+ All Categories
Home > Documents > Document of The World Bank Report No: 66702-BJ PROJECT PAPER · 2016. 7. 15. · REPUBLIC OF BENIN...

Document of The World Bank Report No: 66702-BJ PROJECT PAPER · 2016. 7. 15. · REPUBLIC OF BENIN...

Date post: 24-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
46
Document of The World Bank FOR OFFICIAL USE ONLY Report No: 66702-BJ PROJECT PAPER ON A PROPOSED ADDITIONAL GRANT IN THE AMOUNT OF SDR 6.5 MILLION (US$10 MILLION EQUIVALENT) AND RESTRUCTURING TO THE REPUBLIC OF BENIN FOR THE HEALTH SYSTEM PERFORMANCE PROJECT February 17, 2012 This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • Document of

    The World Bank

    FOR OFFICIAL USE ONLY

    Report No: 66702-BJ

    PROJECT PAPER

    ON A

    PROPOSED ADDITIONAL GRANT

    IN THE AMOUNT OF SDR 6.5 MILLION

    (US$10 MILLION EQUIVALENT)

    AND

    RESTRUCTURING

    TO THE

    REPUBLIC OF BENIN

    FOR THE

    HEALTH SYSTEM PERFORMANCE PROJECT

    February 17, 2012

    This document has a restricted distribution and may be used by recipients only in the

    performance of their official duties. Its contents may not otherwise be disclosed without World

    Bank authorization.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • 2

    CURRENCY EQUIVALENTS

    (Exchange Rate Effective 01/31/2012)

    Currency Unit = CFA Franc (XOF)

    XOF 507.02 = US$1

    SDR 0.65 = US$1

    FISCAL YEAR

    January 1 – December 31

    ABBREVIATIONS AND ACRONYMS

    ACT Artemisinin-based combination therapy

    AF Additional Financing

    BCC Behavior Change Communication

    BCEAO Banque Centrale des Etats de l’Afrique de l’Ouest

    CAME Central Drugs Procurement Unit

    CAS Country Assistance Strategy

    CBO Community Based Organization

    CSR Country Status Report

    DHS Demographic and Health Survey

    EEZS Equipe d'Encadrement de la Zone de Santé

    FMCI Free Malaria Care Initiative

    GAVI Global Alliance for Vaccines and Immunization

    GoB Government of Benin

    GSM General Secretary of the Ministry

    HEF Health Equity Fund

    HF Health Facilities

    HSPP Health System Performance Project

    ICB International Competitive Bidding

    IDA International Development Association

    IPT Intermittent Preventive Treatment

    ISR Implementation Status and Results

    M&E Monitoring and Evaluation

    MDG Millenium Development Goal

    MoH Ministry of Health

    MWMP Medical Waste Management Plan

    NCB National Competitive Bidding

    NMCP National Malaria Control Program

    OBD Output-based Disbursement

    PCU Project Coordination Unit

  • 3

    PDO Project Development Objective

    PMI President's Malaria Initiative (USAID)

    PNDS Plan National Developpement Sanitaire

    RBF Results-Based Financing

    RDT Rapid Diagnostic Test

    RVP Regional Vice President

    SOE Statement of Expenses

    SWAp Sector Wide Approach

    TF Trust Fund

    USD United States Dollars

    WB World Bank

    Vice President: Obiageli K. Ezekwesili

    Country Director: Madani M. Tall

    Sector Director Ritva Reinikka

    Country Manager Olivier Frémond

    Sector Manager: Jean-Jacques de Saint-Antoine

    Task Team Leader: Christophe Lemière

  • 4

    REPUBLIC OF BENIN

    HEALTH SYSTEMS PERFORMANCE PROJECT

    TABLE OF CONTENTS

    Project Paper Data Sheet 5

    Project Paper

    I. Introduction 8

    II. Background and Rationale for Additional Financing 9

    III. Proposed Changes 12

    IV. Appraisal Summary 19

    Annexes

    1. Revised Results Framework and Monitoring Indicators 24

    2. Operational Risk Assessment Framework 36

    3. Costs of the package of the Free Malaria Care Initiative (FMCI) 39

    4. Implementation arrangements 41

    5. Control arrangements 45

  • 5

    REPUBLIC OF BENIN

    HEALTH SYSTEMS PERFORMANCE PROJECT

    ADDITIONAL FINANCING AND RESTRUCTURING

    DATA SHEET

    Basic Information - Additional Financing (AF)

    Country Director: Madani M. Tall

    Sector Director: Ritva Reinikka

    Sector Manager: Jean-Jacques de Saint-

    Antoine

    Team Leader: Christophe Lemière

    Project ID: P129024

    Expected Effectiveness Date: July 31st,

    2012

    Lending Instrument: SIL

    Additional Financing Type: Scale-Up

    and Restructuring

    Sectors: HNP

    Themes: Health system performance

    (67%); Child health (33%)

    Environmental category: B - Partial

    Assessment

    Expected Closing Date: Dec 31, 2015

    Joint IFC:

    Joint Level:

    Basic Information - Original Project

    Project ID: P113202 Environmental category: B- Partial

    Assessment

    Project Name: Health System

    Performance

    Expected Closing Date: Dec 31, 2015

    Lending Instrument: SIL Joint IFC:

    Joint Level:

    AF Project Financing Data

    [ ] Loan [] Credit [ X] Grant [ ] Guarantee [ ] Other:

    Proposed terms:

    AF Financing Plan (US$m)

    Source Total Amount (US $m)

    Total Project Cost:

    Cofinancing:

    Borrower:

    Total Bank Financing:

    IBRD

    IDA

    New

    Recommitted

    US$10 million

    US$10 million

    Client Information

    Recipient: Republic of Benin

    Responsible Agency: Ministry of Health

    Contact Person: Mr Valere Goyito, General Secretary

    Telephone No: +229 21 33 21 41

    Fax No.:

    Email: [email protected]

    mailto:[email protected]

  • 6

    AF Estimated Disbursements (Bank FY/US$m)

    FY 12 13 14 15 16

    Annual 1.0 5.0 4.0 0 0

    Cumulative 1.0 6.0 10.0 0 0

    Project Development Objective and Description

    Original project development objective: The first PDO consists in increasing the coverage of

    quality maternal and neonatal health care services in targeted districts. This PDO is broken down

    in two intermediate outcomes: (i) improving health facilities performance through Result-Based

    Financing (RBF); and (ii) enhancing financial accessibility to these health services. The second

    PDO is to strengthen the institutional capacity of the Ministry of Health.

    Revised project development objective The objectives of the Project are (i) to increase coverage of quality maternal, neonatal and child

    health care services in the Targeted Areas, and (ii) to strengthen the institutional capacity of the

    MoH.

    Project description

    Under the original Project, the first component aims to: (i) improve performance of health

    facilities through a Result-Based Financing (RBF) mechanism; (ii) strengthen capacities of the

    Ministry of Health to facilitate and to monitor the implementation of this RBF mechanism; and

    (iii) support the recruitment of specialist doctors in the target districts.

    The second component aims to increase financial accessibility of health care services, by: (i)

    strengthening the existing process for identifying the poorest and for exempting them from

    health user fees; (ii) strengthening health services in 4 of the target districts; (iii) funding free

    malaria care for pregnant women and under five children; and (iv) supporting the development

    of a universal health care insurance system.

    The third component aims to strengthen capacities of the Ministry of Health in planning,

    budgeting, management and monitoring and evaluation.

    Activities supported by this Additional Financing (AF) will fall under Components 1 and 2 to

    enhance financial accessibility of health care services through support to implementation of the

    Free Malaria Care Initiative (FMCI) launched by the Government of Benin in October 2011. In

    the eight health districts of the Health System Performance Project (HSPP), additional activities

    will comprise: (i) Procurement of goods included in the four packages of the FMCI, including

    Artemisinin-based combination therapy (ACTs), Rapid Diagnostic Test (RDTs) and treatment

    kits; (ii) reimbursement of non procurable costs associated with the four packages of the FMCI

    through an output-based disbursement mechanism (i.e. Result-Based Financing); and (iii)

    Communication, information and training activities as described in the strategic FMCI

    document.

    Safeguard and Exception to Policies

  • 7

    Safeguard policies triggered:

    Environmental Assessment (OP/BP 4.01)

    Natural Habitats (OP/BP 4.04)

    Forests (OP/BP 4.36)

    Pest Management (OP 4.09)

    Physical Cultural Resources (OP/BP 4.11)

    Indigenous Peoples (OP/BP 4.10)

    Involuntary Resettlement (OP/BP 4.12)

    Safety of Dams (OP/BP 4.37)

    Projects on International Waterways (OP/BP 7.50)

    Projects in Disputed Areas (OP/BP 7.60)

    [X]Yes [ ] No

    [ ]Yes [ X] No

    [ ]Yes [ X] No

    [ ]Yes [ X] No

    [ ]Yes [ X ] No

    [ ]Yes [ X ] No

    [ ]Yes [X ] No

    [ ]Yes [X ] No

    [ ]Yes [ X ] No

    [ ]Yes [X ] No

    Does the project require any waivers of Bank policies?

    Have these been endorsed or approved by Bank management?

    [ ]Yes [X ] No

    [ ]Yes [ ] No

    Conditions and Legal Covenants:

    Financing Agreement

    Reference

    Description of Condition/Covenant Date Due

    4.01(a) The Recipient has adopted a revised Procedures

    Manual, in form and substance satisfactory to

    the Association, to incorporate the requisite

    guidelines and procedures for the activities

    under Parts A.1 (III), B4 and B5 of the project

    Effectiveness

    4.01(b) The amendment to the Trust Fund Grant

    Agreement has been executed and delivered

    Effectiveness

    Section II, B.2 The Recipient shall install and make operational

    in the General Secretariat, no later than two (2)

    month after the Effective Date, an accounting

    system software for the Project which is

    acceptable to the Association.

    No later than two

    (2) month after the

    Effective Date

    Section II, B.2 The Recipient shall appoint, no later than two

    (2) months after the Effective Date, financial

    auditors in accordance with the provisions of

    Section III of this Schedule.

    No later than two

    (2) month after the

    Effective Date

    Section V.1 The Recipient shall, no later than twelve (12)

    months after the Effective Date, adopt a strategy

    for funding the FMCI that is in form and

    substance acceptable to the Association.

    No later than

    twelve (12) months

    after the Effective

    Date

  • 8

    REPUBLIC OF BENIN

    HEALTH SYSTEMS PERFORMANCE PROJECT

    I. INTRODUCTION

    1. This Project Paper seeks the approval of the Executive Directors to restructure and provide an additional grant in the amount of SDR 6.50 million (USD 10 million equivalent)

    to the Republic of Benin for the Health System Performance Project (HSPP) (Grant H564-BJ).

    This additional financing (AF) is in response to the Government of Benin’s (GoB) request to

    support implementation of the recently launched national Free Malaria Care Initiative (FMCI)

    for pregnant women and children under five. With the AF, the total grant of HSPP would come

    to USD 43.8 million.

    2. In Benin, malaria is endemic nationwide and is a major cause of morbidity and mortality, affecting children under five and pregnant women in particular. For example,

    data from the 2006 Demographic and Health Survey (DHS) show that among children the age of

    6- 59 months old, 78% had anemia, which is likely to be caused by malaria. 26.1% of all patients

    and 36.7% of under-five children are dying from severe malaria in health facilities according to

    the Health Statistic Directory 2010. It is also reported to account for 40% of outpatient

    consultations and 25% of all hospital admissions. Furthermore, financial access to malaria care

    has been a major concern in Benin. Evidence shows indeed significant difference in access to

    malaria drugs between wealth quintiles. For example, among under-five children who had fever,

    51% from the wealthier quintile took malaria drugs the same day or the day after fever, as

    compared to only 31.2% from the poorest quintile (DHS 2006).

    3. The FMCI was launched by the GoB in October 2011, with an aim to remove user fees for simple and severe malaria cases for vulnerable groups. The strategy prioritizes

    pregnant women and under-five children, considered the vulnerable groups at most risk in the

    country. As proven in other countries, large-scale malaria control (including high coverage with

    effective prevention and treatment) has the potential to cut overall child mortality by 20-25% and

    deaths attributable to malaria by up to 80%. Furthermore, as households contribute up to 42% of

    total health expenditures in the public sector, the FMCI could have significant impact on

    coverage and accessibility to maternal and child health services. This initiative would also

    enhance health system performance through supporting improvements in malaria cases

    management, supplying of drugs and commodities, quality controls and a better use of the

    referral health system.

    4. The proposed AF would strengthen and expand the impact and development effectiveness of the HSPP, which aims at increasing the coverage of quality maternal and

    neonatal services and enhance financial accessibility to health services. Indeed, by removing

    financial barriers to access malaria care for two vulnerable groups (pregnant women and under-

    five children), the proposed AF would contribute to improved maternal and child health

    outcomes in Benin. This AF is in compliance with (ii) of OP/BP 13.20, as it proposes the

  • 9

    implementation of additional or expanded activities that scale up a project’s impact and

    development effectiveness.

    II. BACKGROUND AND RATIONALE FOR ADDITIONAL FINANCING IN THE

    AMOUNT OF US$10 MILLION

    Free Malaria Care Policy

    5. Benin officially launched its FMCI on October 4th 2011 to radically enhance financial accessibility for malaria care to vulnerable groups. The FMCI removes user fees for

    simple and severe malaria interventions through four packages that include diagnostics,

    treatment, exams and visits/hospitalization for: (i) simple malaria for under-five children; (ii)

    severe malaria for under-five children; (iii) simple malaria for pregnant women; and (iv) severe

    malaria for pregnant women. Annex 3 describes the content and average cost of these four

    packages. While the packages are focused on diagnostic and treatment function, the Government

    is taking measures to ensure that prevention remains a priority. Bednets distributions, Behavior

    Change Communication (BCC), capacity building and other functions are supported from their

    own resources or other donor contributions.

    6. Recent fiscal deterioration, exacerbated by global economic slowdown, creates a challenge for the Government of Benin to cover the entire cost of this new policy. An

    estimated cost of implementing this Strategy nationwide is approximately USD 19 million per

    year (see Annex 3 for details of calculations). Other donors, such as USAID, are planning to

    provide some financing (under parallel financing) to support the initiative. However, available

    estimates to-date shows that the required costs far exceed available resources. The proposed AF

    intends to bridge some of this financial gap by covering the cost of four packages in eight of the

    34 health districts for a period of two years, bringing an important contribution to the first step of

    rolling out the policy nationwide. Given that the Government has maintained active dialogue

    with other donors, it is expected that the Bank’s financing will serve as a catalyst to mobilize

    additional resources for this initiative in the medium- and long-term.

    7. The FMCI will be fully integrated in the national health system. Institutionally, the initiative will be managed by the National Malaria Control Program (NMCP). The NMCP would

    be responsible for implementation of the policy at both central and local levels. At district and

    community levels, District Health Management Teams (i.e. Equipe d’Encadrement de la Zone

    Sanitaire) and mayors would be in charge of monitoring FMCI implementation. To avoid any

    negative impacts of this new policy on service delivery, some mitigation measures would be

    implemented such as offsetting revenues loss for health centers (given that they can no longer

    charge malaria drugs), quality controls on produced services, as well as provision of bonuses for

    health workers to cope with the expected increased workload.

  • 10

    Other Free Care Policies

    8. Benin has already implemented several user fees exemptions policies, such as Free C-Section and Free Health Care for the Poorest supported under the Health Equity Fund (HEF).

    Experiences from these free care measures have been incorporated to better design the FMCI.

    Two important lessons learnt are that: (i) the reality of provided free services has to be rigorously

    verified; and (ii) the content of invoices sent by health facilities for reimbursement also need to

    be strictly controlled. These two key lessons have been incorporated in the design of this AF.

    Consistency with the existing Health System Performance Project

    9. The original grant amount for the HSPP was USD 33.8 million (USD 22.8 million from IDA and USD 11 million from the Multi-Donor Trust Fund for Health Results Innovation).

    It was approved on April 9, 2010 and became effective on September 30, 2011. The first project

    development objective (PDO) is to increase the coverage of quality maternal and neonatal

    health care services in the target districts. This PDO is broken down into two intermediate

    outcomes: (i) improving health facilities performance through Result-Based Financing (RBF);

    and (ii) enhancing financial accessibility to these health services. The second PDO is to

    strengthen the institutional capacity of the Ministry of Health (MoH). Through this PDO, the

    Project will: (i) prepare the implementation of a Sector Wide Approach (SWAp); and (ii)

    improve planning, budgeting and monitoring functions within the MoH.

    10. The HSPP has three components: (i) strengthening accountability of health facilities through the piloting of an RBF mechanism (USD 18.0 million); and (ii) increasing financial

    accessibility to health services, through improvements of the HEF (USD 13.8 million). Malaria

    care is one of the services targeted by both components. There is also a third small component on

    technical assistance for institutional strengthening (USD 2.0 million). Since the proposed AF will

    enhance the impact of Project’s Component 1 on health facilities performance and Component 2

    on financial accessibility, it is fully consistent with the original Project, not only in terms of

    development objectives, but also in terms of design and geographical scope.

    11. The project is currently rated Satisfactory for progress towards achievement of PDO. Implementation progress had long been rated Moderately Satisfactory due to delay in

    project effectiveness. The delay was due to the fact that the Bank’s internal approval process for

    selection of a consulting firm (which was the last effectiveness condition to be fulfilled) took

    almost five months, because of suspicions of procurement irregularities, which had to be

    investigated (and turned out to be non substantial). This led to an effectiveness flag, which will

    be turned off in May 2013 (according to OP/BP 13.00). To mitigate risk for further procurement

    delays, supervision has been strengthened by adding one more senior procurement specialist to

    the task team. In addition, procurement training for the MoH has been scheduled for February

    2012 to ensure capacity strengthening at government level. Note also that all audits on the

    project are current. Given that effectiveness has been declared only in September 2011, no audit

    is due yet. While the proposed AF satisfies the requirement of 12 months of project

    implementation since the Board approval, an approval from the Regional Vice President (RVP)

    has been obtained to proceed with this AF, given that the project has only been effective since

    September 30, 2011.

  • 11

    12. Since effectiveness (Sept 30, 2011), project implementation has been on track, as described in the latest Implementation Status & Results (ISR). Overall safeguard compliance

    has been so far rated Satisfactory. The Project has already committed an amount of $5 millions.

    Key tasks for components 1 and 3 are under implementation. A first disbursement request of

    USD 2 million has already been submitted, and a second request of another USD 2 million is

    scheduled for February 2012. The Project is in substantial compliance with the legal covenants,

    with some slight delays in meeting two (2) dated covenants given the associated delays related to

    harmonization efforts with other donors. These two legal covenants are (i) the purchase of an

    accounting software and (ii) the recruitment of a financial auditor. The approval of the Terms of

    Reference (TORs) has been delayed by the fact that it has been recently agreed (after Board

    approval) that both services will be used by 3 partners (Bank, Global Alliance for Vaccines and

    Immunization and Global Fund). The TORs are now finally approved and the procurement

    process is ongoing. Completion of this process is expected by February 2012.

    13. The World Bank (WB) has been actively engaged in malaria control interventions in Benin, especially through the Malaria Control Support Project which closed in June 2011. As

    part of the Africa Region Malaria Booster Program, the project aimed to support the

    implementation of the Second National Malaria Control Strategy (2006-2010), measured through

    increased access to, and utilization of, an effective package of malaria control interventions. Data

    from the NMCP shows that there has been a steady decline between 2005-2009 on some of the

    key indicators including number of reported malaria deaths, malaria case fatality rates, and

    number of simple and severe malaria cases reported by health facilities. While these rapid

    declines are plausibly attributed to all Roll Back Malaria partners’ support to Benin’s new

    malaria policy and protocols, the role of the Bank’s project is strongly acknowledged by both

    NMCP and partners on two fronts: (i) it allowed for a substantial injection of resources in

    supporting the Strategy1; and (ii) it was instrumental in attracting substantial additional

    resources, notably from the USAID/PMI2. The proposed AF will thus be a way for the WB to

    stay engaged in supporting the GoB’s effort to malaria control. In addition, a follow-on Malaria

    Booster operation is currently under development to continue critical support focusing on Bank’s

    comparative advantage, especially in areas of strategic program management, capacity building

    and health systems strengthening.

    14. Processing of a new lending operation was considered as an alternative but dropped for two reasons. First, preparation of a USD 10 million project would result in high transaction

    costs. Secondly, the tight timeline for implementing the FMCI would not be consistent with the

    time requirements associated with preparing a new project. Another alternative was to restructure

    the parent Project, given that it had not disbursed anything so far. This option was also ruled out

    for two reasons. First, the lack of disbursement is explained by the fact that the parent Project

    just recently became effective on Sept 30, 2011 due to delays in meeting one of the project

    effectiveness conditions (as explained in paragraph 11). Since then, implementation has been on

    track. Second, out of the USD 33.8 million designated for the parent Project, USD 16 million

    cannot be reallocated as it includes: (i) USD 11 million from a Trust Fund dedicated to RBF, and

    (ii) USD 5 million committed for the payment of a contract with a technical assistance firm.

    1 The Project constituted about 65% of all available financing (at the time of project approval),

    2 Draft Implementation Completion and Results Report, Malaria Control Support Project, December 2011

  • 12

    Consequently, if the project was restructured without AF, only USD 17.8 million could be

    reallocated to fund the FMCI. This would leave a mere USD 7.8 million to implement all the

    activities of the parent Project. Obviously, a 56% reduction in the parent Project’s available

    budget would require removing or scaling down most of the activities, resulting in a significant

    risk of poor implementation of the parent Project.

    Consistency with Government priorities and Country Assistance Strategy (CAS)

    15. Benin’s new Poverty Reduction Strategy Paper (March 2011) includes strengthening of human capital as one of the six pillars, making reference to improving

    accessibility and quality of health services and highlighting the importance of three Millenium

    Development Goals (MDGs): under-five mortality rate; maternal mortality and combating

    malaria, HIV/AIDS and tuberculosis3. The 10-year National Health Sector Development Plan

    (PNDS 2009-2018) recognizes malaria as the main cause of child mortality and adult morbidity

    and calls for concerted action to combat this disease as a priority. The third NSP 2011-2015

    builds on the PNDS and supports the same objectives, specifying the interventions with some

    refinements to: (i) extend coverage of target groups from vulnerable groups to cover the entire

    population; and (ii) ensure more routine testing in health facilities to confirm malaria diagnosis

    dispensing ACT.

    16. The proposed AF is consistent with the CAS 2009-2012 which plans to direct Bank support towards increasing “access to basic services”, and more specifically, towards

    “improving health services”. The AF is also consistent with the Bank’s new Africa strategy:

    Pillar 2 of this strategy focuses on implementing mechanisms for protecting households from

    various shocks, including those related to health. The proposed AF is expected to reduce the

    financial and clinical burden of malaria morbidity. In addition, Benin has already implemented

    several user fees exemptions policies in health services, such as Free C-Section and Free Health

    Care for the poorest through the HEF. The original HSPP is expected to support the HEF,

    therefore the proposed AF will increase synergies with the ongoing Bank’s support to the

    country’s free care strategies.

    III. PROPOSED CHANGES

    17. As the AF intends to fund the FMCI for pregnant women and children under five, the first PDO will be slightly expanded to increasing the coverage of quality maternal,

    neonatal and child health care services in the targeted districts. The second PDO will remain

    unchanged. In addition, an outcome indicator will be added so as to follow and monitor the

    impact of this FMCI policy. This indicator is the following (for PDO 1, indicators for coverage

    in the targeted districts): Number of beneficiaries of the Free Malaria Care4.

    18. New activities to be added to support the FMCI would be under Component A and B of the parent project:

    3 Malaria specific interventions include: prevention, case management, behavior change communication,

    epidemiological and entomological surveillance and research. 4 Number of beneficiaries (under-five children and pregnant women) benefiting from free malaria care in the 8

    districts. Only cases confirmed by biological tests and validated by the NMCP are considered.

  • 13

    Component A: Improvement of health facilities performance through Result-

    Based Financing (additional USD 2.7 million)

    Reimbursement of services and operating costs associated with the four packages of

    the FMCI in the eight health districts targeted by the HSSP. These costs include

    medical services and top-ups for health workers. Estimated costs are USD 2.7

    million. Disbursements for this activity follow an output-based disbursement

    mechanism: after going through a verification process, the health facilities assigned

    to RBF and contracted by the MoH will be reimbursed on the basis of number of

    (fee exempted) malaria services they have provided. The AF will follow the same

    mechanism but with four additional indicators added to the existing RBF design to

    ensure provision of services related to FMCI.

    Component B: Support to improved financial accessibility (additional USD 7.3

    million)

    Procurement of goods included in the four packages of the FMCI in the eight

    health districts targeted by the HSSP, including Artemisinin Combination Therapy

    (ACT), Rapid Diagnostic Tests (RDTs) and treatment kits. Overall cost is estimated

    at USD 6.3 million. Procurement procedures will be launched well in advance and

    will be organized in such way so as to allow for ACT treatment to take place in

    parallel to the rolling out of RDTs, in order to reduce misuse of ACTs for fever not

    attributable to malaria, as well as to avoid inefficiencies and high costs. Required

    quantities have been reflected in the procurement plan.

    Communication, information, M&E and training activities (USD 1 million) as

    described in the strategic FMCI document including community mobilization about

    the Free Malaria Care, media communication to communities, information and

    communication to local authorities, health district teams and health workers,

    training for health workers on the diagnostic and treatment of malaria cases.

    19. Note that given the changes mentioned above, the HRIG grant agreement will need to be

    amended accordingly given that it is jointly co-financing Component A of the Project.

    20. The proposed additional grant of USD 10 million would bring the total project

    amount to USD 43.8 million. The table below provides the financing allocation by component

    of the original project and the new proposed AF.

    Table 1: Revised budget allocation by components

    Component Original Cost

    (USD million)

    Additional cost

    (USD million)

    Total revised

    cost

    (USD million)

  • 14

    A:

    Improvement

    of health

    facilities

    performance

    through RBF

    A.1. Financing of RBF

    credits (including malaria

    services)

    12 2.7 14.7

    A.2. Support to RBF

    implementation and

    supervision

    6 -- 6

    B: Support to

    improved

    financial

    accessibility

    B.1. Strengthening of

    processes to identify the

    poorest households

    10.3 -- 10.3

    B.2. Support to the

    Health Equity Fund

    2.5 -- 2.5

    B.3. Support for

    preparation of a proposal

    for a Universal Health

    Insurance Scheme

    1 -- 1

    B.4. Procurement of

    medical goods included

    in the four packages of

    the FMCI in the eight

    health districts targeted

    by the HSPP

    0 6.3 6.3

    B.5. Communication,

    information, M&E and

    training activities for

    implementing the FMCI

    0 1 1

    C: Technical assistance for institutional

    strengthening

    2 -- 2

    Total 33.8 10 43.8

    21. Overall implementation arrangements will remain unchanged from the original project, with the MoH assuming the primary role for project implementation, including oversight,

    coordination and fiduciary management, through a Project Coordination Unit (PCU) placed

    under the General Secretary of the Ministry (GSM). As the AF will focus on supporting the

    GoB’s FMCI, responsibilities of the different entities to implement this initiative will be as

    follows (see also Annex 4 for illustration of the implementation arrangement).

    The PCU will:

  • 15

    - reimburse health facilities for goods related to the four malaria services, once the PCU has received invoices from these health facilities and once

    these invoices have been controlled by the NMCP and the third party

    controller;

    - contract with suppliers of goods related to malaria (drugs, kits and RDTs), according to the WB procurement guidelines;

    The NMCP will: - support the PCU to prepare tenders for malaria-related goods; - control the technical adequacy of invoices submitted by health facilities;

    The CAME (Central Drugs Procurement Unit) will: - store and distribute the malaria-related procurable items to health facilities;

    The health facilities will: - report their production in terms of free malaria services and will submit the

    corresponding invoices (for non-procurable items) to the PCU;

    - receive two types of additional resources related to the free malaria care initiative: (i) additional goods (from CAME) and (ii) additional funding for

    non-goods items (from the PCU).

    A third party controller firm (already in place) will: - control the reality of services to be reimbursed (i.e. ensuring that services to

    be reimbursed have been actually produced and provided to the eligible

    groups).

    22. In addition, a steering committee will continue to monitor project activities. This committee, chaired by the Minister of Health and including the Ministries in charge of Finance,

    Civil Services and Development, will continue to function as an oversight role of the project. In

    particular, it will continue to approve annual work plans, national RBF framework and other

    strategic documents.

    Overall fiduciary arrangements

    23. The proposed AF will include two main types of expenditures. A first type consists of medical goods, including drugs (mostly ACTs), RDTs and kits for malaria treatments. The

    estimated amount for these goods is USD 6.3 million (about 70% of the unit cost of the four

    services). These goods will be procured by the PCU, in collaboration with NMCP and CAME.

    24. A second type of expenditures is the services and operating costs of the 4 services. They include services and top-ups for civil servants. The estimated amount is USD 2.7 million (30%

    of the unit cost of the 4 services). These items will be funded through the Output-Based

    Disbursement (OBD) mechanism already in place with the parent Project5. That will require a

    rigorous evaluation of the unit costs.

    25. Overall, to cover the costs faced by health facilities because of the removal of user fees on malaria care, these facilities will receive two distinct types of support: (i) an in-kind support,

    consisting in goods (drugs, RDTs…) distributed free of charge by the CAME to the health

    5 In the parent project, the categories A.1 and B.2 are funded through OBD. The Additional Financing also

    introduces A.3, for malaria services.

  • 16

    facilities, and (ii) a monetary support, consisting of services and operating costs (services, top-

    ups…) funded through an OBD mechanism. This combination ensures both (i) a high efficiency

    for procurable expenditures (70% of the unit costs) and (ii) a strong accountability of health

    facilities (through the OBD mechanism).

    26. Both mechanisms (standard procurement and OBD) are already in place within the parent Project.

    27. Finally, an amount of USD 1.0 million is allocated to strengthen communication and M&E related to free malaria care. This support will consist in training, workshops, consulting

    services and operating costs.

    Financial management arrangements

    28. To implement this proposed AF, no changes in financial management arrangements and requirements are necessary. As for the parent project, the PCU-HSPP will be in charge of the

    financial management of the AF including the preparation of technical and financial reports. It

    will also monitor the disbursements of the funds and will ensure that they are in compliance with

    IDA requirements. The PCU-HSPP has already been strengthened by key staffs including

    Financial and Procurement Specialists.

    29. The table below summarizes the fiduciary arrangements for this AF:

    Table 2: Cost allocation by activity

    Activities Eligible expenditures Cost

    Funding of malaria care

    services at facility level

    Procurable items:

    Drugs (mostly CTAs), RDTs

    and kits for malaria treatments

    $6.3 million (70% of the

    unit cost of the malaria care

    services)

    Non-procurable items:

    services and top-ups for civil

    servants

    $2.7 million (30% of the

    unit cost of the malaria care

    services)

    Communication and

    M&E strengthening at

    central and district level

    Training, workshops and

    consulting services and

    operating costs

    $1.0 million

    30. Disbursements. In order to promote a single project approach, the AF will use the existing designated account at the BCEAO (Banque Centrale des Etats de l’Afrique de l’Ouest).

    The ceiling of the Designated Account has been set to CFAF 1 billion. The proceeds of the AF

    grant have been allocated to the RBF component under a specific category (category 4), given

  • 17

    that these proceeds will fund only malaria care services. All disbursements for the Project will be

    based on monthly Statement Of Expenditures (SOE). In addition, disbursements for results based

    financing component (under categories (1) for the Original Financing and (4) for AF of the

    disbursement table) will be supported with a certified SOE (in the form attached to the

    Disbursement Letter) signed by the independent verification agent in accordance with terms of

    reference acceptable to IDA and consistent with external controls provisions set out in the legal

    agreement (cf. Section I.E of the Amended and Restated Financing Agreement).

    31. The expenditures related to the malaria-related “non-procurable items” (see table above) will be funded through the existing Output-Based Disbursement (OBD) arrangement.

    Practically, four services/packages will be added to the existing list of outputs. The arrangements

    for OBD are the same as for the parent Project. As mentioned in the PAD of the parent Project,

    all disbursements from the Grant accounts regarding the RBF component (A.1 and A.3) will be

    certified SOE (as stated above). This auditor (already selected) has set up a full-time “district

    controller” in each of the 8 districts. These controllers verify the reality of outputs, in checking

    consistency between reported outputs and facilities registers. In addition, the operational auditor

    is currently selecting Community Based Organizations (CBOs) to conduct community checks.

    The detailed arrangements for controlling output are presented in the annex 5 of this Project

    paper. Under the RBF component, subsidiaries’ accounts in an acceptable commercial bank will

    be opened by eligible health centers. To avoid misuses of RBF credits, the Finance specialist at

    each district level will provide ex-ante clearance for all expenditures to be made by the health

    center.

    Table 3: Revised Disbursement Table - Original and Additional Financing Category Amount of the Original

    Grant Allocated (USD)

    Amount of

    the

    Additional

    Grant

    Allocated

    (USD)

    Percentage of

    Expenditures to be

    Financed

    (inclusive of Taxes)

    IDA TF IDA IDA TF

    (1) Goods and services to

    be financed from the proceeds of

    Maternal, Neonatal and Child

    Health Services Grants under

    Parts A.1(i) and A.1(ii) of the

    Project

    1,000,000 11,000,000

    8.33% 91.67%

    (2) Goods and services to

    be financed from the proceeds of

    HEF Health Services Grants

    under Part B.2 of the Project 2,500,000 0 0 100.00%

    (3) Goods, consultants’

    services, Training, and Operating

    Costs for Parts A.2, B.1, B.3, B.4

    and B.5 and C of the Project 19,300,000 0 7,300,000 100.00%

  • 18

    (4) Goods and services to

    be financed from the proceeds of

    Maternal, Neonatal and Child

    Health Services Grants under

    Part A.1(iii) of the Project

    0 0 2,700,000 100% 0

    TOTAL AMOUNT 22,800,000 11,000,000 10,000,000

    AF Estimated Disbursements (Bank FY/US$m)

    FY 12 13 14 15 16

    Annual 1.0 5.0 4.0 0 0

    Cumulative 1.0 6.0 10.0 10.0 10.0

    Procurement arrangements

    32. All goods and services will be procured according to the provision of Annex 8 (Procurement Arrangements) of the parent project Appraisal Document. The only changes to the

    existing procurement arrangements in the parent Project are that:

    Procurement would be carried out in accordance with the World Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January

    2011; “Guidelines: Selection and Employment of Consultants by World Bank

    Borrowers” dated January 2011; as well as "Guidelines on Preventing and

    Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA

    Credits and Grants”, dated October 15, 2006 revised in January 2011.

    The drugs and other procurable medical items will be procured in collaboration with the NMCP and with CAME who will ensure the storage and distribution..

    33. The summary of procurement plan is provided in Annex 4 of the present document.

    Closing date

    34. The project closing date is extended by a year, from December 31, 2014 to December 31, 2015. This extension is justified by the delay in effectiveness (one year) of the parent Project.

    The extension will restore the initial duration for the Project (4 years).

    Other legal changes

    35. As mentioned in paragraph 12, after Board approval of the parent project, harmonization efforts have been made with two other partners (GAVI and Global Fund). As a consequence, it

    has been agreed that the three partners will use the same accounting software and will be audited

    by the same auditor. This harmonization has led to some delays in purchasing the accounting

    software and selecting the auditor. Consequently, it is proposed that these actions will have to be

    completed no later than two months after effectiveness of this Additional Financing.

  • 19

    Monitoring and Evaluation (M&E)

    36. Under the RBF component of the original Project, an independent “district controller” is assigned in each of the eight health districts to support the district health team to measure,

    control and verify the RBF results reported by the health facilities. It is proposed that the scope

    of work of these “district controllers” be extended to also include the control of the malaria care

    services supported by the AF. These “district controllers” would also be part of the quality

    control missions for the FMCI led by the NMCP. In addition, the same mechanisms used for

    RBF would be used for the proposed AF, such as consistency check between registers and

    reported information, as well as contracting of Community Based Organizations (CBO) to

    conduct patient satisfaction surveys in order to measure the qualitative aspects of care. Annex 5

    provides a detailed description of these control arrangements.

    37. A baseline household survey was already conducted in the eight districts as part of the Impact Evaluation of the RBF component under the original project. This survey included

    questions related to health service utilization. In order to rigorously measure the impact of FMCI

    in the eight target districts, follow-up surveys foreseen under the original project will include

    additional questions linked to the new Policy.

    IV. APPRAISAL SUMMARY

    Economic and financial analyses

    38. The expanded activities funded through the Additional Financing do not lead to any significant difference in the results of the economic analysis from the original one. Indeed, these

    additional activities will improve the cost-effectiveness of the existing Project. Increasing access

    to malaria care by removing the financial barriers for vulnerable groups would allow early

    diagnosis and prompt treatments which prevent from complications, more severe morbidity and

    mortality. And there is a huge potential for such improvements. For instance, only 10% of under-

    five children are treated with an ACT (ACTWatch survey, 2009). Moreover, the odds of

    receiving ACT and diagnostic testing is 2.68 for children from the wealthiest quintile in

    comparison with those from the lowest one6. It is consequently expected that the Malaria Free

    Care will reduce inequities in malaria care access.

    39. Malaria health burden is heavy in Benin. According to a survey conducted in November 2011 by the National Malaria Control Program, parasitological malaria prevalence is 41% for

    under-five children and 33% for pregnant women. For Sub-Saharan Africa, it is estimated that,

    malaria-associated anemia is responsible for 3.7% of maternal mortality7. Indeed, malaria can

    induce under-nutrition, low birth weight, increased susceptibility to general infection. For

    6 Littrell et al, Monitoring fever treatment behaviour and equitable access to effective medicines in the context of

    initiatives to improve ACT access: baseline results and implications for programming in six African countries,

    Malaria Journal , October 2011. 7 Breman, Mills, Snow and al., Disease control priorities in developing countries, April 2006.

  • 20

    children, severe malaria could lead to some major relapses including cognitive impairment,

    behavioral disturbance and blindness.

    40. Thus, additional activities linked to free malaria care would increase the impact of the Project on the reduction of maternal and child mortality. The impact of the free care will

    be complementary with the national prevention strategy for the two vulnerable groups (for

    instance, the national bednets campaign in 2011 for under-five children, where 1.7 millions

    bednets were distributed) and synergic with services subsidized through RBF in the 8 targeted

    districts (for instance, Intermittent preventive treatment (IPT) during pregnancy and bednets for

    pregnant women).

    41. Case management with ACT has proven to be a cost effective intervention in West Africa with an average cost effectiveness of 9$ per Disability-Adjusted Life year (DALY)

    averted (with 80% coverage)8. Estimates by NMCP of number of cases are consistent with the

    malaria situation and the important efforts made on prevention in Benin: one case per under-five

    children per year and 40% of pregnant women having malaria. These numbers would be adjusted

    during implementation of the Initiative and considering the expected improvements in malaria

    diagnostic and case management. The cost of the Free Malaria Care funded by the Additional

    Financing is small: around 2.3$ per capita or 9.9$ per vulnerable targeted person in the eight

    districts.

    Technical and sustainability analysis

    42. The proposed AF would support the GoB’s effort to enhance financial accessibility for malaria care to vulnerable groups through their newly launched FMCI. The initiative aims at

    removing user fees for simple and severe malaria interventions for pregnant women and children

    under five years of age through four packages that include diagnostics, treatment, exams and

    visits/hospitalization at health facility levels in their communities. The contents of the package,

    conditions of eligibility, modalities of execution and monitoring are determined by the National

    Strategy for FMCI which was developed by the NMCP and adopted by the GoB and partners in

    August 20119.

    43. This strategy suffers from a lack of funding. As estimated by the NMCP and confirmed during appraisal, the annual cost of FMCI is at least 9 billion CFA francs ($ 19 million). The

    Government has allocated a billion FCFA ($ 2 million) in its 2012 budget, while USAID has

    committed funding of 2.5 billion CFA francs ($ 5 million) per year for 4 years. Without support

    by the WB, the annual gap is 5.5 billion FCFA ($ 12 million).

    44. The main discussion during appraisal focused on the scope of activities of FMCI to be financed by additional funding. An initial proposal was to fund the overall FMCI, that is to say

    mainly to finance inputs, as does USAID. The World Bank has expressed strong reservations on

    this proposal, for two reasons. First, it must be remembered that a policy of free care does not

    merely consist in providing free inputs. A free care policy is about reimbursing services to health

    8 Morel, Lauer and al., Cost effectiveness analysis of strategies to combat malaria in developing countries, 2005.

    9 Stratégies de la mise en œuvre de la gratuité de la prise en charge des cas de paludisme chez les femmes enceintes

    et les enfants de moins de 5 ans, August 2011

  • 21

    facilities. This assumes (i) a mechanism for reimbursement that is fast and reliable, and (ii) a

    mechanism to control the reality and quality of the provided services. None of these mechanisms

    is now in place in Benin, except in the eight health areas already supported by the HSPP. Second,

    by allocating the entire additional funding to inputs, Bank funding would be exhausted after

    about 6 months, inevitably triggering questions about the sustainability of FMCI. Such a

    sustainability issue cannot be resolved in 6 months.

    45. For these two reasons, a second proposal made by the World Bank and accepted by the Government is to limit the scope of additional funding to the eight health districts of the HSPP.

    Funding will then cover the needs of these eight areas for 2 years. This arrangement meets the

    fiduciary requirements of the World Bank, while leaving sufficient time to prepare for the

    sustainability and nationwide implementation of FMCI. To do this, it was agreed that the

    implementation of additional funding in year 2 will be conditioned by the production by the

    Government of a report identifying domestic and external resources to sustain the FMCI. This

    condition will ensure that, as soon as the end of the first year of implementation, the Government

    will have defined a strategy to fund the whole program (including the small amounts for civil

    servants’ incentives) with only domestic resources10

    . This condition is consistent with the

    arrangement made in the parent Project (para 78), where in year 3 of implementation, the

    Government will start to redirect existing funds to the benefit of the RBF program (also funding

    incentives for civil servants).

    46. Also, in order to enhance efficacy of intervention, the proposed AF will take a two-pronged approach: (i) provision of medical procurable goods, including drugs (mostly ACTs),

    RDTs and kits for malaria treatments which will be procured by the PCU following the same

    arrangements used in the recently closed Malaria Booster Control Program; and (ii) payment to

    health facilities through an Output-Based Disbursement (OBD) mechanism already in place

    under the parent Project whose design of RBF has incorporated lessons from other countries’

    successful RBF projects and adapted to the Benin environment.

    47. As usual in programs where providers are paid on the basis of the production they report, there is a high risk that these providers will artificially inflate their reported production. This risk

    exist for the FMCI supported by the AF. It is however fully addressed by the strong control

    arrangements that are in place with the parent Project (see para 36 for details).

    48. Another risk with the proposed approach (i.e. supporting only 8 districts) is that people from other districts may travel to the Bank 8 districts to receive free care. The Team believes this

    risk is rather limited, for the following reason. Available data show that people are ready to

    travel far away only for major health services, such as surgery, delivery or c-section. To seek

    basic health services (such as malaria diagnosis and treatment), people will usually not travel

    10

    It is worth mentioning here that there is currently an untapped and important financial resource in health facilities.

    Since last year, the Government has indeed decided to hire as civil servants (paid by the Government) all contract-

    based staff (previously paid by health facilities out of user fees). This major shift in financing has led to a situation

    where many health facilities have now a significant surplus of financial resources, which could be used for funding

    the FMCI. The Government has agreed to assess the extent of this surplus and to use it - in the above mentioned

    study - as a way to mobilize national resources for the FMCI.

  • 22

    farther than 5-10kms. In other words, this “spill-over effect” will be limited to the villages in the

    immediate neighborhood of the 8 districts.

    49. Implementing a free care strategy could end up in “crowding out” resources at the expense of prevention, which remain a highly cost-effective intervention. On the basis of the

    existing national strategy against malaria and its funding structure, there is no evidence that such

    a crowding out can occur. The national strategy still puts prevention as its very first priority (see

    pillar 1.1 in the strategy). In addition, most of the funding for preventive interventions

    (especially the distribution of bed nets) till 2014 comes from the Global Fund. As mentioned

    before, this funding cannot be redirected to FMCI, as this is a new activity. This lack of funding

    flexibility (or lack of “crowding out”) is actually one of the reasons why the Bank is proposing

    this AF, given that the Global Fund cannot fund it now.

    Fiduciary

    50. The AF procurement activities will be implemented by the existing PCU, under the existing arrangements of the parent project. Procurements processes for drugs, kits and RDTs,

    will be carried out by the PCU with technical support from the NMCP and CAME. Note that the

    PCU includes a recruited procurement specialist, who happened to be the former procurement

    specialist of the Malaria Booster Control program.

    51. As for financial management, the proposed AF will not include any new arrangement. The existing ones are acceptable for the Bank.

    Social and environmental

    52. The underlying technical appraisal of the original project remains valid. As explained in the original PAD, the project is expected to have a positive social impact by: (i) improving

    accessibility of health care for the poorest households, especially targeting the most vulnerable

    groups of the population; (ii) enhancing community ownership as for monitoring the quality of

    basic health services; and (iii) the preparation process of the Benin Health System Performance

    Project remains highly participatory with extensive work and consultation among the key

    stakeholders, especially on decentralized levels in project target districts.

    53. As with the parent Project, the provision of malaria care services might entail an increased production of medical waste, especially in relation to planned procurement of goods

    such as ACTs, RDTs and lab reagents. Consequently, the proposed project has been classified as

    Category B for environmental screening purposes given the risks associated with the handling

    and disposal of medical and general health waste. This project is not expected to generate any

    major adverse environmental impact.

    54. The proposed Additional Financing does not introduce new activities that will trigger additional safeguards policies to the original project; but enhances the impacts of component 2

    on financial accessibility, thus, making it fully consistent with original project, not only in terms

    of development objectives, but also with respect to design and geographic coverage. The

    implementation of the prepared safeguards instrument of the parent project: the Medical Waste

  • 23

    Management Plan (MWMP) has been satisfactory; there has been training to health care

    providers and health care personnel on medical waste management procedures and practices.

    Further, some MWMP equipment such as waste bins, handgloves and needle cutters have been

    purchased and are in the process of being distributed to the regional and local health centers.

    55. The overall implementation risk is rated as moderate. The main risk is the weak financial sustainability of the program. This risk is mitigated by the dated covenant requiring the

    Government to produce (by the end of the first year of implementation) a strategy for mobilizing

    additional resources and therefore for being able to fund the program without Bank support.

  • 24

    Annex 1:

    BENIN: Health System Performance Project

    Revised Results Framework

    Revisions to the Results Framework Comments/ Rationale for Change

    PDO

    Current (PAD) Proposed The first PDO would consist in

    increasing the coverage of quality

    maternal and neonatal health care

    services in the target districts. The

    PDO would be broken down in

    two intermediate outcomes: (i)

    improving health facilities

    performance through Result-

    Based Financing (RBF); and (ii)

    enhancing financial accessibility

    to these health services. The second PDO is to strengthen

    the institutional capacity of the

    Ministry of Health.

    The first PDO would consist in

    increasing the coverage of quality

    maternal, neonatal and child health

    care services in the target districts.

    The PDO would be broken down

    in two intermediate outcomes: (i)

    improving health facilities

    performance through Result-Based

    Financing (RBF); and (ii)

    enhancing financial accessibility

    to these health services. The second PDO is to strengthen

    the institutional capacity of the

    Ministry of Health.

    The financing of the Free

    Malaria Care for under-five

    children is expected to impact

    highly the coverage and the

    quality of these services for

    the children, who come

    mainly to health centers due

    to malaria.

    PDO indicators

    Current (PAD) Proposed change*

    1. Increasing

    coverage of

    quality

    maternal,

    neonatal and

    child health

    care services

    1. Rate of pregnant

    women that had at least 4

    antenatal care visits

    before delivery

    Continued

    2. Rate of poorest

    pregnant women that had

    at least 4 antenatal care

    visits before delivery

    Continued

    3. Rate of assisted

    deliveries among all

    pregnant women

    Continued

    4. Rate of assisted

    deliveries among the

    poorest pregnant women

    Continued

    5. Number of pregnant

    women receiving

    antenatal care during a

    visit to a health provider

    (IDA 15 Core Indicator)

    Continued

    6. Rate of antenatal care

    visits (among all

    pregnant women)

    Continued

  • 25

    Revisions to the Results Framework Comments/ Rationale for Change

    complying with quality

    standards 7. Rate of deliveries

    adequately referred by

    primary care level

    facilities

    Continued

    8. Number of children

    immunized (IDA 15

    Core Indicator)

    Continued

    9. Number of

    beneficiaries11

    of the

    Free Malaria Care

    New The Additional Financing will fund the Free Malaria Care

    for pregnant women and

    under five children in 8

    districts. 10. Direct beneficiaries

    (with % of women) (IDA

    15 CORE)

    Change in the end of

    the project target

    value

    The project target value will

    increase as more pregnant

    women and under-five

    children will benefit from the

    Project, notably through the

    funding of the Free Malaria

    Care in the 8 targeted

    districts. 2.Strenghtening

    institutional

    capacities of

    the Ministry of

    Health (MoH)

    Share of MoH budget

    allocated to health

    districts

    Continued

    Concentration index of

    budget allocation to

    health district across

    population densities

    Continued

    Intermediate Results indicators

    Current (PAD) Proposed change*

    Component 1 –

    Improvement

    of health

    facilities

    performance

    through Result-

    Based

    Financing

    (RBF)

    1. Competency score of

    health workers in

    maternal and neonatal

    health

    Continued

    2. Health personnel

    receiving training (IDA

    15 CORE)

    Continued

    3. Average availability of

    essential drugs in health

    facilities

    Continued

    4. Average availability of Continued

    11

    Beneficiaries of the Free Malaria Care are defined as under-five children and pregnant women who benefit for

    free of one of the four packages of care of the policy and whose cases are confirmed through RTD or microscopy. It

    means that only cases validated by district controllers, EEZS and the NMCP would be considered as Beneficiaries of

    the Free Malaria Care.

  • 26

    Revisions to the Results Framework Comments/ Rationale for Change

    essential equipment in

    health facilities 5. Average availability of

    health workers (i.e. “one minus

    absenteeism rate”)

    Continued

    6. Motivation of health

    workers (Likert scale,

    spanning from 1 to 5)

    Continued

    7. % of facilities that

    received RBF credits

    each year

    Continued

    8. % of facilities whose

    RBF results have been

    fully verified each year

    Continued

    Component 2 –

    Support to

    Improved

    Financial

    Accessibility

    1. Average cost of key

    maternal health services

    for patients (including

    informal payments)12

    Continued

    2. Index of benefit of

    maternal health services

    as perceived by women

    (on a Likert scale,

    spanning from 1 to 5)

    Continued

    3. Number of poor

    households identified Continued

    4. % of identified poor

    households enrolled in

    the e-health card

    program

    Continued

    5. % of identified poor

    households being

    exempted from fees

    thanks to their e-health

    card

    Continued

    6. Percentage of under

    five children receiving

    Free Malaria Care

    Services

    New The Additional Financing will fund the 2 packages of Free

    Malaria Care for under-five

    children in the 8 targeted

    districts. 7. Percentage of

    pregnant women

    receiving Free Malaria

    Care Services

    New The Additional Financing will fund the 2 packages of Free

    Malaria Care for pregnant

    women in the 8 targeted

    districts.

    12

    This amount is equal to the average of the amount of costs for (i) one antenatal care visit, (ii) one uncomplicated

    delivery and (iii) one complicated delivery.

  • 27

    Revisions to the Results Framework Comments/ Rationale for Change

    Component 3 –

    Technical

    Assistance for

    Institutional

    Strengthening

    1. Number of SWAp

    “building blocks” in

    place (see table 2 for

    details)

    Continued

    2. Strategic 3-year plans

    developed according to

    defined principled

    Continued

    3. New formulas for

    allocation of the budget

    to districts are utilized

    Continued

    4. M&E system with no

    overlapping processes Continued

    * Indicate if the indicator is Dropped, Continued, New, Revised, or if there is a change in

    the end of project target value

  • 28

    Annex 1: Revised Project Results Framework

    Project Development Objective (PDO):

    The first PDO would consist in increasing the coverage of quality maternal, neonatal and child health care services in the target districts. The PDO would be broken down in two

    intermediate outcomes: (i) improving health facilities performance through Result-Based Financing (RBF); and (ii) enhancing financial accessibility to these health services.

    The second PDO is to strengthen the institutional capacity of the Ministry of Health.

    PDO Level Results

    Indicators13

    Co

    re

    UOM14

    Baseline

    Original

    Project

    Start

    (2010)

    Progres

    s To

    Date

    (2012)15

    Cumulative Target Values16

    Frequency Data Source/

    Methodology

    Responsibility

    for Data

    Collection

    Comments 2012 2013 2014 2015

    1. Rate of pregnant women

    that had at least 4 antenatal

    care visits before delivery

    % 61% 61% 65% 70% 75% 81% - Every 3

    months

    - Facilities

    records

    - Control of

    facility

    records for a

    random

    sample of

    women

    - Health

    district teams

    - M&E third

    party17

    2. Rate of poorest pregnant

    women that had at least 4

    antenatal care visits before

    delivery

    % 51% 51% 56% 62% 68% 75% - Every 3

    months

    - Facilities

    records

    - Control of

    facility

    records for a

    random

    sample of

    women

    - M&E third

    party

    - M&E third

    party

    13

    Please indicate whether the indicator is a Core Sector Indicator (for additional guidance – please see http://coreindicators). 14

    UOM = Unit of Measurement. 15

    For new indicators introduced as part of the additional financing, the progress to date column is used to reflect the baseline value. 16

    Target values should be entered for the years data will be available, not necessarily annually. Target values should normally be cumulative. If targets refer to

    annual values, please indicate this in the indicator name and in the “Comments” column. 17

    As explained earlier, there are two third parties involved in data collection and verification. One is the M&E third party, which is an international firm with

    permanent presence in every RBF district. The other one is the IE (for Impact Evaluation) third party, which is an independent entity carrying out data collection

    annually.

    http://coreindicators/

  • 29

    - Annually - Household

    survey

    - IE third party

    3. Rate of assisted

    deliveries among all

    pregnant women

    % 78% 78% 80% 83% 85% 88% - Every 3

    months

    - Facilities

    records

    - Control of

    facility

    records for a

    random

    sample of

    women

    - Health

    district teams

    - M&E third

    party

    4. Rate of assisted

    deliveries among the

    poorest pregnant women

    % 56% 56% 61% 67% 73% 80% - Every 3

    months

    - Facilities

    records

    - Control of

    facility

    records for a

    random

    sample of

    women

    - M&E third

    party

    - M&E third

    party

    - Annually - Household

    survey

    - IE third party

    5. Number of pregnant

    women receiving antenatal

    care during a visit to a

    health provider (IDA 15

    Core Indicator)

    Number

    220,000 220,000 235,000 250,000 265,000 280,000 - Every 3

    months

    - Facilities

    records

    - M&E third

    party Annual

    visits - Annually - Household

    survey

    - IE third party

    6. Rate of antenatal care

    visits (among all pregnant

    women) complying with

    quality standards

    % 39% 39% 45% 50% 60% 70% - Every 3

    months

    - Facilities

    records

    - Health

    district teams

    - Exiting

    patients

    surveys

    - M&E third

    party

    7. Rate of deliveries

    adequately referred by

    primary care level facilities

    % 10% 10% 12% 15% 20% 25% - Every 3

    months

    - Facilities

    records

    - Health

    district teams

    - Exiting

    patients

    surveys

    - M&E third

    party

    - Analysis of

    medical

    records in

    - M&E third

    party

  • 30

    referral

    facilities

    8. Number of children

    immunized (IDA 15 Core

    Indicator)

    Number

    70,000 70,000 75,000 80,000 90,000 100,000 - Every 3

    months

    - Facilities

    records

    - M&E third

    party

    - Annually - Household

    survey

    - IE third party

    9. Number of beneficiaries

    of the Free Malaria Care

    Number

    0 0 0 150,000 320,000 415,000 - Every 3

    months

    - Facilities

    records and

    bills sent to

    PNLP

    - Health

    district teams

    with district

    controllers

    Number of

    beneficiaries

    (under-five

    children and

    pregnant

    women)

    benefiting

    for free of

    malaria care

    in the 8

    districts.

    Only cases

    confirmed

    by

    biological

    tests and

    validated by

    the NMCP

    are

    considered.

    - Annually - Household

    survey

    - IE third party

    Share of MoH budget

    allocated to health districts % 39% 39% 40% 45% 55% 65% - Annually - Annual

    budget

    - Ministry of

    Health

    Concentration index of

    budget allocation to health

    district across population

    densities

    0.22 0.22 0.18 0.15 0.12 0.10 - Annually - Annual

    budget

    - Ministry of

    Health

    Beneficiaries18

    Project beneficiaries,

    Number

    0 0 340,000

    510,000

    710,000

    840,000

    - Every 3

    months

    - Project

    records

    - Ministry of

    Health

    Addition of

    under-five

    children

    18

    All projects are encouraged to identify and measure the number of project beneficiaries. The adoption and reporting on this indicator is required for

    investment projects which have an approval date of July 1, 2009 or later (for additional guidance – please see http://coreindicators).

    http://coreindicators/

  • 31

    Of which female

    (beneficiaries)

    Number

    (60%) (60%) (60%) (45%) (35%) (32%) - Every 3

    months

    - Project

    records

    - Ministry of

    Health

    benefiting of

    FMCI in the

    8 districts,

    which

    highly

    increases the

    number of

    project

    beneficiaries

    but

    decreases

    the share of

    female

    beneficiaries

    .

  • 32

    Intermediate Results and Indicators

    Intermediate Results Indicators

    Co

    re Unit of

    Measure

    ment

    Baseline

    Original

    Project

    Start

    (2010)

    Progress

    To Date

    (2012)

    Target Values

    Frequency Data Source/

    Methodology

    Responsibility

    for Data

    Collection

    Comments 2012 2013 2014 2015

    Component 1: Improvement of health facilities performance through Result-Based Financing (RBF)

    Intermediate Result 1: Improved skills and knowledge of qualified staff

    1. Competency score of health

    workers in maternal and

    neonatal health (see table 2 for

    details)

    %

    52% 52% 58% 65% 72% 80% - Every 3

    months

    - Knowledge

    test

    - M& E third

    party

    2. Health personnel receiving

    training (number) (IDA 15

    CORE Indicator)

    Number

    0 0 650 700 800 1,000 - Every 3

    months

    - Project

    records

    - Ministry of

    Health

    Intermediate Result 2: Increased availability of essential drugs and equipment

    3. Average availability of

    essential drugs in health

    facilities

    %

    56% 56% 60% 70% 80% 85% - Every 3

    months

    - Observation

    in facilities

    - M& E third

    party

    4. Average availability of

    essential equipment in health

    facilities

    %

    66% 66% 70% 73% 76% 80% - Every 3

    months

    - Observation

    in facilities

    - M& E third

    party

    Intermediate Result 3: Increased motivation and availability of qualified staff

    5. Average availability of health

    workers (i.e. “one minus

    absenteeism rate”)

    %

    60% 60% 70% 80% 85% 90% - Every 3

    months

    -

    Unannounced

    visits

    - M& E third

    party

    6. Motivation of health workers

    (see table 2 for details)

    Number

    between

    1-5

    2 2 2.5 3 3.5 4 - Annually - Health

    workers

    survey

    - IE third party

  • 33

    Intermediate Results and Indicators

    Intermediate Results Indicators

    Co

    re Unit of

    Measure

    ment

    Baseline

    Original

    Project

    Start

    (2010)

    Progress

    To Date

    (2012)

    Target Values

    Frequency Data Source/

    Methodology

    Responsibility

    for Data

    Collection

    Comments 2012 2013 2014 2015

    Intermediate Result 4: Effective implementation and monitoring of the RBF

    7. % of facilities that received

    RBF credits each year %

    0% 0% 100% 100% 100% 100% - Annually - Project

    records

    - Ministry of

    Health

    8. % of facilities whose RBF

    results have been fully verified

    each year

    %

    0% 0% 80% 100% 100% 100% - Annually - Project

    records

    - Ministry of

    Health

    Intermediate Result 5: Component 2 – Support to Improved Financial Accessibility

    9. Average total cost of key

    maternal health services for

    patients (formal and informal

    payments)

    Amount

    in $

    $16 $16 $15 $14 $12 $10 - Every 3

    months

    - Exit surveys - M& E third

    party

    10. Index of benefit of maternal

    health services as perceived by

    women (see table 2 for details)

    Number

    between

    1-5

    2 2 2.5 3 3.5 4 - Annually - Household

    survey

    - IE third party

    11. Number of poor households

    identified (see table 2 for details) Number

    0 0 50,000 100,000 110,000 110,000 - Every 6

    months

    - Annually

    - MoH records

    - Control

    through a

    targeted

    household

    survey

    - Ministry of

    Health

    12. % of identified poor

    households enrolled in the e-

    health card program

    %

    0% 0% 20% 60% 100% 100% - Every 6

    months

    - MoH records

    - Ministry of

    Health

    13. % of identified poor

    households being exempted from

    fees thanks to their e-health card

    %

    0% 0% 10% 30% 60% 90% - Every 6

    months

    - MoH records

    and facilities

    records

    - Ministry of

    Health

    14. Percentage of under five

    children receiving Free Malaria %

    0% 0% 0% 40% 80% 100% - Every 3

    months

    - Facilities

    records and

    - Health

    district teams

    PNLP

    estimates

  • 34

    Intermediate Results and Indicators

    Intermediate Results Indicators

    Co

    re Unit of

    Measure

    ment

    Baseline

    Original

    Project

    Start

    (2010)

    Progress

    To Date

    (2012)

    Target Values

    Frequency Data Source/

    Methodology

    Responsibility

    for Data

    Collection

    Comments 2012 2013 2014 2015

    Care Services bills sent to

    PNLP

    with district

    controllers

    that in

    average

    there is one

    malaria

    episode per

    children

    per year.

    Numbers

    are only for

    the 8

    selected

    districts.

    - Annually - Household

    survey

    - IE third party

    15. Percentage of pregnant

    women receiving Free Malaria

    Care Services

    %

    0% 0% 0% 10% 30% 40% - Every 3

    months

    - Facilities

    records and

    bills sent to

    PNLP

    - Health

    district teams

    with district

    controllers

    PNLP

    estimates

    that 40% of

    pregnant

    women

    have

    malaria per

    year.

    Numbers

    are only for

    the 8

    selected

    districts.

    - Annually - Household

    survey

    - IE third party

    Component 3: Strengthening Institutional Capacity of the Ministry of Health

    Intermediate Result 6: Preparing the implementation of a SWAp

  • 35

    Intermediate Results and Indicators

    Intermediate Results Indicators

    Co

    re Unit of

    Measure

    ment

    Baseline

    Original

    Project

    Start

    (2010)

    Progress

    To Date

    (2012)

    Target Values

    Frequency Data Source/

    Methodology

    Responsibility

    for Data

    Collection

    Comments 2012 2013 2014 2015

    16. Number of SWAp “building

    blocks” in place19

    Number

    between

    0-8

    1 1 3 5 7 8 - Annually - Documents

    review

    - Ministry of

    Health

    Intermediate Result 7: Improved planning, budgeting and monitoring

    17. Strategic 3-year plans

    developed according to defined

    principled (yes/no)

    Yes/no

    No No No No Yes Yes - Annually - Documents

    review

    - Ministry of

    Health

    18. New formulas for allocation

    of the budget to districts are

    utilized (yes/no)

    Yes/no

    No No No Yes Yes Yes - Annually - Documents

    review

    - Ministry of

    Health

    19M&E system with no

    overlapping processes (yes/no) Yes/no

    No No No Yes Yes Yes - Annually - Documents

    review

    - Ministry of

    Health

    19

    About eight (8) SWAp “building blocks” are usually identified. They are the following: (i) a comprehensive plan, (ii) an evidence-based plan, (iii) a

    decentralized planning process , (iv) a strong link between planning and budgeting, (v) a comprehensive budget, (vi) an MTEF, (vii) a common M&E system

    among donors and MoH and (viii) an MoU between donors and MoH.

  • 36

    Annex 2: Operational Risk Assessment Framework (ORAF)

    Benin: Health System Performance Project (HSPP) & additional financing

    Stage: Appraisal

    1. Project Stakeholder Risks Rating Moderate

    Description:

    Regarding the AF, the only foreseeable stakeholder risk come

    from health facilities and health workers. Currently, these

    facilities sell malaria drugs and use the profit from these drug

    sales for paying extra staff and some (small) staff incentives.

    Depending on the level of reimbursement, the Free Malaria

    Care Initiative (FMCI) may remove these profits.

    Risk Management: During appraisal, unit costs of packages have been reviewed to ensure they

    adequately cover all expenditures currently faced by health facilities.

    Resp: Bank Stage: Appraisal Due Date : before

    negotiations Status: Completed

    Description:

    Another risk with the proposed approach (i.e. supporting only

    8 districts) is that people from other districts may travel in

    the Bank 8 districts to receive free care. The Team believes

    this risk is rather limited, for the following reason. Available

    data show that people are ready to travel far away only for

    major health services, such as surgery, delivery or c-section.

    To seek basic health services (such as malaria diagnosis and

    treatment), people will usually not travel farther than 5-10kms.

    In other words, this “spill-over effect” will be limited to the

    villages in the immediate neighborhood of the 8 districts.

    Risk Management: Based on data collected during appraisal, the Team believes the impact of thus risk

    is rather limited, for the following reason. Available data show that people are ready to travel far away

    only for major health services, such as surgery, delivery or c-section. To seek basic health services

    (such as malaria diagnosis and treatment), people will usually not travel farther than 5-10kms. In other

    words, this “spill-over effect” will be limited to the villages in the immediate neighborhood of the 8

    districts.

    Resp: Bank Stage: Appraisal Due Date : before

    negotiations Status: Completed

    2. Implementing Agency Risks (including fiduciary)

    2.1. Capacity Rating: Moderate

    Description: Ministry has substantial experience in managing

    World Bank projects. While the Ministry has developed a

    capacity in arranging vertical programs (HIV-AIDS and

    malaria), there is room for improvement for cross-cutting

    programs focusing on health system strengthening.

    Risk Management: A Project Coordination Unit (PCU) has been set up for the Project and is now

    functional. The same unit will be used for implementing the AF activities.

    Resp: Bank Stage: Appraisal Due Date : Status: Completed

    Risk Management: The PCU benefits from permanent support from a technical assistance firm, which

    is now recruited.

    Resp: Bank Stage: Appraisal Due Date : Status: Completed

    2.2. Governance Rating: Substantial

    Description: Components 1 and 2 of the Project are using

    output-based disbursement mechanisms. As such, there is a

    risk that completion of outputs will not be measured

    adequately. This risk is exacerbated by deficiencies in the

    health information system and lack of social accountability

    Risk Management: Component 3 will strengthen the health information system.

    Resp: Client Stage: Impl Due Date : by end of

    Project Status: In progress

    Risk Management : All outputs will be verified by an external firm, which will use several data

  • 37

    mechanism. A similar risk may occur with the activities

    financed through the AF.

    collection methods for each output (to ensure triangulation)

    Resp: Client Stage: Impl Due Date : by

    effectiveness Status: Completed

    Risk Management: In addition to the external verification (as mentioned above), the Project will fund

    Community-Based Organizations (CBOs) to contribute to the external verification of outputs and to the

    identification of the poorest patients.

    Resp: Client Stage: Impl Due Date : by end of

    Project Status: Not yet Due

    3. Project Risks

    3.1. Design Rating: Moderate

    Description: PDO of the original Project may not be achieved

    because of inadequate timeline and/or funding of the project

    Description: The AF funding may have limited outcomes due

    to barriers (for accessing health care services) other than

    financial ones.

    Description: The AF-funding (Malaria Free Health Care)

    could boost the demand for health care services beyond the

    existing supply capacity of the system

    Risk Management: For estimating the most realistic contribution of the project to the PDO indicators,

    a Marginal Budgeting for Bottleneck (MBB) analysis has been conducted with UNICEF support.

    Additional data will be obtained at appraisal to set the PDO targets at a realistic level.

    Resp: Bank Stage: Prep Due Date : Status: Completed

    In Benin in 2006, 76.4% of the population lived at less than 5km to a health center (and 92.8% less than

    15km). Geographical access is clearly not the main issue to access care. The 2009 country status report

    has also confirmed that cultural/social obstacles for accessing health care are limited.

    Resp: Bank Stage: Appraisal Due Date : Status: Completed

    The above-mentioned 2009 Country Status Report has found the Benin health system to be severely

    underutilized (as demonstrated, for instance, by the low productivity of health workers).

    The main bottleneck is related to the number and quality of community health workers, as they will be

    heavily involved in providing free malaria care. This component will be strengthened, through the

    proposed AF.

    Resp: Bank Stage: Appraisal Due Date : Status: Completed

    3.2. Social & Environmental Rating: Low

    Description: From the received RBF bonuses, health facilities

    may purchase medical equipment which might invariably

    result


Recommended