OBERMEYER – IPSA Joint Venture
BOSNIA AND HERZEGOVINA
Bosnia and Herzegovina Public Railways Corporation
(BHPRC)
REGIONAL RAILWAYS PROJECT II
Quarterly Report
For
April to June 2011
Submitted by
OBERMEYER – IPSA Joint Venture
OBERMEYER – IPSA Joint Venture
14 July 2011 Page 2 of 42
OBERMEYER – IPSA Joint Venture
BOSNIA AND HERZEGOVINA
REGIONAL RAILWAY PROJECT II
RECONSTRUCTION OF TRACK AND SIGNALLING
OF
RAILWAYS IN BOSNIA AND HERZEGOVINA
(TRACK OVERHAUL AND SIGNALLING IMPROVEMENT)
QUARTERLY REPORT
for
APRIL to JUNE 2011
REVISION DATE DESCRIPTION PREPARED CHECKED APPROVED
Rev 00 14 July 2011 Version 00 I Garner Fuad Pašalić G Cummings
14 July 2011 Page 3 of 42
OBERMEYER – IPSA Joint Venture
Contents
1. Project Description
1. Project Overview
2. Contract Reports, each comprising:-
Contract Description
Overview
Key Achievements
Areas of Concern
Progress During Period
Lookahead
PT-01 / 2008
PT-02 / 2008
PT-03 / 2008
PS-01 / 2008
PS-02 / 2008
3. Project Staffing
Appendices
Appendix A : PT-01 – Log of Contractor’s Submittals
Appendix B : PT-02 – Log of Contractor’s Submittals
Appendix C : PT-03 – Log of Contractor’s Submittals
Appendix D : PS-01 – Log of Contractor’s Submittals
Appendix E : PS-02 – Log of Contractor’s Submittals
Appendix F : OPB and IPSA timesheets
14 July 2011 Page 4 of 42
OBERMEYER – IPSA Joint Venture
1. Project Description
Bosnia and Herzegovina Railways Public Corporation (BHRPC) and Railways of the
Federation of Bosnia and Herzegovina (ŽFBIH) and Railways of Republic of Srpska
(ZRS), (the Employer), are using part of the proceeds of a loan from the European Bank
for Reconstruction and Development and the European Investment Bank (the Banks)
towards the cost of the track overhaul and signalling improvement of Sarajevo-Ploče
railway (Line A) Konjic – Čapljina – border with Republic of Croatia and track overhaul
and signalling improvement of Doboj – Banja Luka – Bosanski Novi / Novi Grad (Line
B), Kostajnica – Josavka (all hereinafter referred to collectively as “the Project”).
Under the Terms of Reference, the Project Implementation Consultant (“Consultant”)
has, apart from the normal implementation and supervisory roles, to closely examine
and report on the Main Design and Tender Documents that were, in fact, prepared by
other consultants under a totally separate European Commission funded contract.
The Project comprises five (5) separate contracts, three (3) for track overhaul and two
(2) for signalling and interlocking, as follows:-
PT-01 / 2008 : Track Overhaul Sarajevo – Capljina, Konjic to Raska Gora, a
length of 45 kilometres
PT-02 / 2008 : Track Overhaul Sarajevo – Capljina, Raska Gora to Capljina, a
length of 54 kilometres
PT-03 / 2008 : Track Overhaul Doboj – Banja Luka – Bosanski Novi / Novi Grad,
Kostajnica to Josavka, a length of 64.8 kilometres
PS-01 / 2008 : Signalling and Interlocking Sarajevo – Capljina, Konjic to Capljina,
a length of 99 kilometres
PS-02 / 2008 : Signalling and Interlocking Doboj – Banja Luka – Bosanski Novi /
Novi Grad, Kostajnica to Josavka, a length of 64.8 kilometres
Where the term “Engineer” is used in this document, it means the person of the
Consultant who acts as the Engineer within the meaning of the PT Contracts, or his
14 July 2011 Page 5 of 42
OBERMEYER – IPSA Joint Venture
authorised delegates(s). Where the term “Project Manager” is used in this document, it
means the person of the Consultant who acts as the Project Manager within the
meaning of the PS Contracts, or his authorised delegate(s).
14 July 2011 Page 6 of 42
OBERMEYER – IPSA Joint Venture
2. Project Overview
This report covers the period 01 April 2011 to 3 June 2011. This period has been very
productive with a great deal of effort and hard work being put in by all parties - the PIU,
the Railway Companies and the Consultant.
Following receipt of the Banks’ no objection statements in respect of the tender
evaluation reports for the PS and the PT contracts, all five (5) contracts detailed above
in “Project Description” were awarded, by way of Letters of Acceptance to the
Contractors, during the fourth quarter of 2009, as follows:-
PT contracts : 12 October 2009
PS contracts : 04 December 2009
The Commencement Date for the three (3) PT Contracts has been established as being
23 November 2009, with an earliest Site access date in each case of 30 November
2009. With all relevant documentation from the PT Contractor being in place, the
Contractors’ rights to access and possession of the PT-02 and PT-03 Sites were
established as being in the second half of May 2010. The Contractor formally
commenced the PT-01 Works on 23 February 2011, and the construction log and
measurement book for each of the two Sites were opened accordingly.
The time for completion of the PT Contracts is, in each case, 730 days starting from 23
November 2009, with the date for completion being, therefore, 22 November 2011.
There has been no change to the date for completion of any of the PT Contract Works.
The advance payment under each of the PS-01 and PS-02 Contracts was received by
the Contractor on 20 July 2010, and said date was, therefore, established as being the
Effective Date in each case. The time for completion of the Facilities is twenty four (24)
months; the Date for Completions is, therefore, 19 July 2012 for each PS Contract.
The PS Contractor has made submittals and construction of the Facilities has
commenced and is proceeding well.
14 July 2011 Page 7 of 42
OBERMEYER – IPSA Joint Venture
During the reporting period, the Consultant has assisted the Employer in ensuring that
the PT and PS Contractors fully met their respective contractual obligations and that all
interfaces proceeded smoothly.
Agreement Nr. 1 in respect of the PT Contracts was executed on 18 May 2011 whereby
both parties’ claims accounts were wiped clean in exchange for the Contractor being
permitted to open more than two (2) Sections of each PT Contract at the same time.
The PS Contractor has been adhering to the prescribed communication protocols.
14 July 2011 Page 8 of 42
OBERMEYER – IPSA Joint Venture
3. Contract Reports
14 July 2011 Page 9 of 42
OBERMEYER – IPSA Joint Venture
PT-01 / 2008
TRACK OVERHAUL SARAJEVO-CAPLJINA
KONJIC TO RASKA GORA
(A LENGTH OF 45 KM)
14 July 2011 Page 10 of 42
OBERMEYER – IPSA Joint Venture
3.1 PT-01 / 2008
3.1.1 Contract Description
Contract PT-01/2008, Konjic – Raska Gora (inclusive), comprises a 45 kilometre long
single-track railway line from km 71+385 to km 117+116.80 and the Works consist of
track overhaul improvements. The work also includes the supply of the required
Materials and Plant.
The Contractor is JV Swietelsky Bau GmbH / Alpine Bau GmbH (“JV Swietelsky-
Alpine“).
The Time for Completion of the Works is 730 days commencing 23 November 2009.
The Date for Completion is, therefore, no later than 22 November 2011.
3.1.2 Overview
On the PT-02 Works, the Contractor has been allowed, via accommodations offered by
the railway company, to have open up to eight (8) interstation distances / stations at the
same time, and the Contractor has greatly benefitted from these accommodations by
being able to maximize the use of his high output equipment. Such accommodations
were based, inter alia, on the Contractor demonstrating an ability and willingness to
progressively complete interstation distances / stations for handover.
Following the execution of Agreement Nr. 1 on 18 May 2011, it is expected that the
Contractor will be encouraged to expeditiously progress and complete the primary work
and the completion work on the Sections of PT-01.
However, because of the Contractor’s previous failures on PT-02 to expeditiously
complete sections, part of Agreement Nr. 1 says that the Contractor will be paid for work
done in no more than two (2) Sections at once, irrespective of the actual number of
Sections (beyond 2) open and worked on at the same time. This is intended to
encourage the Contractor to timeously complete Sections in an orderly manner so that
he becomes eligible to be paid for the work he has performed in subsequent Sections.
14 July 2011 Page 11 of 42
OBERMEYER – IPSA Joint Venture
Pursuant to Agreement Nr. 1, the Contractor submitted a new work programme (Draft
18) which is considered to be workable in principle.
The Contractor started work on replacing the old rails and sleepers on Section
Jablanica – Grabovica.
3.1.3 Key Achievements
During the reporting period, the following key achievements were accomplished:-
the Contractor finished replacing the old ballast in two (2) Sections Grabovica –
Drežnica and Drežnica – Raška Gora
the Contractor finished replacing rails and sleepers in three (3) Sections
Jablanica – Grabovica, Grabovica – Drežnica and Drežnica – Raška Gora
on 22 May 2011, the Contractor finished changing rails and sleepers in tunnel
Jedrinje
4,337 wooden sleepers and 772 bridge sleepers were accepted at the factory by
the Employer
On 18 May 2011, a meeting was held between the PIU, the PT Contractor and the
Consultant. At the meeting, the PIU and the Contractor agreed that, in exchange for
making a fund of € 450,000 available, the Contractor would be permitted to utilised his
pool of Contractor’s Equipment between all three (3) PT Contracts. Two (2) further
meetings were held, on 24 May 2011 and 04 June 2011, to agree the precise procedure
to be adopted for taking-over Sections of the Works.
During the reporting period, the Contractor submitted the following documents for
information only or for review and approval (as stated):-
14 July 2011 Page 12 of 42
OBERMEYER – IPSA Joint Venture
Date receivedDocument
forPT-01 document
Document
status
06 April 2011 ApprovalRequest for executing work in Section
Jablanica – Grabovica
Not
approved
25 May 2011 ApprovalRequest for executing preparation
work in Section Jablanica - GrabovicaApproved
01 June 2011 Approval
Request for executing preparation
work in Section Ostrožac – Jablanica
without track closure
Approved
27 June 2011 ApprovalRequest for executing preparation
work in Section Ostrožac – JablanicaApproved
See Appendix A for log of submittals made in the period covered by the Report.
3.1.4 Areas of Concern
Areas of concern in the reporting period are:-
ability of the Contractor to complete the Works on time
the Contractor has not started work on replacing the old ballast in Section
Jablanica – Grabovica, an activity which was due to start on 12 June 2011
the Contractor has reported the possible presence of mines in some culverts in
Section Grabovica – Drežnica and, therefore, has not carried out cleaning at
those locations
poor ballast test results
the Contractor’s reports on progress are incomplete
the Contractor installed turnouts in station Raška Gora without approval and
without previous inspection, a matter recorded in letter PT-01/11/069/S dated 22
June 2011. The Contractor has not yet responded to the letter
14 July 2011 Page 13 of 42
OBERMEYER – IPSA Joint Venture
3.1.5 Progress During Period
The following matters were progressed during the reporting period:-
the Contractor finished replacing old rails and sleepers in Sections Jablanica –
Grabovica, Grabovica – Drežnica and Drežnica – Raška Gora
the Contractor excavated and constructed foundations for OCL masts
the Contractor stopped delivery of new ballast on site landfills on 10 May 2011
because the ballast was not up to standard
the Contractor delivered necessary documentation for the new quarry
“Papratnica” in Žepče
3.1.6 Lookahead
It is anticipated that the following tasks will be undertaken during the next reporting
period:-
full mobilization of the Contractor’s resources to enable him to fully prosecute the
Works
preparation and submittal of next period’s Progress Report
14 July 2011 Page 14 of 42
OBERMEYER – IPSA Joint Venture
PT-02 / 2008
TRACK OVERHAUL SARAJEVO-CAPLJINA
RASKA GORA TO CAPLJINA
(A LENGTH OF 54 KM)
14 July 2011 Page 15 of 42
OBERMEYER – IPSA Joint Venture
3.2 PT-02 / 2008
3.2.1 Contract Description
Contract PT-02/2008, Raška Gora (exclusive) – Čapljina is a 54 kilometre long single
track railway line from 117+116.80 km 170+390 km. The work is track overhaul
improvements. The work also includes the supply of the required Materials and Plant.
The Contractor is JV Swietelsky Bau GmbH / Alpine Bau GmbH (“JV Swietelsky-
Alpine“).
The Time for Completion of the Works is 730 days commencing 23 November 2009.
The Date for Completion is, therefore, no later than 22 November 2011.
3.2.2 Overview
On the PT-02 Works, the Contractor has been allowed, via accommodations offered by
the railway company, to have open up to eight (8) interstation distances / stations at the
same time, and the Contractor has greatly benefitted from these accommodations by
being able to maximize the use of his high output equipment. Such accommodations
were based, inter alia, on the Contractor demonstrating an ability and willingness to
progressively complete interstation distances / stations for handover.
Following the execution of Agreement Nr. 1 on 18 May 2011, it is expected that the
Contractor will be encouraged to expeditiously progress and complete the completion
work on the Sections of PT-02.
However, because of the Contractor’s previous failures on PT-02 to expeditiously
complete sections, part of Agreement Nr. 1 says that the Contractor will be paid for work
done in no more than two (2) Sections at once, irrespective of the actual number of
Sections (beyond 2) open and worked on at the same time. This is intended to
encourage the Contractor to timeously complete Sections in an orderly manner so that
he becomes eligible to be paid for the work he has performed in subsequent Sections.
14 July 2011 Page 16 of 42
OBERMEYER – IPSA Joint Venture
The Contractor has prepared interstation distance Mostar Terena - Bačevići for
technical acceptance.
3.2.3 Key Achievements
During the reporting period, the following key achievements were accomplished:-
installing and regulating of point switches type P - 60 - 200 – 60 and type P - 60
- 300 – 60 together with new ballast
installing oil cups
electro-welding of rails
stress relief of CWR track
constructing gabions on prepared base (item completed for whole Contract)
concreting foundations for OCL masts (item completed for whole Contract)
transporting new igneous ballast to station Mostar Teretna and station Čapljina
unloading and spreading new igneous ballast up to full ballast profile
installing and regulating of level crossings
cleaning channels and culverts
installing and regulating of switches in stations Žitomislići ,Šurmanci and Čapljina
replacing damaged wooden sleepers at old switches
on 11 April 2011, interface meeting PT-PS Contracts was held in Mostar
14 July 2011 Page 17 of 42
OBERMEYER – IPSA Joint Venture
on 21 April 2011, meeting with PIU and Railway Company representatives held
in Sarajevo
on 24 May 2011, meeting with PIU, Contractor and Railway Company
representatives held in Sarajevo
on 09 June 2011, meeting with PIU, Contractor and Railway Company
representatives held in Doboj
on 15 June 2011, meeting with PIU, Contractor and ŽFBiH representatives held
in Mostar
On 18 May 2011, a meeting was held between the PIU, the PT Contractor and the
Consultant. At the meeting, the PIU and the Contractor agreed that, in exchange for
making a fund of € 450,000 available, the Contractor would be permitted to utilised his
pool of Contractor’s Equipment between all three (3) PT Contracts. Further meetings
were held, on 24 May 2011, 09 and 15 June 2011, to agree the precise procedure to be
adopted for taking-over Sections of the Works and other related matters.
During the reporting period, the Contractor submitted the following documents for
approval (as stated):-
Date receivedDocument
forPT-02 document
Document
status
04 May 2011 ApprovalRequest for approval of Method
Statement for level crossingapproved
17 May 2011 Approval Request for approval of gradient poles approved
25 May 2011 ApprovalRequest for approval of PT-02
Detailed OCL construction plansapproved
16 June 2011 ApprovalRequest for approval of OCL Design
Tunnel Stolacapproved
3.2.4 Areas of Concern
Current areas of concern are:-
14 July 2011 Page 18 of 42
OBERMEYER – IPSA Joint Venture
handover of old materials to Railway company ŽFBiH
stolen OCL equipment
ŽFBiH has renewed the illegal level crossing at station Šurmanci; this may cause
the PT Contractor to invalidate his warranties on this part of the track
3.2.5 Progress During Period
The following matters were progressed during the reporting period:-
installing oil cups in interstation distances Žitomislići – Šurmanci and Šurmanci -
Čapljina
welding of rails in stations Mostar Putna and Žitomislići
stress relief of CWR track in interstation distance Šurmanci – Čapljina – state
border
stress relief of CWR track to switches in stations Šurmanci and Žitomislići
constructing gabions on prepared base (item completed for whole Contract)
concreting foundations for OCL masts (item completed for whole Contract)
transporting and placing new igneous ballast to station Mostar Teretna and
station Čapljina to full ballast profile
installing and regulating level crossing at km 138+840.47
installing and regulating level crossing at km 148+045.48
installing and regulating level crossing at km 165+206.79
14 July 2011 Page 19 of 42
OBERMEYER – IPSA Joint Venture
installing and regulating level crossing at km 166+860.67
installing and regulating point switches type P - 60 - 200 - 60 (4 nr.) together with
new ballast in station Žitomislići
installing and regulating point switches type P - 60 - 300 - 60 (4 nr.) together with
new ballast in station Šurmanci
installing and regulating point switches type P - 60 - 300 - 60 (4 nr.) together with
new ballast in station Čapljina
installing and regulating point switches type P - 60 - 300 - 60 (1 nr.) together with
new ballast at Km 161+600 near station Čapljina
the Contractor collected, sorted and handed over to the Railway Company old
materials from interstation distance Raštani – Mostar Putna
the Railway Company Commission for internal technical acceptance of Section
Raštani – Mostar Putna completed its work on 31 May 2011
the Railway Company Commission for internal technical acceptance of Section
Mostar Teretna - Bačevići completed its work on 14 June 2011
According to laboratory testing, the delivered ballast is up to standard.
3.2.6 Lookahead
It is anticipated that the following tasks will be undertaken during the next reporting
period:-
Contractor to submit a Schedule for acceptance / handover of sections
preparation and submittal of the Progress Report for the next period
14 July 2011 Page 20 of 42
OBERMEYER – IPSA Joint Venture
PT-03 / 2008
TRACK OVERHAUL DOBOJ-BANJA LUKA-BOSANSKI NOVI / NOVI GRAD
KOSTAJNICA TO JOSAVKA
(A LENGTH OF 64.8 KM)
14 July 2011 Page 21 of 42
OBERMEYER – IPSA Joint Venture
3.3 PT-03 / 2008
3.3.1 Contract Description
Contract PT-03/2008 comprises the track overhaul of a single track railway and the
adjustment of the 25 kV OCL at railway line Doboj – Banja Luka – Bosanski Novi / Novi
Grad, line 3, 64, 8 km long section from Kostajnica to Jošavka from kilometre point 5 –
218 to km 70-015. The work also includes the supply of the required Materials and
Plant.
The Contractor is JV Swietelsky Bau GmbH / Alpine Bau GmbH (“JV Swietelsky-
Alpine“).
The Time for Completion of the Works is 730 days commencing 23 November 2009.
The Date for Completion is, therefore, no later than 22 November 2011.
3.3.2 Overview
On the PT-02 Works, the Contractor has been allowed, via accommodations offered by
the railway company, to have open up to eight (8) interstation distances / stations at the
same time, and the Contractor has greatly benefitted from these accommodations by
being able to maximize the use of his high output equipment. Such accommodations
were based, inter alia, on the Contractor demonstrating an ability and willingness to
progressively complete interstation distances / stations for handover.
Following the execution of Agreement Nr. 1 on 18 May 2011, it is expected that the
Contractor will be encouraged to expeditiously progress and complete the primary work
and the completion work on the Sections of PT-03. As a result of the Agreement, the
Contractor is working on five (5) Sections; Jošavka – Snjegotina, Snjegotina – Ukrina,
Ukrina – Prisoje, Prisoje – Dragalovci and Dragalovci – Stanari.
However, because of the Contractor’s previous failures on PT-02 to expeditiously
complete sections, part of Agreement Nr. 1 says that the Contractor will be paid for work
done in no more than two (2) Sections at once, irrespective of the actual number of
14 July 2011 Page 22 of 42
OBERMEYER – IPSA Joint Venture
Sections (beyond 2) open and worked on at the same time. This is intended to
encourage the Contractor to timeously complete Sections in an orderly manner so that
he becomes eligible to be paid for the work he has performed in subsequent Sections.
At the request of the Contractor, the working window was extended from 8 hours to 10
hours and the extended window is still in operation.
During this reporting period progress was made in approving all key materials for which
the PIU has issued its approval as well as other materials needed for the track overhaul.
The Safety Plan in conjunction with the Temporary Traffic Management Manual are
approved and have become operational. In the event that no work activities are
planned on Site, the Contractor cancels the working window in advance. There have
been no problems related to track closures during this reporting period, except for at the
end of June 2011 when ŽRS reduced the working windows.
Factory inspections for major materials such as rails, concrete and wooden sleepers,
switches for stations Snjegotina, Ukrina and Prisoje, ballast, fasteners and OCL
materials have been carried out prior to delivery. The railway company has approved
the detailed design for elevating the OCL in tunnel Tromeđa.
The Contractor has all necessary materials on stock and has rented locomotives.
Replacement of the existing ballast and substructure work were carried out without any
holdups during the reporting period. 40,795 m track worth of ballast on Sections
Jošavka – Snjegotina, Snjegotina – Ukrina, Ukrina – Prisoje, Prisoje – Dragalovci and
Dragalovci – Stanari have been fully replaced, including tunnel “Tromeđa” (1,514 m);
the PM-200 machine was sent off site on 28 June 2011 after the aforementioned work
had been completed.
The track has been replaced with the SMD-80 machine in Sections Jošavka –
Snjegotina, Snjegotina – Ukrina and Ukrina – Prisoje for a length of 27,970 m and the
machine will start working again on 02 July 2011 from station Prisoje.
14 July 2011 Page 23 of 42
OBERMEYER – IPSA Joint Venture
Four (4) 90 m protective sections have been installed in the conventional manner, four
(4) switches in stations Snjegotina and Ukrina have been replaced and switches are
being installed in Station Prisoje.
20,503 m of 5.30 m wide geotextile have been incorporated, 2050 m of drainage has
been constructed and 31534 m of the base has been placed in station tracks.
On 22 May 2011, the Contractor overran the working window by 65 minutes due to a
malfunction of his PM machine. The working window was reduced by a total of 16
hours in the period 15 to 26 May 2011 because of the need to allow the passage of
trains after the strike of ŽRS’s staff.
The head of ŽRS’ Coordination Team for monitoring the overhaul has changed. Aco
Maksimović has been nominated for the new head of ŽRS’ Coordination Team as of 01
June 2011.
During the reporting period, the cooperation between the PIU, ŽRS’ Coordination and
Technical Team, the Contractor and the Supervision was good.
3.3.3 Key Achievements
The following achievements were made to the end of June 2011 in the first track
overhaul zone comprising Sections Jošavka – Snjegotina, Snjegotina – Ukrina, Ukrina –
Prisoje and Prisoje – Dragalovci:-
the Resident Engineer convened four (4) operational meetings with the
Contractor and members of ŽRS’ Coordination Team. Operational matters were
considered and the conclusions reached are set out in the minutes of the
meetings
on 01 April 2011, ŽRS formed a Committee to perform a preliminary technical
inspection of completed overhaul works and rehabilitated OCL on the first
Section Jošavka – Snjegotina including station Snjegotina. The same Committee
is tasked with performing a preliminary inspection and acceptance of all
subsequent completed Sections
14 July 2011 Page 24 of 42
OBERMEYER – IPSA Joint Venture
on 14 May 2011, an expert team comprising representatives of the railway
company, the Contractor and the Supervision, fully inspected executed overhaul
works and developed a record prior to the inspection of the Committee. Based on
the state of executed works, the Resident Engineer invited the Committee to start
with the inspection
on 19 May 2011, the Committee commenced the inspection of the second
section Snjegotina – Ukrina (excluding station Ukrina) and accepted the said
section with no conditional remarks
On 20 May 2011, the railway company approved the Contractor’s request to work
on the fourth section Prisoje – Dragalovci provided that the running speed on the
third section Ukrina – Prisoje is raised to 50 km/h and that the remarks of the
Committee for section Snjegotina – Ukrina are rectified, which the Contractor has
accomplished
On 24 May 2011, a meeting was convened in Sarajevo, at which time operational
issues pertaining to track closures, take over of completed works and other
issues were considered
On 26 May 2011, a meeting was convened in Doboj between the railway
company, the Contractor and the Supervision to clarify operational issues
concerning the OCL
On 26 May 2011, drainage works were completed in station Prisoje
On 16 and 24 June 2011, an expert inspection of tunnel “Ljeskove Vode” was
conducted and the Contractor was warned that the shotcrete insulation layer may
detach from some parts of the tunnel roof due to vibrations from major
equipment. The Contractor was warned in writing and he is to provide for the
safety of workers and equipment at such locations
on 28 June 2011, the PM 200 machine completed the replacement of ballast on
Sections Ukrina – Prisoje, Prisoje – Dragalovci and Dragalovci – Stanari and was
then sent off Site
14 July 2011 Page 25 of 42
OBERMEYER – IPSA Joint Venture
Sleepers, rails and ballast were regularly delivered in this reporting period and now
there are sufficient stocks for the continuation of works using major Equipment.
The Contractor collected, sorted and handed over old materials to the railway company,
expanded the subgrade, installed caps against lateral movement of track, installed anti-
creeping devices, installed track markings and carried out other work during this
reporting period.
On 18 May 2011, a meeting was held between the PIU, the PT Contractor and the
Consultant. At the meeting, the PIU and the Contractor agreed that, in exchange for
making a fund of € 450,000 available, the Contractor would be permitted to utilised his
pool of Contractor’s Equipment between all three (3) PT Contracts. Two (2) further
meetings were held, on 24 May 2011 and 04 June 2011, to agree the precise procedure
to be adopted for taking-over Sections of the Works.
During the reporting period, the Contractor has made the following submittals for review,
approval and information:-
Date receivedDocument
forPT-03 document
Document
status
05 May 2011 Approval Relocation of pole 176 km approved
24 May 2011 Approval New work programme Draft 17 Under review
26 May 2011 ApprovalDetailed OCL design B.7.8 B.7.10
Kostajnica-JošavkaUnder review
15 June 2011 ApprovalDetailed OCL design for Snjegotina-
Jošavka Book B.7.18Under review
See Appendix C for log of submittals made in the period covered by the Report.
3.3.4 Areas of Concern
Current areas of concern are:-
the Contractor is 10 days behind draft 18 of the work programme but is
anticipated to catch up the delay
14 July 2011 Page 26 of 42
OBERMEYER – IPSA Joint Venture
especially worrying is the delay to secondary work. However, towards the end of
the reporting period, progress in completing secondary work was evident
3.3.5 Progress during Period
The following progress was made during the period covered by this report:-
new quantities of ballast are being stored at permanent storage areas and these
are of satisfactory quality according to laboratory testing
technical acceptance of the first Section Jošavka – Snjegotina and station
Snjegotina and the Second section Snjegotina-Ukrina has been completed,
however, the Contractor has not rectified all comments of the Committee and has
not asked for a Taking-Over Certificate from the Engineer
old materials are being sorted and handed over to the railway company
the Contractor has developed a new programme (Draft 18) according to which
the Works will be completed by the Time for Completion. This programme is
interrogated on a weekly basis
the Contractor has revised the design for rehabilitating landslide Ljeskove Vode
at km 19-575/650 and has submitted the design to ŽRS for review and approval
3.3.6 Lookahead
It is anticipated that the following tasks will be undertaken during the next reporting
period:-
the Contractor is expected to rectify all remarks of the Committee pertaining to
completion of the first and second Sections in order to receive a Taking-Over
Certificate from the Engineer. The Contractor is expected to increase his output
of secondary works in order to fully complete the Works
14 July 2011 Page 27 of 42
OBERMEYER – IPSA Joint Venture
the Contractor is expected to carry out all necessary preliminary activities in
order to fully rehabilitate landslide Ljekove Vode during a track closure totaling 7
days
14 July 2011 Page 28 of 42
OBERMEYER – IPSA Joint Venture
PS-01 / 2008
SIGNALLING AND INTERLOCKING SARAJEVO-CAPLJINA
KONJIC TO CAPLJINA
(A LENGTH OF 99 KM)
14 July 2011 Page 29 of 42
OBERMEYER – IPSA Joint Venture
3.4 PS-01 / 2008
3.4.1 Contract Description
Contract PS-01 / 2008 Signalling and Interlocking Sarajevo – Capljina, Konjic to
Capljina comprises the following along a 99 km length of track:-
rehabilitation of the existing relay interlocking in stations Čelebići, Ostrožac,
Jablanica, Žitomislići, Šurmanci and Čapljina
a completely new interlocking system with microprocessor equipment in stations
Grabovica, Drežnica, Raška Gora, Raštani and Mostar Freight
adjustment of the existing interlocking to track overhaul in stations Mostar
Passenger and Bačevići
level crossings Rulna Staza, Bačevići, Žitomislići, Struge and Gabela (the level
crossing at Rulna Staza is in process of being omitted from the scope of the
Facilities)
interstation dependence Čelebići – Čapljina
electrical heating of switches in stations Čelebići, Ostrožac, Jablanica Grabovica,
Drežnica, Raška Gora and Raštani
power supply from the OCL
The Contractor is Thales Rail Signalling Solutions GmbH (“Thales”).
The Time for Completion of the Facilities is twenty four (24) months. The Effective Date
(Date for Commencement) has been established as being 20 July 2010, therefore, the
Date for Completion is 19 July 2012.
14 July 2011 Page 30 of 42
OBERMEYER – IPSA Joint Venture
3.4.2 Overview
With the payment of the advance payment having been made on 20 July 2010, the
Effective Date was established as being 20 July 2010. Therefore, the time for
Completion of the Facilities is now underway and is to take no longer than twenty four
(24) months. The Date for Completion is, therefore, 19 July 2012. The Contractor has
mobilized his resources to Site and is currently finalizing his designs. Delays in
establishing the Effective Date arose from the Contractor’s tardy establishment of his
tax proxy.
The Contractor’s Representative has appointed his delegate (assistant) and has also
appointed his Construction Manager and his deputy. The Contractor has also
appointed a person to deal solely with design matters.
The Contractor is now substantially complying with the communication protocols
prescribed in the Contract.
During the reporting period, the Contractor submitted the final parts of his detailed
design, and a workshop will be convened early in the upcoming period to settle all
outstanding matters.
3.4.3 Key Achievements
During the reporting period, the following key achievements were accomplished:-
cabling was completed in stations Čelebići, Ostrožac, Jablanica, Žitomislići,
Šurmanci and Čapljina
switches have been replaced in stations Žitomislići, Šurmanci and Čapljina, the
designed point machines (L 700 H) have been installed and connected to the
central command
14 July 2011 Page 31 of 42
OBERMEYER – IPSA Joint Venture
the necessary documents to form a part of interim payments have been agreed
with the Contractor. Interim payments 1, 2, 3 and 4 have been signed and
forwarded for payment
technical rooms in stations Grabovica, Drežnica, Raška Gora, Raštani and
Mostar Teretna have been refurbished. The rooms are ready for indoor
installation
During the reporting period, the Contractor submitted the following documents for
information only or for review and approval (as stated):-
Date receivedDocument
forPS-01 document
Document
status
01 June 2011 Approval
Detailed designs:
- power supply from the OCL
- switch heating
- low voltage network and
energisation
Not approved
20 May 2011 ApprovalCRS for PS-01 and PS-02 without
Diagnostic CatalogApproved
06 May 2011 Approval
Detailed design ESTW layout
stations Grabovica, Dreznica and
R.Gora
Approved
06 May 2011 Approval
Dislocation ZKO cabinet in
st.Grabovica, Dreznica, R.Gora,
Rastani and Mostar T
Approved
05 May 2011 Approval Changing of APB housings with
adequate cabinetsNot approved
11 April 2011 ApprovalCRS Diagnostic Catalog for PS-01
and PS-02Not approved
07 April 2011 Approval
Detailed design, cabling plan for
stations Grabovica, Dreznica, R.
Gora, Rastani, Mostar P, Mostar T
and Bacevici
Not approved
See Appendix D for log of submittals made in the period covered by the Report.
14 July 2011 Page 32 of 42
OBERMEYER – IPSA Joint Venture
3.4.4 Areas of Concern
Areas of concern in the reporting period are:-
there are delays to the delivery of detailed designs. An analysis of the delays
has been developed
3.4.5 Progress During Period
The following matters were progressed during the reporting period:-
operational agreements at Site level were reached every week / fortnight (as
necessary) and minutes were taken
progress meetings were held twice a month in Sarajevo / Doboj for the purpose
of monitoring the execution of activities on Projects PS-01 and PS-02
Site interface meetings between PS Contractor, PT Contractor, ŽFBiH and the
Consultant were held as necessary. Frequent meetings will continue to be held
as necessary
3.4.6 Lookahead
It is anticipated that the following tasks will be undertaken during the next reporting
period:-
a detailed analysis of the Time Schedule for PS-01 has been carried out covering
the period up to 06 June 2011. An update of the analysis of the Time Schedule
is ongoing and is nearing completion. It is expected to demonstrate delays to
certain activities
14 July 2011 Page 33 of 42
OBERMEYER – IPSA Joint Venture
proposals regarding the eradication of recorded delay will be developed after the
analysis is completed
14 July 2011 Page 34 of 42
OBERMEYER – IPSA Joint Venture
PS-02 / 2008
SIGNALLING AND INTERLOCKING DOBOJ-BANJA LUKA-BOSANSKI NOVI / NOVI
GRAD
KOSTAJNICA TO JOSAVKA
A LENGTH OF 64.8 KM)
14 July 2011 Page 35 of 42
OBERMEYER – IPSA Joint Venture
3.5 PS-02 / 2008
3.5.1 Contract Description
Contract PS-02 / 2008 Signalling and Interlocking Doboj-Banja Luka-Bosanski Novi /
Novi Grad Section Kostajnica To Josavka comprises the following along a 64.8 km
length of track:-
a completely new interlocking system with microprocessor equipment in stations
Ukrina, Dragalovci and Stanovi (Rudanka)
adjustment of the existing interlocking to track overhaul in stations Prisoje and
Stanari
level crossings Ukrina, Dragalovci, Stanari and Rudanka
interstation dependence at Ukrina – Prisoje, Prisoje – Dragalovci, Dragalovci -
Stanari
electrical heating of switches in stations Ukrina, Dragalovci, Stanovi and
Rudanka
power supply from the OCL and the power distribution network
The Contractor is Thales Rail Signalling Solutions GmbH (“Thales”).
The Time for Completion of the Facilities is twenty four (24) months. The Date for
Commencement has been established as being 20 July 2010, therefore, the Date for
Completion is 19 July 2012.
3.5.2 Overview
With the payment of the advance payment having been made on 20 July 2010, the
Effective Date was established as being 20 July 2010. Therefore, the time for
14 July 2011 Page 36 of 42
OBERMEYER – IPSA Joint Venture
Completion of the Facilities is now underway and is to take no longer than twenty four
(24) months. The Date for Completion is, therefore, 19 July 2012. The Contractor has
mobilized his resources to Site and is currently finalizing his designs. Delays in
establishing the Effective Date arose from the Contractor’s tardy establishment of his
tax proxy.
The Contractor’s Representative has appointed his delegate (assistant) and has also
appointed his Construction Manager and his deputy. The Contractor has also
appointed a person to deal solely with design matters.
The Contractor is complying with the communication protocols prescribed in the
Contract.
During the reporting period, the Contractor submitted the final parts of his detailed
design, and a workshop will be convened early in the upcoming period to settle all
outstanding matters.
The following progress was achieved on PS-02 Contract during the reporting period:-
roof refurbishment has been completed in stations Ukrina, Dragalovci, Stanovi
and Rudanka
station Ukrina
- old signalling safety equipment has been dismantled and handed over to
the beneficiary
- cable distribution cabinets have been mounted; cables have been installed
and connected to terminal blocks and cable dividers
- signals have been erected
- cabling has been completed
- transformers and equipment for power supplying signalling safety devices
and switch heating from the OCL have been installed
14 July 2011 Page 37 of 42
OBERMEYER – IPSA Joint Venture
station Prisoje
- the device in the station, which has been interlocked with a new electronic
signalling safety device, is turned off from time to time because switches
are being replaced
- after the track has been overhauled, the point machines will be mounted
and the device adjusted accordingly, then the device will be turned on
station Dragalovci
- switches 1 and 2 have been replaced; the remaining switches are
currently being replaced
- trenches from km 29+653 to km 31+753 and from 33+170 to km 340+720
have been excavated and cables have been laid
stations Stanovi and Rudanka
- trenches are being excavated and cables are being laid down in stations
Stanovi and Rudanka
- foundations for transformers for power supplying the signalling safety
device from the OCL are being installed
3.5.3 Key Achievements
During the reporting period, the following key achievements were accomplished:-
detailed designs for installing signalling / safety devices in stations Ukrina and
Dragalovci have been submitted and reviewed and the Contractor has been
permitted to install outdoor and indoor devices
14 July 2011 Page 38 of 42
OBERMEYER – IPSA Joint Venture
the refurbishment of rooms for signalling / safety devices in stations Dragalovci,
Stanovi, Rudanka and Ukrina has been completed
equipment for level crossings at Ukrina, Dragalovci and Žitomislići was inspected
in Katovice in Poland
A FAT was carried out in Germany
Site meetings were held as necessary and agreements regarding joint activities
were reached
During the reporting period, the Contractor submitted the following documents for
information only or for review and approval (as stated):-
Date received Document for PS-02 documentDocument
status
18 May 2011Approval and
execution
Detailed Design for Ukrina and
Dragalovci
Reviewed,
comments
submitted
20 May 2011
Submission to
acceptance
committee
Measurement lists for cables
Handed over
to the
committee
24 May 2011Approval and
execution
Detailed designs: power supply from
the OCL, switch heating, low voltage
cable network and energisation
Review by
ŽRS and
accepted
25 May 2011 ApprovalComments on the Contractor’s
DesignsSubmitted
03 June 2011 ApprovalDetailed designs for Ukrina and
Dragalovci
Submitted to
ŽRS
09 June 2011 For the recordRecord of acceptance of equipment
KalderaIn process
O8 June 2011 For the record Record of acceptance of equipment In process
15 June 2011 For the recordTables, request for cable
measurementsCompleted
21 June 2011 For the recordRecord of acceptance of equipment
ArnstadtIn process
14 July 2011 Page 39 of 42
OBERMEYER – IPSA Joint Venture
Date received Document for PS-02 documentDocument
status
28 June 2011 For the recordRecord of acceptance of equipment
in Dragalovci, Ukrina and RudankaIn process
See Appendix E for log of submittals made in the period covered by the Report.
3.5.4 Areas of Concern
Areas of concern in the reporting period are:-
The Contractor has made good preparations, most of the equipment and
materials have been procured and delivered. Detailed designs for stations
Ukrina and Dragalovci have been submitted. It is necessary to expedite the
remaining documents. The period envisaged for developing documents has
expired. It is necessary for the Contractor to engage more qualified workers for
installation, because the current state is not satisfactory
3.5.5 Progress During Period
The following matters were progressed during the reporting period:-
detailed designs for Ukrina and Dragalovci have been submitted
changes to the main designs have been approved
room refurbishment has been completed in stations Ukrina, Dragalovci, Stanovi
and Rudanka
equipment has been procured and accepted
all subcontractors have been brought on board and work is being executed on all
Facilities
14 July 2011 Page 40 of 42
OBERMEYER – IPSA Joint Venture
operational meetings are convened on a regular basis as well as meetings
between the Contractor, the Supervision and the Employer, at which time all
important issues are resolved
3.5.6 Lookahead
It is anticipated that the following tasks will be undertaken during the next reporting
period:-
outdoor equipment will be installed in station Ukrina
replacement of switches will be complete in station Prisoje
replacement of switches will be completed in station Dragalovci
Since work in all stations is in progress and since the equipment has been delivered, it
is expected that all participants will be engaged so as to complete the Facilities on time.
14 July 2011 Page 41 of 42
OBERMEYER – IPSA Joint Venture
4. Staffing
The following personnel are employed on the Project by the Consultant.
Mr. Gerard Cummings Resident Project Manager
Mr. Fuad Pašalić Deputy Resident Project Manager
Mr. Ian Garner Contracts and Claims Specialist
Ms. Amina Subašić Assistant / Secretary (Sarajevo)
Ms. Nataša Trifkovic Assistant / Secretary (Doboj)
Mr. Zlatko Bevanda Resident Engineer (PT-01)
Mr. Zijo Ligata Resident Engineer (PT-02)
Mr. Ivica Beus Engineer for substructure and superstructure
(PT-02)
Mr. Dusan Bosanac Resident Engineer (PT-03)
Mr. Muhamed Škiljo Engineer for superstructure (PT-03)
Mr. Alija Tabakovic Signalling Expert / Resident Engineer (PS-01)
Mr. Midhat Galijatović Signalling Coordinator (PS-01 and PS-02)
Mr. Ilija Sović Signalling Expert / Resident Engineer (PS-02)
Mr. Zdenko Stanić Engineer for OCL and energetic (PS-02)
Mr. Đorđe Lukić Assistant to the Supervision Engineer for OCL
Mr. Mehmed Mesihović Substructure / superstructure Supervisor)
Mr. Emir Ferhatbegović Signalling Engineer (PT-01)
Mr. Nedžad Mašnić Geodesic Supervisor
Mr. Ibrahim Kadić Substructure Supervisor (PT-03)
Mr. Salih Hadziomerović Superstructure Supervisor
Mr. Slavko Simić OCL Supervisor
Mr. Salih Dupovac Superstructure Supervisor (PT-01)
Mr. Rudolf Prskalo Assistant Supervisor (OCL)
Mr. Zlatan Šimunović Assistant Supervisor (PS-01)
Mr. Zoran Zakosek Assistant Supervisor (PT-01)
Mr. Stanislav Pavlov Assistant Geodesic Engineer (PT-01)
14 July 2011 Page 42 of 42