+ All Categories
Home > Documents > Dppm v6 Without Redline

Dppm v6 Without Redline

Date post: 03-Apr-2018
Category:
Upload: kumar-amit
View: 225 times
Download: 0 times
Share this document with a friend

of 23

Transcript
  • 7/29/2019 Dppm v6 Without Redline

    1/23

    WECC Data Preparation

    ManualFor Power Flow Base Cases and

    Dynamic Stability Data

    July 2009

    REV. 6

  • 7/29/2019 Dppm v6 Without Redline

    2/23

    I. INTRODUCTION.................................................................................................................................................................................................................1

  • 7/29/2019 Dppm v6 Without Redline

    3/23

  • 7/29/2019 Dppm v6 Without Redline

    4/23

    Reporting Procedures

    FAC-009-1: Establish and Communicate Facility Ratings

    III. Data Requirements and Reporting Procedures

    A. Data Requirements

    The WECC staff, in concert with the System Review Work Group (SRWG) of the

    Technical Studies Subcommittee (TSS), and other entities as appropriate, is

    responsible for maintaining the appropriate DPM and managing the collection of thesteady-state and dynamic system modeling data required to comply with applicable

    NERC Standards and Measurements. The data are collected periodically over a

    calendar-year and solved base cases are maintained in a data base library which isavailable to all WECC members and currently located at

    http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/BaseCases/Pages/default.aspx..

    The current base case compilation schedule is made available to WECC members inthe PCC Handbook under Section VI, TSS Activities. Section VI of the PCC

    Handbook is available on the WECC web site athttp://www.wecc.biz/committees/StandingCommittees/PCC/TSS/SRWG/Shared

    %20Documents/Forms/AllItems.aspx, under Data Compilation Schedules.

    Facility owners are responsible for submitting the pertinent data on their solely- or

    jointly-owned Facilities in a timely manner and in accordance with the current year

    WECC Annual Study Program schedule, and the WECC Generating Unit ModelValidation Policy. Facility owners are required to comply with the following data

    collection requirements and guidelines related to the accurate modeling of generation,transmission and load in WECC base cases.

    WECC maintains a Master Dynamics File (MDF) for use in all stability simulations.The MDF contains model data for all dynamic devices in the WECC system Facility

    http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/SRWG/Shared%20Documents/Forms/AllItems.aspxhttp://www.wecc.biz/committees/StandingCommittees/PCC/TSS/SRWG/Shared%20Documents/Forms/AllItems.aspxhttp://www.wecc.biz/committees/StandingCommittees/PCC/TSS/SRWG/Shared%20Documents/Forms/AllItems.aspxhttp://www.wecc.biz/committees/StandingCommittees/PCC/TSS/SRWG/Shared%20Documents/Forms/AllItems.aspx
  • 7/29/2019 Dppm v6 Without Redline

    5/23

    B. Reporting Procedures

    1. Steady State Data

    WECC base cases are compiled relative to a base case compilation schedule that

    is prepared each year and included in Section VI of the PCC Handbook (link isincluded in Section A above).

    On the appropriate date, a data request letter will be prepared; specifying the next

    case that is to be compiled. This letter will be distributed via email to the

    Technical Studies Subcommittee (TSS) and the System Review Work Group(SRWG). The data request letter outlines desired system conditions, such as year

    and season being modeled, load and generation levels, and path flow levels (if

    requested). Steady state data, along with corresponding dynamics data, isrequested for the base case and must meet data submittal due dates from the base

    case compilation schedule.

    Facility owners are responsible to test and validate steady state power flow data

    for any of their solely- or jointly-owned facilities to be modeled in power flowcases. Facility owners shall provide test and validation reports and steady state

    power flow data to its Transmission Planner. Transmission Owners,Transmission Planners, Generator Owners and Resource Planners are responsible

    to submit the steady state data to Area Coordinators without delay. AreaCoordinators are responsible to compile the initial power flow base case and

    balance the in-area loads and resources and coordinate area interchange with

    neighboring areas. Area Coordinators are also responsible to submit the initialsolved power flow base case with any updated and/or new dynamics data received

    to WECC Staff on schedule. Data submittals are required in either GE PSLF epc

    or sav file format in the version of the GE PSLF program currently accepted forproduction use. Data submittals shall be submitted to the WECC staff via email

    to [email protected].

  • 7/29/2019 Dppm v6 Without Redline

    6/23

    Facility owners are responsible to test and validate dynamics data for any of their

    solely- or jointly owned dynamic equipment to be modeled in power flow cases.

    Facility owners shall provide test and validation reports to its TransmissionPlanner. Transmission Planner shall collect facility data and model data validation

    reports from facility owners. Transmission Planner shall verify that the WECC-

    approved model parameters provided by the facility owners are adequatelyvalidated by reviewing the test and validation reports; but Transmission Planner

    shall not be responsible for any failure by facility owner to adequately validate

    any WECC-approved model parameters provided by facility owner to theTransmission Planner. Transmission Planners shall submit to the WECC Staff

    any dynamics data received from the facility owner for any new dynamicequipment to be modeled in power flow cases.

    Dynamics data updates are also submitted via the WECC generator testingprogram. For the roles and responsibilities of the Generator Owner, the

    Transmission Planner, and WECC, see the WECC Generating Unit Model

    Validation Policy under 2006 Generator Test Policy in:http://www.wecc.biz/library/WECC%20Documents/Forms/AllItems.aspx?RootFolder=%2flibrary%2fWECC%20Documents%2fDocuments%20for%20Generators%2fGenerator%20Testing

    %20Program&FolderCTID=&View=

    %7bAF8E6257%2d3EB9%2d4A21%2d8853%2d6477737956B4%7d.

    The most recent version of the MDF is available in the current year, and the GE

    PSLF library at the following link:

    http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/BaseCases/Pages/default.aspx

    IV. Steady State Power Flow Data Requirements

    In order to provide consistency in data submittals and help avoid potential solutionproblems WECC members shall follow the guidelines below to the maximum extent

    http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/BaseCases/Pages/default.aspx%20http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/BaseCases/Pages/default.aspx%20
  • 7/29/2019 Dppm v6 Without Redline

    7/23

    5. DC Bus numbering should be coordinated with WECC Staff prior to model

    submission.

    B. Zones and facility owner numbers should be provided for each bus. All zone and

    owner numbers used must be entered in the zone and owner tables. Generation

    1. Generating Units (including synchronous condensers, pumped storage, etc.) shall

    include: connection point, minimum and maximum Ratings (net Real andReactive Power), regulated bus and voltage set point, and equipment status.

    2. Load netting of generation in power flow data should be minimized. If the

    aggregate sum of generation on a bus exceeds 10 MVA it should not be netted.The total netted generation in an area should not exceed 5% of the areas totalgeneration.

    3. Data entered for the power flow Pmax should accurately reflect the capability of

    the unit, but under no circumstances should it be greater than the maximum

    capability of the turbine, as represented by Pmax parameter in the dynamicturbine-governor model.Exceptions may be allowed for de-rated generators.

    4. Generators with single unit Capacity of 10MVA or higher or facilities withaggregate capacity of 20MVA and larger and which are connected to the

    transmission system by generator step-up transformer(s) to 60 kV or highervoltage shall be modeled individually with their respective step-up

    transformers.

    Collector based systems such as wind & solar farms connected to the transmission

    system may be aggregated through 1) an equivalent generator, 2) a low voltage to

    intermediate voltage transformer, 3) an equivalent collector circuit, and 4) thesubstation transformer between the collector and the transmission bus of 60kV or

    a higher voltage. Reactive devices should be represented at the appropriatevoltage buses. Owners of any other generators determined by WECC, and the

  • 7/29/2019 Dppm v6 Without Redline

    8/23

    C. Transmission Lines

    1. AC Transmission Line or Circuit (overhead and underground)

    requirements shall include: nominal voltage, impedance, line charging, Normaland Emergency Ratings (consistent with methodologies defined and Ratings

    supplied per the current Reliability Standard FAC-008-0 and FAC-009-0)

    equipment status, and metering locations.

    2. DC Transmission Line (overhead and underground) requirements shallinclude at a minimum: line parameters, Normal and Emergency Ratings, control

    parameters, rectifier data, and inverter data.

    3. Transmission facilities represented should be consistent with current

    facility owners plans and should represent the system under normal conditionsunless otherwise stated in the case description sheet.

    4. Equivalent transmission system representations are discouraged.

    However, any equivalency should yield almost identical performance in both

    static and dynamic results compared to full representation. All equivalentbranches must have a circuit id of eq or 99. Line ratings should be provided

    for any equivalent circuits. If no rating is available, then 9999 should be used.5. All transmission lines 115-kV and above should be modeled explicitly

    except for very low impedance lines (see Item 10), the modeling of which hascaused numerical problems in running the power flow program. Significant

    looped transmission less than 115-kV should also be modeled.

    6. Transmission paths identified in the "Path Rating Catalog" should be

    modeled in sufficient detail, such that users can calculate the flow on the path.

    The power flow case should also accurately represent conditions that are used todetermine path ratings.

    7. Facilities out of service for voltage control should be noted. Also,

  • 7/29/2019 Dppm v6 Without Redline

    9/23

    11. The appropriate ratings of all facilities are required to determine if study

    results meet the requirements of WECC disturbance-performance table and

    NERC Standard TPL-001-0 Table 1 (Transmission System Standards Normaland Emergency Conditions). This includes but is not limited to system elements

    such as transmission lines, series capacitors, and transformers. The rating of a

    system facility (e.g., transmission line, transformer, etc.) shall not exceed therating of the most limiting series element in the facility, including terminal

    connections and associated equipment. In cases where protection systems and

    control setting constitute a loading limit on a facility, this limit shall become therating for that facility. (See NERC Standards FAC-008-1, R1.1)

    D. Transformers

    1. Transformer (voltage and phase-shifting) requirements shall include: nominal

    voltages of windings, impedance, tap ratios (voltage and/or phase angle or tap

    step size), regulated bus and voltage set point, Normal and Emergency Ratings

    (consistent with methodologies defined and Ratings supplied per ReliabilityStandard FAC-008-0 and FAC-009-0.), and equipment status.

    2. Transformers for which partial or no Tap Changing Under Load (TCUL) data hasbeen provided should not be modeled as TCUL transformers. The GE PSLF

    program accepts partial TCUL data as input, but treats the transformer as a fixedtap transformer during solution. Problems may occur when the data records for

    these transformers with partial data are converted to PTI.

    3. For TCUL transformers, the step size reported should be small enough or the

    voltage bandwidth large enough that the adjustment of a TCUL does not result in

    the voltage at the controlled bus moving completely through the reportedbandwidth, thus causing solution problems at the bus.

    4. For TCUL transformers, the maximum tap reported should be greater than the

    minimum tap and the maximum step reported should be greater than the minimum

  • 7/29/2019 Dppm v6 Without Redline

    10/23

    4. Loads of differing ownership, but at the same bus, can be represented

    by separate load records with unique IDs. However, all loads at the same bus

    must be specified as being in the same area as the bus.5. Generator station service load should be modeled explicitly and given

    an id of SS to make it distinguishable from other loads.

    F. Fixed Reactive Elements

    1. Reactive Compensation (shunt and series capacitors and reactors)

    requirements shall include: nominal Ratings, impedance, connection point, and

    controller device.2. All existing fixed shunt elements should be modeled explicitly. If theshunt is not in service, then the status should be set to zero. This allows members

    who may be unfamiliar with the number and amount of shunt devices in an area to

    make voltage adjustments in that area if the need arises.

    3. Fixed shunt elements that are directly connected to abus should be represented as bus shunts.

    4. Fixed shunt elements that directly connect to and switch

    with a branch should be represented as line shunts.

    G. Switched Reactive Devices

    1. Reactive Compensation (shunt and series capacitors and reactors)

    requirements shall include: nominal Ratings, impedance, connection point, andcontroller device.

    2. Switched shunt elements should be modeled explicitly. All availableswitchable elements should be listed on the data record.

    3. When listing switchable elements in the data record, reactors should be

  • 7/29/2019 Dppm v6 Without Redline

    11/23

    1. Interchange Schedules shall include existing and future Interchange Schedules

    and/or assumptions.

    2. All transactions between areas must be coordinated between areas.

    3. Whenever reported interchanges between areas differ by more than 10 MW, theArea Coordinator for each area will be contacted. The Area Coordinators must

    work out the discrepancy and report their solution to the WECC staff. For

    reported interchanges between areas that differ by 10 MW or less, SRWG agreedthat the WECC staff may modify one or both of the interchange schedules so that

    they agree.

    4. The sum of net area interchanges for all areas must net to 0.

    5. The total area interchange tolerance for an area should be 1.0.

    6. Interchange schedules should reflect the objectives of the case. In particular, they

    must include potential economy transfers and not be limited to contractual oranticipated commitments. Target levels specified refer to either actual or

    scheduled flows.

    J. Master Tie Line File

    1. The Master Tie Line file is maintained by the WECC staff.

    2. The Master Tie Line file is used in the compilation of all WECC base cases.

    3. Efforts should be made to include in-service and out-of-service dates to all tie

    lines so that the proper status of the tie line is easily determined.

    4. Only tie line changes approved by the Area Coordinators from both areas

    connected by the tie line will be made to the file.

    5. Area numbers representing a member area should not be changed.

    In addition to tie line information the Master Tie Line file contains area number zone

  • 7/29/2019 Dppm v6 Without Redline

    12/23

    .A General Dynamic Modeling

    Unit-specific dynamics data shall be reported for generators and synchronous

    condensers (including, as appropriate to the model, items such as inertia constant,damping coefficient, saturation parameters, and direct and quadrature axes reactance

    and time constants), excitation systems, voltage regulators, turbine-governor systems,

    power system stabilizers, and other associated generation equipment.

    Estimated or typical manufacturers dynamics data, based on units of similar designand characteristics, may be submitted when unit-specific dynamics data cannot be

    obtained. In no case shall other than unit-specific data be reported for generator units

    installed after 1990

    Approved dynamics models (including renewable generation) as recommended by theWECC MVWG to be used to represent dynamic equipment to be modeled in power

    flow cases are provided in the Approved Dynamic Model Library document

    (http://www.wecc.biz/library/default.aspx?RootFolder=%2flibrary%2fWECC%20Documents%2fDocuments%20for%20Generators%2fGenerator%20Testing

    %20Program&FolderCTID=&View=%7b8D18396E%2d7F8B%2d4472%2dAB30%2d18D2A9576FF0%7d), and conform to the WECC Dynamic

    Modeling Procedure(http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/MVWG/Shared

    %20Documents/WECC%20Dynamic%20Modeling%20Procedure.pdf). and conform

    to the WECC Dynamic Modeling Procedure. Requests for new models that are not inthe Approved Dynamic Model Library list shall follow the WECC Dynamic

    Modeling Procedure.

    Where there is a difference between the requirements of this document and the

    WECC Generating Unit Model Validation Policy, the WECC Generating Unit ModelValidation Policy shall preside.

  • 7/29/2019 Dppm v6 Without Redline

    13/23

    6 PSS data should be submitted for all generators that have PSS and suitable

    excitations systems, as defined in the report Criteria to Determine Excitation Systems

    Suitability for PSS dated December 1992. The complete WECC Policy Statement on PowerSystem Stabilizers is available in the PCC Handbook on the WECC web site athttp://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/WECC_PSS-%20Policy-

    Statement.pdf. Periodic testing and/or model validation of generating units in accordance to WECC Policies and Standards is required to facilitate the best

    representation possible. See WECC Generating Unit Model Validation Policy.

    .C Loads

    1. Dynamics data representing electrical Demand characteristics as a function of

    frequency and voltage shall be included.2. Dynamics data shall be consistent with the reported steady-state (power flow)

    data supplied.

    3. Explicit modeling representing voltage and frequency characteristics is

    encouraged for each individual load; however, default zone or area records can be

    utilized for buses not explicitly defined.

    4. In addition to individual load modeling information provided for each load, a

    default area load representation record should be provided for each area. Thiswill cover any new load that may have been added to the powerflow without

    explicit load modeling information provided for the Master Dynamics File(MDF). This is to avoid the load representation defaulting to constant power (GE

    program default).

    5. If actual dynamic load characteristics are not available, load should be modeled as

    constant current P, and constant impedance Q.

    6. Default 20% induction motor models are created for every in-service load in the

    power flow greater than 5 MW at load buses and 80 MW at generator buses. If a

    different representation is desired for any load(s), it must be submitted to the

    ff f i l i i h i il ( )

  • 7/29/2019 Dppm v6 Without Redline

    14/23

    2. The pick-up and delay setting for each stage must be coordinated with the

    previous stage.

    3. Pertinent load data must be in the Master Dynamics File (MDF).

    .F DC Lines, SVC, and DVAR systems

    1. Device specific dynamics data shall be reported for dynamic devices, including,among others, static VAR controllers, high voltage direct current systems, flexible

    AC transmission systems, and static compensators.

    2. To the maximum extent possible, DC lines and SVC systems should be modeled

    to accurately reflect actual system performance.3. DC Bus numbering should be coordinated with WECC Staff prior to model

    submission.

    VI. Facility Rating Requirements

    Facility owners are responsible for submitting the applicable rating data to WECC Staff and

    Area Coordinators. Seasonal variations in ratings shall be included as appropriate. Theratings shall be developed using the facility owners current facility ratings methodology that

    was documented to meet NERC Reliability Standards FAC-008-1.

    Complete facility rating data shall be provided on time, in accordance with the current year

    WECC Annual Study Program schedule.

    A. WECC Requirements

    1. The appropriate ratings of all facilities are required to determine if study results meet

    the requirements of the WECC disturbance-performance table and NERC Reliability StandardsTPL-001-0 Table 1 (Steady State Performance)... This includes but is not limited to system

    elements such as transmission lines, series capacitors, and transformers.

  • 7/29/2019 Dppm v6 Without Redline

    15/23

    3. The rating of a system facility (e.g. transmission line, transformer, etc.) shall notexceed the rating of the most limiting series element in the circuit or path of the

    facility, including terminal connections and associated equipment. (See NERC

    Standards FAC-008-1, R1.1).

    4. In cases where protection systems and control settings constitute a loading limit on afacility, this limit shall become the rating for that facility.

    5. Ratings of jointly-owned facilities shall be coordinated and provided on a consistent

    basis.

  • 7/29/2019 Dppm v6 Without Redline

    16/23

    Appendix I

    LATE DATA PROCEDURE

    The objective of the Late Data Procedure is to preserve the original schedule for the development

    of base cases in accordance with each year's Data Bank Compilation Schedule and the CaseDescription sheet in the data request letter for each case. The Late Data Procedure describes

    Area Coordinator and Staff data submittal responsibilities and actions to be taken for actual

    delays or anticipated delays in the submittal of data or for the submittal of unusable data 1. ThisProcedure does not take effect until a data submittal date has been missed or, if prior to the

    submittal date, there is sufficient reason to believe that a submittal date will be missed, or it isdetermined that the submitted data is not usable data.

    Success of the case development program depends on timely and accurate data submittal, review

    and support of the development of each base case. An Area Coordinator or Member System not

    meeting a scheduled response date listed in the Data Bank Compilation Schedule section of theHandbook with a usable response could result in a delay in the case development schedule if left

    uncorrected. An example of unusable data is data from two neighboring Area Coordinators

    whose inter-area schedules do not match. Another example of unusable data is data with suchsignificant problems that it can not be used for the comment phase development process which,

    therefore, delays the progress of the case development. Any unusable data received by the Area

    Coordinator or the Staff must be corrected by the responsible party so as to not further impair theschedule or it will be rectified in accordance with this Late Data Procedure as will any late data

    or anticipated late data.

    Area Coordinator and Staff Responsibilities

    It is the responsibility of each and every "data owner" to submit timely and accurate data in

    accordance with the Data Bank Compilation Schedule and the Case Description sheet in the data

  • 7/29/2019 Dppm v6 Without Redline

    17/23

    original schedule is maintained or not further impaired.

    At the time the Area Coordinator takes over data submittal responsibility for the MemberSystem, the Area Coordinator will immediately notify the Staff. The Staff will then notify the

    WECC Member Representative of the Member System with copies to the PCC and TSS

    representatives of the Member System of the action taken. Copies shall also be sent to all AreaCoordinators and Sub-Coordinators directly involved. A letter shall also be sent to the PCC,

    TSS and SRWG Chairs as well as all of TSS and SRWG with copies to the Operating Committee

    (OC) and the Operating Transfer Capability Policy Group Study Group (OTCPGSG) when thecase involved is an operating case for OTC studies. The notification will consist of the nature

    and extent of the action taken and the reasons for it. The Staff will take the same notificationaction if they themselves must exercise their late data responsibility in the interest of an Area

    Coordinator.

    Those who consistently abuse the base case development process by submitting late or unusable

    data may be significantly compromising the reliability of the WECC transmission system whichmay eventually become a NERC compliance issue.

    Back-Fitting of Late Data

    The Late Data Procedure allows for an Area Coordinator or the Staff to take over data submittal

    responsibilities for a delinquent entity in the event that entity is unable to submit usable data inaccordance with the defined schedule. If the delinquent entity's data should subsequently

    become available, the data shall be submitted to the appropriate Area Coordinator or to the Staff

    to partially or fully replace that which was previously submitted. The Staff may, however, refuse

    to accept this back-fit data if, in their judgment, the back-fit data is no better than the dataalready in the case or if there would be unacceptable impairment of the schedule by accepting the

    back-fit data.

  • 7/29/2019 Dppm v6 Without Redline

    18/23

    Appendix II

    AREA, ZONE, AND BUS NUMBER ASSIGNMENTS

    Southwest Region

    Area Number Range: 10-18

    Zone Number Range: 100-199

    Bus Number Range: 10000-19999Member System

    Area No. Zone Range Area Name Member System Bus Range10 100-109 New Mexico PNM 10000-10999

    120-139 TSGT 12000-12999LAC 13000-13999

    NAPI, TNP

    11 110-119 El Paso EPE 11000-11999

    14 140-179 Arizona APS 14000-1499984000-85999

    SRP,APA 15000-15999

    TEP 16000-16999AEPC,Others 17000-17999

    190-199 WALC 19000-19999

    18 180-189 Nevada NEVP 18000-18999

    Southern California Region

  • 7/29/2019 Dppm v6 Without Redline

    19/23

    26 260-299 LADWP LDWP 26000-26999

    BURB,GLEN 27000-27999Others 28000-28999

    Northern California Region

    Area Number Range: 30-39

    Zone Number Range: 300-399

    Bus Number Range: 30000-39999

    Member SystemArea No. Zone Range Area Name Member System Bus Range

    30 300-399 PG and E PG&E 30000-36999SMUD 37000-37499

    WAPA SNR 37500-37899

    REDDING 37900-37999NCPA 38000-38199

    MID 38200-38399

    TID 38400-38599CDWR 38600-38899

    Others 38900-39999

    Northwest Region

    Area Number Range: 40-49Zone Number Range: 400-499

    Bus Number Range: 40000-49999

  • 7/29/2019 Dppm v6 Without Redline

    20/23

    AVA 48000-49999

    Canadian Region

    Area Number Range: 50-59

    Zone Number Range: 500-599

    Bus Number Range: 50000-59999

    Member SystemArea No. Zone Range Area Name Member System Bus Range

    50 500-519 B.C.Hydro BCHA 50000-51999

    52 520-539 Fortis BC FBC 52000-53999

    54 540-599 Alberta ESBI 54000-59999

    Central Region

    Area Number Range: 60-69Zone Number Range: 600-699

    Bus Number Range: 60000-69999

    Member SystemArea No. Zone Range Area Name Member System Bus Range

    60 600-619 Idaho IPC 60000-60999

    BPA,Others 61000-61999

  • 7/29/2019 Dppm v6 Without Redline

    21/23

    70 700-729 PSColorado PSC 70000-70999

    WPE 71000-71999

    Eastern Region (cont.)

    Area Number Range: 70-79

    Zone Number Range: 700-799Bus Number Range: 70000-79999

    Member SystemArea No. Zone Range Area Name Member System Bus Range

    TSGT 72000-72999

    73 730-799 WAPA R.M. WALM 73000-73999BHPL 74000-74999

    PRPA 75000-75999

    BEPC 76000-76999WAUC 79000-79999

  • 7/29/2019 Dppm v6 Without Redline

    22/23

  • 7/29/2019 Dppm v6 Without Redline

    23/23

    II-2


Recommended