GAIL (INDIA) Limited
(A Government of India Undertaking- A Navratna Company) Petrochemical Complex, Pata,
Distt- Auraiya- 206 241, U.P. (India) Phone No. (05683) 282062, (05683) 283403-05 Extn- 30310
DOMESTIC COMPETITIVE BIDDING
FOR
PROCUREMENT OF STEAM VENT SILENCER FOR SIXTH FURNACE, GAIL PATA
BID DOCUMENT NO: 10059-41-MR-005
Volume 2 of 2 (Technical)
DUE DATE & TIME FOR
BID SUBMISSION : 25-05-2009 at 1500 HRS (IST)
DUE DATE & TIME FOR BID OPENING : 25-05-2009 at 1530 HRS (IST)
Page 1 of 1
J.O. NO.:
CLIENT: GAIL (INDIA) Ltd. REQUISITION NO.: 10059-41-MR-005
PROJECT: SIXTH FURNACE PROJECT REQUISITION TITLE: MECHANICAL DESIGN,SUPPLY,FABRICATION, INSPECTION AND TESTING OF STEAM VENT SILENCER
LOCATION: PATA ,DIST-AURAIYA,U.P., INIDA
REVISION
0 1 2 3 4 5 6
REV.DESC
ISSUED FOR INQUIRY
PREPARED BY/ DATE BGA/05-MAR-09
CHECKED BY/ DATE MSC/05-MAR-09
APPROVED BY /DATE SKS/05-MAR-09
10059
COVER SHEET
SCHEDULE OF REQUIREMENTS
Page 1 of 2 J.O. NO.:
CLIENT: GAIL (INDIA) Ltd. REQUISITION NO.: 10059-41-MR-005
PROJECT: SIXTH FURNACE PROJECT REQUISITION TITLE: MECHANICAL DESIGN,SUPPLY,FABRICATION, INSPECTION AND TESTING OF STEAM VENT SILENCER
LOCATION: PATA , DIST-AURAIYA,U.P,INDIA
REVISION
0 1 2 3 4 5 6
REV.DESC
ISSUED FOR INQUIRY
PREPARED BY/ DATE BGA/05-MAR-09
CHECKED BY/ DATE MSC/05-MAR-09
APPROVED BY /DATE SKS/05-MAR-09
10059
SCHEDULE OF REQUIREMENTS SI
No. Brief Description Specifications Quantity Delivery Requirement
1.
Design, Manufacture, Testing and Supply of Steam Vent Silence (SP-8605)
See applicable specifications, standards, drawings and datasheet paragraph of this MR
1 No.
2. Documentation See Schedule of Required Vendor Data
16 Weeks from the date of FOI (On FOT Dispatch Point Basis)
Spec. No.: 10059-PS-F06-001-Rev.B Page 2 of 3
1.0 SCOPE
This specification calls for the design, fabrication, painting, shop/site testing and supply of one number vent silencer as per this specification and data sheet.
2.0 TECHNICAL REQUIREMENTS
2.1 All the pressure parts of the silencer shall be designed as per ASME Section VIII; Div.I.All welding shall be as per ASME Section IX. Latest editions of codes existing as on Feb01, 2009 will be applicable.
2.2 Materials used for the silencer shall be as per the requirements in the data sheet /MR.
For absorptive silencer all acoustic insulation (internal) shall be constructed with mineral wool and shall be strengthened with a wire mesh. The insulation shall be protected with SS perforated sheet (1.6mm thick min) in entire path of fluid stream. When the insulation length is more, it shall be supported with the circular steel rings, against collapsing of the insulation due to its own weight. Vent silencer shall be provided with rain hoods (detachable) and a bird screen, at the outlet. In case of external hot insulation, required for the service the silencer shall be supplied with suitable cleats, for insulation fixing at site. All internal insulation tubes, if any, shall be properly supported. Design of silencer shall allow for easy replacement of internal insulation, during maintenance. The silencer is mounted vertically with proper support-brackets (4nos.min).
2.3 Silencer shall have drain connection, with 1” inch globe valve as per valve material specification attached with MR.
2.4 All welding on the silencer shall be full penetration welds.
3 INSPECTION AND TESTING
3.1 All welds of pressure parts shall be fully radiographed as per code. Material shall be inspected & punch-marked prior to fabrication.
3.2 The Silencer shall be tested for a period of 20 minutes for performance evaluation under minimum operation conditions at vendors work. If facilities for testing do not exist at works, performance test of silencer shall be carried out at site in the presence of vendor’s representative and vendor’s offer shall be deemed to include the same. Any defects/defective parts shall be rectified/replaced by vendor free of cost to the purchaser.
Equipment shall be deemed to be accepted by purchaser only after successful performance testing as per conditions in the data sheet.
3.3 The silencer shall be submitted for inspection to purchaser or his authorized representative by the vendor prior to dispatch.
B
B
1Q.100A (1195) PAGE 1 OF 1
J.O. NO.: 10059
Inspection Attributes List ITEM NUMBER: SP-8605
CLIENT: GAIL (INDIA) Ltd. L.O.C NO.:
PROJECT SIXTH FURNACE P.O. CHANGE NO.:
SELLER/LOCATION: SUPPLEMENT NO.:
SUBCONTRACTOR/LO SHOP ORDER NO.:
SUBORDER NO.: DESCRIPTION: STEAM VENT SILENCER SUBCONTRACTOR SHOP NO.:
REFERENCE DRAWING(S): None
SWRL SPECIFICATION As Listed in 10059-41-MR-005
Initial Report In-Process Report Shipping Report Final Report
INSP.STATUS
NO.
INSPECTION ATTRIBUTES LIST PRIOR VISIT
THIS VISIT
*V *W *P
1. Vendor’s QA/QC Program and procedures – Covering various activities like design and Engineering, Material Procurement, Manufacture, Inspection & Testing, Documentation, Dispatch to site, Erection & Commissioning and Maintenance of quality records.
X
2. Inspection and test plan X
3 Drawing Schedule X
4 Progress Report and Manufacture Schedule X
5 Waiver & Deviation X
6 Procurement of bought-out materials X
7 Verify materials supplied comply with data sheets and approved drawings X
8 Review Material Test Reports prior to and during fabrication X
9 Calibration Records X
10 Inspection Test Status X
11 Quality Records X
12 Identification and Traceability X
13 Vendor Drawing for SWRL review / Information / Record X X
14 Visual Inspection X
15 Documentation review prior to inspection release X
16 Shipping release-SWRL X X
*V (VERIFIED) - CONFIRMED THAT A FUNCTION OR REQUIREMENT IS TRUE BY EVIDENCE *W (WITNESSED) - PERSONAL OBSERVATION WHILE MANUFACTURER PERFORMS TASK *P (PERFORMED) - PERSONAL PERFORMANCE OF THE TASK
INSPECTION STATUS CODES: (S) SATISFACTORY (ACCEPT) (U) UNSATISFACTORY (NCR) NONCONFORMANCE
(NA) NOT APPLICABLE (RW) REWORKED AND SATISFACTORY (N) NO ACTIVITY PERFORMED ON THIS VISIT
REVIEWED BY: PREPARED BY:
Inspection Coordinator Requisitioning Engineer
OFFICE: REPORTED BY DATE:
SIGNED IF FINAL
REQ ENGINEER BGA
REV. NO. & DATE [0] 05-MAR-09 [1] [2] [3] [4]
DESCRIPTION ISSUED FOR INQUIRY
5B.200.1B(0996)W PAGE 1 OF 1
J.O. NO.:
CLIENT: GAIL (INDIA) Ltd. REQUISITION NO.: 10059-41-MR-005
PROJECT: SIXTH FURNACE SCHEDULE OF REQUIRED VENDOR DATA FOR:
STEAM VENT SILENCER (SP-8605) LOCATION: PATA, DIST-AURAIYA, U.P., INDIA
THIS SCHEDULE DESCRIBES THE TYPE AND NUMBER OF PRINTS TO BE FURNISHED TO SWRL UPON THE AWARD OF A PURCHASE ORDER. THE DRAWINGS, DOCUMENTS, ETC. LISTED HEREIN FORM AN INTEGRAL PART OF THE VENDOR'S COMMITMENT TO THAT PURCHASE ORDER. ALL DATA SHEETS SHALL BE IDENTIFIED WITH THE SWRL JOB ORDER NUMBER, PROJECT DESCRIPTION, PURCHASE ORDER NUMBER, REQUISITION NUMBER, EQUIPMENT NUMBER DESCRIPTION AND CLIENT NAME. REVISION BOXES SHALL BE PROVIDED TO DESCRIBE DRAWING REVISIONS IN DETAIL. INDICATIONS OF DIMENSIONS, FORCES AND WEIGHTS SHALL BE LISTED IN THE METRIC UNITS. MAIL DATA TO: M/S.GAIL (INDIA) Limited (A Government of India Undertaking- A Navratna Company) Petrochemical Complex, Pata, Distt- Auraiya- 206 241, U.P. (India) Attn: Mr. M.V. Ravi Someshwarudu. (GM-GCU) Phone No. (05683) 282062, (05683) 283403-05 Extn- 30310 Mobile :91- 9412284214 E-mail : [email protected]
MAIL DATA TO: M/S Shaw Rolta Limited Rolta Tower – C, Rolta Technology Park, MIDC-Marol, Andheri (East). Mumbai: 400 093. India. Attn: Mr. S.K Somashekar (Sr.Project Manager) Tel: 022- 3087-8174 Mobile: 91-9323966629 [email protected]
DATA
ENG FAB
HOLD
AS-BUILT
CERTIF REQD
COPIES FOR
REVIEW
FINAL COPIES
DESCRIPTION QTY WKS ARO QTY WKS
ARO GA AND CROSS SECTION DRAWING WITH DIMENSIONS AND MATERIAL LIST OF EQUIPMENT
X X 3 2 6 BS
MECHANICAL DESIGN CALCULATION X X 3 2 6 BS EQUIPMENT DATA SHEET DULY FILLED IN THE FORMAT ATTACHED WITH THE MR, TO BE SUBMITTED WITH BID AS WELL.
X 3 2 6 BS
FABRICATION DRAWINGS X 3 2 6 BS ACCOUSTIC CALCULATION, ESTIMATED PERFORMANCE DATE X 3 2 6 BS
MATERIAL TEST CERTIFICATE 3 4 6 BS INSTRUCTIONS: 1. ALL FINAL COPIES OF DRAWINGS / DATA MARKED "AS-BUILT CERTIFICATION REQUIRED" SHALL BE STAMPED "CERTIFIED”
BY THE VENDOR ON A CLEAN COPY OF THE “NO COMMENTS" DRAWING AND RETURNED TO SWRL. 2. ARO = AFTER RECEIPT OF ORDER BY THE VENDOR. 3. BS=BEFORE SHIPMENT. 4. ALL FINAL DOCUMENTS (AS BUILT) TO BE SUBMITTED IN THE FORM OF 3 CD’S AS WELL.
10059
Page1 of 3
J.O. NO.:
CLIENT: GAIL ( INDIA) LTD. DOCUMENT NO.: 10059-TQ-41-005
PROJECT: SIXTH FURNACE PROJECT REQUISITION TITLE: MECHANICAL DESIGN,SUPPLY,FABRICATION, INSPECTION AND TESTING OF STEAM VENT SILENCER
LOCATION: PATA, DIST. AURAIYA, U.P., INDIA
REVISION
0 1 2 3 4 5 6
REV.DESC
ISSUED FOR INQUIRY
PREPARED BY/ DATE BGA/05-MAR-09
CHECKED BY/ DATE MSC/05-MAR-09
APPROVED BY /DATE SKS/05-MAR-09
10059
TECHNICAL QUESTIONAIRE AND DEVIATION SCHEDULE
Page 2 of 3
J.O. NO.:
CLIENT: GAIL ( INDIA) LTD. DOCUMENT NO.: 10059-TQ-41-005
PROJECT: SIXTH FURNACE
PROJECT REQUISITION TITLE:
MECHANICAL DESIGN,SUPPLY,FABRICATION, INSPECTION AND TESTING OF STEAM VENT SILENCER
LOCATION: PATA, DIST. AURAIYA, U.P., INDIA
REVISION
0 1 2 3 4 5 6
REV.DESC
ISSUED FOR INQUIRY
PREPARED BY/ DATE BGA/05-MAR-09
CHECKED BY/ DATE MSC/05-MAR-09
APPROVED BY /DATE SKS/05-MAR-09
10059
TECHNICAL QUESTIONNAIRE (NOTE: BIDDER TO SUBMIT PARAWISE REPLY/CONFIRMATION FOR THIS TQ IN THIS FORMAT ONLY, WITHOUT THESE CONFIRMATIONS, OFFER SHALL NOT BE CONSIDERED COMPLETE)
Sr. No.
QUERY BIDDER’S REPLY
1. (a) Confirm all the documents listed in the REQUISITION are received and all these have been considered while quoting.
(b) Confirm the requirements of the REQUISITION have been fully understood and clarifications where necessary have been discussed & obtained.
2. (a) Confirm the offer is in line with the REQUISITION and no deviation has been taken.
(b) In case of any deviation, confirm that the same has been included in Bid under “DEVIATION SCHEDULE” attached herewith.
(c) Bidder to note that the deviations given under “DEVIATION SCHEDULE” only will be considered for evaluation. Any deviation appearing elsewhere in the offer will not be considered. Confirm compliance.
3. Bidder to note that his scope covers all the items covered in the requisition and are required to complete the job as per drawings, standards & specifications enclosed with the requisition. Confirm compliance.
BIDDER’S NAME BIDDER SIGNATURE WITH STAMP/SEAL DATE
Page 3 of 3
J.O. NO.:
CLIENT: GAIL ( INDIA) LTD. DOCUMENT NO.: 10059-TQ-41-005
PROJECT: SIXTH FURNACE
PROJECT REQUISITION TITLE:
MECHANICAL DESIGN,SUPPLY,FABRICATION, INSPECTION AND TESTING OF STEAM VENT SILENCER
LOCATION: PATA, DIST. AURAIYA, U.P., INDIA
REVISION
0 1 2 3 4 5 6
REV.DESC
ISSUED FOR INQUIRY
PREPARED BY/ DATE BGA/05-MAR-09
CHECKED BY/ DATE MSC/05-MAR-09
APPROVED BY /DATE SKS/05-MAR-09
10059
Deviation Schedule Bid No : Bid Invitation No. : Job : Bidder’s Name :
Sl. Clause no. as per Bid docuemnt
Brief Description of the clause
Description of Deviation taken from bidder
Remarks