+ All Categories
Home > Documents > Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and...

Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and...

Date post: 02-Jun-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
57
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003678 IMPLEMENTATION COMPLETION AND RESULTS REPORT (SRF‐CTF GRANT TF014613) ON A GRANT IN THE AMOUNT OF US$8 MILLION TO THE LAO PEOPLE’S DEMOCRATIC REPUBLIC FOR A LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT September 21, 2018 Macroeconomics, Trade, And Investment Global Practice East Asia And Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

Document of 

The World Bank 

FOR OFFICIAL USE ONLY  

 Report No: ICR00003678 

  

 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

(SRF‐CTF GRANT TF014613) 

ON A 

GRANT  

IN THE AMOUNT OF US$8 MILLION 

TO THE 

 LAO PEOPLE’S DEMOCRATIC REPUBLIC   

FOR A 

LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT  

September 21, 2018     

 

 

 

Macroeconomics, Trade, And Investment Global Practice 

East Asia And Pacific Region 

 

 

   

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

CURRENCY EQUIVALENTS  

(Exchange Rate Effective as of September 21, 2018) 

 

Currency Unit =   Lao Kip (LAK) 

US$1 =  LAK 8,523  

 FISCAL YEAR 

July 1 ‐ June 30   

ABBREVIATIONS AND ACRONYMS  

ADB  Asian Development Bank 

AHS  Annual Household Survey 

BOL  Bank of Lao PDR 

BOP   Balance of Payment 

BPM  Balance of Payment Manual 

CSTA  Consulting Service Technical Assistance 

CPF  Country Partnership Framework 

CPI  Consumer Price Index 

CPS  Country Partnership Strategy 

CSPro  Census and Survey Processing System 

FDI  Foreign Direct Investment 

GDP  Gross Domestic Product 

GNI   Gross National Income 

GOL  Government of Lao PDR  

GVA  Gross Value Added 

ICR  Implementation Completion and Results Report 

ICT  Information and Communication Technology 

IMF  International Monetary Fund 

IIP  International Investment Position 

IRR  Internal Rate of Return 

ISR  Implementation Status and Results Report 

IT  Information Technology 

LAOSTAT  Lao PDR’s Strengthening the National Statistical System Project 

LCPA  Lao Classification of Products by Activity  

LECS  Household Expenditure and Consumption Survey 

LSB  Lao Statistics Bureau 

M&E  Monitoring and Evaluation  

MDG  Millennium Development Goal 

MEM  Ministry of Energy and Mines 

MMFT  Macroeconomic Monitoring and Forecasting Team 

MOIC  Ministry of Industry and Commerce 

MOF  Ministry of Finance 

Page 3: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

  

MOLSW  Ministry of Labour and Social Welfare 

MPI  Ministry of Planning and Investment  

NIER  National Institute of Economic Research 

NPV  Net Present Value 

NSEDP   National Socio‐Economic Development Plan 

NUOL  National University of Laos 

PDO  Project Development Objective  

PSC  Project Steering Committee  

SCI  Statistical Capacity Index 

SDNSS  Strategy for Development of the National Statistical System  

SIDA  Swedish International Development Agency 

SMA  Sectoral Ministry and Agency 

SMS  Statistical Metadata System 

SNA  System of National Accounts 

SPSS  Statistical Package for the Social Sciences 

SQL  Structured Query Language 

SRF‐CF  Statistics for Results Facility Catalytic Fund  

SUT  Supply and Use Table 

SWG  Statistical Working Group   

Regional Vice President: Victoria Kwakwa 

Country Director: Ellen A. Goldstein 

Senior Global Practice Director: John Panzer 

Practice Manager: Deepak K. Mishra 

Task Team Leader(s): Somneuk Davading 

ICR Main Contributor: Konesawang Nghardsaysone  

Page 4: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National
Page 5: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 

 

TABLE OF CONTENTS  

DATA SHEET ............................................................................................................................ 1 

I.   PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ....................................................... 5 

A.   CONTEXT AT APPRAISAL ....................................................................................................... 5 

B.   SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ................................. 10 

II.   OUTCOME ...................................................................................................................... 10 

A.   RELEVANCE OF PDOs .......................................................................................................... 10 

B.   ACHIEVEMENT OF PDOs (EFFICACY) ................................................................................... 11 

C.   EFFICIENCY ......................................................................................................................... 17 

D.   JUSTIFICATION OF OVERALL OUTCOME RATING ................................................................. 18 

E.   OTHER OUTCOMES AND IMPACTS (IF ANY) ........................................................................ 19 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 19 

A.   KEY FACTORS DURING PREPARATION ................................................................................ 19 

B.   KEY FACTORS DURING IMPLEMENTATION .......................................................................... 20 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 20 

A.   QUALITY OF MONITORING AND EVALUATION (M&E) ......................................................... 20 

B.   ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ................................................. 22 

C.   BANK PERFORMANCE ........................................................................................................ 22 

D.   RISK TO DEVELOPMENT OUTCOME .................................................................................... 23 

V.   LESSONS AND RECOMMENDATIONS .............................................................................. 24 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 25 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 35 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 37 

ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 38 

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 41 

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) ...................................................................... 48 

   

Page 6: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National
Page 7: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 1 of 51  

      

        

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P129825 LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL 

SYSTEM PROJECT 

Country  Financing Instrument 

Lao People's Democratic Republic  Investment Project Financing 

Original EA Category  Revised EA Category 

Not Required (C)   

Organizations 

Borrower  Implementing Agency 

Lao People's Democratic Republic  Lao Statistics Bureau (LSB) 

Project Development Objective (PDO)  Original PDO 

10.   The objective of the Project is to improve the capacity of the Recipient’s national statistical system to produce and disseminate reliable and timely macroeconomic and poverty statistics in accordance with international standards and in response to user needs.   

Page 8: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 2 of 51  

      

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        TF‐14613 

8,000,000  7,980,215  7,980,215 

Total    8,000,000  7,980,215  7,980,215 

Non‐World Bank Financing       

Borrower     0     0     0 

Foreign Multilateral Institutions (unidentified) 

   0     0     0 

Total     0     0     0 

Total Project Cost  8,000,000  7,980,215  7,980,215  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

07‐May‐2013  05‐Jul‐2013    30‐Jun‐2017  28‐Feb‐2018 

   RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

06‐Jun‐2017  6.26  Change in Loan Closing Date(s) Reallocation between Disbursement Categories 

  

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Moderately Satisfactory  Moderately Satisfactory  Modest 

 

Page 9: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 3 of 51  

      

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  19‐Oct‐2013  Satisfactory  Satisfactory  .40 

02  22‐Sep‐2014  Satisfactory  Moderately Satisfactory  .50 

03  01‐May‐2015  Moderately Satisfactory  Moderately Satisfactory  1.25 

04  30‐Dec‐2015  Moderately Satisfactory  Moderately Satisfactory  2.62 

05  24‐Jun‐2016  Moderately Satisfactory  Moderately Satisfactory  3.87 

06  22‐Feb‐2017 Moderately 

Unsatisfactory Moderately Satisfactory  4.94 

07  25‐Jun‐2017  Satisfactory  Moderately Satisfactory  6.26 

08  25‐Jan‐2018  Satisfactory  Moderately Satisfactory  7.21 

 

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Public Administration   100 

Central Government (Central Agencies)  100 

  Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  

Page 10: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 4 of 51  

      

Economic Policy  0  

Fiscal Policy  9  

Fiscal sustainability  3   

Public Expenditure Policy  3   

Tax policy  3    

Macro‐financial policies  9  

External Finance  3   

Monetary and Credit Policies  3   

Macroeconomic Resilience  3  

   Public Sector Management  0  

Public Administration  35  

Administrative and Civil Service Reform  17   

E‐Government, incl. e‐services  18    

Data Development and Capacity Building  47  

Data production, accessibility and use  47  

   

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  Axel van Trotsenburg  Victoria Kwakwa 

Country Director:  Annette Dixon  Ellen A. Goldstein 

Senior Global Practice Director:  Sudhir Shetty  John Panzer 

Practice Manager:  Mathew A. Verghis  Deepak K. Mishra 

Task Team Leader(s):  Somneuk Davading  Somneuk Davading 

ICR Contributing Author:    Konesawang Nghardsaysone 

         

Page 11: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 5 of 51  

      

I.    PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

A.    CONTEXT AT APPRAISAL 

Context 

1. At the time of appraisal, Lao People’s Democratic Republic (Lao PDR) was at an early stage of transition from a centrally planned to a market‐oriented economy. The country’s output grew at an annual average rate of  7.9  percent  between  2007  and  2012,  driven  primarily  by mining  and  hydropower  sectors  and moderate contribution from light manufacturing, agriculture, tourism and services. With a gross national income (GNI) per capita of US$1,380, Lao PDR graduate from a low‐income to a lower‐middle‐income economy in 2012. Poverty incidence was halved from 46 percent in 1993 to 28 percent in 2008. Some economic reforms in the country had focused on market‐oriented foundations that allowed the emergence of domestic private sector and inflows of foreign direct investments (FDIs). Lao PDR also began to open the country to international trade and commenced the WTO accession process,  following decades of  isolation. However, with a growth model based on natural resources, there were concerns on the inclusiveness and sustainability of the development process.  

2. Against this context, the Government of Lao PDR (GOL) pursued a broad‐based growth strategy with focus on poverty reduction in the Seventh National Socio‐Economic Development Plan (NSEDP) for 2011–2015. The NSEDP emphasized the need for reducing social  inequities and building stronger capacity  to manage the country’s rich natural resources. It emphasized informed policy making and evidence‐based economic policies. Subsequently, the Strategy for Development of the National Statistical System (SDNSS) 2011–2020 was approved in September 2010. The Strategy was meant to help the GOL take more informed decisions in formulating and monitoring economic policies and public service delivery, supported by a statistical system that is credible, timely and accessible. The country had made some progress in building the basic statistical foundation between the 1990s and 2000s, thereby producing statistics on population, sectoral, and economic census, as well as some macroeconomic statistics, including national accounts by the production approach. 

3. Lao PDR’s national statistics system, however,  lagged countries with a similar per capita  income  in three important dimensions. First, there was a limited availability of statistics, on variables such as investment, private consumption, labor force, business registry, manufacturing, and retailing statistics. Second, it suffered from poor quality and timeliness of key statistics,  including national accounts,  international trade, balance of payment (BOP), sectoral output, and investment. And, third, the available statistics were not accessible to public since there was no central database containing consolidated macroeconomic and time‐series data within the GOL. In addition, there was also a limited use of statistical data across government and limited independence of the production process, conditioned by the legacy of a planned economy in Lao PDR. 

4. The  GOL  requested  the World  Bank’s  support  to modernize  and  streamline  its  national  statistical system. Specifically, the objectives were to improve human resource capacity, essential tools, and infrastructure to effectively produce and disseminate reliable and good quality statistics. The Prime Minister’s Decree no.51/PM (2011)  provided  the  legal  basis  for upgrading  the Department  of  Statistics  to  the  Lao  Statistics Bureau  (LSB) headed by a vice minister and included four newly created departments with a massive increase in new staff. This created significant need for capacity building. These objectives were highlighted in the needs assessment for the SDNSS and the evaluation of the statistical capacity support from the Swedish International Development Agency (SIDA) to LSB at the Ministry of Planning and Investment (MPI). These objectives were also aligned with 

Page 12: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 6 of 51  

      

and  supported  by  the  NSEDP.  LSB  already  benefited  from  some  initial  supports  of  the  World  Bank  on improvement of household expenditure and consumption survey (LECS) processes and some capacity building activities by a technical assistance on statistical capacity building (STATCAP). 

5. Major gaps in the national statistical system included the capacity to gather, analyze, and interpret, data from both administrative and surveyed sources. While a Law on Statistics was enacted in 2010, Lao PDR’s statistical  system  remained  highly  decentralized  with  limited  interagency  coordination  and  weak  statistical capacity.  The  LSB  had  limited  statistical  capacity  that  delayed  complete  adoption  of  the  System of National Accounts (SNA) 1993 and statistics production was still on a piecemeal basis. The limited analytical capacity of LSB  constrained  the  use  of  statistics  from both  administrative  and  surveyed  sources. Many  specific  surveys, including the population census, economic census, three rounds of LECSs were already conducted by the GOL but survey methodologies required further optimization especially for questionnaire designs and sampling frame. In a highly decentralized statistical  system,  the  lack of effective and timely  inter‐ministerial coordination and communication led to delays in the production of national accounts every year. Poor statistical collection and reporting at the provincial and district levels compromised the quality and timeliness of data. While the GOL had a clear policy framework of the national statistical system, the lack of professional statisticians at all  levels of administrative structure prevented effective and efficient collection, analysis, and interpretation of statistics for evidence‐based policy making. 

6. The World Bank’s involvement in strengthening the national statistical system in Lao PDR was fully aligned  with  the  2011–2015  Country  Partnership  Strategy  (CPS).  It  incorporated  the  IDA  15–16  Results Measurement System and the Seventh NSEDP for the relevance of providing information and statistical support to monitor development targets and performance indicators of these strategies as well as for formulating and updating development policies.  In addition,  the World Bank’s  support was also  in  line with  the Statistics  for Results Facility Catalytic Fund (SRF‐CF) that provided support to developing countries,i including Lao PDR, to help them improve their statistical capacity. It was a continued support building on capacity foundation made through the past support of the STATCAP. 

Theory of Change (Results Chain) 

7. Lao PDR’s Strengthening  the National Statistical System Project  (LAOSTAT)  responded to  the GOL’s request  to  improve  the capacity of  the national  statistical  system.  It aimed at producing and disseminating reliable and timely macroeconomic and poverty statistics that follow international standards and respond to the needs of users. 

8. The project was expected to have significant economic impact. During the project’s lifetime, Lao PDR’s was  expected  to  achieve  8  percent  annual  growth,  driven  by  expansionary  development  in  the mining  and hydropower sectors and improvements  in manufacturing and services. Poverty  incidence was expected to be reduced by 9 percentage points from 28 percent in 2008 to 19 percent in 2015. Strengthening the production and dissemination of macroeconomic and poverty statistics in the country was expected to help the GOL fulfill its  commitments  to  improve measurement of  and monitor  development  targets  and  result  indicators  in  the Seventh  NSEDP.  The  national  statistical  system  of  Lao  PDR  could  be  strengthened  to  produce  quality macroeconomic and poverty statistics on time, which could be widely disseminated to users and the public. The project was expected to support LSB and to contribute to higher‐quality macroeconomic and poverty statistics that  would  help  provide  more  accurate  and  consistent  measurement  and  monitoring  of  macroeconomic performance and efforts in poverty reduction. Access to and availability of these statistics would also allow users 

Page 13: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 7 of 51  

      

to perform specific and high‐level economic assessment of macro and micro links for inclusiveness and poverty reduction.  

9. Improved  capacity  to  produce  macroeconomic  and  poverty  statistics  in  accordance  with internationally accepted standards was to be achieved through strengthening macroeconomic and poverty data  development  and  management.  Data  development  and  management  for  national  accounts,  relevant macroeconomic statistics, and household surveys would be strengthened to generate quality statistics on time to monitor macroeconomic health and risks. These statistics were also used for planning and evaluating of the economic  and  social  development  program.  The  development  of  national  accounts  data  would  use  the expenditure approach. Other  relevant macroeconomic statistics would be compiled  in  line with  international standards. Poverty statistics would be improved through some adjustments in the LECS. Data analysis aimed at macroeconomic  research  and modeling  as  well  as  gender‐related  analysis.  The  LSB  and  sectoral  ministerial agencies  (SMAs)ii  would  use more  internationally  accepted  standards  and methodologies  in  data  collection, compilation, classification, and validation. 

10. Improved dissemination of macroeconomic and poverty statistics in response to user needs was to be achieved through improvements in data sharing and access. At the end of the project, the LSB and statistical units of SMAs would implement an appropriate data sharing and access to information strategy with adequate physical infrastructure and equipment. It would also upgrade the LSB web portal for improved dissemination. A clear business processes and information management would be implemented by LSB through an adoption of modernized information and communication technology (ICT) infrastructure and improved IT capacity. The staff capacity of LSB and SMAs would be strengthened through training and technical assistance to vitalize the needs of quality statistics  in their  respective ministries. Statistical working groups would be  important to elicit data requirements  and  to  improve  confidence  to  share  and use  the  available  data. Duplication  of  responsibilities among agencies would be removed. Compilation and analysis processes and workflows would be strengthened. LSB  would  be  able  to  coordinate  with  SMAs  more  effectively  and  efficiently  to  compile  data,  especially administrative data, and disseminate statistical products and services to these agencies. 

11. The above‐mentioned cause‐effect links underlying the theory of changes for the project are illustrated in figure 1. 

Project Development Objectives (PDOs) 

12. The  PDO was  to  improve  the  capacity  of  the  Recipient’s  national  statistical  system  to  produce  and disseminate reliable and timely macroeconomic and poverty statistics in accordance with international standards and in responses to user needs.  

Page 14: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 8 of 51  

      

Figure 1. Theory of Changes 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Long‐term results 

Inputs (Activities)  Outputs  PDO/Outcomes 

1. National SNA manual and methodology developed. 2. Re‐benchmarking of the National Accounts to 2012. 3. National  account  development  strategy  and 

methodology was developed and implemented. 4. Generic methods  and  tools  for  economic  surveys 

were developed and used. 5. Supply and Use Table  6. Surveys  on  International  Investment  Position  and 

International Trade in Services were completed. 7. Guidelines  and  measures  to  have  data  quality 

assurance for surveys and administrative data were developed and used. 

8. Training  on  National  Accounts,  economic  survey method, and data quality assurance was delivered. 

9. Macroeconomic framework and modeling capacity was built and used by the GOL. 

1. Institutional  capacity  plan  was  developed  and implemented. 

2. Human  resources  strategy  and  implementation plan were developed and implemented. 

3. Coordination of the National Statistical System was strengthened. 

4. Training  on  management  and  coordination  was completed. 

Component C. Improving Data Access and Sharing: 1. Development and implementation of a 

macroeconomic and poverty data dissemination strategy for the LSB and SMAs. 

2. Development of an ICT Plan. 3. Strengthening ICT infrastructure and 

capacity of the LSB and SMAs. 4. Upgrading the LSB Web Portal for 

improved data dissemination 

Component A. Strengthening Macroeconomic and Poverty Data Development and Management: 1. Improvement of National Accounts (by 

expenditure) and other macroeconomic statistics. 

2. Household survey and poverty‐ and gender ‐related analysis and dissemination. 

3. Strengthening macroeconomic research and modeling capacity for the GOL. 

4. Adaptation of international standards and methodologies in data collection, compilation, and validation and improvement of questionnaires and sampling frames. 

Component B. Improving Policies and Strengthening Implementation Capacity: 1. Strengthening the capacity of the LSB and 

SMAs’ Statistical Units to implement Component A. 

2. Enforcing policy and regulations on statistics and eliminating duplication of responsibilities between the LSB and SMAs –reinforcing LSB’s role as a lead coordinating institution. 

1. Data  dissemination  strategy  and  implementation plan were developed and implemented. 

2. Metadata development strategy. 3. ICT Plan for the National Statistical System. 4. ICT System established for the LSB. 5. Statistical  datasets  partially  migrated  to  the  new 

server and LSB Web Portal. 6. Manuals  on  contents  and  publication  design  and 

maintenance. 7. Training on dissemination, metadata, and ICT. 

Intermediate Outcome 

1. Macroeconomic statistics are produced in line with internationally accepted standards. 

2. Social and demographic statistics (particularly household and poverty data including sex‐disaggregated data) are produced in line with internationally accepted standards. 

3. Internationally accepted standards, classifications, and methodologies in macroeconomic and poverty related data collection, compilation, and validation are in place. 

(Sub‐PDO 2) … disseminate reliable and timely macroeconomic and poverty statistics in response to user needs: 3. Improved user satisfaction with macroeconomic and poverty statistical products and services of the National Statistical System. 

1. Sustained capacity to measure the progress of and monitor results of NSEDP  

2. Sustained monitoring and measurement of economic growth 

 3. Sustained focus 

and estimation of poverty reduction 

4. Interagency coordination mechanism (rules and regulations) between the LSB and other agencies (SMAs) on macroeconomic and poverty statistics are in place and operational. 

5. Human resource management strategy is in place and the LSB and MDA SMAs staff trained and maintained their skills 

6. Data user‐producer dialog established and functional 

7. Dissemination strategy is developed and implemented 

8. IT plan for LSB and SMAs is developed and implemented 

9. LSB web portal improved with increased number of data available 

10. IT staff trained and retained their skills. 

(Sub‐PDO 1) … produce reliable and timely macroeconomic and poverty statistics in accordance with international standards:  1. A comprehensive macroeconomic framework is developed and used within the GOL for policy making and planning process 

2. Improved macroeconomic and poverty‐related statistical capacity score and disaggregated by: a.  Methodology b.  Source data c.  Periodicity and timelines (average):  Survey data  Admin data 

PDO: To improve the capacity of the Recipient’s national statistical system to … 

Page 15: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 9 of 51  

      

Key Expected Outcomes and Outcome Indicators 

13. Key outcome indicators for the project were the following:  

(a) User satisfaction with macroeconomic and poverty statistical products and services of the national statistical system (disaggregated by LSB and SMAs) improved. 

(b) Macroeconomic  and  poverty  related  statistical  capacity  score  improved  and  disaggregated  by methodology, source data, and periodicity and timeliness. 

(c) A  comprehensive macroeconomic  framework  is  developed  and used within  the GOL  for  policy making and planning process. 

Components 

Component A. Strengthening Macroeconomic and Poverty Data Development and Management 

14. This component was to improve production and dissemination of reliable and timely macroeconomic and poverty  statistics.  Lao PDR was  already  compliant with  SNA 1993 during project  appraisal  but wanted  to implement SNA 2008 in national account statistics and include the use of the expenditure approach. Lao PDR was also committed to strengthening macroeconomic research and modelling capacity in key Government agencies. It would help enhance survey methodologies by optimizing questionnaire design and sampling frame, to ensure that surveys would be in line with international standards. This component intended to finance technical assistance, training,  and  workshops  for  (a)  improvement  of  the  national  accounts  by  expenditure  and  other  key macroeconomic statistics; (b) improvement of analysis and dissemination of LECS for poverty‐ and gender‐related analysis;  (c)  strengthening  macroeconomic  research  and  modeling  capacity;  and  (d)  adapting  internationally accepted standards and methodologies, including questionnaire designs and sampling frames in data collection, compilation, and validation by the LSB and statistical units in the SMAs. 

Component B. Improving Policies and Strengthening Implementation Capacity 

15. This component was meant to enhance the institutional capacity for the LSB and statistical units in SMAs. It aimed to remove duplicate responsibilities between agencies. The national statistical system in Lao PDR was highly decentralized and not very well integrated by having several levels and agencies producing and disseminating duplicate  statistics  as well  as  conducting  surveys.  The  component was  to  complement  the GOL’s  decision,  by following the approval of the Law on Statistics in June 2010, to rationalize the LSB as the lead agency in production, management, coordination, and dissemination of national statistics in Lao PDR. To that end, the project intended to finance technical assistances, training, and workshops on (a) capacity building for the LSB and statistical units in SMAs  and  (b)  review  and  formulation  of  policy  and  regulations  on  statistics  aiming  at  eliminating  duplicate responsibilities between the LSB and statistical units in SMAs. 

Component C. Improving Data Access and Sharing 

16. This component was to support data sharing and access to information strategy and increase efficiency of data collection and processing through the establishment of cost‐effective ICT infrastructure and equipment. While  the  LSB  already  had  a  series  of  datasets,  for  example  LECS  1–3  and  economic  censuses  that were  at  a disaggregate level, these data were not shared adequately and efficiently, often constrained by a lack of a clear data sharing and access to information policy framework. The GOL was committed to enhance the access to data 

Page 16: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 10 of 51  

      

by stakeholders in policy making, planning, and monitoring of development programs by increasing the efficiency and effectiveness in data collection, data processing, analysis, and timely dissemination. The project intended to provide support for (a) development of a dissemination strategy, (b) development of an ICT plan, (c) procurement of new ICT infrastructure for the LSB and statistical units in some SMAs, and (d) technical assistance to upgrade the LSB web portal for improved data dissemination. 

B.    SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) 

Revised PDOs and Outcome Targets 

17. There were  no  changes  to  the  PDOs  or  to  the  outcome  targets.  The  closing  date  of  the  project was extended  from  June  30,  2017,  to  February  28,  2018,  to  complete  some  delayed  outputs,  especially  the implementation  of  Component  C,  which was  caused  by  a  significant  delay  in  the  LSB’s  headquarters  building construction. 

Revised PDO Indicators 

18. Not applicable. 

Revised Components 

19. Not applicable. 

Other Changes 

20. Not applicable. 

Rationale for Changes and Their Implication on the Original Theory of Change 

21. Not applicable. 

II.   OUTCOME 

A.    RELEVANCE OF PDOs 

Assessment of Relevance of PDOs and Rating 

22. The PDO was well‐aligned to the policy priorities of Lao PDR, as expressed in the SDNSS 2011–2020. The latter aimed to achieve a “comprehensive, timely, transparent, and reliable supply of good quality socioeconomic and environment statistics in meeting with an increasing demand of the Government and other statistics users. It also  aimed  to  support M&E  and  formulation  of  Lao  PDR’s  socioeconomic  development  programs, Millennium Development Goals (MDGs) by 2015, and its graduation from Least Developed Country status by 2020.” The SDNSS was guided by the Seventh NSEDP 2011–2015 that focused on poverty reduction through a combination of broad‐based  economic  growth  and  specific  policy  interventions.  An  improved  statistical  system would  help  support monitoring  and  evaluation  of  development  targets  and  results.  The  project  focused  on  an  improvement  of institutional and staff capacity enabling the national statistical system to produce as well as disseminate reliable and timely macroeconomic and poverty statistics. The availability of macroeconomic and poverty statistics would 

Page 17: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 11 of 51  

      

also allow Government researchers and academia to conduct more relevant researches to inform decision making and planning of a wide variety of social and economic development programs. 

23. The PDO remained highly relevant at the Implementation Completion and Results Report (ICR) stage. The PDO continues to be highly relevant and aligned with the current Eighth NSEDP (2016–2020) aiming to reduce the poverty incidence rate from 23.2 percent in 2012 to 10 percent in 2020 and to maintain an average annual growth rate at 7–7.5 percent. The reliable and timely measurement of these targets and other targets is necessary to  have  reliable  and  timely  statistics  by  the  national  statistical  system.  Furthermore,  the World  Bank Group’s Country Partnership Framework1 (CPF) for Lao PDR identified the continued relevance of supporting the national statistical  system  to  ensure  that  reliable  and  timely  data  are  available  to  assess  the  country’s  economic performance and to formulate relevant development programs and instruments in support of Lao PDR’s social and economic development. 

Rating of Relevance of PDO: High 

24. The PDO clearly  targeted specific  constraints of  Lao PDR’s national  statistical  system to produce and disseminate reliable and timely statistics. These constraints were identified, analyzed, and consulted extensively by the LSB and statistical units in SMAs in the SDNSS. Lao PDR did not have a proper macroeconomic framework that was developed and used within the GOL. The macroeconomic and poverty statistics were unreliable and were unavailable on time. Credible measurement and estimates of economic performance or poverty reduction require strong statistical evidence and data support. The focus of the PDO on production and dissemination of reliable and timely macroeconomic and poverty statistics already stressed the high  importance of trying to satisfy the huge needs and increasing demand of statistics users. These two sets of statistics are highly relevant to measure and monitor the NSEDP targets and indicators at the annual performance, at midterm review, and at final evaluation of the plan. They are also highly relevant for formulation of the new follow‐on future NSEDPs. 

B.    ACHIEVEMENT OF PDOs (EFFICACY) 

25. The efficacy  assessment decomposes  the PDO  into  two outcome objectives.  They  are  to  (a)  produce reliable  and  timely macroeconomic  and  poverty  statistics  in  accordance  with  international  standards;  and  (b) disseminate macroeconomic and poverty statistics in response to user needs. The decomposition is in line with the appraised PDO of  the Project Appraisal Document and  the grant agreement of  the project. The PDO reads “to improve the capacity of the Recipient’s national statistical system to produce and disseminate reliable and timely macroeconomic and poverty statistics in accordance with international standards and in responses to user needs.” As  the theory of change  in  figure 1 shows,  these amplified parts of  the PDO were  intermediate outcomes and activity outputs supported by the project. Key achievements of the PDO indicators were presented in Table 1. 

   

                                                       1 Report no. 110813.  

Page 18: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 12 of 51  

      

Table 1. Summary of Indicators and Achievements  

Indicators  Unit  of Measure 

Baseline Value 

End  Target Value 

End  Actual Value 

Achievement (%) 

PDO level           Macroeconomic and poverty related statistical capacity score2 improved and disaggregated by 

Number  61.00  75.00  65.00  87.8 

a. Methodology  Number  50.00  65.00  50.00  78.1 

b. Source data  Number  50.00  65.00  60.00  93.8 

c. Periodicity and timeliness  Number  74.00  85.00  93.00  110.7 

A comprehensive macroeconomic framework is developed and used within the GOL for policy making and planning process 

Text 

None  is available 

The framework  is produced and used  by  the GOL 

The framework  is produced and used  by  the GOL 

100.0 

User satisfaction3 with macroeconomic and poverty statistical products and services of the national statistical system (disaggregated by LSB and SMAs) improved. 

Percent  33.00  52.80  34.00  65.64 

 

Assessment of Achievement of Each Objective/Outcome 

26. The  sub‐objectives of  the project were  to  (a) produce  reliable  and  timely macroeconomic and poverty statistics in accordance with international standards and (b) disseminate macroeconomic and poverty statistics in response  to  user  needs.  The  achievements  of  each  sub‐objective were  assessed  as  explained  in  the  following paragraphs.  

Objective 1: Produce reliable and timely macroeconomic and poverty statistics in accordance with international standards 

27. The project has  achieved many of  the expected outcomes  in producing macroeconomic and poverty statistics. The achievements of this sub‐objective at both outputs and intermediate outcomes are significant. A remarkable result was a significant improvement in the dimension of periodicity and timeliness of statistics. The 

                                                       2 Statistical capacity score is, also known as the Statistical Capacity Index (SCI), constructed by the World Bank in partnership with other international organizations including the IMF, United Nations (UN), the United Nations Educational, Scientific and Cultural Organization (UNESCO), and World Health Organization (WHO). The statistical score is measured in a scale from 1 to 100 points. A higher point refers to a better capacity of the national statistical system. The latest available SCI for Laos which is used for this ICR was a bit outdated (based on data from 2016 WDI/WEO) and it did not capture recent achievements made by the GOL with support from the project about rebase of GDP and CPI, BOP and poverty update. By incorporating these changes, the score would certainly be higher.  3 User satisfaction is measured in percentage constructed from the user satisfaction survey. A higher percentage refers to higher satisfaction of users. Two surveys were conducted. The first survey was completed in 2015 to establish the baseline of the indicator and the second survey was completed in 2018 to provide the actual end‐result. 

Page 19: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 13 of 51  

      

main outputs of the project include (a) Lao PDR’s national accounts manual, (b) supply and use tables (SUT); (c) rebase of gross domestic products (GDP) to 2012, (d) investment position survey, (e) new consumer price index (CPI)  basket  to  improve price  statistics,  (f)  poverty  analysis  and  report  based on  LECS  5,  (g)  national  accounts development strategy, (h) LSB’s human resource strategy, and (i) capacity building for sectoral statistics agencies. Key macroeconomic and poverty  statistics as well  as population census data were produced and disseminated much faster than before and with better quality and standards.  

28. Lao  PDR’s  national  accounts manual.  To  enable  the  LSB  to  transition  from  SNA  1993  to  SNA  2008,  a supplementary customized manual of national accounts for Lao PDR was approved in May 2017. In line with SNA 2008 by  the United Nations,  the manual provides procedures and guidelines  for data  sources and compilation methods to be used to estimate GDP at the national level. The manual is in line with good practices for a small economy in adopting SNA 2008. The manual focuses mainly on the SUT and estimation processes of GDP at the national  level, not  suitable at  the provincial  level. Broadly,  the supplementary national account manual  is only partially  in  line with the full SNA 2008 manual  iii. A complete transition toward a more robust use of SNA 2008 would require further upgrades of both institutional and staff capacity in LSB and improvement of data sources. Currently, Lao PDR does not use the SNA 2008 methodology completely.  

29. Supply and Use Tables (SUT). An update and expansionary data compilation was supported by the project to finalize the construction of the 2012 SUTiv in support of the GDP rebase to 2012. Key datasets assembled include (a) a series of annual household surveys (AHSs) and the 2015 Enterprise Survey (Establishments Survey); (b) data on agriculture and informal businesses assembled from the LECS 2012–2013; and, (c) the 2012 Economic Census. The constructionv of the 2012 SUT was completed in March 2017. Most componentsvi of the SUT framework were compiled and completed except for Part C ‘Make or Supply Matrix’ because of lack of information from producers in Lao PDR to compile the intermediate consumption matrix. Part E on ‘Further Details of gross value added (GVA)’ was also not complete because  information  for disaggregate  income details was not available. To mitigate  the shortfall of Part C, the LSB used estimated coefficients4 from a neighboring country as a starting point. The total by products  for  Part  C  were  compared  to  the  initial  estimates  of  Part  B  on  ‘Balance  of  supply  and  demand  or commodity flows accounts’ to produce an approximate balance through some adjustments by using the approach of adjustment and updating of the technical coefficients, known as the RASvii method. 

30. GDP  rebase  to  2012.  Based  on  the  SUT  completed  in March  2017,  the  Lao  PDR’s  GDP  by  production approach was estimated and rebased to 2012. The 2012 SUT framework generated new estimates of GDP at current prices in 2012 at LAK 81.6 trillion, 8 percent higher than the GDP of the same year previously estimated at LAK 75.3 trillion by  the 2002 SUT  framework. The GVA of  some economic activities was much higher  than  the previous estimates in the 2002 SUT framework. Based on the 2012 GDP rebase, GDP estimates from 2002 to 2011 were also re‐estimated and aligned. New estimates of GDP from 2012 to 2016 were extrapolated. The next rebase year was expected to be 2017 and a new 2017 SUT framework was to be compiled in 2019/2020. The LSB would need to improve  the quality  and  coverage of  data  sources,  better methodology,  and  institutional  and  staff  capacity  to implement the task that would be very demanding in time, budget, and expertise. 

31. International investment position (IIP) surveys. Two IIP surveys were conducted by the Bank of Lao PDR (BOL) to collect investment data to adjust and improve the compilation of the BOP statistics and establish the IIP and external statistics for Lao PDR. These statistics were critical for the estimation of GDP and GNI and to align Lao 

                                                       4 The coefficients from Thailand were used to combine and apply to Lao PDR’s estimates of intermediate demand by product at the 3‐digit level of the Lao Classification of Products by Activity (LCPA). 

Page 20: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 14 of 51  

      

PDR’s  BOP  statistics  to  comply with  international  standards.  The  first  IIP  survey was  conducted  in  2016  (with support from the project) to collect investment position data for 2014 and 2015. It was a joint effort between the BOL, LSB, and the Ministry of Industry and Commerce (MOIC). The second survey to collect investment position data for 2016 and 2017 was directly financed by the BOL and was completed in June 2018. The two surveys would provide a series of adequate years of the investment position data that could help the BOL improve parts of IIP and external debts in the BOP statistics. The IIP surveyviii was for the first time to provide total FDI estimates in Lao PDR. In the 2016 survey for 2014 and 2015 data, the total FDI (excluding the banking sector) estimate was US$5.3 billion, about 36 percent higher than the total FDI in 2014. The second survey was conducted during the first semester of 2018 and its result is being finalized. 

32. New CPI baskets were used to improve price statistics. With the project’s support, Lao PDR had compiled a monthly CPI with a new CPI basket and a new base year of 2015 (December 2015 = 100), started in July 2016. Two major changes were made in the CPI estimation. They were (a) expanding items in the basket from 245 to 485 items and (b) including all 18 provinces instead of 12 previously. The weights were also updated based on the Lao Social Indicator Survey in 2012.  

33. Poverty analysis and report based on LECS 5. Lao PDR’s poverty analysis and report based on LECS 5 was completed and published on time in October 2015. The poverty analysis was robust because of higher quality of poverty data from the recent LECS 5 in 2012–2013 and detailed analysis of transition of poverty reduction by having the  proper  panel  from  the  LECS  3–5  surveys.  A  2015  census‐based  poverty  incidence  mapping  was  jointly conducted and completed between the LSB and the World Bank in June 2016. The questionnaire for LECS 6 was improved with the project’s support to rationalize key principles in designing new questionnaires to enable data of the upcoming LECSs 6 and 7 to meet data requirements of national accounts and poverty analysis. The AHSs 5 were already conducted to fill data gaps, but there were some inconsistencies in methodologies between AHSs and LECS. The new questionnaire of AHS was also improved to align with the LECS 6 questionnaires to reduce the difference. The sample size of the 2014 AHS was smaller than 2,700 households. The suggested size should be increased to about 50 percent of the LECS 6. The LSB started to conduct the LECS 6 in June 2018.  

34. National accounts development strategy was developed in June 2017. For building capacity of the LSB and statistical units in line ministries, the national accounts development strategy and methodology was developed to  outline  the  priority  areas  that  need  improvement  and  need  to  comply  with  the  SNA  2008  methodology. Following the use of the 2012 SUT framework and the GDP rebase to 2012, key priorities were to  improve the quality and standard of statistical data, increase the frequency of GDP estimates on a quarterly basis, and improve methodology to exploit key datasets. Some error detection methodologies were developed to identify and correct mistakes to obtain high‐quality national accounts. The Excel template used for compiling the 2012 SUT needed to be  adapted  to  compile  new  data  sources  for  the  next  GDP  rebase  to  2017.  At  the  end  of  the  project,  the implementation of the strategy was just at the beginning and has not yet yielded any significant changes. 

35. LSB human resource strategy and Institutional Capacity Plan 2016–2020. In July 2016, a human resource strategy was developed in preparation of the LSB staff to respond to the changing environment and to support statistics  production  and  dissemination.  The  human  resource  strategy  outlined  a  clear  set  of  the  LSB’s  vision, mission, and strategic priorities, where its (a) vision was to enable organizational change that delivers greater staff performance  and  business  effectiveness;  (b) mission was  to  organize  Lao  PDR’s  statistics  to make  them more globally accessible and provide Lao people with easy access to global information; and (c) strategic priorities were 

                                                       5 The AHS was conducted in 2003, 2004, 2005, 2008, 2011, and 2014 by the LSB. The AHS is a shortened version of the LECS. 

Page 21: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 15 of 51  

      

to have clear workforce planning, motivate great staff, and provide excellent processes. At the end of the project, the LSB has only implemented some of the priorities.  

36. The Institutional Capacity Plan 2016‐2025 (ICP) is a short and direct document, highlighting the areas that needed to change, including a schedule of survey activities, and containing a matrix illustrating strategic pillars, outcomes, objectives and activities. It provides the basis for LSB’s efforts to build capacity but also a template for future resource mobilization. The four pillars of the ICP, which are cross‐referenced to SDNSS 2016‐2025, are: (i) developing  the  LSB  leadership  role  in  the  coordination  of  the  National  Statistical  System;  (ii)  strengthening organizational development; (iii) modernizing the statistical infrastructure; (iv) improving the service to users. 

37. Capacity building for sectoral statistics agencies. Several key sectoral statistics agencies were supported by  the  project  to  improve  their  statistical  capacity  and  communication  for  providing  economic  data  from administrative  sources.  Key  support  included methodology  skills  training  and  revision  of  the  sectoral  statistics manuals, templates, and procedures. The beneficiary agencies included the MOIC’s Statistics Center, the Statistics Office of the Ministry of Energy and Mines (MEM), BOL’s BOP Office, Tax Department of the Ministry of Finance (MOF), the Faculty of Economics and Management of the National University of Laos (NOUL), and the National Institute of Economic Research (NIER). 

38. A comprehensive macroeconomic framework is developed and used. The project successfully achieved targets in this indicator. A comprehensive macroeconomic framework and modelling was fully established in 2016 and was built on the earlier framework that had been already used by NIER since 2011. Such a framework was delivered because of a strong macroeconomic monitoring and forecasting team (MMFTix), which was established with the project’s support to compile the macroeconomic framework and modelling. Several rounds of workshops, trainings, and consultations were organized for the MMFT. Since 2016, the MMFT, led by NIER, has been able to make projections of key macroeconomic indicators until 2020. NIER’s annual economic review reports were issued in the first quarter of each calendar year. The latest report was issued in March 2018.6 However, preparation of quarterly  macroeconomic  updates  had  significant  challenges  because  of  limited  high  frequency  data  and insufficient budget for conducting small quarterly surveys as needed. 

Objective 2: Disseminate macroeconomic and poverty statistics in response to user needs 

39. The  project  partially  achieved  the  expected  outcome  in  disseminating  macroeconomic  and  poverty statistics in response to user needs. The targets in the PDO indicator were only partially achieved because of the lag in translating outputs and intermediate results into outcomes and impact by the time when the end‐project user  survey was  conducted  (June  2017).  Despite  significant  improvements  in  production  and  dissemination  of macro  and  poverty  statistics  through  hard  paper  publication,  online  data  access  and  sharing  have  not  been improved  as  expected  because  data  interface  platforms  and  consolidated  website  for  data  sharing  were  not completed due  to  significant delays  in operational  and  technical  changes.    First,  there was a  long delay  in  the Government‐financed  construction  of  the  LSB  office  building  that  would  house  the  ICT  infrastructure.  The construction of the LSB office building started late and the contractors were slow in conducting the civil works. The LSB  office  building was  only  completed  in  the  fourth  quarter  of  2017.  Second,  there was  some  challenges  in migration of various Microsoft Access datasets that were managed on various personal computers and were often shifted from the server to local personal computers and vice versa to the new data warehouse platform and to be uploaded  into  the web portal,  supported by  the project.  The  LSB  staff  still  lack  the  skills  to  use  the  relational 

                                                       6 Report of Lao PDR’s macroeconomic review for 2017 and its trend in 2018. 

Page 22: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 16 of 51  

      

database  management  system  (for  example,  Structured  Query  Language  [SQL]  server  and MySQL)  from  data acquisition to data dissemination. The LSB did not have a data warehouse platform before the project.  

40. Despite limited improvements in online data access and sharing, it is essential to recognize the important outputs supported by the project. The achievements of the expected outputs at the end of the project could be a stepping  stone  for  the  LSB  to  enhance  future  dissemination  of  national  statistics.  Main  contributions  to  an improved  policy  framework  on  data  sharing  and  access  to  information  and  an  improved  ICT  environment  in facilitating data access in the following paragraphs.  

41. LSB  ICT  plan  2016–2020.  The  ICT  plan  outlined  detailed  guidelines  for  the  use  of  ICT  to  support  the modernization  of  statistical  processes  to  ensure  alignment  with  international  standards  and  supports  the development of  an  ICT platform and  the  strengthening of  the  ICT human  resource  capacity.  The  ICT plan was prepared with  the project’s  support  and was  approved  in April  2016.  The  implementation of  the  ICT plan has started, including the key information technology (IT) infrastructure and capacity‐building support financed by the project. The multiyear ICT plan was initially implemented by the LSB between 2016 and 2017. More outputs under the ICT plan still need to be delivered during the remaining period of the plan. Currently, it is unclear whether the LSB will be able to secure funding from the Government’s budget allocation to implement the plan. 

42. Metadata  development  strategy  and  maintenance  manual.  In  July  2016,  a  metadata  development strategy  was  developed,  with  the  project’s  support,  to  provide  the  LSB  some  concrete  steps  to  develop  and implement a statistical metadata system (SMS) that would be in line with international standards. The SMS was to improve the efficiency of data and metadata preparation, storage, access, management, and dissemination for statistical  products  produced  across  the  GOL.  In  line  with  the  metadata  development  strategy,  a  metadata development  and  maintenance  manual  was  also  prepared.  The  manual  helped  guide  the  LSB  to  define  key components of a metadata management systemx. With the project’s support, an SMS was established in the new data warehouse platform in the LSB and a metadata unit was assigned to lead this important priority, but it faced several  constraints  to  maintain  and  further  develop  it.  Major  constraints  include  limited  ICT  and  database development skills in the LSB. There are only two database developers who have the basic skills and they would require significant training and skills upgrade to deliver an efficient metadata management system. 

43. A  strategy  to  upgrade  the microdata management  system. With  the  project’s  support,  a  strategy  to upgrade the microdata management system was prepared and approved in December 2015. The strategy focused on implementable technical and organizational changes as well as complex technical approaches, including data integration and data warehousing. The strategy included (a) establishing a centralized storage and a centralized control of microdata; (b) having a distributed access to microdata; (c) establishing a structured working procedures; and  (d)  strengthening  staff  to  be  adequately  competent  in  the  following  roles:  system  architect,  system administrator, ICT security, database administrator, database designer, Access, SQL, or Visual Studio developers, and  statistical  software professionals  (Statistical  Package  for  the  Social  Sciences  (SPSS),  Stata,  and Census  and Survey Processing System (CSPro)) to ensure connectivity between statistical software and rational database.  

44. Data dissemination strategy. In March 2017, a data dissemination strategy was prepared and approved by the LSB. The strategy attempted to set priorities for the LSB to adopt international good practices in improving (a) the limited accessibility of statistics and metadata, (b) weak impartiality and objectivity; (c) the poor relevance of statistics,  (d)  less  timeliness and periodicity of  statistics;  and  (d) weak  confidentiality practices.  The  strategy  is comprehensive to transform the LSB’s dissemination approach. The strategy defined clear dissemination principles on  equal  access,  impartiality  and  transparency,  online  dissemination  database,  and  bilingual  publication  on  a 

Page 23: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 17 of 51  

      

centralized web portal. However, the strategy has not yet been implemented to fully realize all these important priorities. At  the  time of project closing,  the LSB has not been able to centralize and upgrade the existing web portals.  It  could  not  make  any  significant  organizational  and  technical  changes  to  adopt  a  new  approach  to dissemination by launching the centralized web portal that was supported by the project. Significant efforts would be needed in the coming year to achieve the target set in the strategy. 

Justification of Overall Efficacy Rating 

Rating: Substantial 

45. The overall efficacy rating is Substantial. The project has achieved most of its outputs and significant parts of its two sub‐objectives. At the end of the project, the production of macroeconomic and poverty statistics has been improved with the LSB’s ability to have GDP estimates for the actual economic growth and projection for the next  statistical  year.  Data  collection  from  surveys  sources  has  also  been  improved  with  enhanced  survey questionnaires and methodologies and use of digital survey technology (tablets)  through the project’s support. Likewise,  data  collection  from  administrative  sources  has  also  been  gradually  efficient  because  of  clearer coordination  and  communication  roles  between  the  LSB  and  sectoral  statistics  agencies  as  well  as  improved manuals and templates. The project contributed to a stronger foundation for future improvements. The project was behind expectation in producing a GDP by expenditure approach due to low quality and timeliness of some sectoral data. It was also behind expectation in dissemination of statistics due to limited operational and technical changes. The project‐supported LSB web portal has not yet been launched and upgraded to centralize all datasets and statistics including macroeconomic and poverty data to allow greater access and improved outreach. Currently, the LSB still maintains three different domains for data dissemination supported by different donors (Lao Info, Lao Decide Info, and Lao PDR National Data Archive (LNADA)) and LSB is in the process of consolidating and streamlining these websites to increase efficiency and improve online data dissemination.  

C.    EFFICIENCY 

Assessment of Efficiency and Rating 

Rating: Substantial 

46. The  project  had  some  broad  economic  benefits  and  welfare  gains  through  improvement  in administrative efficiency. An economic analysis was performed at the ICR stage. The broad economic benefits are derived from existence of improved quality and timely information and inputs for evidence‐based policy making for the GOL and other users, and monitoring of overall economic performance and emerging risks, measurement of  results  of  GOL  development  programs  and  improvement  in  budget  allocation.  Despite  the  delays  in implementation  particularly  in  the  third  component,  which  showed  partial  achievement  of  results  on  data dissemination, the project generated important cost savings and welfare gains. The economic and welfare analysis focused in three ways: (a) timely production of macroeconomic and poverty statistics would increase cost saving for the LSB and reduce waiting times for statistical users; (b) quality production of macroeconomic and poverty statistics  would  minimize  efforts  of  users  to  further  verify  and  gather  more  evidence;  and  (c)  effective dissemination of statistics would  increase data sharing and reduce the time that users  take  to access statistics (metadata,  administrative  data,  macrodata,  and  survey  data).  Because  this  project  was  not  to  generate  any additional revenue for the LSB or the economy cost‐saving and value of time saved for the LSB and the economy are key benefits gained through the project’s support. With some caution, these benefits are interpreted only in the context of availability of and access to statistics. The analysis period is from 2013 to 2021, covering the project 

Page 24: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 18 of 51  

      

life and beyond with the assumption that some of the benefits require time to be gained as several strategies and plans are being  implemented. The discount rate was maintained at 5 percent. The expected economic benefits were estimated based on the assumptions shown in table 1 in Annex 4. Efficiency Analysis. 

47. Based on the assumptions, the project’s key benefits at the ICR stage included some cost savings and marginal welfare gains. This project was not to generate any revenue flows for the LSB. The internal rate of return (IRR) was estimated at 6 percent and the net present value (NPV) was estimated at US$6,149,508. First, the project investments contributed to more timely production of statistics, especially macroeconomic and poverty statistics that could save some administrative costs for the LSB in comparison with the baseline costs which the LSB would have without the project. The incremental cost saving was estimated at US$214,478 or 7 percent of the LSB’s total administrative costs. Likewise, the incremental value of time saved for the LSB was also estimated at US$526,863. The value of time saved was translated to infer an incremental saving for the economy that was also estimated at US$8,579,499 or about 0.01 percent of GDP.  

Table 2. Estimated Economic Benefits 

Description  At Appraisal 

At ICR 

Estimated savings     Incremental administrative cost savings for the LSB (2013–2021)  —  US$214,478 

Incremental saving for the value of time saved to the LSB (2013–2021)  —  US$526,863 

Incremental savings for the value of time saved to the economy (2013–2021)  —  US$8,579,499 

IRR and NPV estimation     IRR  —  6 % 

NPV  —  US$6,149,508 

D.    JUSTIFICATION OF OVERALL OUTCOME RATING 

Rating: Moderately Satisfactory 

48. The project achieved major parts of its objectives. All objectives of the LAOSTAT were highly relevant, as they were  aligned  to  the  government  policy  and Bank  strategy  of  enhancing  the  national  statistical  system  in support of Lao PDR’s social and economic development. Efficacy and efficiency were rated substantial. With the project,  production  of  macroeconomic  and  poverty  statistics  has  been  improved  in  line  with  international standards. Macroeconomic and poverty statistics are released faster than before and on time. Access to raw survey data is still slow and remain challenging. Although the overall statistical score for Lao PDR has slightly improved from  61  to  68  in  a  scale  from  1  to  100  points,  it  still  falls  short  of  the  end  target  of  75  points7.  Noticeable improvements were made in the dimension of periodicity and timeliness of statistics by 6.67 points from 86.67 in 2011 to 93.33 in 2017. The actual end score of statistical methodologies has not changed from its baseline at 50 points. The score of statistical source data or data collection and compilation at the end of the project was at 60 points, 10 points higher than the baseline but it was still behind the end target of 65 points. Limited improvements 

                                                       7 The latest available SCI score is a bit outdated (based on data from 2016 WDI/WEO) and make it difficult to establish a complete picture and have a full assessment of this PDO indicator at ICR stage. The new update is expected to be available by end‐2018 and it will likely incorporate recent improvements made by the GOL (with support from the project), especially on GDP and CPI rebase, BOP and poverty update. New score in the next update would surely be improved. 

Page 25: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 19 of 51  

      

in  the  scores  reflect  some  delays  in  translating  project  outputs  into  results  by  Lao  PDR  during  the  project implementation. In addition, some improvements such as GDP rebase to 2012 were timely reflected in the updating of the score. 

E.    OTHER OUTCOMES AND IMPACTS (IF ANY) 

Gender 

49. The project co‐financed LECS 5 survey and Population and Housing Census 2015, which produced gender disaggregated statistics on poverty, employment, education, health and intra‐household time use. These statistics were further disaggregated at the province level, improving the understanding of gender gaps spatially too. 

Institutional Strengthening 

50. The  project  provided  significant  support  on  institutional  strengthening  for  LSB  and  several  related ministries and agencies through: (i) a series of leadership, management and technical training for senior and young statistical officials (about 100 training workshops and knowledge exchange visits were organized with support from the project and nearly 1700 people were trained); (ii) development of a long term institutional capacity plan and human resource strategy  for LSB; (iii) and modernization of ICT infrastructure for LSB and three pilot provinces.  

Mobilizing Private Sector Financing 

51. Not applicable. 

Poverty Reduction and Shared Prosperity 

52. The project provided support on poverty analysis for LECS5 and survey design for the next round of LECS surveys and some poverty related training for LSB to strengthen their capacity to produce good dataset including 

with  sex‐disaggregation  for  the  LECS,  population  census,  enterprise  surveys  and  economic  census  to  better monitor economic performance and poverty reduction targets. 

Other Unintended Outcomes and Impacts 

53. Not applicable. 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME 

A.    KEY FACTORS DURING PREPARATION 

54. The project preparation was informed by extensive diagnostics conducted by the GOL, the World Bank, and other development partners. The GOL’s needs assessment for the SDNSS and the final evaluation report of SIDA’s statistical capacity support to the LSB at the MPI were the key documents that were considered as inputs for the project design. Lao PDR had strong appetite for transitioning (a) from SNA 1993 to SNA 2008, (b) the national accounts base year from 2002 to 2012, and (c) from the Fifth Edition of Balance of Payment Manual (BPM5) to the Sixth Edition of BPM (BPM6). The GDP estimate was only performed by using the production approach, which was in line with SNA 1993. It wanted to adopt the expenditure approach and produce quarterly GDP, but it was not 

Page 26: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 20 of 51  

      

possible at that time because of poor quality and lack of source data. The project design was based on extensive consultations with the LSB, SMAs, academia, and development partners in Lao PDR. The preparation of the project also  benefited  greatly  from  some  interventions  of  the World  Bank  Group  through  the  Lao  statistics  capacity technical  assistance  (STATCAP),  studies  and  policy  notes  of  the  development  partners,  including  the  Asian Development Bank (ADB), the International Monetary Fund (IMF), and SIDA. 

B.    KEY FACTORS DURING IMPLEMENTATION 

55. The project experienced a classical U shape curve with a swift startup of implementation but later faced some significant constraints in procurement before more tangible processes were made at the end of the project. At the  launch of the project,  the LSB demonstrated strong ownership  in  implementing the project  in preparing work plans and initiating procurement of goods and consultants for project implementation. However, there were some challenges in selecting a qualified procurement specialist at the first two years of the project. There was a limited pool of qualified procurement consultants in the local market. The project, therefore, faced some significant delays in having a technical assistance expert team to provide comprehensive consulting services to the LAOSTAT on technical assessments and development of manuals and key operational strategies. The technical assistance expert team was only on board during the midterm of the project. Most technical outputs and ICT‐related outputs were delivered quite close to the end of the project, especially Component C on ICT infrastructure. Due to such delays, LSB had only limited time to fully translate delivered outputs into actions and results.  

56. LSB had a weak absorptive capacity to fully apply advanced statistical methodologies and international standards in statistical production. Most of the junior staff had a limited statistical background and qualifications. The already delayed implementation of ICT also faced further slowdown with a significant delay in the LSB’s new headquarters building construction in Vientiane. The new headquarters building was not financed by the project, but through the Government’s state budget, and was completed in the third quarter of 2017. The major ICT‐related activities  (network  cabling  and  system  installation,  development  of  data  center,  installation  of  electricity generators, and so on) were started in July 2017 and were only completed by the end of February 2018. 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

A.    QUALITY OF MONITORING AND EVALUATION (M&E) 

M&E Design 

57. The M&E design was relevant at the time of project preparation when the availability of information and data was  limited.  Two  of  the  three  PDO  indicators were  considered measurable  and  attributable  to measure improvements in the capacity of the Lao PDR’s national statistical system as whole but partially at specific project levels and at ICR stage as it would take some time to see impacts after project completion. The first indicator was to rely on two satisfaction surveys of statistical users in Lao PDR by the project. At design, there was no survey being conducted to establish the baseline. The first satisfaction survey of statistical users was conducted in 2014.  

58. The second PDO indicator was highly relevant for cross country comparisons because it measured scores of national statistical capacities in three dimensions: statistical methodology, source data, and periodicity and timeliness. This indicator is an internationally recognized indicator that is jointly constructed by the World Bank, IMF, UN, UNESCO, and WHO, but this indicator source was not updated on a regular basis to reflect the progress made in the field. 

Page 27: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 21 of 51  

      

59. The  third  PDO  indicator  was  important  to  measure  the  development  and  use  of  a  macroeconomic framework by the Government. However, it was quite broad, and the means of verification appear quite limited with  just a descriptive narration  that could not capture  tangible  results and  its quality. Nearly all  intermediate outcome indicators were descriptive, but not quantitative. Likewise, the means of verification for these indicators were also descriptive and were not in any references of an independent assessment of the targets. Such weakness in  the  indicators  left  some  quality  gaps  that  the  project  should  focus  on  to  track  the  quality  of  progress  and achievement in the intermediate and PDO results. 

M&E Implementation 

60. The  M&E  implementation  was  relatively  adequate  at  least  for  those  indicators  that  relied  on administrative  and  project  data  sources.  These  included  the  third  PDO  indicator  and  almost  all  intermediate outcome indicators. However, it was challenging for the LSB to keep track and obtain information or evidence to track the progress and achievement of targets for PDO indicators 1 and 2.  

61. For PDO indicator 1, the LSB was able to conduct two satisfaction surveys during the project life of four years, but it also faced some delays in completing them on time. The baseline for this indicator was populated quite late after the project started. The baseline was only established with the first satisfaction survey that was conducted only in 2014 and completed in 2015. As consequence, the second satisfaction survey was subsequently conducted in 2017, but it was completed in early 2018 to track achievements of the targets in this indicator. By January 2018, the project had only one month toward the end date of the project. As such, the result of the survey was not incorporated in the project M&E framework. The last Implementation Status and Results Report (ISR) was submitted in December 2017 and was approved in January 2018.  

62. Likewise, the project also faced some delays in updating the second PDO indicator because of time lags for international organizations to reflect some of the improvements in Lao PDR’s statistical capacity score. There were some gaps between reporting of in‐country improvements to the relevant partners that perform the update of the statistical capacity score. The process of updating the SCIs has also been complex and time‐consuming. 

M&E Utilization 

63. The PDO indicators were useful not only to measure the achievements of the project targets, but LSB also used it to keep track of the overall capacity of the national statistical system. Most notably, the second PDO indicator was an indicator that the LSB could keep track of its performance in the future because it relies on an open source that does not require much of an effort by the LSB to obtain the data and undertake verification for the source. In addition, this indicator measures three main dimensions: methodology, source data, and periodicity and timeliness. The LSB appeared to have more difficulty in using the first PDO indicator because it requires both financial  and  human  resources  to  conduct  the  survey  on  a  periodical  basis.  It  was  assessed  that  it  would  be challenging  for  the LSB to conduct any  follow‐up satisfaction surveys without project support after  the project closed because of  limited  capacity  and  lack of  funding. A  typical  satisfaction  survey would  cost  the  LSB about US$50,000. The possibility that the LSB would be able to secure a sufficient budget to conduct such a survey in the future would be limited unless it could be financed by external sources. 

Justification of Overall Rating of Quality of M&E 

Rating: Modest 

Page 28: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 22 of 51  

      

64. The design of the PDO indicators was broadly of acceptable quality, but the targets were not realistic during project implementation. M&E implementation faced some shortcomings in obtaining realistic and relevant data  and  evidence  to  update  targets  in  the  project’s  Results  Framework.  The  overall  statistical  score was  not reflected because of gaps in communication and time lags in the update of the score by international organizations. The second follow‐up satisfaction survey was conducted late and there was also a delay in completing the survey to  provide  the  required data  on  time  for  updating  targets  in  the  indicator. Only  the  second PDO  indicator  on statistical  capacity  score would  remain  relevant and would have  less  financial burdens on  the  LSB  to  continue monitoring the overall capacity of the national statistical system. However, the LSB would still need to improve its reports  and  communications  with  international  organizations  to  frequently  update  the  score  to  reflect improvement of the overall capacity in the country. 

B.    ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE 

65. The project’s fiduciary performance was Moderately Satisfactory. The key fiduciary issues were delays in project  procurement  and  weak  capacity  in  financial  management  in  the  LSB.  The  project  experienced  some significant delays in procurement operation and there were not many project activities implemented during the first and second year of the project. An experienced procurement officer was only on board in July 2014 to help the LSB to expedite the large procurement packages, including (a) technical assistance on capacity building for the LSB  in which  the  technical  assistance  consultancy  contract was  signed  in  July 2015 and  (b)  an  ICT package  for supplying and installing ICT equipment, software, and related services, for which the procurement contract was signed in December 2016. With respect to financial management, the LSB also had limited experience in managing any large project of this size. It faced some difficulties to familiarize and follow the project financial management manual and procedures at the beginning of the project. 

66. The environmental and social safeguards policies were not applied to this project as it was classified as ‘Category C’ during project appraisal. No safeguards issue was triggered during project implementation. 

C.    BANK PERFORMANCE 

Quality at Entry 

Rating: Satisfactory 

67. The project’s  theory of  change was well  articulated.  The World Bank benefited  significantly  from  the existing diagnostics of Lao PDR’s national statistical system, including the final evaluation report of SIDA’s support to build the LSB’s capacity, ADB’s technical assistance on SUT to  improve macroeconomics statistics, and IMF’s existing  assessment  of  statistical  issues.  During  project  preparation  and  appraisal,  the World  Bank  conducted several missions and carried out some extensive consultations with stakeholders in the Government, academia, and development partners to validate the project design. It identified that strengthening the LSB’s overall capacity in methodology, source data, and periodicity and timeliness would contribute to organizational, operational, and technical changes in the LSB and SMAs to improve production and dissemination of economic and social statistics.  

68. Project design was relevant by emphasizing on adopting  international standards and methodology  in statistical  production  in  response  to user  needs.  Because of  the  competing priorities  in  various  statistics,  the project approach and design were selectively focusing on improvement of LSB’s core capacity in production and dissemination of reliable and timely macroeconomic and poverty statistics. The project design was in line with the 

Page 29: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 23 of 51  

      

GOL’s priorities and action plan defined in the SDNSS (2011–2020) aiming at leveraging the LSB’s role as the leading agency in national statistics. It also aimed at upgrading its overall statistical capacity to produce and disseminate economic and social statistics in Lao PDR in accordance with international standards and in response to user needs. 

Quality of Supervision 

Rating: Moderately Satisfactory 

69. Project implementation support by the World Bank was carried out through two main channels. First, the World Bank task team was based in Vientiane and this helped the LSB obtain immediate access to advice and technical backstopping for project implementation on a daily and weekly basis. Second, it benefited from formal implementation support missions. Despite there were only four main project implementation support missions in a five‐year project with formal Aide Mémoires submitted to MPI and LSB, the project was claimed to benefit from many specific missions and visits by individual experts and consultants of the World Bank. The latter appeared to provide specific and timely support to each implementing department within the LSB and in SMAs. The mission notes and key steps for actions to be taken were discussed and agreed with the client.  

70. Despite some delays in project procurement, the project rebounded at the second half of the project by onboarding of the consulting team and a strong presence of a single Task Team Leader from the start to the end of the project.  The project consultants had delivered all expected outputs to the LSB. The World Bank task team provided regular reviews of these outputs and provided timely comments to the LSB and the project consultants. The supervision task teams comprised members with an appropriate skill mix given the scope and status of the project. Site visits to monitor implementation progress and quality of works were carried out jointly with the client during each mission and  visit.  Fiduciary  and  safeguards monitoring,  and guidance were  sufficient,  helpful,  and timely with local presence. A total of eight ISRs were candidly prepared. Issues were reported on time to the World Bank management and they were communicated to LSB.  

Justification of Overall Rating of Bank Performance 

71. The  overall  rating  of  World  Bank  performance  is  Moderately  Satisfactory,  because  of  the  moderate shortcomings in supervision.  

D.    RISK TO DEVELOPMENT OUTCOME 

72. There are  some  clear  risks  likely  to  affect  the  LSB’s  ability  to  sustain  the achieved outcomes  and  to translate some delayed outputs  into future results that are critical  for additional  improvements of statistical production and dissemination. Looking forward, the LSB would depend on timeliness and quality of source data (administrative and surveyed sources) and qualified statisticians to apply international standards in its statistical methodologies  in  statistical  production.  Unless  the  existing  gap  of  limited  qualified  statisticians  is  addressed seriously by LSB, workloads for the existing qualified statisticians would compromise its capability in production of statistics.  

73. Dissemination  of  statistics  through  an  ICT‐based  data  platform  such  as  a  web  portal  will  require significant upgrade in LSB’s ICT capability to maintain and update it. While the operation and maintenance of the facilities was financed directly by the project, the risk that such facilities may not be used is high in the future, if adequate financial and human resources are not allocated to support the initiative. At the end of the project, a disaster recovery center has not been established to provide a back‐ up of the data platform. In addition, backup 

Page 30: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 24 of 51  

      

power provided (with two electrical generators) has not been fully connected to the entire building of IT equipment and some lighting and devices. This poses some risks of disruption and business discontinuity. 

V.   LESSONS AND RECOMMENDATIONS  74. A focused and simple project design, consistent with the client’s absorptive capacity, is key to producing results.  Project design  should  sequence project  activities  to match  the  client’s  absorptive  capacity. During  the appraisal, the detailed assessments of organizational and operational capacity was missing. The project design was to  assume  that  a  large package of  international  technical  assistance  (twining  arrangement) would provide  the required inputs and deliver outcomes on time. This arrangement has been useful for provide technical assistance needed  during  the  implementation,  however  its  procurement was  very  cumbersome with weak  procurement capacity of the client. Because of the delays in procurement, several outputs were delivered late and the LSB had limited absorptive technical capacity to translate technical recommendations and action plans into results. Most deliverables were strategies, manuals, and action plans financed by the project. For instance, despite all outputs delivered for statistical dissemination, the LSB could not centralize and launch the supported web portal, a main public domain channel to disseminate statistics online. 

75. While  adopting  international  standards  is  quite  straight  forward  for  macroeconomic  and  poverty statistics, it was challenging for the LSB to collect source data with quality and timeliness from administrative sources. The project relied intensively on the LSB for upgrading its capacity in methodology and survey processes, but  efforts  by  the  project  and  the  LSB were  limited  to  improving  quality  and  timeliness  of  source  data  from administrative  sources.  Source  data  from  administrative  sources  in  line  ministries  and  sectors  are  still  too aggregate, less well‐organized, and are not in time series. Future support should focus on making organizational and operational changes to have good quality administrative sources. 

76. Selection  of  project  indicators  must  be  carefully  assessed  regarding  data  sources,  frequency,  and accessibility  to  ensure  timely  update  of  project  targets.  Using  the World  Bank’s  SCIs  to  assess  the  national statistical system’s capacity was relevant to track improvement in key dimensions of statistical capacity and provide cross  country  comparisons.  However,  it  would  be  helpful  for  specific  statistical  projects  if  the  SCI  could  be customized to suit the need at project or program levels. In this project, the SCI is used as one of three key PDO result  indicators  but  updating  the  indicator  at  ICR  stage  was  challenging  because  the  SCI  was  not  updated frequently. The process of updating the SCIs has also been complex and time‐consuming.  

77. Further support to the LSB is highly recommended. The LSB will still need to optimize the use of its ICT infrastructure,  network  system  and  data  center,  and  web  portal  to  further  improve  data  dissemination  and management  and  strengthen  IT  capacity.  An  operation  team  should  be  created  to  provide  maintenance  and upgrades of all ICT components. Specialized skills in data migration and system integration with other offices are highly  required.  Data  dissemination will  strongly  require  institutional  commitments  to  activate, maintain,  and update the web portal to enable easy access to data and sharing. In addition, future support to the implementation of  key  strategic  Plans  adopted  by  the GOL,  such  as  the  institutional  capacity  development  plan,  ICT  and  data dissemination strategies, and human resource strategy under overall Strategy for  the Development of National Statistical System (2016‐2025) would be very critical to further strengthen the national statistical system’s capacity to produce reliable and timely data to the GOL for evidence‐based policy making.   

. . 

Page 31: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 25 of 51  

      

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

       A. RESULTS INDICATORS  A.1 PDO Indicators       

 Objective/Outcome: To produce reliable and timely macroeconomic and poverty statistics in accordance with international standards 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Macroeconomic and poverty related statistical capacity score improved and disaggregated by: 

Number  61.00  75.00    65.00 

  31‐Dec‐2011  30‐Jun‐2017    22‐Jun‐2017 

 

(a)  Methodology  Number  50.00  65.00    50.00 

  31‐Dec‐2011  30‐Jun‐2017    22‐Jun‐2017    

(b) Source Data  Number  50.00  65.00    60.00 

  31‐Dec‐2011  30‐Jun‐2017    22‐Jun‐2017    

(c)  Periodicity & timeliness: 

Number  74.00  85.00    93.00 

  31‐Dec‐2011  30‐Jun‐2017    22‐Jun‐2017  

 

Comments (achievements against targets):  

Page 32: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 26 of 51  

      

 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

A comprehensive macroeconomic framework is developed and used within the GOL for policy making and planning process. 

Text  None is available.  Framework is institutionalized. 

  Framework is institutionalized. 

  31‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017 

 

Comments (achievements against targets): A macroeconomic framework was developed jointly by the Government's macroeconomic working group and it has been used by the National Institute of Economic Research (NIER)‐‐the lead think thank of the Government of Lao PDR. By using the framework, NIER has been able to produce annual macroeconomic review on a regular basis to inform decision making and economic policy formulation. 

     

 Objective/Outcome: To disseminate macroeconomic and poverty statistics in response to user needs. 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

User satisfaction with macroeconomic and poverty statistical products and services of the NSS (disaggregated by LBS and SMAs) improved. 

Percentage  33.00  52.80    34.00 

  28‐Mar‐2014  30‐Jun‐2017    28‐Feb‐2018 

 

Comments (achievements against targets): The actual baseline from the LSB's satisfaction survey in 2014 was 33 percent instead of 49, previously reported in the ISRs. Likewise, the formulation of the end target of this indicator was that there would be an improvement in user satisfaction by 60 percent at the end of the project. Based this formulation, the correct end target for this indicator was 54.78 percent. LBS should be LSB because LBS was incorrectly entered in the indicator narrative. NSS refers to the national statistical system. 

Page 33: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 27 of 51  

      

 

  

 A.2 Intermediate Results Indicators      

 Component: A: Strengthening Macroeconomic and Poverty Data Development and Management 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Macroeconomic statistics (especially GDP and prices) are produced in line with internationally accepted standards. 

Text  Poor qualiy  Quality improved.    Quality improved. 

  28‐Dec‐2012  30‐Jun‐2017    27‐Oct‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Social and demographic statistics (particularly household and poverty data including sex‐disaggregated data) are produced in line with internationally accepted standards. 

Text  Partially use of international standards 

International standards fully applied. 

  International standards fully applied. 

  28‐Dec‐2012  30‐Jun‐2017    22‐Jun‐2017 

 

Comments (achievements against targets):  

   

Page 34: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 28 of 51  

      

 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Internationally accepted standards, classifications and methodologies in macroeconomic and poverty related data collection, compilation, and validation are in place. 

Text  Partially in use, especially data collected from administrative reporting system. 

International standards applied. 

  International standards mostly applied except for some administrative sources. 

  28‐Dec‐2012  30‐Jun‐2016    22‐Jun‐2017  

Comments (achievements against targets): International standards, classifications and methodologies were mostly applied in macroeconomic and poverty related data. However, some sectoral economic data collection and compilation has not been fully in use of international standards, classifications and methodologies in reality. This has been a major issue on the quality of source data and it has constrained the production of quarterly GDP and GDP by expenditure and income approaches. 

     

 Component: B: Improving Policies and Strengthening Implementation Capacity 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Interagency coordination mechanism 

Text  Project Steering Committee (PSC) and Statistical Working Group (SWG) will be in place including necessary regulations should be prepared. 

Inter‐agency coordination improved. 

  Inter‐agency coordination improved. 

  28‐Dec‐2012  30‐Jun‐2017    10‐Nov‐2017 

Page 35: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 29 of 51  

      

   

Comments (achievements against targets): PSC and SWG were established in 2014. Inter‐agency coordination improved through a regular conduct of relevant agencies meetings and consultations on statistical issues including data collection, compilation, analysis and dissemination. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Human resource management strategy is in place and LBS and SMA staff trained and maintained their skills. 

Text  No human resource strategy and training program is in place 

Human resource strategy is implemented. 

  Human resource strategy is partially implemented. 

  28‐Dec‐2012  30‐Jun‐2017    30‐Nov‐2017  

Comments (achievements against targets): The human resource strategy was approved by LSB in 2016. However, the institutional capacity plan (ICP) was finalized and formally approved by LSB by end‐Nov 2017. LBS should be LSB but it was entered incorrectly. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Data user‐producer dialog established and functional 

Text  The dialogue is random and infrequent 

Data user‐producer dialogue improved. 

  Data user‐producer dialogue improved. 

  28‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017  

Comments (achievements against targets): The annual data user‐producer forum (dialogue) was organized regularly. The last forum was conducted in June 2017. LSB has continued to conduct the data user‐producer dialogue through various channels including the last one that was conducted on International Statistics Day in October 2017. 

     

Page 36: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 30 of 51  

      

 

 Component: C: Improving Data Sharing and Access 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Dissemination strategy is developed and implementation plan is prepared. 

Text  No policy. Drafting process started. 

Dissemination strategy in place. 

  Dissemination strategy in place. 

  28‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017  

Comments (achievements against targets): The dissemination strategy was prepared and approved in March 2017. A subsequent dissemination plan were prepared and approved by LSB. The strategy has been only partially implemented. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

IT plan for LBS and SMAs is developed and implemented. 

Text  No plan  Good plans in place and implemented. 

  Good plan in place but partially implemented. 

  28‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017  

Comments (achievements against targets): The ICT strategy and action plan were in place. The implementation of the ICT plan has started including the key IT infrastructure and capacity building supports financed by the project. The multi‐year ICT Plan has been initially implemented by LSB between 2016 and 2017. More outputs under the ICT Plan still need to be delivered during the remaining period of the plan. As mentioned previously, LBS should be LSB. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

LSB web portal improved with increased number of 

Text  Needs significant improvement. 

The web portal improved. 

  The web portal improved. 

Page 37: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 31 of 51  

      

 data available.    28‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017  

Comments (achievements against targets): The web portal improved but it has not been launched by LSB. It has some issues with migration of datasets that are in various forms, most notably MS Access in different versions and there would need to be migrated into a newer version and the database format. LSB still operates its data dissemination with three different domains namely Lao Info, Lao Decide Info and LNADA that were previously supported by different donors. The new web portal supported by LAOSTAT project was to centralize and rationalize into a single public domain while various older domains will remain for internal use. However, LSB has not decided to take action for launching the new web portal developed. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

IT staff trained and retained their skills. 

Text  Limited number of IT staff and skills. 

Skills learned and applied. 

  Skills learned and applied. 

  28‐Dec‐2012  30‐Jun‐2017    20‐Dec‐2017  

Comments (achievements against targets): The IT skills of LSB staff has been strengthened. Intensive workshops and training on key IT competency and skills including database administration and development, system administration, ICT security, access/visual studio developers with SQL, application software (CAPI/STATA/SPSS), networking and infrastructure maintenance were delivered to LSB ICT staff. However, key issue is the limited number of qualified IT staff available for obtaining the required training. LSB would need to recruit more qualified IT staff. 

   

         

Page 38: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 32 of 51  

      

     B. KEY OUTPUTS BY COMPONENT 

  

Objective/Outcome 1: To produce reliable and timely macroeconomic and poverty statistics in accordance with international standards 

 Outcome Indicators 

1. Macroeconomic and poverty related statistical capacity score improved and disaggregated by: methodology, source data, and periodicity and timeliness 

2. A comprehensive macroeconomic framework is developed and used within the GOL for policy making and planning process 

Intermediate Results Indicators 

1. Macroeconomic statistics (especially GDP and prices) are produced in line with internationally accepted standards 

2. Social and demographic statistics (particularly household and poverty data, including sex‐disaggregated data) are produced in line with internationally accepted standards 

3. Internationally accepted standards, classifications, and methodologies in macroeconomic and poverty related data collection, compilation, and validation are in place 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 1) 

1. National SNA manual and methodology developed. 2. Re‐benchmarking of the national accounts to 2012. 3. National account development strategy and methodology was 

developed and implemented. 4. Generic methods and tools for economic surveys were 

developed and used. 5. SUT. 6. Surveys on IIP and international trade in services were 

completed. 

Page 39: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 33 of 51  

      

7. Guidelines and measures to have data quality assurance for surveys and administrative data were developed and used. 

8. Training on national accounts, economic survey method, and data quality assurance was delivered. 

9. Macroeconomic framework and modeling capacity was built and used by the GOL. 

Objective/Outcome 2: To disseminate macroeconomic and poverty statistics in response to user needs. 

 Outcome Indicators 1. User satisfaction with macroeconomic and poverty statistical 

products and services of the national statistical system (disaggregated by LSB and SMAs) improved. 

Intermediate Results Indicators 

1. Interagency coordination mechanism 2. Human resource management strategy is in place and LSB and 

SMA staff trained and maintained their skills 3. Data user‐producer dialog established and functional 4. Dissemination strategy was developed, and implementation 

plan is prepared 5. IT plan for LBS and SMAs is developed and implemented 6. LSB web portal improved with increased number of data 

available 7. IT staff trained and retained their skills 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. Institutional capacity plan was developed and implemented. 2. Human resource strategy and implementation plan were 

developed and implemented. 3. Coordination of the national statistical system was 

strengthened. 4. Training on management and coordination was completed. 5. Data dissemination strategy and implementation plan were 

developed and implemented. 

Page 40: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 34 of 51  

      

6. Metadata development strategy. 7. ICT plan for the national statistical system. 8. ICT system established for LSB. 9. Statistical datasets partially migrated to the new server and 

LSB web portal. 10. Manuals on contents and publication design and 

maintenance. 11. Training on dissemination, metadata, and ICT. 

  

Page 41: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 35 of 51  

      

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

A. TASK TEAM MEMBERS 

 

Name  Role 

Preparation   

Somneuk Davading  Senior Economist/Task Team Leader(s) 

Mustafa Dinc  Senior Economist/Statistician 

Genevieve F. Boyreau  Senior Country Economist 

Carlos E. Sobrado  Senior Poverty Specialist 

Naomi J. Halewood  ICT Policy Specialist 

Richard Record  Senior Trade Specialist 

Keomanivone Phimmahasay  Economist 

Christopher Robert Fabling  Senior Financial Management Specialist 

Siriphone Vanitsaveth  Financial Management Specialist 

Souphanthachak Sisaleumsak  Procurement Specialist 

Roch Levesque  Legal 

Chau‐Ching Shen  Senior Finance Officer/Disbursement 

Viengkeo Phetnavongxay  Environmental Safeguards Specialist 

Kanitta Kaikittipoom  Trust Funds Operations Analyst 

Vatthana Singharaj  Program Assistant 

   

Supervision/ICR   

Somneuk Davading  Senior Economist/Task Team Leader(s) 

Latharo Lor  Procurement Specialist(s) 

Siriphone Vanitsaveth  Financial Management Specialist 

Sivaramen Ramasawmy  Senior IT Officer 

Evgenij Najdov  Senior Country Economist 

Naomi J. Halewood  Senior ICT Policy Specialist 

Sybounheung Phandanouvong  Social Safeguards Specialist 

Waraporn Hirunwatsiri  Environmental Safeguards Specialist 

Viengsamay Srithirath  Country Officer 

Page 42: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 36 of 51  

      

Soulivong Chanthalangsy  IT Analyst 

Konesawang Nghardsaysone  Economist/Primary ICR Author 

Keomanivone Phimmahasay  Economist 

Obert Pimhidzai  Senior Economist 

Souksavanh Sombounkhanh  Program Assistant 

Phet Udom Mainolath  Program Assistant 

Alina Phonvisay  Program Assistant 

Sourignahak Sakonhninhom  Program Assistant 

       

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY13  1.000  3,835.20 

Total  1.00  3,835.20  Supervision/ICR 

FY12  21.016  79,957.90 

FY13  7.165  13,566.02 

FY14  25.530  41,708.82 

FY15  33.950  43,864.74 

FY16  52.240  123,763.57 

FY17  50.173  134,544.78 

FY18  41.265  111,727.29 

FY19  11.602  25,435.68 

Total  242.94  574,568.80     

  

   

Page 43: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 37 of 51  

      

ANNEX 3. PROJECT COST BY COMPONENT 

 

Components Amount at Approval 

(US$, million) 

Actual at Project Closing (US$, 

million) 

Percentage of Approval (US$, 

million) 

A. Strengthening Macroeconomic and Poverty Data Development and Management 

3.13  3.13  100 

B. Improving Policies and Strengthening Implementation Capacity 

1.16  1.16  100 

C. Improving Data Access and Sharing  

2.69  2.68  100 

D. Supporting LAOSTAT Project Management 

0.80  0.80  100 

Unallocated budget  0.23  0.23  100 

Total  8.00   8.00  100 

  

   

Page 44: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 38 of 51  

      

ANNEX 4. EFFICIENCY ANALYSIS 

   Introduction 

1. An economic analysis was conducted at the ICR stage to assess the resource efficiency and cost‐effectiveness of the project. The economic analysis is, however, constrained by the characteristics of the project that are not amenable to a cost and benefit analysis as it was argued at the time of appraisal. In such circumstance, the economic analysis at the ICR stage was also limited but was intended to assess resource efficiency  and  cost  effectiveness by  looking  at  some broad economic benefits  resulted  from project investments. 

Economic Analysis at Appraisal 

2. At  the  appraisal  stage,  the  project  was  characterized  as  nonamenable  to  a  cost  and  benefit analysis. However, at  the time of appraisal,  the economic benefits of  the project were assumed to be derived from three main sources: First, existence of data would enhance the potential for evidence‐based decision making, at policy, program, and project levels. Second, an improved statistical system in Lao PDR would  enable  the  GOL  and  international  community  to  measure  and  track  the  results  of  national development  programs  and  plans,  including  the NSEDP  implementation, MDGs,  and  the GOL’s  vision 2020. Third,  the efficiency would be  improved  from better allocation of  resources and more effective implementation of planned and ongoing development programs. 

3. Likewise, there was not financial analysis at appraisal as the LSB does not operate on commercial terms. Some general assumptions were highlighted as follows: 

(a) National statistics are a public good and are generally financed from tax revenue and aid as they have limited potential for cost recovery. 

(b) Costs of statistical reports and data for sales are kept at minimum to foster demand and use of statistics. 

(c) Only marginal  financial  returns are expected  from  the project because  reports  are often produced  on  the  basis  of  usefulness  to  the  whole  development  community,  but  not  to generate any significant fiscal revenue. 

Economic Analysis at ICR 

4. At ICR, the economic analysis of the project focused on broad economic benefits and welfare gains in three ways: (a) timely production of macroeconomic and poverty statistics would increase cost saving for the LSB and reduce waiting times for statistical users; (b) quality production of macroeconomic and poverty  statistics would minimize efforts of users  to  further verify and gather more evidence; and  (c) effective dissemination of statistics would increase data sharing and reduce the time that users take to access to statistics (metadata, administrative data, macrodata, and survey data). Since this project was not to generate any additional revenue for the LSB or the economy, cost savings, and value of time saved for the LSB and the economy are key benefits gained through the project’s support. With some caution, 

Page 45: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 39 of 51  

      

these benefits are interpreted only in the context of availability of and access to statistics. The analysis period is from 2013 to 2021, covering the project life and beyond with the assumption that some of the benefits require time to be gained as several strategies and plans are being implemented. The discount rate  was  maintained  at  5  percent.  The  expected  economic  benefits  were  estimated  based  on  the assumptions shown in table 4.1. 

Table 1. Key Assumptions for an Economic Analysis 

KEY ASSUMPTIONS 

Baseline (back track to 2013) 

Unit  Targets (%) 

Description  Actual (2018) 

Unit 

GDP growth        7 a year          

Cost saving because of efficiency improvement   

Staff months  720  staff months 

10  Drops in year 3 of the project forward because of efficiency improvement in statistical production 

10  Percent drop 

Waiting time between production and release   Macroeconomic statistics 

18  months  33  Drops  12  Months 

Poverty statistics (LECS)  

24  months  25  Drops  18  Months 

Economic census 

24  months  25  Drops  24  Months 

AHS  18  months  25  Drops  24  Months 

Time take to access to statistics   Macroeconomic statistics 

0.5  months  50  Drops because of improved dissemination for data access and sharing 

0.25  Months 

Poverty statistics (LECS)  

2  months  50  Drops  2  Months 

Economic census 

2  months  50  Drops  2  Months 

AHS  2  months  50  Drops  2  Months 

5. Based on these assumptions, the project’s key benefits at ICR are more cost savings and some 

welfare gains. This project was not to generate any revenue flows for the LSB. The IRR was estimated at 6 

percent and the NPV was estimated at US$6,149,508. First, the project investments contributed to more 

timely  production  of  statistics  especially macroeconomic  and  poverty  statistics  that  could  save  some 

administrative costs for the LSB in comparison with the baseline costs which the LSB would have without 

the project. The  incremental  cost  saving was estimated at US$214,478 or 7 percent of  the LSB’s  total 

administrative  costs.  Likewise,  the  incremental  value of  time saved  for  the  LSB was also estimated at 

Page 46: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 40 of 51  

      

US$526,863. The value of time saved was translated to infer an incremental saving for the economy that 

was also estimated at US$8,579,499 or about 0.01 percent of GDP.  

Table 2. Estimated Economic Benefits 

Description  At Appraisal  At ICR 

Estimated savings     Incremental administrative cost savings for the LSB (2013–2021) 

—  US$214,478 

Incremental saving for the value of time saved to the LSB (2013–2021) 

—  US$526,863 

Incremental savings for the value of time saved to the economy (2013–2021) 

—  US$8,579,499 

IRR and NPV estimation     IRR  —  6 % 

NPV  —  US$6,149,508 

  

   

Page 47: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 41 of 51  

      

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS 

 

CONSOLIDATED COMMENTS from the LSB, LAOSTAT and CSTA team 

on the IMPLEMENTATION COMPLETION AND RESULTS REPORT 

(SRF‐CTF GRANT TF014613) 

 We  would  like  to  thank  the  WB  for  giving  us  opportunity  to  provide  comments  on  the  draft Implementation Completion and Results Report (ICR) dated 6 September 2018. After consultation with the members of the National Implementation and Coordination Team (NICT), the LAOSTAT Consultancy Services for a Twinning Arrangement (CSTA) as well as the respective departments of the LSB, we have prepared  a  list  of  comments  and  suggestions  below  (general  and  specific  comments)  for  your consideration. 

  General comments:  Overall, the ICR is well written and aligned with LSB’s Project Completion Report. We agree with most of what has been assessed in the ICR. Nevertheless, we have three observations below: 

− The assessment of the outcomes and the associated rating: considering the discussion on the limitations of  the  PDO  indicators  selected,  the  team  considers  that  there  could  be  a  case  for  upgrading  the Outcome rating to Satisfactory considering the outputs of the project as reflected in the achievement against the Intermediary Results Indicators. 

− The World Bank’s performance: In absence of evidence of shortcomings included in the ICR, again the team considers that there could be a case for upgrading the Bank Performance’s rating to Satisfactory. 

− The  lessons  learned:  It  would  be  helpful  to  include more  discussion  in  the  ICR  on  the  efficacy  or otherwise of  the public‐private partnership approach adopted. Perhaps also, more emphasis on the role of the twinning arrangement in the project could be put as most activities and outputs mentioned have benefitted from significant contributions from the modality. 

Specific comments: The comments are organized following the ICR structure.  

    

Page 48: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 42 of 51  

      

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

A.  CONTEXT AT APPRAISAL 

Context 

§5 (paragraph 5) 

Fully  using  the  1993  SNA  was  not  possible  partly  because  of  the  poor  quality  of  the  BOP  statistics (compiled by the Central Bank).  It is extremely doubtful that a small country like Lao should or could fully implement the SNA as in large sophisticated economies. 

B.  SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) 

II.  OUTCOME 

A.  RELEVANCE OF PDOs 

B.  ACHIEVEMENT OF PDOs (EFFICACY) 

Table 1. Summary of indicators and achievement The percentages of achievement should not assume the base (starting) value to be zero.  If the calculation is indeed to be made, it should be in the form ((End actual value minus base value) / (End target value minus base value)) * 100.  But it is not clear how the calculation would add much to the analysis.  

Assessment of Achievement of Each Objective/Outcome 

Objective 1: Produce reliable and timely macroeconomic and poverty statistics in accordance with 

international standards 

§28 

As mentioned earlier, transition from 1993 to 2008 SNA is one thing.  This was done for that part of the SNA that was being compiled.  That Lao PDR is not fully using the 2008 SNA is another.  It was not fully using the 1993 SNA.  The project did not extent the scope of the SNA use.  This was not possible partly because of the poor quality of the BOP statistics (compiled by the Central Bank).  It is extremely doubtful that  a  small  economy  like  Lao  should  or  could  fully  implement  the  SNA  as  in  large  sophisticated economies.  But there is perhaps a need to focus on benchmarking the BOP as well as the GDP. 

There  is  no way  to  estimate  GDP  by  expenditure  reliably without  high  quality  continuous  household expenditure data.  Very costly in a small country. 

Quarterly GDP covering all formal activities is not possible without access to VAT data.   Although access to VAT data was not achieved until the very end of the project, this was a big breakthrough. 

Enterprise surveys for this are costly and usually unreliable. In fact, successful comprehensive enterprise surveys  yielding  reliable  financial  data  (including  cost  structures)  are  extremely  rare.   Focusing  on  a particular economic activity at a time seems to be a better approach. 

Page 49: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 43 of 51  

      

The extrapolation system put in place would require additional specialist support to be sustainable. 

Insert after §34 

The development and promotion of generic methods and quality assurance (LOSQAF) should probably be more  explicitly  mentioned  among  the  main  outputs  of  the  project.  Even  though  the  effective implementation has been  limited, this was an addition to the original requirements and a response to needs expressed by LSB that have laid the basis for a more methodical and effective way of conducting surveys and assessing their quality in the future. 

Insert after §35 

The ICP would also deserve a mention. At LSB’s request, priority was first given to the preparation of a Human Resources  Framework and HR Strategy and  Implementation Plan, which also necessitated  the early drafting of a Training and Development Plan (including management and coordination training) on the basis of a training needs analysis that had been conducted. 

Although  the  development  of  the  Institutional  Capacity  Plan  (ICP)  commenced  later  than  originally planned, it was noted that it could be viewed as the most important of the CSTA project deliverables, as it provided not only the basis for LSB’s efforts to build capacity but also a template for future resource mobilization.   

Justification of Overall Efficacy Rating 

Rating: Substantial 

§44 

The overall assessment “Substantial” seems reasonable. 

Because of the nature of the SCI, it is uncertain whether it will reflect ‘recent achievements made by the client’. See “Note on the World Bank Statistical Capacity Indicator” for more details. 

Similarly, and as evoked earlier in the report, there is by nature a lag between eventual improvements in the dissemination capacity and  the translation  into  improved user satisfaction measurable  in  the user satisfaction survey. 

C.  EFFICIENCY 

D.  JUSTIFICATION OF OVERALL OUTCOME RATING 

Rating: Moderately Satisfactory 

§47 

Based on the PDO indicators selected it is difficult to assess the overall outcome of the project. 

Concerning the SCI, there may be delays or omissions by the country issuing the information, and/or on 

Page 50: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 44 of 51  

      

the part of the respective international organizations in updating their databases from which the Bank compiles the SCI. The 2018 SCI figures which should be published shortly should help clarify the situation. More generally and as mentioned earlier, an evaluation of statistical capacity based on the World Bank Statistical  Capacity  Indicator  should  be  conducted  with  full  recognition  of  its  limitations.  The  SCI  is considered useful as a broad indicator of statistical capacity. However, the SCI, with its preponderant use of  statistical  activities  and  outputs  as  its  component  indicators,  is  a  better measure  of  the  statistical performance than statistical capacity. Even in this case using pluri‐annual moving averages rather than single year figures would be more advisable. See “Note on the World Bank Statistical Capacity Indicator” for more details. 

Concerning  the  USS,  and  as  evoked  earlier  in  the  report,  there  is  by  nature  a  lag  between  eventual improvements  in  the  dissemination  capacity  and  the  translation  into  improved  user  satisfaction measurable in the user satisfaction survey. This limits the quality of the USS as PDO indicator. 

In light of the achievements against the IRI and despite the mixed results against the PDO indicators, it is considered that the project has permitted to make significant progress towards the achievement of the stated overall objective  to  improve  the capacity of  the Lao national  statistical  system  to produce and disseminate reliable and timely macroeconomic and poverty statistics in accordance with international standards and in response to user needs. Hence there may be a case for upgrading the project Rating from Moderately Satisfactory to Satisfactory. 

IV.   BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

A.  QUALITY OF MONITORING AND EVALUATION (M&E) 

M&E Design 

§56 

As  evoked  earlier  in  the  report,  there  is  by  nature  a  lag  between  eventual  improvements  in  the dissemination  capacity  and  the  translation  into  improved  user  satisfaction  measurable  in  the  user satisfaction survey. This limits the quality of the USS as PDO indicator. 

§57 

“this indicator source was not updated on a regular basis to reflect the progress made in the field” The (published) SCI being updated annually, it is unclear what is meant by this statement. We agree however that there may be delays or omissions by the country issuing the information, and/or on the part of the respective international organizations in updating their databases from which the Bank compiles the SCI. More generally and as mentioned earlier, an evaluation of statistical capacity based on the World Bank Statistical Capacity Indicator should be conducted with full recognition of its limitations. The SCI is considered useful as a broad indicator of statistical capacity. However, the SCI, with its preponderant use of statistical activities and outputs as its component indicators, is a better measure of the statistical performance than statistical capacity. Even in this case using pluri‐annual moving averages rather than single year figures would be more advisable. See “Note on the World Bank Statistical Capacity Indicator” for more details. 

Page 51: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 45 of 51  

      

§58 

“Nearly all intermediate outcome indicators were descriptive, but not quantitative. Likewise, the means of verification for these indicators were also descriptive and were not in any references of an independent assessment of the targets. Such weakness in the indicators left some quality gaps that the project should focus on to track the quality of progress and achievement in the intermediate and PDO results.” 

The team agrees with the statement but is simultaneously wondering whether anything could have been specified that would be more quantitative and at the same time meaningful and realistic of attainment.  

M&E Implementation 

§61 

The  delays  in  updating  the  second  PDO might  be  an  issue  but  it  is  doubtful  that  it  is  the  only  one surrounding the SCI. 

M&E Utilization 

§62 

 “the second PDO indicator was an indicator that LSB could keep tracks of its performance in the future because it relies on an open source that does not require much of an effort by LSB to undertake to obtain the  data  and  verification  for  the  source.  In  addition,  this  indicator measures  three main  dimensions: methodology, source data and periodicity and timeliness.”   

True, but the SCI is quite a blunt instrument, especially over a relatively short time period.  See the 2016 “Note  on  the  World  Bank  Statistical  Capacity  Indicator”  for  the  IEG  for  some  of  the  strengths  and limitations of the SCI. 

Justification of Overall Rating of Quality of M&E 

Rating: Modest 

§63 

“The overall statistical score was not reflected because of gaps in communication and time lags in the update of the score by international organizations.” 

Again, this is likely to be only part of the problem. 

B.  ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE 

C.  BANK PERFORMANCE 

Page 52: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 46 of 51  

      

Justification of Overall Rating of Bank Performance 

“The  overall  rating  of World  Bank  performance  is Moderately  Satisfactory,  because  of  the moderate shortcomings in supervision.” 

Having read paragraph 75 and 76, where no negative comments can be found, it can be considered surprising that this rating is not higher. Without evidence of the ‘moderate shortcomings in supervision’ to be provided in order to justify the rating given, a “Satisfactory” rating would be considered more appropriate. D.  RISK TO DEVELOPMENT OUTCOME 

§71 and §72 

The team agrees with the risks presented and much of them are reflected in the conclusions and recommendations of the CSTA report V.  LESSONS AND RECOMMENDATIONS 

§73 

 “During the appraisal, the detailed assessments of organizational and operational capacity was missing.” 

This was true to some extent at the design stage (the assessment was made  in the PAD, arguably not sufficiently), but this was compensated for (again to some extent) by the assessment activities at the start of each of the 3 substantive components.  However, they would no doubt have been more useful if they could have been conducted earlier in the LAOSTAT project as a whole. 

“However, because of the delays in procurement and in LSB new building’s construction, several outputs were  delivered  late  and  the  LSB  had  limited  absorptive  technical  capacity  to  translate  technical recommendations and action plans into results within the timeframe of the project.” 

More generally the team considers that the main factor explaining the delay in recruitment of the local procurement and financial management consultants (and the consequent initial delays in procurement) is the limited pool of fiduciary professionals in the Lao labor market. In addition, there was a mismatch between the budget available and the salary expectation of some of the suitably experienced and qualified consultants. 

§74 

 “Future  support  should  focus  on  making  organizational  and  operational  changes  for  the  national statistical system in order to have good quality of administrative sources in particular disaggregated data.” 

§75 

“Selection of project indicators must be carefully assessed with regard to data sources, frequency, and accessibility to ensure timely update of project targets” 

Page 53: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 47 of 51  

      

The  project M&E  framework  should  clearly  identify  project  expected  inputs,  outputs,  outcomes  and eventually impacts (the latter being more appropriate for programme rather than project support). 

“Using WB statistical capacity indicators (SCI) to assess capacity of national statistical systems was relevant to  track  improvement  in  key dimensions of  statistical  capacity  but  they have not been updated more frequently in the expected reporting time intervals. In this project, the SCI is used as one of three key PDO result indicators but updating the indicator was challenging because SCI has not updated frequently. The process of updating the SCIs has also been complex and time consuming” 

As noted earlier,  this  is  probably only  part  of  the problem and may need  to be  further  discussed. As mentioned  earlier,  an  evaluation  of  statistical  capacity  based  on  the World  Bank  Statistical  Capacity Indicator should be conducted with full  recognition of  its  limitations. The SCI  is considered useful as a broad indicator of statistical capacity. However, the SCI, with its preponderant use of statistical activities and outputs as its component indicators, is a better measure of the statistical performance than statistical capacity. Even in this case using pluri‐annual moving averages rather than single year figures would be more advisable. 

§76 

“Further support to the LSB is highly recommended.” ‐ It is even considered essential. 

“Further  support  to  LSB  to  translate  some  outputs  and  key  strategy  documents  into  results  is  highly recommended.”  ‐ The team fully agrees with this statement. 

In addition to the lesson learned already mentioned in the report, the team proposes to add the following one on the CSTA role: 

The Team noted  that  the burden on LSB management had been alleviated  through  the adoption of a twinning approach: The Bureau had to deal with only one implementing entity, relieving it of the necessity of recruiting and managing many individual consultants and of monitoring their interventions. In addition to  the  constant  presence  on‐site  of  the  project  team,  the  strengths  of  the  public‐private  partnership arrangement adopted included continuous backstopping support, access to a vast pool of highly qualified experts, the ability to finance their early mobilization and rapid deployment, the efficient coordination of Team  members’  work,  flexibility  in  meeting  changing  priorities,  and  the  potential  to  ensure  the sustainability of the project’s  impact. However, the implementation of the twinning approach requires timely availability of appropriate capacity for processing large procurement packages and availability of the client to work effectively with the technical team from the twinning arrangement. 

.     

Page 54: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 48 of 51  

      

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) 

 I. Lao PDR Policy and Strategy Documents 

(a) Law on Statistics issued on June 30, 2010, National Assembly. 

(b) Strategy for the Development of National Statistical System (SDNSS) 2010–2020, Lao PDR. Lao Statistics Bureau (LSB), Ministry of Investment and Planning (MPI). 

(c) Seventh National Socio‐Economic Development Plan (NSEDP) for 2011–2015, October 2011, the Government of Lao PDR. 

(d) Eighth National Socio‐Economic Development Plan (NSEDP) for 2016–2020. 

II. World Bank Group Engagement Strategy Documents 

(a) Lao People's Democratic Republic  ‐ Country Partnership Strategy  for  the Period FY12–FY16, Report # 66692, dated January 25, 2012, World Bank. 

(b) Country  Partnership  Framework  for  Lao  People's  Democratic  Republic  for  the  Period FY2017–2021, Report # 110813, dated March 2, 2017, the World Bank Group. 

III. Project and Financing Documents 

(a) Aide Mémoires for Project Implementation Support Missions, World Bank, 2013–2018. 

(b) Project Implementation Status and Results Reports (ISRs), World Bank, 2013–2018. 

(c) Project Appraisal Document, Report No.: 74377, 2013. 

(d) Statistics for Results Facility Catalytic Trust Fund Grant Agreement dated May 17, 2013. 

IV. Other documents 

(a) Consultants’ Deliverables financed under the LAOSTAT. 

(b) Progress reports of the LAOSTAT from 2014–2018. 

(c) Statistics for Results Facility Catalytic Fund: Annual Report 2017, dated May 2017. 

(d) Report of Lao PDR’s macroeconomic review in 2017 and its trend in 2018, March 2018, NIER. 

(e) Lao  People’s  Democratic  Republic:  Staff  Report  for  the  2002 Article  IV  Consultation  and Second Review under the Poverty Reduction and Growth Facility, and Request for Waiver of Performance Criteria, dated July 12, 2002, IMF. 

Page 55: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 49 of 51  

      

(f) Lao  People’s  Democratic  Republic:  IMF  Executive  Board  Concludes  2016  Article  IV Consultation with the Lao People's Democratic Republic, dated February 15, 2017, IMF. 

(g) Lao  People’s  Democratic  Republic:  IMF  Executive  Board  Concludes  2017  Article  IV Consultation with the Lao People's Democratic Republic, dated February 23, 2018, IMF. 

(h) Technical  Assistance  Report:  Updating  and  Constructing  the  Supply  and  Use  Tables  for Selected  Developing  Member  Countries,  Project  #  48387‐001  Regional—Capacity Development Technical Assistance (RCDTA), December 2014. 

End notes 

i The SRF‐CF provides statistical capacity‐building support to several developing countries (pilot countries), such as Afghanistan, the Democratic Republic of Congo (DRC), Ghana, Lao PDR, Nigeria, and Rwanda. 

ii SMAs include technical departments in the MPI, MOF, BOL, MOIC, and MEM. 

iii SNA 2008 is a statistical framework that provides a comprehensive, consistent, and flexible set of macroeconomic accounts for policy making, analysis, and research purposes. The SNA 2008 manual was jointly issued by the United Nations, the World Bank Group, IMF, Organisation for Economic Co‐operation and Development, and European Commission in 2009 Further details can be accessed at https://unstats.un.org/unsd/nationalaccount/docs/sna2008.pdf. 

iv SUT was first introduced for the GDP rebase to 1997 and 2002 at an aggregate level in line with the SNA 1993 Methodology or Manual. The 2012 SUT was initially supported by a technical assistance project of the ADB focusing on procedures, training and workshops on how to compile required data to populate the SUT. The Lao PDR Strengthening of the National Statistical System (LAOSTAT) was to fill the gaps and to assemble more datasets, including some new surveys for the 2012 SUT finalization. 

v The 2012 SUT was constructed with two digits of the International Standard Industrial Classification Revision 4 and includes 215 products of the LCPA. Finalization of the SUT for Lao PDR was challenging because of (a) poor quality of data collection from both surveys and administrative sources (for example, the LSB was not able to exploit information on business turnover from value added taxes and other taxes) and (b) methodologies, including questionnaires that were used for the annual enterprises survey and the AHS did not include details on the costs of production. 

vi The 2012 SUT framework has five parts: Part A on Production Accounts, Part B on Balance of Supply and Demand; Part C on An Intermediate Consumption Matrix; Part D on Make or Supply Matrix; and Part E on Further Details of GVA. The SUT framework if all datasets are compiled could incorporate all three approaches to measure GDP: Part A covers the Production Approach; Part B covers the Expenditure Approach; and Part E covers the Income Approach. 

vii RAS method is a well‐known method for data reconciliation. Its aim is to achieve consistency between the entries of some nonnegative matrix and pre‐specified row and column totals. The method was devised in a time when powerful computers were not available. It is very easy to apply and to understand. However, it has a narrow scope of applicability. It can only be applied to nonnegative matrices. Mathematically, the method is an iterative scaling method. 

                                                       

Page 56: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 50 of 51  

      

                                                                                                                                                                               

viii Each survey covered 402 enterprises in 17 provinces and was stratified across the following sectors: (a) agriculture, forestry, and fishing; (b) manufacturing; (c) mining and quarrying; (d) wholesale and retail trade; (e) construction; and (f) electricity supply. 

ix The MMFT was represented by the MPI (Department of Planning and LSB), MOF, BOL, MOIC, MEM, NUOL, the Ministry of Labor and Social Welfare (MOLSW), and NIER (which was then called the National Economic Research Institute under the MPI). 

x The components of a metadata management system include (a) setting up a metadata unit in the LSB in charge of metadata management and a working group represented by all statistical domains and cross‐cutting units; (b) creating a repository to handle statistical concepts, classifications, and code lists; and (c) defining a common data modelling system for statistical domains that facilitates statistical dissemination. 

 

Page 57: Document of The World Bankdocuments.worldbank.org/curated/en/... · ISR Implementation Status and Results Report IT Information Technology LAOSTAT Lao PDR’s Strengthening the National

 The World Bank   LAOSTAT‐STRENGTHENING THE NATIONAL STATISTICAL SYSTEM PROJECT (P129825) 

 

 

     Page 51 of 51  

      

                                                                                                                                                                               

 


Recommended