PRINCE2TM 2009: An Overview o Backgroundo Overview:• Basics• Principles• Themes• Processes• Tailoring• Exams
o Summaryo Question Session
v7
Background
o Evolution of 2005 to 2009 edition
o Reflects:
― Changes in Best Practice
― Alignment with MSP, MoR, P3O
o 2005 remains valid until 31 Dec 09
v7v7
PRINCE defines a project as:
“… a temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case.”
v7
The Basics
v7
Characteristics of a PRINCE2 Project:
• Change• Temporary• Cross-functional• Unique• Uncertainty
v7v7
The Basics
v7
Project Management
Plan
Delegate
Monitor
Control Delegate
Monitor
Control
Plan
v7v7v7
The Basics
Plan
v7
The 6 Project Objectives
Timescale
s
v7v7v7
The Basics
CostsQu
ality
ScopeBenefit
sRi
sks
interrelatedTolerances
v7
The Project Environment
PRINCE2 PROCESSES
PRINCE2 THEMES
PRINCE2 PRINCIPLES
Progress Business CaseOrganisation
QualityRisks
Change
Plans
© Crown Copyright 2009. Reproduced under Licence from OGC.v7
The Basics
v7
Principles
• Universal• Self-validating • Empowering
v7
Principles
• Continued business justification• Learn from experience• Defined roles and responsibilities• Manage by stages• Manage by exception• Focus on products• Tailor to suit the project environment
v7
Themes
“…aspects of project management that must be
addressed continually.”
v7
v7
© Crown Copyright 2009. Reproduced under Licence from OGC.v7
PRINCE2 PROCESSES
PRINCE2 THEMES
PRINCE2 PRINCIPLES
Progress Business CaseOrganisation
QualityChange
PlansRisks
Progress Business Case
Organisation
QualityPlansRisks
Change
v7
o Generico Shows how the Themes are used
at each point in the projecto Aligned to management levelso Processes – Activities – Actionso Always consider “How to tailor”
v7
Process ModelCorporate or Programme Management
Directing – Project Board
Managing – Project Manager
Delivering - Team Manager Pr
ojec
t Man
agem
ent T
eam
v7
Final deliverystage
Processes
Controlling a Stage
Managing Product Delivery
Controlling a Stage
ManagingProduct Delivery
Directing a Project
SB CPSB
IP
SUDirecting
Managing
Delivering
Pre-project Initiationstage
Subsequentdelivery stage(s)
v7
v7
Processes
Controlling a Stage
Managing Product Delivery
Controlling a Stage
ManagingProduct Delivery
SB SB
Initiationstage
IP
Directing
Managing
Delivering
Pre-project
Subsequentdelivery stage(s)
Final deliverystage
CorporateProject
Authorisation
Notification
CP
Authorisation to
Initiate a ProjectSU
Project Mandate
Stage Authorisati
on
Stage Authorisati
on
Outline Business Case, Project Brief,
Organisation Structure
Directing a Project
Project Board:“Should we agree toauthorise the next
Stageor stop the project
here?”
Do we have a Project?
Define the project
environment - PID
Stage Plan 2
Canwe authorise the project & Stage Plan 2?
The heart ofday-to-day
projectmanagemen
tProject Manager
gives Team Manager authority to deliver a Work
Package Work PackageAccepted &
work executed
Work PackageCompleted & handed back
to Project Manager
Next Stage Plan
Authority to deliver a
Work Package
Completed Work
Package
Customer Acceptance
follow-on actions, &
Project evaluation
Board reportscompletion to
Corporate Mgt
v7
v7
PRINCE2 – what it is not
v7
PROJECT MANAGEMENTo Detailed Techniqueso Specialist Aspectso Leadership Capabilities
v7
Tailoring PRINCE2
“..the appropriate use of PRINCE2 on any given project…
General ApproachProgramme Environment
ScaleCommercial environment
Multi-organizationalProject type
SectorsBodies of Knowledge
v7
v7v7
Examinations
o Practitioner
o Foundation
o Re-Registration
v7v7
Global Knowledge Courses
PractitionerFoundation
Re-Registration
MSPMoRPMPITIL
MicrosoftCiscoVM Ware
PRINCE2TM Consultancy
Upgrade
Summary
v7
o Basicso Principleso Themeso Processeso Tailoringo Exams