and

    irrigation sector aiming at devolution and unbundling of management responsibilities to

    provincial and district governments. It introduced stakeholder participation to enhance

    sustainable management of the resource and infrastructure, and put more emphasis on demand

    responsive and decentralized service delivery.

    1.1.4 These reforms were fully supported by the Bank. The Country Assistance Strategy

    (CAS) (2001) had three main objectives, (a) promoting broad-based growth; (b) building

    national institutions for accountable government;, and (c) delivering better public services to

    the poor, including support to local governments that put reform into practice. The WISMP

    program and this first phase project contributed substantially to objectives (b) and (c) of the

    CAS.

    1.1.5 Rationale for Bank Assistance: After the 1997/98 financial crisis, the Bank played a

    leadership role through its support to the regulatory reform (Water Resources Sector

    Adjustment Loan (WATSAL, Ln. 4469-IND) (1999 - 2003)) and the large-scale field pilot of

    new institutional arrangements for irrigation and basin water resources management (Java

    Irrigation Improvement and Water Management Project (JIWMP, Ln. 37624) (1995 - 2002)

    and Indonesia Water and Irrigation Reform Implementation Project (IWIRIP, TF 29896)

    (2001 - 2004) resulting in a new Law on Water Resources in 2004. Other donors were also

    actively supporting the reform process, leading to the formation of the Donor Water

    Resources Sector Support Group in October 2000. The Asian Development Bank (ADB) and

    the Japan Bank for International Cooperation (JBIC), which both held larger water resources

    portfolios than the bank, increasingly adopted the principles and concepts emerging from

    JIWMP and WATSAL. As a result, both ADB and JBIC harmonized their own project

    designs, culminating in the ADP Participative Irrigation Project (PISP) and participatory

    approaches in JBIC loans for small-scale irrigation management projects. The Government of

    Indonesia‟s intention was to implement these reforms in the decade up to 2014. Due to its

    deep involvement in WATSAL and the other projects piloting the reforms, the Bank was well

    positioned to support WISMP to implement and further the sector reforms. Furthermore, the

    Bank‟s long-standing involvement in Indonesia‟s water sector provided a sound basis for

    project design, in particular sequencing priorities and benefiting from earlier project

    implementation experiences.

  • 2

    1.1.6 When GOI and the European Union (EU) decided to undertake a project with similar

    institutional reform goals with more poverty focus in the province of Nusa Tenggara Barat

    (NTB), it was agreed that the EU grant could best be administered by the Bank. In addition to

    increasing the geographic coverage of the WISMP water sector reforms, it was in line with

    the on-going Good Governance in Water Resource Management Project (GGWRMP)

    financed by EU and covering three river basins (respectively in DI Yogyakarta, East Java and

    Lampung).

    1.2 Original Project Development Objectives and Key Indicators

    1.2.1 The WISMP was designed as a twelve-year adaptable program loan (APL). The

    WISMP program objectives were as follows:

    (a) Sustainable and equitable management of surface water resources and their

    utilization infrastructure by: (i) transparent sector governance institutions and, (ii)

    more accountable and better performing sector agencies;

    (b) Increased irrigation farm household incomes and improved regional food security

    as a result of raising the overall productivity of irrigated agriculture and reducing its

    vulnerability to natural and economic shocks through: (i) sustainable participatory

    irrigation management for more reliable and equitable water provision and, (ii) better

    agricultural and marketing support services for members of irrigation water user

    associations; and

    (c) More cost-effective and fiscally sustainable management of sector agencies.

    1.2.2 Within these overall program objectives the project development objectives of the

    WISMP Phase I (WISMP1) were stated as follows:

    (a) Water allocation, water quality and water conservation improved in Project basins,

    and river infrastructure better maintained, through strengthened capacity for planning

    and management; and investments;

    (b) Sector governance enhanced, and sector fiscal sustainability strengthened,

    nationally, and in Project basins, through setting up Water Resources Councils

    (WRCs); ensuring stakeholder involvement; unbundling of operational tasks, and

    Private Sector Participation; and improved cost recovery; and

    (c) Increased agricultural productivity and improved performance of irrigation, based

    on participatory irrigation management, through setting up and strengthening Water

    User Association Federations (WUAFs); strengthening restructured Local

    Government Public Works Water Resources Departments (Dinas PUPs); financing

    rehabilitation and improvement of existing irrigation schemes; and facilitating access

    to agricultural support services and micro-credit.

    All the triggers for WISMP to migrate to Phase II (WISMP2) were met satisfactorily and

    WIMSP 2 loan was approved in 2011, and is now under implementation. This ICR covers

    both the WISMP1 and NTB-WRMP projects as approved by the OPCS.

    1.2.3. The NTB-WRMP had similar institutional reform objectives with a more clear focus

    on poverty alleviation by being located in one of the poorest provinces of Indonesia over a

    five year project period. The purpose of the Grant was to assist the Recipient in attaining a strengthened water and irrigation sector in its Province of Nusa Tenggara Barat and in the

    Kabupatens in the said province by improving the performance of the Province‟s and the

    Kabupatens‟ water resources and irrigation sector, and rehabilitating and upgrading the

    infrastructure of said sector.

  • 3

    1.2.4 The Key Indicators identified for the WISMP project were as follows (See details in

    the Data Sheet):

    Governance and Institutional Capacity-building: National Water Council (NWC)

    established and focusing on implementation of the National Water Policy (as a transitional

    arrangement, the National Coordination Team (of Ministers) for Water Resources

    Management is upgraded). Basin policy decisions and basin agency operations are transparent

    and reviewed by provincial and basin councils or committees that include stakeholders

    (including representation of the interests of women and vulnerable isolated indigenous

    peoples). Irrigation schemes are governed by WUAFs in partnership with kabupatens via the

    Komisi Irigasi, which have stakeholder representation. Water use rights system piloted for

    more rational and fair water allocation and providing for in-stream needs.

    Management Performance of Sector Agencies: Management audits show that kabupaten

    agency assistance to WUAFs is participatory and effective, with Management Information

    System (MIS) being maintained, hydrology operations improving, and National Water

    Quality Monitoring Network operational in pilot sites.

    Fiscal Sustainability of Sector: Cost recovery mechanisms for river infrastructure

    maintenance identified and arrangements made for its implementation. Arrangements for fees

    on effluent discharges and for water abstraction were operationalized in two basins. KIIF

    funds disbursement on a matching basis under way.

    (Initiation of) Integrated Approach to Irrigated Agriculture Support: Farmers use extension

    services more regularly, raise income (i.e. increased farm incomes).

    1.2.5 The Key Indicators for NTB-WRMP were analogous to those for WISMP and were

    as follows (See details in the Data Sheet):

    (a) A Provincial Water Resources Council (PWRC) with appropriate stakeholder

    representation and its Secretariat established and functional;

    (b) Basin Water Resources Council (BWRC) established with appropriate

    stakeholder representation and functional; (c) Balai PSDA covering entire provincial territory established and operational

    with trained staff;

    (d) A Dinas PUP Surat Keputusan has been issued for role sharing in

    hydrometeorology between the relevant Dinas PUP and UPTD or Balai PSDA, and

    the hydromet network operational;

    (e) The provincial planning unit in Dinas PUP is established with appropriate

    staffing and funding, and starts producing strategic and master plans for provincial

    basins;

    (f) Quality Assurance Plans and infrastructure maintenance plans produced and

    being implemented;

    (g) At least 60,000ha of irrigation system is co-managed by WUAFs;

    (h) At least 160 WUAFs established in the 71 participating kabupaten;

    (i) At least 100 IMF funding proposals received by the Irrigation Commissions

    from WUAFs in the 7 Participating Kabupaten; and

    (j) At least 3 Participating Kabupaten provide from their APBD at least

    Rp60,000/ha O&M budget for their project schemes.

    1 Originally 6 kabupaten but later Sumbawa was split into two.

  • 4

    1.3 Revised PDO and Key Indicators

    1.3.1 The WISMP PDO remained the same throughout implementation. The loan/credit for

    the project was negotiated but the signing and effectiveness of the loan was delayed by two

    years because government wanted to ensure consistency with the new law on water

    resources only issued in 2004 (Law 7/2004). The consequent changes in the legal and

    institutional environment required changes to some key outcome indicators which were

    amended accordingly (as expressed in the restated Development Credit Agreement (DCA) of

    2009, and shown in the ICR Data Sheet). The PDO for NTB-WRMP was unchanged during

    implementation. The key outcome indicators were amended through the Grant Agreement, as

    shown in the ICR Data Sheet.

    1.4 Main Beneficiaries

    1.4.1 The primary target population of WISMP comprised:

    (a) The water users in the Project‟s river basins in the 14 Project provinces, notably

    men and women farmers, urban and rural settlements, industries, and communities

    that depend for their livelihood on water from the rivers;

    (b) Men and women farmers, as well as landless laborers and by extension the rural

    population, in the Project areas, as they will benefit from better water availability and

    from programs to assist in strengthening the rural economy. As the Project intended

    to cover approximately 2.35 million ha of irrigated area, it would affect around 6.7

    million farmer households or 40 million rural dwellers that directly depended on

    irrigation, whilst an additional group‟s income in the rural space depended indirectly

    on the performance of irrigated agriculture;

    (c)The population on Java as food security and environmental quality will be

    improved; and

    (d) The communities living in the upper catchment areas in the Project areas and that

    would be assisted with programs to improve the management of the soils and land

    cover to reduce soil erosion.

    1.4.2 For WISMP 1 at least 1.3 million poor farm families, especially share-croppers, as

    well as possibly 1 million daily laborers were likely to benefit directly from the more reliable

    irrigation service and increased income, and indirectly from improved access to agricultural

    information and extension services, and new business opportunities. For NTB-WRMP the

    beneficiaries were estimated at around 200,000 households.

    1.5 Original Components

    1.5.1 The WISMP1 project has the following three components:

    Component A. Basin Water Resources Management (Base Cost – US$56.7M)

    A1. Sector Governance and Basin Planning (Base cost – US$14.1M): to assist in

    establishing and/or strengthening of the following institutions: (a) National Water Council

    (NWC) and its precursor the Coordination Team (of Ministers) for Water Resources

    Management, with their Secretariats; (b) National Steering Committee for Water Resources

    (NSCWR) plus Secretariat; (c) Provincial Water Resources Council (PWRC) plus Secretariat,

    in 12 provinces; (d) Basin Water Resources Committees (BWRC) in project river basins; and

    (e) Dam Safety Commission (DSC) and Dam Safety Unit. In addition, Provincial Planning

    Units were to be established as well as the Central Basin Planning Unit.

  • 5

    A2. Management Capacity of Basin Agencies (Base Cost - US$10.4 M): to establish

    and/or strengthen the River Basin Management Units (Balai PSDA), under provincial budget

    and Basin Corporations (PJTs), including all studies, training and technical assistance.

    A3. Fiscal and Cost Recovery Policy (Base Cost - US$2.00 M): to establish and/or

    strengthen the fiscal position and cost recovery of water management in river basins through

    funding to the Balai PSDA, PJT (Basin Corporations), provincial and kabupaten Bapedaldas

    (Environmental Management Offices) and provincial Dinas PUP, contingent upon the Annual

    Work Plan/Program (AWP) review.

    A4. Basin Management and River Infrastructure Improvement (Base Cost - US$28.7

    M): including: (a) support for operation and monitoring; (b) river infrastructure maintenance

    (RIM) - operationalization of asset management and routine maintenance; (c) prioritized

    urgent repairs of key river and flood control infrastructure; and (d) establishment of a

    National Water Quality Monitoring Network.

    A5. National Capacity Building Network (Base Cost - US$1.6 M): To develop a

    sustainable human resources (HR) capacity building process for water resources and irrigation

    management, it was necessary to reorient higher education programs towards multi-

    disciplinary and integrated approaches.

    Component B. Participatory Irrigation Management (Base Cost - US43.0 M)

    B1. Water User Associations Capacity Building (Base Cost - US$8.3 M): to establish and

    operationalize: (a) Kabupaten Irrigation Commissions (Komisi Irigasi), with Kabupaten

    Dinas, WUAFs (GP3A) and other stakeholders and gender sensitive; and (b) scheme-level or

    apex WUAFs (IP3A), and individual WUAs, with voluntary active women‟s participation

    (GP3A,IP3A2) in all schemes.

    B2. Irrigation Department Capacity Building (Base Cost - US$5.1 M) at Kabupaten level

    since the role of Kabupaten Dinas PUP would orient more to facilitation and be reorganized

    so technical staff, extension workers (KF'L) and Community Organizers would work with

    WUAFs to provide technical/management guidance for O&M and construction, including:

    B3. Irrigation Infrastructure Improvement (Base Cost - US$26.8 M) funded Kabupaten

    and provinces that adopted the institutional model of the irrigation reform PKPI. Once the

    Kabupaten Irrigation Improvement Facility (KIIF) had been established WUAF could also be

    funded.

    B4. Irrigated Agriculture Improvement Program (IAIP) (Base Cost - US$2.7 M) aimed

    to: (a) strengthen farmer organizations‟ (WUAFs) technical, organizational, and managerial

    capacity to formulate demands and to interact efficiently and with bargaining power with

    service providers (research, extension, agricultural inputs, processing, credit, etc.); and (b)

    make service providers (public and private) more responsive (demand driven), farmer

    oriented and accountable.

    Component C. Project Management (Base Cost US$8.1M)

    This Component would support the National Project Management Unit and the National

    Project Implementation Units, as well as the Provincial and Kabupaten Project Management

    2 IP3A is Induk P3A or apex WUAF and is the voluntary working entity of all GP3As in one irrigation

    system

  • 6

    and Project Implementation Units. The following were the main Technical Assistance

    packages to support Project Management: (a) Financial Management Service (FMS); (b)

    Impact Monitoring and Evaluation Unit (IMEU); and (c) Preparation of WISMP 2.

    1.5.2 The NTB-WRMP intentionally had an identical project structure, components and

    sub-components. More specifically it has three components: (a) Basin Water Resources

    Management (Euro 5.17 million); (b) Strengthening Participatory Irrigation Management

    (Euro 4.60 million) and (c) Project Management and Technical Assistance (Euro 0.93

    million). Despite this overall similarity, there was a significant difference in the proportion of

    costs of the various expenditure categories between the two projects. For NTB-WRMP the

    Services category (TA, Training, Studies and M&E) amounted to 56% of total costs and

    Works to 36% compared with 46% and 37%3 respectively for WISMP.

    1.6 Revised Components

    1.6.1 There was no significant modification of the components in the program project,

    except that under WISMP1 the activities related to dam safety management and some

    activities related to water environment management were taken out. This is because: (a) the

    dam safety management related activities were taken up by a parallel Dam Operational

    Improvement and Safety Project financed by the Bank; and (b) the Ministry of Environment

    had already got its own similar program funded by the Government.

    1.7 Other Significant Changes

    1.7.1 Changes in design. Some aspects of the Program changed after WISMP 1 was

    approved in 2003 prior to the issue of UU 7/2004, such as the re-arrangement of irrigation

    system and basin water resources management authority and mandates. These adjustments

    mainly affected the irrigation component and were accommodated in the restated DCA and

    approved by management:

    Transfer of irrigation management authority to the WUAFs was replaced by participatory irrigation management (PIM) as public irrigation asset ownership and

    control was vested in the State. PIM Principles were agreed upon and confirmed in

    the restated DCA;

    Cost recovery through service fees by government agencies was precluded through the Law on Water Resources and the regulations on public administration. As

    a consequence, alternative mechanisms were developed through (i) enhanced

    contributions from water users by sharing management tasks and responsibilities and

    (ii) enhanced government budget allocations. Another consequence was that the

    support for corporatization of basin agencies that recover costs from irrigation water

    users could not be materialized.

    1.7.2 Changes in regulations. The issuance of revised government and ministerial regulations necessitated a further adjustment at the Mid-Term Review (MTR) through a DCA

    Amendment. This involved some changes in the key indicators.

    1.7.3 Changes in financing mechanism of GoI contribution. The co-financing method for the GoI contribution was changed into parallel financing for participating provinces

    and kabupaten to harmonize central and local government project budgeting

    processes. Under the initial co-financing arrangement both central government

    budget (APBN) and local government funds (APBD) were applied together which

    3 Including all River Infrastructure Maintenance (RIM) expenditures.

  • 7

    caused administrative difficulties during implementation. Parallel financing separated

    the central and local budget processes. After the change, disbursement increased

    significantly. The change was approved by the management and incorporated in the

    DCA amendment of 2009.

    1.7.4 Changes in implementation arrangements. Following the issue of Government

    Regulation 38/2007, the responsibility for guidance to WUAF was changed from MoPW to

    MoA. This had only budgeting consequences as MoA was already fully engaged in the

    implementation process. This minor change was approved by management through the

    supervision aide memoire.

    1.7.5 Changes in scope and scale. The scope of activities remained the provincial and

    district water resources and irrigation agencies and their river basins and irrigation systems.

    National basins and systems were excluded from the project after the new water resources law

    UU 7/2004 because of the lack of downstream regulations on management arrangements for

    national basins. The geographic scope of activities increased during the implementation of the

    program and was approved by management through the supervision aide memoires:

    The number of provinces included increased by 2 to 14 with the inclusion of Aceh and the splitting of South Sulawesi into South and West Sulawesi;

    For the Basin Water Resources Management component, the initial number of 42 basins grew to 54 basins due to re-delineation of the river basin boundaries in 2006;

    For PIM the number of participating districts (kabupaten) grew from 70 initially to ultimately 99 due to splitting of 6 participating districts and the introduction of 23

    new districts in 2009 for initial introduction of the reform only.

    1.7.6 The above changes also affected NTB-WRMP. In addition, during implementation

    increased attention was given to watershed conservation, which was an issue of particular

    relevance to NTB, but of less crucial interest to most of the 12 provinces covered by WISMP.

    2. Key Factors Affecting Implementation and Outcomes

    2.1 Project Preparation, Design and Quality at Entry

    2.1.1 Soundness of Background Analysis: WISMP was an extension and consolidation of

    the broad and coherent support the Bank provided from 1997 onwards. This support

    emphasized institutional development. It took both the form of gradual introduction of new

    administrative and regulatory mechanisms at local and national government levels, and the

    extensive piloting thereof in the field. Even after the issuance of proper “facilitating”

    national-government regulations, few local governments were able to act upon them. Water

    users, and especially farmer irrigators, were ill prepared to assume their new responsibilities.

    Progress was slow since the local governments, newly empowered by the 1999 Regional

    Autonomy Laws, and civil society-based organizations had to adjust and develop the requisite

    local consensus and absorb the new opportunities.

    2.1.2. JIWMP first introduced and piloted novel irrigation management arrangements on

    Java and notably set up, and “coached” a large number of autonomous, self-governing

    Federations of Water User Associations (WUAFs) of irrigators. JIWMP also introduced and

    supported River Basin Management Units under provincial governments (Balai PSDA) and

    Water Resources Management Committees to foster integrated resource management and

    enhance accountability. In parallel, WATSAL built on this new body of field experience, and

    supported the development of a broad-based framework of policy, legal, regulatory and

    administrative reforms at national and local levels. Thereafter, IWIRIP replicated these

    reforms in seven provinces outside Java, whilst continuing support in the Java provinces. The

    pilot reforms under JIWMP and IWIRIP had been successful as demonstrated in a

  • 8

    representative household survey completed in April 2003. They appeared robust after four

    solid years of field implementation, and the gradual consolidation of the new legal and

    regulatory frameworks at the national level. These pilot areas covered approximately 235,000

    ha in 63 kabupatens in 12 provinces.

    2.1.3. WISMP Phase I was the response to the challenges of the reform implementation and

    a consistent and systematic extension of this prior support, whilst offering the opportunity to

    further improve and adapt the institutional designs to Indonesia‟s diversity. Project

    preparation and design was therefore firmly grounded in a wealth and depth of prior

    experience and piloting. The whole WISMP program was sensibly structured as a three-

    tranche, 12-year APL, which ensured the longer period of continued financing required with

    benefits not only in continuity but also greater flexibility.

    2.1.4 Assessment of Project Design. The project development objectives (PDO) were well

    chosen and appropriate, stressing better water allocation and water conservation, better sector

    governance, and increased agricultural productivity and improved irrigation performance. The

    division of the project into two main components, one mainly supporting change in overall

    management and planning institutions and the other looking at participative irrigation

    management and strengthening of Water User Associations and Federations (WUAs/WUAFs)

    struck a good and sensible balance. However, project design was too complex and ambitious

    in a number of respects, although such design may well be justified for an institutional reform

    oriented operation of this nature: (a) the project‟s geographic coverage extended to 12

    provinces and included 70 kabupatens4; (b) the project supported a wide range of reforms and

    initiatives through some 9 sub-components; (c) project organization was also complex,

    involving four ministries, namely the Ministry of Public Works, formerly the Ministry of

    Settlement and Regional Infrastructure (Kimprawil), the Ministry of Home Affairs (MoHA),

    the Ministry of Agriculture (MoA) and the Ministry of Environment (KLH). Implementation

    arrangements involved setting up Project Management Units (PMU) and Project

    Implementation Units (PIU) for each of the participating Ministries at each of the three levels

    – national, provincial and kabupaten; (d) the project was co-financed by the Government of

    Netherlands and the associated NTB-WRMP project parallel financed by the European

    Union.

    2.1.5 The project scope, both geographically and in the range of activities, supported

    imposed a heavy burden on both project management and Bank supervision. Setting up the

    many PMUs and PIUs required significant new recruitment and created difficulties in getting

    staff of adequate qualification and experience. Overall guidance was provided by a National

    Steering Committee (on Water Resources) chaired by the National Development Planning

    Agency (Bappenas) with the main responsibility for implementation resting with the

    Directorate General of Water Resources (DGWR) of Kimprawil and the participating

    provincial and kabupaten governments. The decentralized approach adopted by the project

    and Government‟s fiscal decentralization helped implementation. Adequate regard was paid

    to Bank safeguard policies for environmental and social concerns.

    2.1.6 Government commitment: The overall WISMP program and the WISMP Phase I

    project constituted a major plank in the Government (GoI) policy of decentralization. GoI had

    issued the new decentralization legislation covering administrative regional autonomy (Law

    22) and fiscal balance (Law 25) in 1999. These major sector reforms were to be implemented

    through the Five-Year Development Strategy (Propenas) which became law in 2000. At

    project appraisal, GoI had completed the most significant parts of the Water Resources

    Reform Program on which WISMP was based. All the 12 provinces and their constituent

    4 From 2009 onwards, 14 provinces and 99 kabupaten

  • 9

    kabupaten had 2 to 4 years of piloting river basin management and participatory irrigation

    management, and had started reforms at the local government level. 63 out of the 70

    kabupatens had already adopted the irrigation reform principles and were participating in the

    JIWMP and IWIRIP programs. In terms of river basin management, some 23 River Basin

    Management Units (Balai PSDA) had been established in all the river basin territories (SWS)

    of Java and a further 10 had been formed in the Outer Islands. The WISMP program and the

    Phase I project were therefore at the heart of a major GoI policy initiative. Weak aspects of

    government commitment were the more than two years delay in WISMP loan effectiveness,

    the inability to introduce legislation to enable cost recovery and frequent late budget releases.

    The two-year delay in loan effectiveness was due to the government‟s decision to await the

    issuance of the new water law in 2004, which led to no disbursement before 2006.

    2.1.7 Stakeholder commitment: Interest in improving irrigation system infrastructure and

    management grew with the advances made by earlier projects. Local government, civil

    society, farmer groups including WUAs and farm families were all enthusiastic about the

    project. However, the speed with which this underlying commitment could be put into

    practice depended on the time taken for issuing of the necessary laws and regulations at

    national, provincial and district (kabupaten) levels.

    2.1.8 Risks: The PAD identified a large number of risks. These included (a) the possibility

    that the sector agencies would dominate the public consultation process; (b) that inadequate

    priority and resources would be given to collect information for management information

    system (MIS) establishment and M&E activities; and (c) that insufficient priority and support

    would be given to the fiscal sustainability and cost recovery aspects.

    2.1.9 The first of these risks has been successfully mitigated during project implementation

    by encouraging the participation of water users and civil society. The other risks duly became

    apparent during implementation. With such a large, complex and innovative project coming at

    a time when political changes and strategy still remained to be consolidated there were clearly

    many uncertainties and numerous risks to be faced. Three important risks were not listed: (a)

    risk of implementation delays due to lack of the necessary laws, decrees or other legal

    instruments to allow implementation to proceed systematically, particularly since in most

    cases enabling legislation was required at the highest level in order to get – “by cascade” - the

    necessary instruments at Ministerial, Provincial and Local Government levels; (b) delays in

    release of government annual budget at the central and local levels, which has been a chronic

    problem for many years; and (c) the over-frequent transfer of staff, which is also a

    longstanding problem and one which has a very negative impact on building institutional

    capacity, dissipates training impact and slows implementation. Considering the number of

    uncertainties and challenges the project faced in implementation, a substantial overall risk

    rating would have been more appropriate.

    2.1.10 QAG “Quality at Entry”. The project was reviewed by the QAG and received an

    overall rating of satisfactory.

    2.1.11 NTB-WRMP did not share the experience of long involvement in water resources and

    Bank projects and the same depth of background analysis. The fact that the province had

    missed out on earlier assistance was one of the reasons for EU interest in funding. To enable

    the project to run concurrently with WISMP it had to be prepared quickly and with a more or

    less identical design as WISMP. There do not appear to have been very substantial inputs of

    government officers in project identification and appraisal. The project assessment was

    carried out on the basis of a consultant assessment report, and there was not a formal appraisal

    mission nor a project appraisal document. As a result, the design in terms of activities to be

    undertaken was identical to those included in WISMP and were not tailored to the particular

    needs of NTB, especially in regard to the need for catchment rehabilitation and management.

    Also some aspects of the design were inadequate, most noticeably in relation to M&E. There

  • 10

    was a serious lack of definition of appropriate key performance indicators, and there was no

    baseline survey. Consequently whatever M&E data was eventually collected provided little

    help to project management since the results could not be interpreted5.

    2.1.12 The project design was almost identical for WISMP 1 and NTB-WRMP. Under the

    WISMP Program, the first phase project focused largely on institutional change and capacity

    building. In contrast, NTB-WRMP‟s targeting of agricultural productivity and income

    improvement, although not officially part of the project objectives, appears overly optimistic.

    The degree of commitment of both the provincial and local governments and other

    stakeholders on the other hand appears to have been equal to or greater than that for WISM


Recommended