Donor Conference
Ministry of Energy of Georgia
Current situation
• Technical problems– Power sector of Georgia – not build to operate
independently
• Economic problems• Collection rate
– Not metered– High Indebt ness– Not rehabilitated properly for 10 years
• Financial aid needed for transition period and basic rehabilitation
Objectives• Self-Sustainability – profitability
– Independently operational – Without additional subsidies from donors and / or
government– Attractive for private investment
• Energy Security– Utilization of transit opportunities– Multiple sources for import – Differentiated markets for export
• Otherwise politically and economically dependent• No prospect for economic development• Social tension
Policy• Collection rate
– Main problem– 40% collection rate– Investment in metering– Legislation against theft of electricity– Public awareness campaign
• Rehabilitation and construction of new grid and high voltage lines– Turkey, Azerbaijan, Russia, Armenia
• Rehabilitation of Existing Hydropower Plants– 40-45 % of installed capacity– Spend less on imports
500KW
Energy System of GeorgiaEnergy System of Georgia
Ministry of Energy
Enguri HPP 1300MW – 700MW
Vardnili HPP 210MW – 60MW
Hydro Power Plants of GeorgiaHydro Power Plants of Georgia
Khrami I HPP 112MW – 60MW
Khrami II HPP 110MW – 0MW
Jinvali HPP 130MW – 90MW
Shaori HPP 38MW – 18MW
Dzevrula HPP 80MW – 54MW
Vartsikhe Cascade HPP 184MW – 132MW
Ministry of Energy
Gumati I,II HPP 66MW – 39MWRioni HPP 48MW – 45MW
Lajanuri HPP 111MW – 30MW
Planned: Hudon HPP 600MW
Current achievementsWithout additional investments
• Decreasing of electricity looses in high voltage grid – 17% in Winter of 2003 – 9.6% in Winter of 2004
• Relatively improved supply of electricity – up by 16% • Installation of meters at borders with neighbor countries• State budget investment - 2,5 mln USD per month
– Enguri HPP rehabilitation project co-financing– Wholesale & commercial metering– Urgent maintenance
• Rehabilitation of the 1st unit of Vardnili HPP (70 MW)• Detailed business plan for 2004-2005• Improved legislation for financial rehabilitation
Projects• Metering
– Improved collections– Decreased consumption– Rustavi example
• Rehabilitation of HPP – 40 - 50% of installed capacity– “Quick Hit” program
• Rehabilitation of Gardabani TPP – Electricity for base load– Problem – Funds for natural gas supply
• Rehabilitation of the network – Increased system stability
• Winter Heat Program– Improved supply and help vulnerable