+ All Categories
Home > Documents > Doreen Gray

Doreen Gray

Date post: 19-Jul-2016
Category:
Upload: uday-gokhale
View: 23 times
Download: 0 times
Share this document with a friend
Description:
cata
26
The Implementation of Effective Key Performance Indicators to Manage Major Hazard Risks Euan Fenelon Global Operational Integrity and RD&I Manager Doreen Gray Operational Integrity Project Manager 18 June 2013
Transcript

The Implementation of Effective Key

Performance Indicators to Manage

Major Hazard Risks

Euan Fenelon – Global Operational Integrity and RD&I Manager

Doreen Gray – Operational Integrity Project Manager

18 June 2013

Safety Contact August 2009 Sayano-Shushenskaya Hydro Plant, Russia – turbine top cover failed, resulting flood killed 76 workers. Investigation found lack of maintenance, flawed plant modifications and a culture of risk taking.

The Drivers Events that drive Operational Integrity

BP Texas City Deep Water Horizon Piper Alpha

Kleen Energy Duhva Sayano-Shushenskaya

Longannet Castellon Arcos

Worldw

ide

Energ

y S

ecto

r Ib

erd

rola

Process Safety Visibility

Which warning

signs are most likely

to help you avoid an

incident?

Immediate Visibility

Competency Checks

Incident Reporting

Management of Change

Technical Risk Management

Operating and Engineering Standards

Technical Recommendations

Maintenance management

Shift Handover Process

Plant Limiting Conditions

Audit Support

Supporting Documentation

The Baker Report – investigation into BP Texas City

UK Health and Safety Executive:

HSE HSG254 “Developing Process Safety Indicators”

HSE RR509 “Plant Ageing Report”

GENSIP formed – Generators Safety Integrity Programme

PAS-55 – publicly accessible standard for Asset Management

Energy Institute’s “High Level Framework for Process Safety Management”

OECD guidance on Safety Performance Indicators

COMAH Guide

API’s guidance on PSPIs

Process Safety and Asset Management now a major focus…

Generator Safety Integrity Partnership:

Hazard Identification

Ran

kin

g

Refe

ren

ce

Fre

qu

en

cy

Co

nseq

uen

ce

Pro

bab

ilit

y

Pro

du

ct

Hazard

1 PS17.   3 10 0.1 0.1 Failure of HP feed system pipework

2 PS 2     3 10 0.1 0.1 Major Loss of Containment from a High Temperature Pipework

3 PS5.       3 10 0.1 0.1 Pipe rupture and catastrophic weld failure from a major low temperature steam line

4 PS7.       4 1 0.1 0.1 Explosive External Boiler Tube Rupture

5 EWG5 3 1 1 0.1 Switchgear arc flash explosion whilst locally operated

6 CSW3 3 1 1 0.1 Walkways and Gratings

7 PS3.       3 3 0.1 0.03Rupture of boiler integral furnace circulating and saturated steam pipework, fabricated in C steel

materials with an internal diameter > 65mm

8 PS10.   2 10 0.1 0.01 Catastrophic failure of boiler feedwater pipework.

9 PS8.       2 10 0.1 0.01 De-Aerator Vessel Rupture

10 PS4.       4 1 0.01 0.01 Rupture of boiler drains pipework systems including blowdown systems.

11 PS25.   4 1 0.01 0.01 Auxiliary Steam and minor systems

12PS11.

PFS2  4 1 0.01 0.01 Combustion generated over pressurisation of enclosures and pipework

13 EWG6 2 1 1 0.01 Electrocution due to contact with live conductors

14 CSW11 5 1 0.001 0.01 Falling claddings and objects from buildings

15 CSW12 2 1 1 0.01 Integrity of buildings fabric to personnel access.

16 CSW17 5 1 0.001 0.01 Spalling of concrete from structures

Understanding hazards & creating barriers (People, Process & Plant)...

James Reason’s “Swiss Cheese” Model

To stop events

from happening

Controls

To reduce the

consequence

from events

Training

PMP

Maintenance

Mitigations

Insurance

Fire Deluge

System

100% Standby

Bunding

Communication

People Threats:

Operating Plant

outside design limits

Profit & Loss:

Cost to fix

failure

H & S:

Fire

Operations:

Loss of pump

Environment:

Oil loss through

pump Failure

Stakeholder:

Negative

publicity from

failure

HAZARD:

Kinetic

Energy

Steam, Fire, Potential &

Kinetic Energy,

Electricity, Noise, Heat,

Chemicals, Vehicles

Process Threats:

Ad hoc Changes to

plant

Plant Threats:

High Vibration on Failure Event:

Catastrophic

pump failure

Event that will

release Hazard

to the work

environment

Threats that will

lead to plant

Failures

Consequences

as a result of

Failure Event

Process Safety Dashboard

Philosophy is to visualise Swiss Cheese Model......

Understanding hazards & creating barriers (People, Process & Plant )...

Risk Control Areas

2

Technical Risk

Management

Plant Modification Procedure

Plant Status Review / Technical Risk Register

Strategic Spares

Engineering Standards

Technical Knowledge Management

Design Review

Asset Investment

Civil Inspections

Pressure System Safety Regulations

3

Critical Systems

Emergency Supplies

Fire Systems

HV Electrical Systems

Main Protection Systems

Oil Separation Systems

4

Alarm and Instrument

Management

Control Systems

Critical Instrumentation

Protective Systems / Devices

Alarm Systems

5

Maintenance Management

Work Prioritisation

Work Identification, Routine Plant Inspections

Work Planning, Scheduling

Work Execution

Personal Risk Assessment

6

Operations Management

Start-up /Shutdown Procedures

Routine Plant Checks

Routine Testing

Shift Handover

Company Safety Rules Management

Plant Limiting Conditions

7

Staff Competence

Communications

Leadership

Training Needs Analysis

Training Plan

Competency Assurance

Staff Knowledge Management

8

Emergency Preparedness

Emergency Planning

Business Continuity Planning

Environmental Containment

Systems

Plant Process People Recovery

1 Operation & Compliance Audit

External Audit Integrated Internal Audit Action Tracking Controlled Documents (Policies, Procedures,

Standards)

Key Performance Indicators

Fully defined KPI,

including:

Objective

Definition

Data Source

Data Aggregation /

Calculation

Targets

Data Recording

Guidelines

Formal sign off by

senior managers

KPI Categorisation

Best Practice

Performance

Performing

At Or Above

Requirement Performing

Below

Requirement

Performing

Significantly

Below

Requirement

No

Process Safety

Incidents

Minor

Process Safety

Incident Significant

Process Safety

Incident

Major Process

Safety Incident

Leading Indicators

Lagging Indicators

Classification Of Process Safety Incidents

3 tier approach based on API guidance... (Lagging Indicators)

Major

Significant

Minor

3 tier approach based on API guidance...

+100 Leading

Indicators

42 Risk Control Systems

3 Classifications Of

Lagging Indicators

+90

Hazards

Feed

Incident

Reporting

Process

Ran

kin

g

Refe

ren

ce

Fre

qu

en

cy

Co

nseq

uen

ce

Pro

bab

ilit

y

Pro

du

ct

Hazard

1 PS17.   3 10 0.1 0.1 Failure of HP feed system pipework

2 PS 2     3 10 0.1 0.1 Major Loss of Containment from a High Temperature Pipework

3 PS5.       3 10 0.1 0.1 Pipe rupture and catastrophic weld failure from a major low temperature steam line

4 PS7.       4 1 0.1 0.1 Explosive External Boiler Tube Rupture

5 EWG5 3 1 1 0.1 Switchgear arc flash explosion whilst locally operated

6 CSW3 3 1 1 0.1 Walkways and Gratings

7 PS3.       3 3 0.1 0.03Rupture of boiler integral furnace circulating and saturated steam pipework, fabricated in C steel

materials with an internal diameter > 65mm

8 PS10.   2 10 0.1 0.01 Catastrophic failure of boiler feedwater pipework.

9 PS8.       2 10 0.1 0.01 De-Aerator Vessel Rupture

10 PS4.       4 1 0.01 0.01 Rupture of boiler drains pipework systems including blowdown systems.

11 PS25.   4 1 0.01 0.01 Auxiliary Steam and minor systems

12PS11.

PFS2  4 1 0.01 0.01 Combustion generated over pressurisation of enclosures and pipework

13 EWG6 2 1 1 0.01 Electrocution due to contact with live conductors

14 CSW11 5 1 0.001 0.01 Falling claddings and objects from buildings

15 CSW12 2 1 1 0.01 Integrity of buildings fabric to personnel access.

16 CSW17 5 1 0.001 0.01 Spalling of concrete from structures

Understanding hazards & creating barriers (People, Process & Plant )...

Applying the KPIs

Further Guidance Not All Indicators are of Equal Importance...

Operational Control Indicators

Lagging Indicators

• Active Monitoring and Logging:

• Breaches Of Plant Limiting Conditions (eg overpressure, overspeed, overtemp)

• Control Loops Out Of Control

• Equipment In Manual

• Operation of protection systems

• Failure of protection systems

Leading Indicators

• Inspection and Maintenance of Control Systems and Critical Systems

• Alarm Management

• Control Loop Performance

• Completion Of Operational Routine Checks / Testing

• Shift Logging & Handover

• Plant Overrides and Defeat of interlock

• Safety Critical Systems not available

Generic

Lagging Indicators

• Incident Reporting and Investigation:

• Near Misses (eg demand on safety system)

• Loss Of Containment (eg release of high pressure steam)

• Process Safety Incident (eg major equipment damage)

Leading Indicators

• Critical processes undertaken correctly

• Operations

• Maintenance

• Engineering

Programme Indicators

Leading Indicators

• Statutory Inspections Completed (eg PSSR)

• Audits To Programme

• Action Closure

• Training and Competence

• Procedures Up To Date

• Improvement programmes

High Low

Predictive of Incident

KPI Development

Based on Key Concepts in HSG 254...

Measuring the Gaps

Overall Site Matrix

Measuring the Gaps

Risk Control Area status

Measuring the Gaps

Monthly Reports for Governance

Future development: Controls linked to Hazard:

Review Level

Scottish Power

Generation

Generation Groups

Power Stations

Governance Body

Health and Safety Steering Group

Generation Risk Review Meeting

Coal RRM

LN

Gas RRM

RH , DC, SH, BB, COGEN

Hydro RRM

CN, GW, LK

Review Guidance

Consolidated Indicators

Major or Key Incidents

Business Wide Indicators

Significant Incidents

Trends

Group Indicators

Significant & Moderate Incidents

Close-out rates

Local Indicators

All Incidents

Frequency

Monthly

Monthly

Monthly

Daily

Group Governance Process Cascade up approach...

21

Generation Risk Review Meeting GRRM

Leading Indicators

Performance

(KPI Dashboard)

Incident Reviews

(Cintellate)

Risks

Action Tracking

Operational Governance

Process Visibility

Immediate Visibility

Quality

Plant Limiting Conditions

Incident Reporting

Management of Change

Technical Risk Management

Operating and Engineering Standards

Technical Recommendations

Maintenance management

Staff Competency

Operations Management

Shift Handover Process

Near real-time measurement of business processess ...

What if PS risks were as visible as Health & Safety risks?

Measuring Process Safety

Immediate Visibility

Competency Checks

Incident Reporting

Management of Change

Technical Risk Management

Operating and Engineering Standards

Technical Recommendations

Maintenance management

Shift Handover Process

Plant Limiting Conditions

Audit Support

Near-time visibility of leading indicators for key risk control systems across all power stations – providing ‘at a glance’” assessment of plant condition and the performance of key processes;

Risk Ranking of KPIs based on risk and Alarp principles

Improved reporting of incidents and near misses, enabling information to be shared more widely and repeat incidents to be prevented;

Provision of timely, accurate and comprehensive information to support the governance of process safety through early identification and proactive management of risks;

A governance framework to ensure that performance and actions are reviewed on a monthly basis.

Delivering Operational Capability

Successful Outcome Criteria

Key success factors

• Buy in and commitment from senior management

• Involvement of staff in designing, developing and embedding

• Clear definition of each KPI is essential

• Common processes across all business units

• Delivery of sustainable solution can only be achieved using integrated IT platforms – i.e. automatic generation of KPIs


Recommended