DEPARTMENT EPARTMENT OF OF H HUMAN UMAN S SERVICES ERVICES Project Manager Checklist Project Manager Checklist Title From: To: Date First Created: Date Last Updated: Author: DHS-OIS-NDS Page 1 of 28 /home/website/convert/temp/convert_html/545692b1af79590d0d8b5658/document.doc Created on:8/26/2022 Last Modified on: 5/23/2006 08:58:00 PM
Transcript
Page 1: Download It.doc

DDEPARTMENTEPARTMENT OFOF H HUMANUMAN S SERVICESERVICES

Project Manager ChecklistProject Manager Checklist

Title

From: To: Date First Created:Date Last Updated:

Author: DHS-OIS-PMO Page 1 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 2: Download It.doc

Project Control Document

Initiation Process: Recognizing that a project or phase should begin and committing to do so. Initiating Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Business Case (Contact P&P)

      Yes No

Yes No

Yes No

Information Security Office (DHS-ISO)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

System Architecture (OIS-SA)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Network & Computer Service -Computer Services (OIS-NCS-Computer Services)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Network &

 <Is there input to the Business Case?>     Yes No

Yes No

Author: DHS-OIS-NDS Page 2 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 3: Download It.doc

Project Control Document

Initiation Process: Recognizing that a project or phase should begin and committing to do so. Initiating Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Computer Service -Network Services (OIS-NCS-Network Services)

Yes No

Customer Service & Support (OIS-CSS)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Information Resource Request (IRR)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Budgeting  <Is there input to the Business Case?>     Yes No

Yes No

Yes No

Strategic System Initiatives

 <Is there input to the Business Case?>     Yes No

Yes No

Author: DHS-OIS-NDS Page 3 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 4: Download It.doc

Project Control Document

Initiation Process: Recognizing that a project or phase should begin and committing to do so. Initiating Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

(OIS-SSI)

Yes No

Application Maintenance & Support (OIS-AMS)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Project Management Office (OIS-PMO)

 <Is there input to the Business Case?>    

Yes No

Yes No

Yes No

Advanced Planning Document (APD) Preconditions and Planning (PAPD) see APD Process

     

Yes No

Yes No

Yes No

DHS-ISO  <Is there input to the APD?>     Yes No

Yes No

Author: DHS-OIS-NDS Page 4 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 5: Download It.doc

Project Control Document

Initiation Process: Recognizing that a project or phase should begin and committing to do so. Initiating Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

OIS-SA  <Is there input to the APD?>     Yes No

Yes No

Yes No

OIS-NCS-Computer Services

 <Is there input to the APD?>    Yes No

Yes No

Yes No

OIS-NCS-Network Services

 <Is there input to the APD?>    Yes No

Yes No

Yes No

OIS-CSS  <Is there input to the APD?>     Yes No

Yes No

Yes No

IRR  <Is there input to the APD?>     Yes No

Yes No

Yes No

Budgeting  <Is there input to the APD?>     Yes No

Yes No

Yes No

OIS-SSI  <Is there input to the APD?>     Yes No

Yes No

Yes No

OIS-AMS  <Is there input to the APD?>     Yes No

Yes No

Yes No

OIS-PMO  <Is there input to the APD?>     Yes No

Yes No

Author: DHS-OIS-NDS Page 5 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 6: Download It.doc

Project Control Document

Initiation Process: Recognizing that a project or phase should begin and committing to do so. Initiating Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Business and Technical Complexity Assessment

     

Yes No

Yes No

Yes No

Project Charter       Yes No

Yes No

Yes No

OIS-SA Group Notified

      Yes No

Yes No

Yes No

Initiation Tools & Techniques

      Yes No

Yes No

Author: DHS-OIS-NDS Page 6 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 7: Download It.doc

Project Control Document

Planning Process: Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address. Planning Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

DHS-ISO Assessment A

      Yes No

Yes No

Yes No

Assessment B – for and from DHS-ISO – Perform this assessment as soon as the technical solution is recommended. DHS-ISO needs to be at the table with OIS-SA, OIS-NCS-Computer Services, OIS-NCS-Network Services and other project planners.

     

Yes No

Yes No

Yes No

Integrated Project       Yes No

Yes No

Author: DHS-OIS-NDS Page 7 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 8: Download It.doc

Project Control Document

Planning Process: Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address. Planning Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Plan (with its Core Work Plans and Facilitating Controls)

Yes No

OIS-SA Output/ Recommendation(s)

     Yes No

Yes No

Yes No

OIS-NCS-Computer Services Output/ Recommendation(s)

     

Yes No

Yes No

Yes No

OIS-NCS-Network Services Output/ Recommendation(s)

     

Yes No

Yes No

Yes No

OIS-CSS Plan & Agreement

      Yes No

Yes No

Yes No

OIS-NCS-Computer

      Yes No

Yes No

Author: DHS-OIS-NDS Page 8 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 9: Download It.doc

Project Control Document

Planning Process: Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address. Planning Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Services Plan & Agreement

Yes No

OIS-NCS-Network Services Plan & Agreement

     Yes No

Yes No

Yes No

OIS-AMS Maintenance, Operations Plan & Agreement

     

Yes No

Yes No

Yes No

OIS-BPE and Performance Measures

     Yes No

Yes No

Yes No

Training Plan – add to the IPP (might be part of OIS-CSS agreement)

     

Yes No

Yes No

Yes No

Requirements Management Plan

      Yes No

Yes No

Yes Contract &       Yes

Author: DHS-OIS-NDS Page 9 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 10: Download It.doc

Project Control Document

Planning Process: Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address. Planning Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

No

Procurement Management Plan – add to the IPP (includes completing Contract Pre-conditions process steps, vendor knowledge transfer plan, etc)

No

Yes No

<List life cycle model(s) selected>

 <Explain why this SDLC was selected>    Yes No

Yes No

Author: DHS-OIS-NDS Page 10 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 11: Download It.doc

Project Control Document

Executing Process: Coordinating people and other resources to carry out the plan. Executing Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Implementation APD (IAPD)

      Yes No

Yes No

Yes No

System Development Life Cycle (SDLC) Documents

     

Yes No

Yes No

Yes No

DHS-ISO  <Is there input to the SDLC?>     Yes No

Yes No

Yes No

DHS-SA  <Is there input to the SDLC?>     Yes No

Yes No

Yes No

OIS-AMS  <Is there input to the SDLC?>     Yes No

Yes No

Yes No

OIS-NCS-Computer Services

 <Is there input to the SDLC?>    Yes No

Yes No

Yes No

OIS-NCS-Network Services

 <Is there input to the SDLC?>    Yes No

Yes No

Author: DHS-OIS-NDS Page 11 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 12: Download It.doc

Project Control Document

Executing Process: Coordinating people and other resources to carry out the plan. Executing Tools & Techniques

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

OIS-CSS  <Is there input to the SDLC?>     Yes No

Yes No

Author: DHS-OIS-NDS Page 12 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 13: Download It.doc

Project Control Document

Controlling Process: To ensure the project objectives are met by monitoring and measuring progress and when necessary, taking corrective action.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Change Management Log

      Yes No

Yes No

Yes No

Change Management Request

     Yes No

Yes No

Yes No

Communication Plan Log

      Yes No

Yes No

Yes No

Contract Process Form

      Yes No

Yes No

Yes No

Contract Procurement Planning Tracking Spreadsheet

     

Yes No

Yes No

Yes No

Decision Request       Yes No

Yes No

Yes No

Generic Quality Standards

      Yes No

Yes No

Author: DHS-OIS-NDS Page 13 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 14: Download It.doc

Project Control Document

Controlling Process: To ensure the project objectives are met by monitoring and measuring progress and when necessary, taking corrective action.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Issue Definition       Yes No

Yes No

Yes No

Issue Management Log

      Yes No

Yes No

Yes No

Meeting Agenda and Minutes

      Yes No

Yes No

Yes No

QA Status Improvements Report

     Yes No

Yes No

Yes No

Risk Management Log

      Yes No

Yes No

Yes No

Status Report Presentation Template

     Yes No

Yes No

Yes No

Status Report Template

      Yes No

Yes No

Yes No

Training Plan Log       Yes No

Yes No

Author: DHS-OIS-NDS Page 14 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 15: Download It.doc

Project Control Document

Controlling Process: To ensure the project objectives are met by monitoring and measuring progress and when necessary, taking corrective action.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

DHS-ISO  <Is there input to the Training Plan?>     Yes No

Yes No

Yes No

OIS-AMS  <Is there input to the Training Plan?>     Yes No

Yes No

Yes No

OIS-NCS-Computer Services

 <Is there input to the Training Plan?>     Yes No

Yes No

Yes No

OIS-NCS-Network Services

 <Is there input to the Training Plan?>     Yes No

Yes No

Yes No

OIS-CSS  <Is there input to the Training Plan?>     Yes No

Yes No

Yes No

Funding Partner Updates:

      Yes No

Yes No

Yes No

APD       Yes No

Yes No

Yes No

Grants       Yes No

Yes No

Yes No

General Funding

      Yes No

Yes No

Author: DHS-OIS-NDS Page 15 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 16: Download It.doc

Project Control Document

Controlling Process: To ensure the project objectives are met by monitoring and measuring progress and when necessary, taking corrective action.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Budget Reporting       Yes No

Yes No

Author: DHS-OIS-NDS Page 16 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 17: Download It.doc

Project Control Document

Closing Process: The purpose of this section is to formalize the acceptance of the project or phase and bring it to an orderly end.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Administrative Closure

      Yes No

Yes No

Yes No

Budget Close-out

      Yes No

Yes No

Yes No

Turn over to OIS-NCS-Computer Services

     

Yes No

Yes No

Yes No

Turn over to OIS-NCS- Network Services

     

Yes No

Yes No

Yes No

Turn over to OIS-AMS

      Yes No

Yes No

Yes No

APD Close-out       Yes No

Yes No

Author: DHS-OIS-NDS Page 17 of 18/tt/file_convert/545692b1af79590d0d8b5658/document.docCreated on: 4/8/2023 Last Modified on: 5/24/2006 03:58:00 AM

Page 18: Download It.doc

Project Control Document

Closing Process: The purpose of this section is to formalize the acceptance of the project or phase and bring it to an orderly end.

New Project Manager Transition Checklist

Required Deliverable Name If no deliverable, why?Deliverable Available?

Deliverable Current?

Yes No

Contract Close-out       Yes No

Yes No

Yes No

Lessons Learned       Yes No

Yes No

Yes No

Project Evaluation       Yes No

Yes No

Project Sponsor Signature: ______________________________ Date: ___________________

Project Manager Signature: ______________________________ Date: ___________________