+ All Categories
Home > Documents > DRAFT& -...

DRAFT& -...

Date post: 06-Feb-2018
Category:
Upload: ngophuc
View: 222 times
Download: 0 times
Share this document with a friend
23
FACILITIES MASTER PLAN PHASE I IMPLEMENTATION Monthly Report – September 2017 DRAFT
Transcript
Page 1: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

FACILITIES  MASTER  PLAN  PHASE  I  IMPLEMENTATION  Monthly  Report  –  September  2017  

DRAFT  

Page 2: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

         

                         

Project  Phase   #  of  Projects   Overall  Budget   Committed  Budget   %  Committed    In  Design   1    $                                              13,360,701     $                                                        813,965     6%  Land  Acquisition   1    $                                                  1,900,000      $                                                1,160,039     61%  

Under  Construction   3    $                                              43,451,821      $                                            41,226,833     95%  

Not  Started   1    $                                              10,359,621      $                                                                  7,950     0.1%  

Completed  Projects   7   $                                                    8,844,476       $                                                8,454,537   96%  

General  Expenses   0   $                                                    4,437,798    $                                                3,934,069   89%  

Additional  Revenue   0   $                                                            831,939    $                                                                                  0   0%  

TOTAL   13   $                                          83,186,356   $                                          55,597,393   67%  

Westside  Community  Schools  Facilities  Master  Plan  Bond  Phase  I  Status  of  Projects  by  Phase  –  September  2017  

IN  DESIGN  1

Land  Aquisition1

Under  Construction

3

Not  Started1

Completed  Projects  7

Status  of    Projects  by  PhaseIn  Design

$13,360,701  

Land  Acquisition$1,900,000  

Construction$43,451,821  

Not  Started$10,359,621  

District  Wide,  $4,437,798  

Additional  Revenue$831,939  

Completed  Projects$8,844,476  

Program  Budget  by  Current  Phase

Page 3: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

                                 

       

 

Overall  Program  Budget  Categories   Overall  Budget   Committed  Cost   %  Committed  Construction     $                                                                              64,433,094    $                                                                      44,585,141   69%  Soft  Cost/FFE     $                                                                                  7,928,287    $                                                                            4,988,042     63%  Land  Acquisition     $                                                                                  1,900.000    $                                                                            1,160,039   61%  

Contingency     $                                                                                  3,655,238    $                                                                                  930,103     25%  

General  Expenses   $                                                                                    4,437,798   $                                                                              3,934,069   89%  

Additional  Revenue   $                                                                                            831,939   $                                                                                                              0   0%  

TOTAL   $                                                                            83,186,356    $                                                                  55,597,393     67%  

Westside  Community  Schools  Facilities  Master  Plan  Bond  Phase  I  Status  of  Overall  Program  Budget  –  September  2017  

Contruction$64,433,094

Soft  Cost/FFE$7,928,287

Contingency$3,655,238

Land  Aquisition$1,900,000 District  Wide

$4,437,798

Overall  Budget  

Construction  $44,585,141

SoftCost/FFE  $4,988,042

Contingency$930,103

Land  Aquisition$1,160,039

General  Expenses$3,934,069

Remaining  Budget$24,302,607

Committed  Cost

Page 4: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

                 

   

   

OVERALL  BOND   BUDGET  PROJECTED  

COST  COMMITTED  

COST  PAID  TO  DATE  

High  Priority  Projects   $          5,035,976   $          4,669,770   $      4,669,770   $    4,632,961  

Oakdale  Elementary   $      14,273,871   $    14,273,871   $  13,526,677   $    8,665,427  Prairie  Lane  Elementary   $      10,359,621   $    10,359,621   $                        7,950   $                      1,650    

Sunset  Hills  Elementary   $      13,012,823   $    13,012,823   $  12,047,259   $    2,346,097  

Swanson  Elementary   $      13,360,701   $    13,360,701   $              813,965   $            171,080    

Swing  School   $          3,808,500   $          3,808,500   $      3,784,760   $    3,742,691  Westside  Middle  

School   $      16,165,127   $    16,165,127   $  15,652,897   $12,878,834  

General  Expenses   $          4,437,798   $          4,437,798   $      3,934,069   $    2,203,434  

Additional  Revenue   $                  843,115   $                                            0   $                                        0   $                                      0  

Land  Acquisition   $          1,900,000   $          1,900,000   $      1,160,039   $    1,160,039  

PROJECT  TOTAL   $      83,186,356   $    81,988,218   $  55,597,393   $35,802,213  

OVERALL  BOND  PROGRAM  

Summary:  The  BOE  commissioned  an  assessment  of  district  facilities  in  May  2013.  This  assessment  was  completed  and  presented  to  the  BOE  in  May  2014.  The  district  created  a  community  Task  Force  in  June  2014  to  evaluate  the  assessment  and  create  a  15-­‐year  phased  Facilities  Master  Plan.  In  May  2015,  the  Westside  Community  approved  a  $79.9  million  bond  issue  with  a  65%  majority  vote.      In  July  2015,  Project  Advocates  was  hired  by  the  District  to  provide  program  management  services  for  the  implementation  of  Phase  I  of  the  Facilities  Master  Plan.  The  value  of  the  work  associated  with  Phase  I  is  $79.9  million,  with  the  work  being  completed  from  FY  2015  through  FY  2021.  The  funds  from  Phase  I  will  be  used  to  address  immediate  needs  at  Hillside  Elementary,  Loveland  Elementary,  Paddock  Road  Elementary,  Rockbrook  Elementary,  Westbrook  Elementary  and  Westgate  Elementary.  Funds  will  also  be  used  to  complete  renovations/additions  to  Prairie  Lane  Elementary  and  to  construct  new  two  section  schools  at  Swanson  Elementary,  Sunset  Hills  Elementary  and  Oakdale  Elementary.  Remaining  funds  will  be  utilized  for  renovations  and  additions  to  Westside  Middle  School.    

Project  Updates  

Community  Comments  

• Analyzing  overall  facilities  master  plan.    

       

Page 5: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

Page  1  of  16

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions    Revised  Budget    Committed  Cost    Potential  Change  Orders  

 Approved  Change  Orders    Projected  Cost    Budget  Variance  

Saving/(Loss)    Paid  to  Date    Notes  

OVERALL  BOND  PROGRAM 79,900,000$                                     3,286,356$                     83,186,356$                             55,597,393$                 26,104,678$                 286,147$                           81,988,218$                 1,198,138$                         35,802,213$                Construction 62,280,181$                                       2,152,913$                     64,433,094$                             44,585,141$                 19,556,321$                 -­$                                           64,141,462$                 291,632$                               27,524,724$                Soft  Cost/FFE 11,012,599$                                     (3,084,312)$                   7,928,287$                                 4,988,042$                     2,945,341$                     -­$                                           7,933,383$                     (5,096)$                                     4,092,479$                    

Soft  Cost   8,982,599$                                         (2,908,028)$                   6,074,571$                                 4,819,926$                     1,259,741$                     -­$                                           6,079,667$                     (5,096)$                                     3,681,395$                    FFE 2,030,000$                                           (176,284)$                         1,853,716$                                 168,116$                           1,685,600$                     -­$                                           1,853,716$                     -­$                                               411,084$                          

Contingency 5,607,220$                                         (1,951,982)$                   3,655,238$                                 930,103$                           2,359,326$                     286,147$                           3,575,576$                     79,663$                                   821,537$                          Land  Acquisition 1,000,000$                                         900,000$                           1,900,000$                                 1,160,039$                     739,961$                           1,900,000$                     -­$                                               1,160,039$                    General  Expenses -­$                                                             4,437,798$                     4,437,798$                                 3,934,069$                     503,729$                           -­$                                           4,437,798$                     -­$                                               2,203,434$                    Additional  Revenue -­$                                                             831,939$                           831,939$                                       -­$                                           -­$                                           -­$                                           -­$                                           831,939$                               -­$                                          

GENERAL  EXPENSES -­$                                                             4,437,798$                     4,437,798$                                 3,934,069$                     503,729$                           -­$                                           4,437,798$                     -­$                                               2,203,434$                     3-­$                                                                 2,938,357$                     2,938,357$                                 2,938,357$                     -­$                                           -­$                                           2,938,357$                     -­$                                               1,767,145$                    

Project  Advocates -­$                                                             2,634,891$                     2,634,891$                                 2,634,891$                     2,634,891$                     -­$                                               1,511,231$                    

DLR  Group  (Ed  Specs) -­$                                                             91,426$                               91,426$                                           91,426$                               -­$                                           -­$                                           91,426$                               -­$                                               91,426$                              

Lamp  Rynearson  (Traffic) -­$                                                             30,200$                               30,200$                                           30,200$                               -­$                                           30,200$                               -­$                                               18,259$                              

IP  Design  (AV/Low  Voltage) -­$                                                             75,090$                               75,090$                                           75,090$                               -­$                                           75,090$                               -­$                                               55,168$                              

Morrissey  Engineering -­$                                                             67,864$                               67,864$                                           67,864$                               -­$                                           67,864$                               -­$                                               52,500$                              

Prime  Communications -­$                                                             26,386$                               26,386$                                           26,386$                               -­$                                           26,386$                               -­$                                               26,386$                              

New  Vista  (Visioning) -­$                                                             12,500$                               12,500$                                           12,500$                               12,500$                               -­$                                               12,175$                              BOND  PREMIMUM  EXPENDATURES 1,499,441$                     1,499,441$                                 995,712$                           503,729$                           -­$                                           1,499,441$                     -­$                                               436,289$                          

Bond  Underwriter's  Discount -­$                                                             467,400$                           467,400$                                       467,400$                           467,400$                           -­$                                               -­$                                          

Bond  Costs  of  Issuance  -­  (Minus  Fraser  Stryker) -­$                                                             342,841$                           342,841$                                       239,112$                           103,729$                           342,841$                           -­$                                               195,801$                          

HVAC  Commisioning   -­$                                                             400,000$                           400,000$                                       -­$                                           400,000$                           400,000$                           -­$                                               -­$                                          

Futureware -­$                                                                 18,716$                               18,716$                                           18,716$                               18,716$                               -­$                                               18,242$                              

Disrec -­$                                                                 14,249$                               14,249$                                           14,249$                               14,249$                               -­$                                               14,249$                              

Perry  Guthery  (Legal  Services) -­$                                                             33,359$                               33,359$                                           33,359$                               -­$                                           33,359$                               -­$                                               33,359$                              

Fraser  Styker    (Legal  Services) -­$                                                             91,049$                               91,049$                                           91,049$                               -­$                                           91,049$                               -­$                                               58,311$                              

Koley  Jessen   -­$                                                             3,276$                                   3,276$                                               3,276$                                   -­$                                           3,276$                                   -­$                                               3,276$                                  

Eznet  Pay -­$                                                             86,667$                               86,667$                                           86,667$                               -­$                                           86,667$                               -­$                                               86,667$                              

Apperson -­$                                                                 343$                                         343$                                                     343$                                         -­$                                           343$                                         -­$                                               343$                                        

Lockton  Companies  (BR  Insurance) -­$                                                             123$                                         123$                                                     123$                                         -­$                                           123$                                         -­$                                               123$                                        

Omaha  World  Herald  (Bid  Posting) -­$                                                             391$                                         391$                                                     391$                                         -­$                                           391$                                         -­$                                               391$                                        

CDW  (Security  Infrastructure) -­$                                                             10,587$                               10,587$                                           10,587$                               -­$                                           10,587$                               -­$                                               10,587$                              

Security  National  Bank  (Bank  Fees) -­$                                                             30,440$                               30,440$                                           30,440$                               -­$                                           30,440$                               -­$                                               14,940$                              

ADDITIONAL  REVENUE -­$                                                             831,939$                           831,939$                                       -­$                                           -­$                                           -­$                                           -­$                                           831,939$                               -­$                                          -­$                                                                 831,939$                           831,939$                                       -­$                                           -­$                                           -­$                                           -­$                                           831,939$                               -­$                                          

Bond  Sale  Premium -­$                                                             2,953,093$                     2,953,093$                                 -­$                                           -­$                                           2,953,093$                         -­$                                          

Investment  Income -­$                                                             281,913$                           281,913$                                       -­$                                           -­$                                           281,913$                              

Budget  Transfer -­$                                                             (1,510,617)$                   (1,510,617)$                               -­$                                           -­$                                           (1,510,617)$                       -­$                                          

Budget  Transfer  (Land  Acquisition) -­$                                                             (900,000)$                         (900,000)$                                     -­$                                           -­$                                           (900,000)$                             -­$                                          

Equipment  Sales -­$                                                             7,550$                                   7,550$                                               -­$                                           -­$                                           7,550$                                       -­$                                          

NOTES

3.  Reallocation  to  be  completed  from  project  budgets  into  General  Expense  budget  for  future  anticipated  cost.

1.    Overage  due  to  additional  scope  of  work  for  area  of  refuge.    

2.    Savings  from  project  used  to  offset  Loveland  area  of  refuge

BUDGET COMMITTED  COST

OVERALL  BOND  PROGRAM  PHASE  1  BUDGETWESTSIDE  COMMUNITY  SCHOOLS  -­‐  Monthly  Report  September  2017

Page 6: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

PROJECTS  UNDER  CONSTRUCTION  

Page 7: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

 

  BUDGET   PROJECTED  COST   COMMITTED  COST  Construction     $                                              12,521,882   $                                              12,521,882   $                                              12,371,465  Soft  Cost/FFE   $                                                  1,558,068   $                                                  1,558,068   $                                                  1,062,462  Contingency   $                                                          193,921   $                                                          193,921   $                                                              92,750  

PROJECT  TOTAL   $                                              14,273,871   $                                              14,273,871   $                                              13,526,677      

OAKDALE  ELEMENTARY  

 Summary:  Based  upon  a  facilities  assessment  that  was  completed  in  2014,  Oakdale  Elementary  will  be  replaced  by  a  new  two-­‐section  school  located  on  the  same  site  as  the  current  Oakdale  Elementary  School  (9801  West  Center  Road,  Omaha  Ne,  68124).      The  current  Oakdale  Elementary  School  will  be  decommissioned  and  razed  after  the  2015-­‐  2016  school  year,  making  way  for  a  new  Oakdale  Elementary  School.      

This  new  school  will  be  approximately  54,000  sf  and  incorporate  historical  attributes  and/or  materials  from  the  existing  elementary  school.  It  will  include:  a  separate  cafeteria  and  gymnasium,  dedicated  elective  classroom  space,  improved  drop  off  and  pick  up  access,  upgraded  security  and  entrance  vestibules,  improved  ADA  access,  and  the  construction  of  FEMA-­‐rated  storm  shelters.    The  new  elementary  school  will  need  to  be  designed  to  allow  project  based  learning  areas.  It  must  also  provide  a  safe,  healthy  and  secure  environment  for  educators,  learners  and  staff.

Project  Updates   Community  Comments  

• Exterior  paving  installation  ongoing.  • Exterior  grading  ongoing  on  East  and  West  side  of  site.  • Exterior  glazing  is  ongoing.  • Interior  framing  and  MEP  rough-­‐ins  ongoing.  • Drywall  ongoing  in  area  C  and  B.  • Primer  paint  started  in  select  area’s.  • WHS  students  framing  media  center  desk  skin  for  install  in  

November.    Currently  stored  at  Westside  Service  Center.  • Joel  meet  with  neighbors  to  review  final  grading  and  landscape  

placement  on  east  side  of  parking.  • Reconstruction  of  copula  commencing.    

 

• Next  meeting  with  neighbors  to  review  final  grading  and  landscape  placement  on  east  side  of  parking  lot  on  .  

         ACTIVITY       Scheduled  Start        Projected  Finish  Construction  Procurement        June  28,  2016              August  19,  2016  Decommission/Raze          May  25,  2016        September  15,  2016  Construction                              September  12,  2016                  November  24,  2017  FFE/Educators  Move-­‐in   November  25,  2017          January  1,  2018    

GENERAL  INFORMATION  Architect:     DLR  Group  General  Contractor:   Prairie  Construction  Project  Phase:     Under  Construction  

Project  Milestones  

Page 8: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

  BUDGET   PROJECTED  COST   COMMITTED  COST  

Construction   $                                                  11,266,544   $                                                  11,266,544   $                                                  11,094,004  Soft  Cost/FFE   $                                                      1,395,136   $                                                      1,395,136   $                                                              895,119  Contingency   $                                                            351,143   $                                                            351,143   $                                                                  58,136  

PROJECT  TOTAL   $                                                  13,012,823   $                                                  13,012,823   $                                                  12,047,259  

SUNSET  HILLS  ELEMENTARY  Summary:  Based  upon  a  facilities  assessment  that  was  completed  in  2014,  Sunset  Hills  Elementary  will  be  replaced  by  a  new  two-­‐section  school  located  on  the  same  site  as  the  current  Sunset  Hills  Elementary  School.  The  current  Sunset  Hills  Elementary  School  will  remain  in  operation  during  the  construction  of  the  new  two-­‐section  elementary  school.    After  the  2017  -­‐2018  school  year,  the  current  Sunset  Hills  Elementary  will  be  razed,  making  way  for  the  final  completion  of  the  new  Sunset  Hills  Elementary  School.  

This  new  school  will  be  approximately  54,000  sf.  It  will  include:  a  separate  cafeteria  and  gymnasium,  dedicated  elective  classrooms,  improved  drop  off  and  pick  up  access,  upgraded  security  and  entrance  vestibules,  improved  ADA  access  and  the  construction  of  FEMA-­‐rated  storm  shelters.    The  new  elementary  school  will  need  to  be  designed  to  allow  project  based  learning  areas.  It  must  also  provide  a  safe,  healthy  and  secure  environment  for  educators,  learners  and  staff.

Project  Updates   Community  Comments  

• Phase  1  of  asbestos  abatement  in  existing  building  completed.    Vrana  Construction  installing  temporary  glazing  on  interior  windows.  

• Masonry  ongoing  in  area  C.  • Exterior  brick  commencing  in  September.  • Structural  steel  and  roofing  installation  ongoing.  • Underground  MEP  installation  ongoing.  • Slab  on  grade  preparation  started  in  area  A.    • Site  grading  on  west  side  commencing  in  order  to  install  parking  lot.  • Front  drive  entry  completed  on  west  side  of  site.  

• PA  and  Vrana  meet  with  Todd  Johnson  from  Sunset  Hills  pool  to  discuss  upcoming  work  impacting  the  pool  on  June  30th.      

       ACTIVITY       Scheduled  Start        Projected  Finish  Design  Procurement      January  8,  2016              March  7,  2016  Construction  Procurement   December  6,  2016              February  6,  2017  Construction          April  3,  2017                May  25,  2018  Demolition/Raze      May  30,  2018                  July  15,  2018  FFE/Educators  Move-­‐in          June  4,  2018            August  8,  2018  

GENERAL  INFORMATION  Architect:     TACKarchitects  Contractor:     Vrana  Construction  Project  Phase:     Under  Construction      

Project  Milestones  

Page 9: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

  BUDGET   PROJECTED  COST   COMMITTED  COST  

Construction     $                                                  13,905,061   $                                                  13,905,061   $                                                  13,905,061  Soft  Cost/FFE   $                                                      1,303,599   $                                                      1,303,599   $                                                        1,266,349  Contingency   $                                                              956,467   $                                                              956,467   $                                                              481,488  

PROJECT  TOTAL   $                                                  16,165,127   $                                                  16,165,127   $                                                  15,652,897  

WESTSIDE  MIDDLE  SCHOOL  

Summary:  Based  upon  a  facilities  assessment  that  was  completed  in  2014,  the  Westside  Middle  School  will  require  interior  renovations  which  will  allow  the  implementation  of  the  Middle  School  Education  Philosophy.    An  addition  will  be  required  to  alleviate  overcrowding  and  allow  for  the  removal  of  portable  classrooms.  It  will  incorporate  facility  needs  that  will  ensure  an  additional  50-­‐year  lifespan  to  the  facility.    

The  Middle  School  will  include:  an  addition  of  approximately  15,000  sf,  renovation  of  75,000  sf,  the  creation  of  a  building  that  supports  the  “Middle  School  Philosophy”  (creating  the  right-­‐size  classrooms,  improving  circulation,  improving  special  education  spaces,  break-­‐down  scale  of  the  building  for  smaller  students  communities,  right-­‐size  food  service  and  cafeteria  space,  and  improvement  to  science  labs)  replace  portable  classrooms,  security  and  entrance  vestibule  upgrades,  electrical  upgrades  and  building  envelope  repairs.  

Project  Updates   Community  Comments  

• Phase  1,  2A,  and  2B  complete.    Upon  students  return  in  August  14,  the  will  access  new  learning  Teams  7A,  7D,  8A,  8B,  8C,  8D,  Media  Center,  Connector,  Council  Suite,  Security  entrance,  Room  206,  and  Nurse  station,  new  office  access  and  office  layout.  

• Common  area  furniture  has  been  installed  in  completed  areas  7A,  7D,  8A,  8B,  8C,  8D  and  Media  Center.  

• Phase  3  demolition  completed  • Interior  framing  and  MEP  rough  in  phase  3  ongoing.      • Roof  replacement  ongoing.  

• No  new  community  input.        

       

ACTIVITY       Scheduled  Start        Projected  Finish  Construction  Procurement     December  17,  2015            February  1,  2016  Phase  I  Construction              May  24,  2016              January  6,  2017  Phase  II  Construction            January  9,  2017          August  8,  2017  Phase  III  Construction                              May  25,  2017     December  15,  2017  Phase  IV  Construction                May  25,  2018                  July  15,  2018  Project  Completion                  July  15,  2018  

GENERAL  INFORMATION  Architect:     BVH  Architects  CMR:       Lueder  Construction  Project  Phase:     Under  Construction    

Project  Milestones  

Page 10: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions    Revised  Budget    Committed  Cost    Potential  Change  Orders  

 Approved  Change  Orders    Projected  Cost    Budget  Variance  

Saving/(Loss)    Paid  to  Date    Notes  

OAKDALE  ELEMENTARY 14,504,000$                 (230,129)$                         14,273,871$                 13,526,677$                 747,194$                           -­$                                           14,273,871$                 -­$                                           8,665,427$                    

Construction 11,351,372$                 1,170,510$                     12,521,882$                 12,371,465$                 150,417$                           -­$                                           12,521,882$                 -­$                                           7,562,201$                    Submittal  Exchange 5,000$                                   -­$                                           5,000$                                   5,000$                                   -­$                                           -­$                                           5,000$                                   -­$                                           -­$                                          

Eahrhart  Griffith  (Surveyor)   19,489$                               -­$                                           19,489$                               19,489$                               -­$                                           -­$                                           19,489$                               -­$                                           19,489$                              

Peitzmier  Construction  (Demolition) 189,000$                           -­$                                           189,000$                           189,000$                           -­$                                           -­$                                           189,000$                           -­$                                           169,200$                          

Prairie  Construction 10,728,357$                 1,209,627$                     11,937,984$                 11,937,984$                 -­$                                           -­$                                           11,937,984$                 -­$                                           7,172,872$                    

Playground  Equipment 150,000$                           -­$                                           150,000$                           -­$                                           150,000$                           -­$                                           150,000$                           -­$                                           64,103$                              

Lockton  Companies  (BR  Insurance) 10,954$                               -­$                                           10,954$                               10,537$                               417$                                         -­$                                           10,954$                               -­$                                           10,537$                              

Trane  (Building  Controls) 248,572$                           (39,117)$                             209,455$                           209,455$                           -­$                                           -­$                                           209,455$                           -­$                                           126,000$                          

Soft  Cost/FFE 2,064,828$                     (506,760)$                         1,558,068$                     1,062,462$                     495,606$                           -­$                                           1,558,068$                     -­$                                           1,010,349$                    Soft  Costs 1,644,828$                     (506,760)$                         1,138,068$                     1,062,462$                     75,606$                               -­$                                           1,138,068$                     -­$                                           858,509$                          

Project  Advocates 504,366$                           (504,366)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

DLR  Group  (Design) 764,589$                           50,000$                               814,589$                           791,589$                           23,000$                               -­$                                           814,589$                           -­$                                           656,699$                          

Lamp  Rynearson  (Traffic) 8,900$                                   (8,900)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

IP  Design  (AV/Low  Voltage) 18,941$                               (6,066)$                                 12,875$                               12,075$                               800$                                         -­$                                           12,875$                               -­$                                           12,414$                              

Prime  Commuications(Security) 12,883$                               (12,500)$                             383$                                         -­$                                           383$                                         -­$                                           383$                                         -­$                                           383$                                        

New  Vista  (Visioning) 2,500$                                   (2,500)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

DLR  Group  (Ed  Specs) 22,428$                               (22,428)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lamp  Rynearson 2,142$                                   -­$                                           2,142$                                   2,142$                                   -­$                                           -­$                                           2,142$                                   -­$                                           2,142$                                  Roger  Kruse  (Kitchen) 20,900$                               -­$                                           20,900$                               20,900$                               -­$                                           -­$                                           20,900$                               -­$                                           17,248$                              

Energy  Studio  (Energy  Modeling) 6,500$                                   -­$                                           6,500$                                   6,500$                                   -­$                                           -­$                                           6,500$                                   -­$                                           6,500$                                  Terracon  (Geotechnical  Survey) 5,500$                                   -­$                                           5,500$                                   5,500$                                   -­$                                           -­$                                           5,500$                                   -­$                                           5,500$                                  

B2  Environmental  (Asbestos  Survey)   1,400$                                   -­$                                           1,400$                                   1,400$                                   -­$                                           -­$                                           1,400$                                   -­$                                           1,400$                                  

B2  Environmental  (Asbestos  Monitoring)   1,000$                                   -­$                                           1,000$                                   1,000$                                   -­$                                           -­$                                           1,000$                                   -­$                                           1,000$                                  

Sabre  Poles  (Sprint  Pole)   24,807$                               -­$                                           24,807$                               24,807$                               -­$                                           -­$                                           24,807$                               -­$                                           24,807$                              

Downs  Electric  (Sprint  Move) 41,530$                               -­$                                           41,530$                               41,530$                               -­$                                           -­$                                           41,530$                               -­$                                           41,530$                              

Terracon  (Material/special  Inspections) 95,000$                               -­$                                           95,000$                               95,000$                               -­$                                           -­$                                           95,000$                               -­$                                           28,693$                              

Davids  Electric  (Move  DCEMS  siren) 5,000$                                   -­$                                           5,000$                                   5,000$                                   -­$                                           -­$                                           5,000$                                   -­$                                           5,000$                                  

Select  Van  and  Storage 49,039$                               -­$                                           49,039$                               49,039$                               -­$                                           -­$                                           49,039$                               -­$                                           49,039$                              

City  of  Omaha 540$                                         -­$                                           540$                                         540$                                         -­$                                           -­$                                           540$                                         -­$                                           540$                                        

MUD  (terminaiton  and  connection  fee  -­  Demo) 10,000$                               -­$                                           10,000$                               5,440$                                   4,560$                                   -­$                                           10,000$                               -­$                                           5,440$                                  

DR  Containers 2,000$                                   -­$                                           2,000$                                   -­$                                           2,000$                                   -­$                                           2,000$                                   -­$                                           175$                                        

Fees  (Zoning/Permit/SWPPP  Fees/OPPD  ect) 44,863$                               -­$                                           44,863$                               -­$                                           44,863$                               -­$                                           44,863$                               -­$                                           -­$                                          

FFE 420,000$                           -­$                                           420,000$                           -­$                                           420,000$                           -­$                                           420,000$                           -­$                                         151,839$                          Sheppards  Business 320,000$                           -­$                                           320,000$                           -­$                                           320,000$                           -­$                                           320,000$                           -­$                                           148,217$                          

Yet  to  be  assigned  budget 96,378$                               -­$                                           96,378$                               -­$                                           96,378$                               -­$                                           96,378$                               -­$                                           -­$                                          

Apple 3,622$                                   -­$                                           3,622$                                   -­$                                           3,622$                                   -­$                                           3,622$                                   -­$                                           3,622$                                  

Contingency 1,087,800$                     (893,879)$                         193,921$                           92,750$                               101,171$                           -­$                                           193,921$                           -­$                                           92,877$                              Remaining  Contingency 370,619$                           39,117$                               409,736$                           -­$                                           -­$                                           -­$                                           -­$                                           409,736$                           -­$                                          

Construction  Contingency  Move  for  Design 623,003$                           (623,003)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

City  of  Omaha  Credit  for  Street  Work -­$                                           50,000$                               50,000$                               -­$                                           -­$                                           -­$                                           -­$                                           50,000$                               -­$                                          

DLR  Change  Order  #001 -­$                                         (50,000)$                             (50,000)$                             -­$                                           -­$                                           -­$                                           -­$                                           (50,000)$                             -­$                                          

Prairie  Construction  Change  Order  #02 -­$                                         (276,631)$                         (276,631)$                         -­$                                           -­$                                           -­$                                           -­$                                           (276,631)$                         -­$                                          

Prairie  Construction  Change  Order  #03 -­$                                         (263,206)$                         (263,206)$                         -­$                                           -­$                                           -­$                                           -­$                                           (263,206)$                         -­$                                          

Prairie  Construction  Change  Order  #04 -­$                                         (46,787)$                             (46,787)$                             -­$                                           -­$                                           -­$                                           -­$                                           (46,787)$                             -­$                                          

Prairie  Construction  Change  Order  #05 -­$                                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Sunset  Hills  Credit  for  Soil  Haul -­$                                           276,631$                           276,631$                           -­$                                           -­$                                           -­$                                           -­$                                           276,631$                           -­$                                          

Eahrhart  Griffith  Contract 1,428$                                   -­$                                           1,428$                                   -­$                                           -­$                                           -­$                                           -­$                                           1,428$                                   -­$                                          

CDW  (Projectors) -­$                                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Centurylink  (Fiber  Move) 5,482$                                   -­$                                           5,482$                                   5,482$                                   -­$                                           -­$                                           5,482$                                   -­$                                           5,482$                                  

A&D  Technical  Supply  (Plans) 13,087$                               -­$                                           13,087$                               13,087$                               -­$                                           -­$                                           13,087$                               -­$                                           13,087$                              

Jamco  (Abatement  Contractor) 73,800$                               -­$                                           73,800$                               73,800$                               -­$                                           -­$                                           73,800$                               -­$                                           73,800$                              

Alvine  and  Associates  (Survey) 381$                                         -­$                                           381$                                         381$                                         -­$                                           -­$                                           381$                                         -­$                                           508$                                        

PROJECTS  UNDER  CONSTRUCTIONWESTSIDE  COMMUNITY  SCHOOLS  -­‐  Monthly  Report  September  2017

BUDGET COMMITTED  COST

Page 11: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions    Revised  Budget    Committed  Cost    Potential  Change  Orders  

 Approved  Change  Orders    Projected  Cost    Budget  Variance  

Saving/(Loss)    Paid  to  Date    Notes  

Yet  to  be  assigned  budget -­$                                         -­$                                           -­$                                           -­$                                           101,171$                           -­$                                           101,171$                           (101,171)$                         -­$                                          

WESTSIDE  MIDDLE  SCHOOL 16,765,000$                 (599,873)$                         16,165,127$                 15,652,897$                 512,230$                           -­$                                           16,165,127$                 (0)$                                               12,878,834$                

Construction 13,361,638$                 543,423$                           13,905,061$                 13,905,061$                 -­$                                           -­$                                           13,905,061$                 -­$                                           11,321,327$                Submittal  Exchange 5,000$                                   -­$                                           5,000$                                   5,000$                                   -­$                                           -­$                                           5,000$                                   -­$                                           -­$                                          

Lamp  Rynearson  (Site  Survey) 9,000$                                   20,000$                               29,000$                               29,000$                               -­$                                           -­$                                           29,000$                               -­$                                           12,363$                              

Lueder  Construction  GMP   12,966,211$                 523,423$                           13,489,634$                 13,489,634$                 -­$                                           -­$                                           13,489,634$                 -­$                                           11,032,671$                

Lockton  Companies  (BR  Insurance) 21,293$                               -­$                                           21,293$                               21,293$                               -­$                                           -­$                                           21,293$                               -­$                                           21,293$                              

Trane  (Building  Controls) 360,134$                           -­$                                           360,134$                           360,134$                           -­$                                           -­$                                           360,134$                           -­$                                           255,000$                          

Soft  Cost/FFE 2,145,987$                     (842,388)$                         1,303,599$                     1,266,349$                     37,250$                               -­$                                           1,303,599$                     -­$                                           1,130,285$                    Soft  Costs 1,795,987$                     (666,104)$                         1,129,883$                     1,098,233$                     31,650$                               -­$                                           1,129,883$                     -­$                                           1,015,099$                    

Project  Advocates 559,873$                           (559,873)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

BVH  Architects  (Design) 1,000,000$                     18,000$                               1,018,000$                     1,006,350$                     11,650$                               -­$                                           1,018,000$                     -­$                                           957,724$                          

IP  Design  (AV/Low  Voltage) 52,708$                               (25,000)$                             27,708$                               27,708$                               -­$                                           -­$                                           27,708$                               -­$                                           22,297$                              

MEI  (Security) 12,500$                               (12,500)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

New  Vista  (Visioning) 2,500$                                   (2,500)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Energy  Modeling -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Thiele  Geotech  (Geotech  Survey) 5,575$                                   -­$                                           5,575$                                   5,575$                                   -­$                                           -­$                                           5,575$                                   -­$                                           2,484$                                  

B2  Environmental  (Asbestos  Survey)   2,600$                                   -­$                                           2,600$                                   2,600$                                   -­$                                           -­$                                           2,600$                                   -­$                                           1,400$                                  

Thiele  Geotech  (Material/special  Inspections) 30,000$                               -­$                                           30,000$                               30,000$                               -­$                                           -­$                                           30,000$                               -­$                                           5,840$                                  

Fees  (Zoning/Permit/SWPPP  Fees/OPPD  ect) 12,000$                               -­$                                           12,000$                               12,000$                               -­$                                           -­$                                           12,000$                               -­$                                           12,000$                              

Prime  Specialty  (Security  Software) 14,000$                               -­$                                           14,000$                               14,000$                               -­$                                           -­$                                           14,000$                               -­$                                           13,355$                              

Security  Infrastructure 20,000$                               -­$                                           20,000$                               -­$                                           20,000$                               -­$                                           20,000$                               -­$                                           -­$                                          

yet  to  be  assigned  budget 84,231$                               (84,231)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

FFE 350,000$                           (176,284)$                         173,716$                           168,116$                           5,600$                                   -­$                                           173,716$                           -­$                                           115,186$                          Engineering  Tech  Tables  (Millwork  -­  Lueder  CO  #4) 34,072$                               (34,072)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Engineering  Tech  Tables  (Electircal) 7,000$                                   -­$                                           7,000$                                   7,000$                                   -­$                                           -­$                                           7,000$                                   -­$                                           -­$                                          

NFM  (FCS  appliances) 4,020$                                   -­$                                           4,020$                                   3,920$                                   100$                                         -­$                                           4,020$                                   -­$                                           3,863$                                  

FCS  sewing  tables 5,500$                                   -­$                                           5,500$                                   -­$                                           5,500$                                   -­$                                           5,500$                                   -­$                                           -­$                                          

Allmakes  (Furniture) 157,196$                           -­$                                           157,196$                           157,196$                           -­$                                           -­$                                           157,196$                           -­$                                           111,323$                          

BVH  (Design  Common  Space) 18,000$                               (18,000)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

yet  to  be  assigned  budget 124,212$                           (124,212)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Contingency 1,257,375$                     (300,908)$                         956,467$                           481,488$                           474,980$                           -­$                                           956,468$                           (0)$                                               427,222$                          Remaining  Contingency (17,309)$                             242,515$                           225,206$                           -­$                                           -­$                                           -­$                                           -­$                                           225,206$                           -­$                                          

Design  Budget  Move 320,000$                           (320,000)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lueder  Construction  Change  Order  #3 183,033$                           (183,033)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lueder  Construction  Change  Order  #4 52,795$                               (52,795)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lueder  Construction  Change  Order  #5 87,206$                               (87,206)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lueder  Construction  Change  Order  #6 -­$                                           108,419$                           108,419$                           -­$                                           -­$                                           -­$                                           -­$                                           108,419$                           -­$                                          

Lueder  Construction  Change  Order  #7 8,808$                                   (8,808)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lueder  Construction  Change  Order  #8 100,000$                           -­$                                           100,000$                           -­$                                           100,000$                           -­$                                           100,000$                           -­$                                           -­$                                          

Heartland  Roofing  (Old  FCS  roofing) 104,350$                           -­$                                           104,350$                           104,350$                           -­$                                           -­$                                           104,350$                           -­$                                           104,350$                          

Jamco  (Abatement  Contractor) 45,000$                               -­$                                           45,000$                               45,000$                               -­$                                           -­$                                           45,000$                               -­$                                           39,512$                              

Royer  Art  Room/Front  Entry/Nurse/Storage 36,355$                               -­$                                           36,355$                               -­$                                           36,355$                               -­$                                           36,355$                               -­$                                           -­$                                          

DR  Containers   2,750$                                   -­$                                           2,750$                                   2,750$                                   -­$                                           -­$                                           2,750$                                   -­$                                           2,750$                                  

Futureware 1,000$                                   -­$                                           1,000$                                   1,000$                                   -­$                                           -­$                                           1,000$                                   -­$                                           871$                                        

Craftsman  Windows 988$                                         -­$                                           988$                                         988$                                         -­$                                           -­$                                           988$                                         -­$                                           988$                                        

Johnson  Hardware 2,951$                                   -­$                                           2,951$                                   2,951$                                   -­$                                           -­$                                           2,951$                                   -­$                                           2,951$                                  

Hiller  Electric 35,977$                               -­$                                           35,977$                               35,977$                               -­$                                           -­$                                           35,977$                               -­$                                           35,977$                              

Kure 4,020$                                   -­$                                           4,020$                                   4,020$                                   -­$                                           -­$                                           4,020$                                   -­$                                           -­$                                          

Larsen  Painting   20,000$                               -­$                                           20,000$                               20,000$                               -­$                                           -­$                                           20,000$                               -­$                                           15,629$                              

Contour  Construction 2,031$                                   -­$                                           2,031$                                   2,031$                                   -­$                                           -­$                                           2,031$                                   -­$                                           2,031$                                  

Sears   30,000$                               -­$                                           30,000$                               30,000$                               -­$                                           -­$                                           30,000$                               -­$                                           26,960$                              

Terracon   1,950$                                   -­$                                           1,950$                                   1,950$                                   -­$                                           -­$                                           1,950$                                   -­$                                           1,950$                                  

JW  Smith   20,820$                               -­$                                           20,820$                               20,820$                               -­$                                           -­$                                           20,820$                               -­$                                           20,765$                              

Electronic  Sound 720$                                         -­$                                           720$                                         720$                                         -­$                                           -­$                                           720$                                         -­$                                           720$                                        

CDW  Government 40,440$                               -­$                                           40,440$                               40,440$                               -­$                                           -­$                                           40,440$                               -­$                                           40,124$                              

Master  Mechanical 479$                                         479$                                         479$                                         -­$                                           479$                                         479$                                        

Mayflower  (Furniture  Moving) 80,000$                               -­$                                           80,000$                               80,000$                               -­$                                           -­$                                           80,000$                               -­$                                           67,972$                              

Prime  Specialty  (Security  Software) 446$                                         -­$                                           446$                                         446$                                         -­$                                           -­$                                           446$                                         -­$                                           446$                                        

University  Pub  (Locker  Move/Supply) 35,000$                               -­$                                           35,000$                               30,000$                               5,000$                                   -­$                                           35,000$                               -­$                                           24,181$                              

Worthington  Direct 8,932$                                   -­$                                           8,932$                                   8,932$                                   -­$                                           -­$                                           8,932$                                   -­$                                           8,932$                                  

M&M  Steel 15,490$                               -­$                                           15,490$                               15,490$                               -­$                                           -­$                                           15,490$                               -­$                                           15,490$                              

Johnson  Deconstruction 5,019$                                   -­$                                           5,019$                                   5,019$                                   -­$                                           -­$                                           5,019$                                   -­$                                           5,019$                                  

BUDGET COMMITTED  COST

Page 12: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions    Revised  Budget    Committed  Cost    Potential  Change  Orders  

 Approved  Change  Orders    Projected  Cost    Budget  Variance  

Saving/(Loss)    Paid  to  Date    Notes  

Glass  Services 8,425$                                   -­$                                           8,425$                                   8,425$                                   -­$                                           -­$                                           8,425$                                   -­$                                           8,425$                                  

Johnson  Drywall 19,000$                               -­$                                           19,000$                               19,000$                               -­$                                           -­$                                           19,000$                               -­$                                           -­$                                          

National  Concrete 700$                                         -­$                                           700$                                         700$                                         -­$                                           -­$                                           700$                                         -­$                                           700$                                        

Yet  to  be  assigned  budget -­$                                           -­$                                           -­$                                           -­$                                           333,625$                           -­$                                           333,625$                           (333,625)$                         -­$                                          

SUNSET  HILLS  ELEMENTARY 13,824,000$                 (811,177)$                         13,012,823$                 12,047,259$                 679,417$                           286,147$                           13,012,823$                 -­$                                           2,346,097$                    

Construction 10,907,482$                 359,062$                           11,266,544$                 11,094,004$                 172,540$                           -­$                                           11,266,544$                 -­$                                           1,479,185$                    Submittal  Exchange 5,000$                                   -­$                                           5,000$                                   5,000$                                   -­$                                           -­$                                           5,000$                                   -­$                                           -­$                                          

Lamp  Rynearson  (Surveyor) 12,000$                               -­$                                           12,000$                               12,000$                               -­$                                           -­$                                           12,000$                               -­$                                           11,812$                              

Lockton  Companies  (BR  Insurance) 13,903$                               -­$                                           13,903$                               13,903$                               -­$                                           -­$                                           13,903$                               -­$                                           13,903$                              

Vrana  Construction 10,427,408$                 635,693$                           11,063,101$                 11,063,101$                 -­$                                           -­$                                           11,063,101$                 -­$                                           1,453,470$                    

Prairie  Construction  (Overex  and  Surcharge) 276,631$                           (276,631)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Trane  (HVAC  Controls) 172,540$                           -­$                                           172,540$                           -­$                                           172,540$                           -­$                                           172,540$                           -­$                                           -­$                                          

Optimized  Systems  (HVAC  Commisioning) -­$                                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Soft  Cost/FFE 1,879,718$                     (484,582)$                         1,395,136$                     895,119$                           500,017$                           -­$                                           1,395,136$                     -­$                                           826,918$                          Soft  Costs 1,459,718$                     (484,582)$                         975,136$                           895,119$                           80,017$                               -­$                                           975,136$                           -­$                                           682,860$                          

Project  Advocates 481,657$                           (481,657)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

DLR  Group  (Ed  Specs) 21,376$                               (21,376)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lamp  Rynearson  (Traffic) 6,200$                                   (6,200)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lamp  Rynearson  (Survey) 10,000$                               -­$                                           10,000$                               10,000$                               -­$                                           -­$                                           10,000$                               -­$                                           7,542$                                  

IP  Design  (AV/Low  Voltage) 12,141$                               (10,313)$                             1,828$                                   1,828$                                   -­$                                           -­$                                           1,828$                                   -­$                                           1,828$                                  

MEI  (Security) 12,500$                               (12,500)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

New  Vista  (Visioning) 2,500$                                   (2,500)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Roger  Kruse  (Kitchen) 20,900$                               -­$                                           20,900$                               20,900$                               -­$                                           -­$                                           20,900$                               -­$                                           18,528$                              

Energy  Modeling -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

TACKarchitects  (Design) 790,794$                           49,964$                               840,758$                           790,758$                           50,000$                               -­$                                           840,758$                           -­$                                           631,517$                          

Terracon  (Geotech) 3,500$                                   -­$                                           3,500$                                   3,500$                                   -­$                                           -­$                                           3,500$                                   -­$                                           3,500$                                  

B2  Environmental  (Asbestos  Survey)   2,000$                                   -­$                                           2,000$                                   2,000$                                   -­$                                           -­$                                           2,000$                                   -­$                                           2,000$                                  

Security  Infrastructure 20,000$                               -­$                                           20,000$                               -­$                                           20,000$                               -­$                                           20,000$                               -­$                                           -­$                                          

Terracon  (Material/special  Inspections) 66,500$                               -­$                                           66,500$                               61,500$                               5,000$                                   -­$                                           66,500$                               -­$                                           13,313$                              

TD2   4,633$                                   -­$                                           4,633$                                   4,633$                                   -­$                                           -­$                                           4,633$                                   -­$                                           4,633$                                  

Fees  (Zoning/Permit/SWPPP  Fees/OPPD  ect) 5,017$                                   -­$                                           5,017$                                   -­$                                           5,017$                                   5,017$                                   -­$                                           -­$                                          

FFE 420,000$                           -­$                                           420,000$                           -­$                                           420,000$                           420,000$                           -­$                                           144,059$                          Sheppards  Business 320,000$                           -­$                                           320,000$                           320,000$                           -­$                                           -­$                                           320,000$                           -­$                                           144,059$                          

yet  to  be  assigned  budget 100,000$                           -­$                                           100,000$                           -­$                                           100,000$                           -­$                                           100,000$                           -­$                                           -­$                                          

Contingency 1,036,800$                     (685,657)$                         351,143$                           58,136$                               6,860$                                   286,147$                           351,143$                           -­$                                           39,994$                              Remaining  Contingency 286,147$                           -­$                                           286,147$                           -­$                                           -­$                                           -­$                                           -­$                                           286,147$                           -­$                                          

TACKarchitects  Change  Order  #1 49,964$                               (49,964)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Vrana  Construction  Change  Order  #02 25,201$                               (25,201)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Construction  Contingency  Move  for  Design 610,492$                           (610,492)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Dostal  Construction  (Move  playground) 29,500$                               -­$                                           29,500$                               29,500$                               -­$                                           -­$                                           29,500$                               -­$                                           29,500$                              

Consol  Electric  (Move  playground) 476$                                         -­$                                           476$                                         476$                                         -­$                                           -­$                                           476$                                         -­$                                           476$                                        

S&W  Fence  (Move  Playground) 9,720$                                   -­$                                           9,720$                                   9,720$                                   -­$                                           -­$                                           9,720$                                   -­$                                           9,720$                                  

McGill  (Abatement  Contractor) 25,000$                               -­$                                           25,000$                               18,140$                               6,860$                                   -­$                                           25,000$                               -­$                                           -­$                                          

Alvine  and  Associates  (Survey) 300$                                         -­$                                           300$                                         300$                                         -­$                                           -­$                                           300$                                         -­$                                           298$                                        

Yet  to  be  assigned  budget -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           286,147$                           286,147$                           (286,147)$                         -­$                                          

NOTES

3.  Reallocation  to  be  completed  from  project  budgets  into  General  Expense  budget  for  future  anticipated  cost.

BUDGET COMMITTED  COST

1.    Overage  due  to  additional  scope  of  work  for  area  of  refuge.    

2.    Savings  from  project  used  to  offset  Loveland  area  of  refuge

Page 13: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

PROJECTS  IN  DESIGN  

Page 14: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

     

  BUDGET   PROJECTED  COST   COMMITTED  COST  

Construction   $                                                  10,962,206   $                                                  10,962,206   $                                                                    17,900  Soft  Cost/FFE   $                                                      1,455,695   $                                                      1,455,695   $                                                              796,065  Contingency   $                                                              942,800   $                                                              942,800   $                                                                                        0  

PROJECT  TOTAL   $                                                  13,360,701   $                                                  13,360,701   $                                                              813,965  

SWANSON  ELEMENTARY  Summary:  Based  upon  a  facilities  assessment  that  was  completed  in  2014,  Swanson  Elementary  will  be  replaced  by  a  new  two-­‐section  school  located  on  the  same  site  as  the  current  Swanson  Elementary  School  (9503  Walnut  Street,  Omaha  Ne,  68124).      The  current  Swanson  Elementary  School  will  be  decommissioned  and  razed  after  the  2017  -­‐  2018  school  year,  making  way  for  a  new  Swanson  Elementary  School.      

This  new  school  will  be  approximately  54,000  sfand  may  incorporate  attributes  from  the  existing  elementary  school.  It  will  include:  a  separate  cafeteria  and  gymnasium,  dedicated  elective  classroom  space,  improved  drop  off  and  pick  up  access,  upgraded  security  and  entrance  vestibules,  improved  ADA  access,  and  the  construction  of  FEMA-­‐rated  storm  shelters.    The  new  elementary  school  will  need  to  be  designed  to  allow  project  based  learning  areas.  It  must  also  provide  a  safe,  healthy,  and  secure  environment  for  educators,  learners,  and  staff.

Project  Updates   Community  Comments  

• Alley  Poyner  to  present  Design  Development  at  Board  of  Education  Luncheon  on  October  6,  2017.  

• Alley  Poyner  to  formally  present  Design  Development  to  the  Board  of  Education  at  the  October  16,  2017  board  meeting.      

• DAC  meeting  #10  was  held  on  August  29,  2017.    This  meeting  reviewed  status  and  provided  update  on  what  was  next.  

• Alley  Poyner  currently  working  on  Design  Development.  • APM  and  PA  to  meet  with  teacher’s  week  of  September  11,  2017  to  review  

casework,  interior  design/elevations.  • DAC  meeting  #11  is  scheduled  for  September  21,  2017.    This  meeting  will  

review  casework  and  interior  design  and  elevations.  • DAC  meeting  #12  is  scheduled  for  October  3,  2017.  

 

• Community  information  session  to  present  Design  Development  tentatively  scheduled  for  mid-­‐October  2017.  

         

   ACTIVITY       Scheduled  Start        Projected  Finish  Design  Procurement     October  1,  2016                            November  7,  2016  Construction  Procurement   January    2018            February  2018  Demolition/Raze      February  2018          March  2018  Construction         March  2018          July  2019  

GENERAL  INFORMATION  Architect:     Alley  Poyner  Contractor:     TBD  Project  Phase:     In  Design      

Project  Milestones  

Page 15: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    $                              45,664    Budget  Revisions    Revised  Budget    Committed  Cost    Potential  Change  Orders  

 Approved  Change  Orders    Projected  Cost    Budget  Variance  

Saving/(Loss)    Paid  to  Date    Notes  

SWANSON  ELEMENTARY 13,904,000$                 (543,299)$                         13,360,701$                 813,965$                           12,546,736$                 -­$                                           13,360,701$                 -­$                                           171,080$                          

Construction 10,862,206$                 100,000$                           10,962,206$                 17,900$                               10,944,306$                 -­$                                           10,962,206$                 -­$                                           12,900$                              Submittal  Exchange 5,000$                                   -­$                                           5,000$                                   5,000$                                   5,000$                                   -­$                                           -­$                                          

Lamp  Rynearson  (Surveyor) 12,900$                               -­$                                           12,900$                               12,900$                               -­$                                           12,900$                               -­$                                           12,900$                              

Lockton  Companies  (BR  Insurance) 10,000$                               -­$                                           10,000$                               -­$                                           10,000$                               10,000$                               -­$                                           -­$                                          

Trane  (HVAC  Controls) 221,000$                           -­$                                           221,000$                           -­$                                           221,000$                           221,000$                           -­$                                           -­$                                          

Optimized  Systems  (HVAC  Commisioning) 20,000$                               -­$                                           20,000$                               -­$                                           20,000$                               20,000$                               -­$                                           -­$                                          

Outdoor  Classroom 200,000$                           100,000$                           300,000$                           -­$                                           300,000$                           300,000$                           -­$                                           -­$                                          

Anticipated  Construction  Costs 10,393,306$                 -­$                                           10,393,306$                 -­$                                           10,393,306$                 10,393,306$                 -­$                                           -­$                                          

Soft  Cost/FFE 1,998,994$                     (543,299)$                         1,455,695$                     796,065$                           659,630$                           -­$                                           1,455,695$                     -­$                                           158,180$                          Soft  Costs 1,578,994$                     (543,299)$                         1,035,695$                     796,065$                           239,630$                           -­$                                           1,035,695$                     -­$                                           158,180$                          

Project  Advocates 484,329$                           (484,329)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

DLR  Group  (Ed  Specs) 21,500$                               (21,500)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Lamp  Rynearson  (Traffic) 7,900$                                   (7,900)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

IP  Design  (AV/Low  Voltage) 14,570$                               (14,570)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

MEI  (Security) 12,500$                               (12,500)$                             -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

New  Vista  (Visioning) 2,500$                                   (2,500)$                                 -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Roger  Kruse  (Kitchen) 20,900$                               -­$                                           20,900$                               20,900$                               20,900$                               -­$                                           -­$                                          

B2  Environmental  (Asbestos  Survey)   1,650$                                   -­$                                           1,650$                                   1,650$                                   -­$                                           1,650$                                   -­$                                           1,650$                                  

Energy  Modeling -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Geotechnical  Survey 10,000$                               -­$                                           10,000$                               -­$                                           10,000$                               10,000$                               -­$                                           -­$                                          

Alley  Poyner  Machetto  (Designer) 753,515$                           -­$                                           753,515$                           753,515$                           -­$                                           753,515$                           -­$                                           150,012$                          

Security  Infrastructure -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Material/special  Inspections 70,000$                               -­$                                           70,000$                               -­$                                           70,000$                               -­$                                           70,000$                               -­$                                           -­$                                          

Lamp  Rynearson  (Tree  Surveyor) 20,000$                               -­$                                           20,000$                               20,000$                               -­$                                           -­$                                           20,000$                               -­$                                           6,375$                                  

Fees  (Zoning/Permit/SWPPP  Fees/OPPD  ect) 30,000$                               -­$                                           30,000$                               -­$                                           30,000$                               30,000$                               -­$                                           -­$                                          

Waste  Management 143$                                         -­$                                           143$                                         -­$                                           143$                                         143$                                         -­$                                           143$                                        

Other  Soft  Cost  FFE 129,487$                           -­$                                           129,487$                           -­$                                           129,487$                           129,487$                           -­$                                           -­$                                          

FFE 420,000$                           -­$                                           420,000$                           -­$                                           420,000$                           420,000$                           -­$                                           -­$                                          Contingency 1,042,800$                     (100,000)$                         942,800$                           -­$                                           942,800$                           -­$                                           942,800$                           -­$                                           -­$                                          

Remaining  Contingency 842,800$                           -­$                                           842,800$                           -­$                                           -­$                                           842,800$                           -­$                                          

Outdoor  Classroom  FFE/Fit  out 100,000$                           (100,000)$                         -­$                                           -­$                                           -­$                                           -­$                                           -­$                                          

Abatement  Contractor 100,000$                           -­$                                           100,000$                           -­$                                           100,000$                           100,000$                           -­$                                          

Yet  to  be  assigned  budget -­$                                           -­$                                           -­$                                           -­$                                           842,800$                           842,800$                           (842,800)$                        

NOTES

3.  Reallocation  to  be  completed  from  project  budgets  into  General  Expense  budget  for  future  anticipated  cost.

2.    Savings  from  project  used  to  offset  Loveland  area  of  refuge

PROJECTS  IN  DESIGNWESTSIDE  COMMUNITY  SCHOOLS  -­‐  Monthly  Report  September  2017

1.    Overage  due  to  additional  scope  of  work  for  area  of  refuge.    

BUDGET COMMITTED  COST

Page 16: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

PROJECTS  NOT  STARTED  

Page 17: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

  BUDGET   PROJECTED  COST   COMMITTED  COST  

Construction   $                                                        8,294,058   $                                                        8,294,058   $                                                                        5,000  Soft  Cost/FFE   $                                                      1,255,788   $                                                      1,255,788   $                                                                        2,950  Contingency   $                                                            809,775   $                                                            809,775   $                                                                                        0  

PROJECT  TOTAL   $                                                  10,359,621   $                                                  10,359,621   $                                                                        7,950  

PRAIRIE  LANE  ELEMENTARY  

Summary:  Based  upon  a  facilities  assessment  that  was  completed  in  2014,  Prairie  Lane  Elementary  will  require  interior  renovations  which  will  allow  project  based  learning  space.    An  addition  will  incorporate  a  dedicated  gym.    Additionally,  it  will  incorporate  facility  needs  that  will  ensure  an  additional  50-­‐year  lifespan  to  the  facility.    

Prairie  Lane  will  include:  an  addition  of  approximately  13,200  sf,  renovation  of  21,500  sf,  relocation  of  administrative  office  for  increased  security,  improve  special  education  areas,  upgrade  HVAC,  a  separate  cafeteria  and  gymnasium,  dedicated  elective  classrooms,  improved  drop  off  and  pick  up  access,  upgraded  security  and  entrance  vestibules,  optimize  classroom  layout,  renovate  restrooms,  new  restrooms  in  early  childhood  and  kindergarten  classrooms,  building  envelope  improvements,    and  provide  storm  shelter  upgrades.    

Project  Updates   Community  Comments  

• Scheduled  to  begin  construction  in  Summer  2020.    

• No  new  community  input.            ACTIVITY       Scheduled  Start        Projected  Finish  Design  Procurement          First  Quarter  2019  Construction                Summer  2020    

GENERAL  INFORMATION  Architect:     TBD  CMR:       TBD    Project  Phase:     Not  Started  

Project  Milestones  

Page 18: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions  

 Revised  Budget  

 Committed  Cost  

 Potential  Change  Orders  

 Approved  Change  Orders  

 Projected  Cost  

 Budget  Variance  Saving/(Loss)    Paid  to  Date    Notes  

PRAIRIE  LANE  ELEMENTARY 10,797,000$   (437,379)$     10,359,621$     7,950$                 10,351,671$           -­$                                     10,359,621$   -­$                                           1,650$                  

Construction 8,294,058$       -­$                       8,294,058$         5,000$                 8,289,058$               -­$                                     8,294,058$       -­$                                           -­$                          Submittal  Exchange 5,000$                     -­$                       5,000$                       5,000$                 5,000$                     -­$                                           -­$                          

Surveyor 8,000$                     -­$                       8,000$                       -­$                       8,000$                             8,000$                     -­$                                           -­$                          

Futureware -­$                             -­$                       -­$                               -­$                       -­$                             -­$                                           -­$                          

Lockton  Companies  (BR  Insurance) 10,000$                 -­$                       10,000$                   -­$                       10,000$                         10,000$                 -­$                                           -­$                          

Anticipated  Construction  Costs 8,271,058$       -­$                       8,271,058$         -­$                       8,271,058$               8,271,058$       -­$                                           -­$                          

Soft  Cost/FFE 1,693,167$       (437,379)$     1,255,788$         2,950$                 1,252,838$               -­$                                     1,255,788$       -­$                                           1,650$                  Soft  Costs 1,273,167$       (437,379)$     835,788$               2,950$                 832,838$                     -­$                                     835,788$             -­$                                           1,650$                  

Project  Advocates 379,642$             (379,642)$     -­$                               -­$                       -­$                             -­$                                           -­$                          

DLR  Group  (Ed  Specs) 16,696$                 (16,696)$         -­$                               -­$                       -­$                             -­$                                           -­$                          

Lamp  Rynearson  (Traffic) 6,900$                     (6,900)$             -­$                               -­$                       -­$                             -­$                                           -­$                          

IP  Design  (AV/Low  Voltage) 19,141$                 (19,141)$         -­$                               -­$                       -­$                             -­$                                           -­$                          

MEI  (Security) 12,500$                 (12,500)$         -­$                               -­$                       -­$                             -­$                                           -­$                          

New  Vista  (Visioning) 2,500$                     (2,500)$             -­$                               -­$                       -­$                             -­$                                           -­$                          

Roger  Kruse  (Kitchen) 1,300$                     -­$                       1,300$                       1,300$                 1,300$                     -­$                                           -­$                          

Energy  Modeling 5,000$                     -­$                       5,000$                       -­$                       5,000$                             5,000$                     -­$                                           -­$                          

B2  Environmental  (Asbestos  Survey)   1,650$                     -­$                       1,650$                       1,650$                 -­$                                     1,650$                     -­$                                           1,650$                  

A/E  Designer 580,000$             -­$                       580,000$               -­$                       580,000$                     580,000$             -­$                                           -­$                          

Geotechnical  Survey 10,000$                 -­$                       10,000$                   -­$                       10,000$                         10,000$                 -­$                                           -­$                          

Churn 237,838$             -­$                       237,838$               -­$                       237,838$                     237,838$             -­$                                           -­$                          

FFE 420,000$             -­$                       420,000$               -­$                       420,000$                     420,000$             -­$                                           -­$                          Contingency 809,775$             -­$                       809,775$               -­$                       809,775$                     -­$                                     809,775$             -­$                                           -­$                          

Remaining  Contingency 739,775$             -­$                       739,775$               -­$                       -­$                             739,775$                           -­$                          

Abatement  Contractor 70,000$                 -­$                       70,000$                   -­$                       70,000$                         70,000$                 -­$                                           -­$                          

Yet  to  be  assigned  budget -­$                             -­$                       -­$                               -­$                       739,775$                     739,775$             (739,775)$                        

NOTES

3.  Reallocation  to  be  completed  from  project  budgets  into  General  Expense  budget  for  future  anticipated  cost.

2.    Savings  from  project  used  to  offset  Loveland  area  of  refuge

PROJECTS  NOT  STARTEDWESTSIDE  COMMUNITY  SCHOOLS  -­‐  Monthly  Report  September  2017

BUDGET COMMITTED  COST

1.    Overage  due  to  additional  scope  of  work  for  area  of  refuge.    

Page 19: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

   

PROJECTS  COMPLETED  

Page 20: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions  

 Revised  Budget  

 Committed  Cost  

 Potential  Change  Orders  

 Approved  Change  Orders  

 Projected  Cost  

 Budget  Variance  Saving/(Loss)    Paid  to  Date    Notes  

HILLSIDE  ELEMENTARY 803,000$           (31,816)$         771,184$           562,377$           -­$                                     -­$                                     562,377$           208,807$                           557,327$           2Construction 661,953$           -­$                       661,953$           464,090$           -­$                                     -­$                                     464,090$           197,863$                           459,040$          

Submittal  Exchange 1,000$                   -­$                       1,000$                   1,000$                   1,000$                   -­$                                           -­$                          

McGill  (Abatement-­  Interior  Tile) 700$                         -­$                       700$                         700$                         700$                         -­$                                           700$                        

McGill  (Abatement  -­  Exterior  Soffit) -­$                         -­$                       -­$                         9,200$                   9,200$                   (9,200)$                                 9,200$                  

ATC  (Asbestos  Survey) 480$                         -­$                       480$                         4,850$                   4,850$                   (4,370)$                                 4,850$                  

ATC  (Asbestos  Monitor  Exterior  Monitor) -­$                         -­$                       -­$                         930$                         930$                         (930)$                                       930$                        

Futureware -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Lockton  Companies  (BR  Insurance) -­$                         -­$                       -­$                         135$                         -­$                                     135$                         (135)$                                       135$                        

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                           -­$                          

RW  Engineering  (Surveyor) 2,400$                   -­$                       2,400$                   1,900$                   1,900$                   500$                                         1,900$                  

Terracon  (Geotech/Testing) -­$                         -­$                       -­$                         1,771$                   1,771$                   (1,771)$                                 1,771$                  

Nebraska  Furniture  Mart -­$                         -­$                       -­$                         870$                         870$                         (870)$                                       870$                        

Ronco  Construction 653,323$           -­$                       653,323$           438,684$           438,684$           214,639$                           438,684$          

Soft  Cost/FFE 129,720$           (31,816)$         97,904$               98,287$               -­$                                     -­$                                     98,287$               (383)$                                       98,287$              Soft  Costs 129,720$           (31,816)$         97,904$               98,287$               98,287$               (383)$                                       98,287$              

Project  Advocates 26,816$               (26,816)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 97,904$               -­$                       97,904$               97,904$               97,904$               -­$                                           97,904$              

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         383$                         -­$                                     383$                         (383)$                                       383$                        

FFE -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          Contingency 11,327$               -­$                       11,327$               -­$                         -­$                                     -­$                                     -­$                         11,327$                               -­$                          

Yet  to  be  assigned  budget 11,327$               11,327$               -­$                         -­$                                     -­$                         11,327$                              

LOVELAND  ELEMENTARY 486,000$           (21,230)$         464,770$           893,978$           -­$                                     -­$                                     893,978$           (429,208)$                         888,929$           1Construction 400,634$           -­$                       400,634$           831,158$           -­$                                     -­$                                     831,158$           (430,524)$                         826,109$          

Submittal  Exchange 1,000$                   -­$                       1,000$                   1,000$                   1,000$                   -­$                                           -­$                          

ATC  (Asbestos  Survey/Mont) 250$                         -­$                       250$                         200$                         200$                         50$                                             200$                        

Ronco  Construction 385,146$           -­$                       385,146$           816,657$           816,657$           (431,511)$                         816,658$          

NuTrend  (Portable  Removal) -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

RW  Engineering  (Surveyor) 2,400$                   -­$                       2,400$                   1,900$                   1,900$                   500$                                         1,900$                  

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                           -­$                          

Futureware -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Lockton  Companies  (BR  Insurance) 855$                         -­$                       855$                         855$                         -­$                                     855$                         -­$                                           855$                        

Terracon  (Testing  and  Inspection) 4,083$                   -­$                       4,083$                   3,646$                   3,646$                   437$                                         3,646$                  

Terracon  (Geotech) 2,850$                   -­$                       2,850$                   2,850$                   2,850$                   -­$                                           2,850$                  

Soft  Cost/FFE 77,353$               (18,098)$         59,255$               62,820$               62,820$               (3,565)$                                 62,820$              Soft  Costs 77,353$               (18,098)$         59,255$               62,820$               62,820$               (3,565)$                                 62,820$              

Moved  from  Contingency 3,132$                   -­$                       3,132$                   -­$                         -­$                         3,132$                                   -­$                          

Project  Advocates 16,230$               (16,230)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 56,123$               3,132$               59,255$               62,437$               62,437$               (3,182)$                                 62,437$              

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         383$                         383$                         (383)$                                       383$                        

FFE -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

PROJECTS  COMPLETEDWESTSIDE  COMMUNITY  SCHOOLS  -­‐  Monthly  Report  September  2017

BUDGET COMMITTED  COST

Page 21: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions  

 Revised  Budget  

 Committed  Cost  

 Potential  Change  Orders  

 Approved  Change  Orders  

 Projected  Cost  

 Budget  Variance  Saving/(Loss)    Paid  to  Date    Notes  

Contingency 8,013$                   (3,132)$             4,881$                   -­$                         -­$                                     -­$                                     -­$                         4,881$                                   -­$                          Remaining  Contingency 8,013$                   -­$                       8,013$                   -­$                         -­$                         8,013$                                  

Move  to  Soft  Cost  for  Design -­$                         (3,132)$             (3,132)$               -­$                         -­$                         (3,132)$                                

Yet  to  be  assigned  budget -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                         -­$                                          

PADDOCK  ROAD  ELEMENTARY 858,000$           (33,653)$         824,347$           805,119$           -­$                                     -­$                                     805,119$           19,228$                               800,069$           2Construction 707,292$           -­$                       707,292$           700,126$           700,126$           7,166$                                   695,076$          

Submittal  Exchange 1,000$                   -­$                       1,000$                   1,000$                   1,000$                   -­$                                           -­$                          

ATC  (Asbestos  Survey) 375$                         -­$                       375$                         375$                         375$                         -­$                                           375$                        

ATC  (Asbestos  Monitoring) -­$                         -­$                       -­$                         1,685$                   1,685$                   (1,685)$                                 1,685$                  

McGill  (Abatement-­  Boiler  Room) -­$                         -­$                       -­$                         5,800$                   5,800$                   (5,800)$                                 5,800$                  

RW  Engineering  (Surveyor) 2,900$                   -­$                       2,900$                   2,900$                   2,900$                   -­$                                           2,900$                  

Terracon  (Testing  and  Inspection) 4,938$                   -­$                       4,938$                   5,918$                   5,918$                   (980)$                                       5,918$                  

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                           -­$                          

MCL  Construction 690,329$           -­$                       690,329$           671,858$           671,858$           18,471$                               671,858$          

Futureware -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Lockton  Companies  (BR  Insurance) -­$                         -­$                       -­$                         1,005$                   -­$                                     1,005$                   (1,005)$                                 1,005$                  

Heartland  Roofing -­$                         -­$                       -­$                         1,835$                   1,835$                   (1,835)$                                 1,835$                  

Terracon  (Geotech) 3,700$                   -­$                       3,700$                   3,700$                   3,700$                   3,700$                                   3,700$                  

Soft  Cost/FFE 138,263$           (33,653)$         104,610$           104,993$           -­$                                     -­$                                     104,993$           (383)$                                       104,993$          Soft  Costs 138,263$           (33,653)$         104,610$           104,993$           -­$                                     -­$                                     104,993$           (383)$                                       104,993$          

Project  Advocates 28,653$               (28,653)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 104,610$           -­$                       104,610$           104,610$           104,610$           -­$                                           104,610$          

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         383$                         383$                         (383)$                                       383$                        

FFE -­$                         -­$                         -­$                         -­$                         -­$                                           -­$                          Contingency 12,445$               -­$                       12,445$               -­$                         -­$                                     -­$                                     -­$                         12,445$                               -­$                          

Remaining  Contingency 12,445$               -­$                       12,445$               -­$                         -­$                                     -­$                         12,445$                              

-­$                         -­$                       -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

ROCKBROOK  ELEMENTARY 1,205,000$   (45,241)$         1,159,759$     1,070,504$     -­$                                     -­$                                     1,070,504$     89,255$                               1,065,454$     2Construction 992,974$           -­$                       992,974$           923,586$           -­$                                     -­$                                     923,586$           69,388$                               918,536$          

Submittal  Exchange 1,000$                   -­$                       1,000$                   1,000$                   1,000$                   -­$                                           -­$                          

McGill  (Abatement  Contractor) 8,740$                   -­$                       8,740$                   8,740$                   8,740$                   -­$                                           8,740$                  

ATC  (Asbestos  Survey/Mont) 5,150$                   -­$                       5,150$                   5,150$                   5,150$                   -­$                                           5,150$                  

RW  Engineering  (Surveyor) 1,900$                   -­$                       1,900$                   1,900$                   1,900$                   -­$                                           1,900$                  

MCL  Construction 964,701$           -­$                       964,701$           870,188$           870,188$           94,513$                               870,188$          

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                           -­$                          

Custom  Iron  Works -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Terracon  (Testing  and  Inspection) 4,033$                   -­$                       4,033$                   4,145$                   4,145$                   (112)$                                       4,145$                  

Terracon  (Geotech) 3,400$                   -­$                       3,400$                   3,400$                   3,400$                   -­$                                           3,400$                  

Heartland  Roofing -­$                         -­$                       -­$                         1,720$                   1,720$                   (1,720)$                                 1,720$                  

Lockton  Companies  (BR  Insurance) -­$                         -­$                       -­$                         418$                         -­$                                     418$                         (418)$                                       418$                        

Tuff  Shed -­$                         -­$                       -­$                         2,342$                   2,342$                   (2,342)$                                 2,342$                  

Sheppard's  Business  Interiors -­$                         -­$                       -­$                         6,549$                   6,549$                   (6,549)$                                 6,549$                  

Creative  Sites  (Playground  Equipment) -­$                         -­$                       -­$                         13,984$               13,984$               (13,984)$                             13,984$              

Soft  Cost/FFE 192,159$           (45,241)$         146,918$           146,918$           -­$                                     -­$                                     146,918$           -­$                                           146,918$          Soft  Costs 192,159$           (45,241)$         146,918$           146,918$           -­$                                     -­$                                     146,918$           -­$                                           146,918$          

Project  Advocates 40,241$               (40,241)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 146,918$           -­$                       146,918$           146,918$           146,918$           -­$                                           146,918$          

BUDGET COMMITTED  COST

Page 22: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions  

 Revised  Budget  

 Committed  Cost  

 Potential  Change  Orders  

 Approved  Change  Orders  

 Projected  Cost  

 Budget  Variance  Saving/(Loss)    Paid  to  Date    Notes  

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         -­$                         -­$                         -­$                                           -­$                          

FFE -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          Contingency 19,867$               -­$                       19,867$               -­$                         -­$                                     -­$                                     -­$                         19,867$                               -­$                          

Remaining  Contingency 19,867$               -­$                       19,867$               -­$                         -­$                         19,867$                              

Yet  to  be  assigned  budget -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                         -­$                                          

WESTBROOK  ELEMENTARY 1,232,000$   (46,143)$         1,185,857$     1,039,221$     -­$                                     -­$                                     1,039,221$     146,636$                           1,029,751$     2Construction 1,015,335$     -­$                       1,015,335$     888,628$           -­$                                     -­$                                     888,628$           126,707$                           879,158$          

Submittal  Exchange 1,000$                   -­$                       1,000$                   1,000$                   1,000$                   -­$                                           -­$                          

McGill  (Abatement  Contractor) 18,780$               -­$                       18,780$               18,780$               18,780$               -­$                                           18,780$              

ATC  (Asbestos  Survey/Mont) 9,715$                   -­$                       9,715$                   8,130$                   8,130$                   1,585$                                   4,330$                  

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                          

Surveyor -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Ronco  Construction  (HP  Work) 981,790$           -­$                       981,790$           831,959$           831,959$           149,831$                           831,959$          

Heartland  Roofing -­$                         -­$                       -­$                         1,900$                   1,900$                   (1,900)$                                 1,900$                  

Lockton  Companies  (BR  Insurance) -­$                         -­$                       -­$                         959$                         -­$                                     959$                         (959)$                                       339$                        

Custom  Iron  Works -­$                         -­$                       -­$                         3,500$                   -­$                                     3,500$                   (3,500)$                                 3,500$                  

Sheppards  Business  Interiors -­$                         -­$                       -­$                         9,310$                   -­$                                     9,310$                   (9,310)$                                 9,310$                  

Waldinger   -­$                         -­$                       -­$                         6,536$                   -­$                                     6,536$                   (6,536)$                                 6,536$                  

Commonwealth  Electric -­$                         -­$                       -­$                         2,504$                   -­$                                     2,504$                   (2,504)$                                 2,504$                  

Soft  Cost/FFE 196,353$           (46,143)$         150,210$           150,593$           -­$                                     -­$                                     150,593$           (383)$                                       150,593$          Soft  Costs 196,353$           (46,143)$         150,210$           150,593$           -­$                                     -­$                                     150,593$           (383)$                                       150,593$          

Project  Advocates 41,143$               (41,143)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 150,210$           -­$                       150,210$           150,210$           150,210$           -­$                                           150,210$          

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         383$                         383$                         (383)$                                       383$                        

FFE -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          Contingency 20,312$               -­$                       20,312$               -­$                         -­$                                     -­$                                     -­$                         20,312$                               -­$                          

Remaining  Contingency 20,312$               -­$                       20,312$               -­$                         -­$                         20,312$                              

Yet  to  be  assigned  budget -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                         -­$                                          

WESTGATE  ELEMENTARY 657,000$           (26,941)$         630,059$           298,578$           -­$                                     -­$                                     298,578$           331,481$                           291,431$           2Construction 539,124$           -­$                       539,124$           218,092$           -­$                                     -­$                                     218,092$           321,032$                           210,945$          

MCL  Construction 534,824$           -­$                       534,824$           213,561$           213,561$           321,263$                           210,606$          

ATC  (Asbestos  Survey/Mont) 250$                         -­$                       250$                         250$                         250$                         -­$                                           250$                        

Security  Infrastructure 4,050$                   -­$                       4,050$                   4,050$                   4,050$                   -­$                                           -­$                          

Lockton  Companies  (BR  Insurance) -­$                         -­$                       -­$                         231$                         -­$                                     231$                         (231)$                                       89$                            

Abatement  Contractor -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          

Soft  Cost/FFE 107,045$           (26,941)$         80,104$               80,486$               80,486$               (382)$                                       80,486$              Soft  Costs 107,045$           (26,941)$         80,104$               80,486$               80,486$               (382)$                                       80,486$              

Project  Advocates 21,941$               (21,941)$         -­$                         -­$                         -­$                         -­$                                           -­$                          

DLR  Group  (Design) 80,104$               -­$                       80,104$               80,104$               80,104$               -­$                                           80,104$              

Prime  Communications  (Security) 5,000$                   (5,000)$             -­$                         382$                         382$                         (382)$                                       382$                        

FFE -­$                         -­$                       -­$                         -­$                         -­$                         -­$                                           -­$                          Contingency 10,831$               -­$                       10,831$               -­$                         -­$                                     -­$                                     -­$                         10,831$                               -­$                          

Remaining  Contingency 10,831$               -­$                       10,831$               -­$                         -­$                         10,831$                              

Yet  to  be  assigned  budget -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                         -­$                                          

-­$                         -­$                       -­$                         -­$                         -­$                         -­$                                          

BUDGET COMMITTED  COST

Page 23: DRAFT& - imagineadistrict.orgimagineadistrict.org/wp-content/uploads/2017/09/Westside-Board-of... · BUDGET! PROJECTED!COST! COMMITTED!COST! Construction!! $!!!!!12,521,882!$!!!!!12,521,882!$!!!!!12,371,465!

PAYMENTSA B   C  =  A+B D E F G  =  D+E+F H  =  C-­‐G J

Description    Budget    Budget  Revisions  

 Revised  Budget  

 Committed  Cost  

 Potential  Change  Orders  

 Approved  Change  Orders  

 Projected  Cost  

 Budget  Variance  Saving/(Loss)    Paid  to  Date    Notes  

WHS  WEST  CAMPUS/SWING  SCHOOL 3,865,000$   (56,500)$         3,808,500$     3,784,760$     23,740$                         -­$                                     3,808,500$     -­$                                           3,742,691$    

Construction 3,186,113$     (20,082)$         3,166,031$     3,166,031$     -­$                                     -­$                                     3,166,031$     -­$                                           3,160,247$    Submittal  Exchange 5,000$                   -­$                       5,000$                   5,000$                   5,000$                   -­$                                           -­$                          

Vrana  Construction   3,104,836$   -­$                       3,104,836$     3,104,836$     -­$                                     -­$                                     3,104,836$     -­$                                           3,104,052$    

Vrana  Construction  Change  Order  2 -­$                         15,131$           15,131$               15,131$               -­$                                     -­$                                     15,131$               -­$                                           15,131$              

Vrana  Construction  Change  Order  3 23,825$               697$                     24,522$               24,522$               -­$                                     -­$                                     24,522$               -­$                                           24,522$              

Vrana  Construction  Change  Order  4 -­$                         15,411$           15,411$               15,411$               -­$                                     -­$                                     15,411$               -­$                                           15,411$              

Prime  Communications  (Security) 15,000$               (15,000)$         -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

Super  Clean  (site  cleaning) 1,131$                   -­$                       1,131$                   1,131$                   -­$                                     1,131$                   -­$                                           1,131$                  

Yet  to  be  assigned  budget 36,321$               (36,321)$         -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

Soft  Cost/FFE 389,012$           (68,012)$         321,000$           321,000$           -­$                                     -­$                                     321,000$           -­$                                           321,000$          Soft  Costs 389,012$           (68,012)$         321,000$           321,000$           -­$                                     -­$                                     321,000$           -­$                                         321,000$          

Project  Advocates 50,000$               (50,000)$         -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

DLR  Group  (Design) 318,000$           -­$                       318,000$           318,000$           -­$                                     -­$                                     318,000$           -­$                                           318,000$          

Lamp  Rynearson  (Traffic) 6,500$                   (6,500)$             -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

Prime  Communications  (Security) 12,500$               (9,500)$             3,000$                   3,000$                   -­$                                     3,000$                   -­$                                           3,000$                  

Yet  to  be  assigned  budget 2,012$                   (2,012)$             -­$                         -­$                         -­$                                     -­$                         -­$                                           -­$                          

FFE -­$                         -­$                       -­$                         -­$                                     -­$                         -­$                                        

Contingency 289,875$           31,594$           321,469$           297,729$           23,740$                         -­$                                     321,469$           -­$                                           261,445$          Remaining  Contingency 18,554$               62,833$           81,387$               -­$                         -­$                                     -­$                                     -­$                         81,387$                               -­$                          

Vrana  Construction  Change  Order  2 15,131$               (15,131)$         -­$                         -­$                         -­$                                     -­$                                     -­$                         -­$                                           -­$                          

Vrana  Construction  Change  Order  3 697$                         (697)$                   -­$                         -­$                         -­$                                     -­$                                     -­$                         -­$                                           -­$                          

Vrana  Construction  Change  Order  4 15,411$               (15,411)$         -­$                         -­$                         -­$                                     -­$                                     -­$                         -­$                                           -­$                          

ATC  Inc.  (asbestos  survey) 40,242$               -­$                       40,242$               40,242$               -­$                                     -­$                                     40,242$               -­$                                           40,242$              

Dostal  Construction 1,300$                   -­$                       1,300$                   1,300$                   -­$                                     -­$                                     1,300$                   -­$                                           1,300$                  

Security  Infrastructure  (Videotronix) 2,251$                   -­$                       2,251$                   2,251$                   -­$                                     -­$                                     2,251$                   -­$                                           2,251$                  

Futureware 474$                         -­$                       474$                         474$                         -­$                                     -­$                                     474$                         -­$                                           474$                        

Lockton  Companies  (BR  Insurance) 2,812$                   -­$                       2,812$                   2,812$                   -­$                                     -­$                                     2,812$                   -­$                                           2,812$                  

Card  Member  Services  (Lowes) 568$                         -­$                       568$                         568$                         -­$                                     -­$                                     568$                         -­$                                           568$                        

McGill  Asbestos 161,550$           -­$                       161,550$           161,550$           -­$                                     -­$                                     161,550$           -­$                                           161,550$          

Select  Van  and  Storage 23,000$               -­$                       23,000$               23,000$               -­$                                     -­$                                     23,000$               -­$                                           1,392$                  

Unite  Private  works  (Fiber) 7,885$                   -­$                       7,885$                   7,885$                   -­$                                     -­$                                     7,885$                   -­$                                           7,885$                  

Syncquip -­$                         -­$                       -­$                         30,000$               -­$                                     -­$                                     30,000$               (30,000)$                             19,199$              

CDW   -­$                         -­$                       -­$                         1,237$                   -­$                                     -­$                                     1,237$                   (1,237)$                                 1,237$                  

Dostal  Construction  (Sidewalk  to  Track) -­$                         -­$                       -­$                         3,192$                   -­$                                     -­$                                     3,192$                   (3,192)$                                 3,192$                  

Glass  at  Kitchen  (Paid  out  of  Special  Services  Funds) -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                                     -­$                         -­$                                           -­$                          

Cubby  Modifications -­$                         -­$                       -­$                         -­$                         -­$                                     -­$                                     -­$                         -­$                                           -­$                          

Prince  Plumbing  (Water  to  Fields) -­$                         -­$                       -­$                         12,948$               -­$                                     -­$                                     12,948$               (12,948)$                             12,948$              

Baxter  Kenworthy  (Intercom  in  Gym  and  Kitchen) -­$                         -­$                       -­$                         1,519$                   -­$                                     -­$                                     1,519$                   (1,519)$                                 1,519$                  

Vrana  (Traffic  Barriers) -­$                         -­$                       -­$                         1,924$                   -­$                                     -­$                                     1,924$                   (1,924)$                                 1,924$                  

A  United  (Handicap  Operator) -­$                         -­$                       -­$                         6,499$                   -­$                                     -­$                                     6,499$                   (6,499)$                                 2,714$                  

Baxter  Kenworthy  Electric  (Handicap  Operator) -­$                         -­$                       -­$                         328$                         -­$                                     -­$                                     328$                         (328)$                                       238$                        

yet  to  be  assigned  budget -­$                         -­$                       -­$                         -­$                         23,740$                         -­$                                     23,740$               (23,740)$                             -­$                          

NOTES

3.  Reallocation  to  be  completed  from  project  budgets  into  General  Expense  budget  for  future  anticipated  cost.

4.  Boiler  replacement  cost  included  in  Ronco's  GMP.    Budget  transferred  from  Special  Building  Fund

2.    Savings  from  project  used  to  offset  Loveland  area  of  refuge

1.    Overage  due  to  additional  scope  of  work  for  area  of  refuge.    

BUDGET COMMITTED  COST


Recommended