Drainage Analysis – The Weiss & Lavine Residence
Prepared December 1, 2020
Site: Owners:40 Montecito Road Tania Weiss & Rich LavineSan Rafael, California 40 Montecito RoadAPN: 016-054-10 San Rafael, CA 94901HLS Project # 3987 (415) 883-8000
Analysis Prepared by:Hogan Land Services, Inc.1702 4th StreetSanta Rosa, CA 95404 Jim Conklin, PE [email protected] 707-544-2104
The Weiss & Lavine Residence Preliminary Hydrology AnalysisJob # 3987 2
PREPARED: December 1, 2020
SUBJECT: 10-Year event hydrology calculations and reasoning for drainage network sizing
PROJECT: Drainage Analysis – The Weiss & Lavine Residence
ADDRESS: 40 Montecito Road, San Rafael, California
APN: 016-054-10
PROJECT DESCRIPTION:The subject parcel is located at 40 Montecito Road in San Rafael, California. Existing onsite infrastructure consists of a single-family dwelling, detached garage, concrete driveway, patio, and retaining walls. The proposed development under this permit includes a replacement main residence, detached garage, concrete driveway, concrete porch, wood deck, and site retaining walls. Only earthwork, grading, and drainage activities are covered under this preliminary civil plan set and preliminary drainage analysis. Topography of the area consists of moderate to steep slopes (10-30%) with the majority of the lot vegetated with native trees and grasses. This preliminary drainage analysis evaluates the potential drainage impacts of the proposed site redevelopment.
EXISTING AND PROPOSED DRAINAGE PATTERN:Runoff from the site and upslope watershed generally sheet flows diagonally across the subject parcel in a northeast direction before converging at an existing roadside ditch. Flow within the roadside concrete curb and gutter enter a public storm drain inlet along Point San Pedro
DESIGN REQUIREMENTS:The subject parcel is located within Marin County and is subject to BASMAA Post Construction requirements (See associated Preliminary Stormwater Control Plan). This analysis focuses strictly on the 10-year event sizing of the proposed drainage improvements. BASMAA Post Construction requirements are addressed within the Preliminary Stormwater Control Plan.
DESIGN CRITERIA & ASSUMPTIONS: This evaluation is based on the policies and procedures detailed in Flood Management Design Manual, by the Sonoma County Water Agency, Revised March 2020. The hydraulic design of the individual drainage improvements is based on the rational formula (Q = C i A ) and is based on the 10-year, 10-minute initial time of concentration storm. A precipitation intensity of 2.45 was used in the analysis and was derived from NOAA Atlas 14, Volume 6, Version 2. Minor downspout storm drain network was evaluated only for the worst case run within the network. The worst-case pipe sizing and slope is then conservatively used throughout the network. METHODOLOGIES USED:Rational Formula calculations for the 10-year storm are included based on the composite runoff coefficients for each tributary for sizing of the individual drainage improvements. The calculation spreadsheets are attached with this submittal. Pipe sizing and swale sizing were determined using Hydraflow Express, a design tool which uses Manning’s equations for circular channels to determine pipe sizing and triangular channels for swale sizing. 100 YEAR STORM IMPACT AND FLOODING CONCERNS:The parcel lies outside of the 100-year flood zone therefore flooding is not expected. A 100-year storm event would likely result in overflow of the culverts and swales and runoff returns to sheet flow downhill.
The Weiss & Lavine Residence Preliminary Hydrology AnalysisJob # 3987 3
CONCLUSION:The calculations and analysis provided herein is based upon the Sonoma County Water Agency Flood Management Design Manual and generally accepted engineering principles. The proposed drainage improvements for the development have been sized to accommodate the 10 year storm event. Drainage network calculations are based on free flow and should be routinely inspected by the property owner. The drainage pattern at a regional scale remains unchanged from pre to post development conditions.
ATTACHMENTS: Watershed Exhibit Rational Method Calculation Spreadsheet Hydraflow Express Calculations NDS Catch Basin Sizing Detail Other Supporting Tables & Figures
WATERSHED EXHIBIT
AREA OF DEVELOPMENT
SHEET FLOW
CONCRETE CURB & GUTTER
PUBLIC STORM DRAIN INLET
PUBLIC STORM DRAIN INLET
3987- THE WEISS & LAVINE RESIDENCE
1
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
1 POC 1 0.02 INITIAL 10 2.45 0.90 0.04 0.04
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
2 POC 2 0.03 INITIAL 10 2.45 0.70 0.05 0.05
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
3 POC 3 0.68 INITIAL 10 2.45 0.60 0.99 0.99
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
4 POC 4 0.06 INITIAL 10 2.45 0.81 0.12 0.12
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
5 POC 5 0.02 INITIAL 10 2.45 0.90 0.05 0.05
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
6 POC 6 0.08 INITIAL 10 2.45 0.90 0.18 0.18
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
7 POC 7 0.01 INITIAL 10 2.45 0.90 0.02 0.02
IntensityRunnoff
CoefficientFlow
Tributary Point of Conc. Area (ac.) Avg. Slope % Length Velocity fpsTravel Time
(sec.)Total Time I C_comp IAC Q (cfs)
8 POC 8 0.04 INITIAL 10 2.45 0.84 0.08 0.08
2
Post-Development - Tributary 7 Time of Concentration
Post-Development - Tributary 8 Time of Concentration
Post-Development - Tributary 4 Time of Concentration
Post-Development - Tributary 5 Time of Concentration
Post-Development - Tributary 6 Time of Concentration
Post-Development - Tributary 3 Time of Concentration
Post-Development - Tributary 1 Time of Concentration
Post-Development - Tributary 2 Time of Concentration
Triburary AcresPost-Dev. Imp.
Acres
Post-Dev.
Vegitated
Acres
C_comp Total Q (cfs)
1 0.02 0.02 0.00 0.90 POC 1 4" PIPE 0.11
2 0.03 0.01 0.01 0.70 POC 2 SLOT DRAIN 0.05
3 0.68 0.16 0.52 0.60 POC 3 (E) PIPE NO CALC 0.99
4 0.06 0.05 0.01 0.81 POC 4 CATCH BASIN 0.12
5 0.02 0.02 0.00 0.90 POC 5 SLOT DRAIN 0.05
6 0.08 0.08 0.00 0.90 4" PIPE 0.18
7 0.01 0.01 0.00 0.90 6" PIPE 0.43
8 0.04 0.03 0.01 0.84 POC 7 SLOT DRAIN 0.02
Total Watershed 0.94 POC 8 6" SWALE 1.42
C_vegitated 0.50 C_impervious 0.90
POC / Design
5
6
7
3, 4, 5, 6, & 8
POC 64, 5, 6 & 8
Tributaries Receiving
1, 2 & 7
2
3
4
Channel Report
Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Wednesday, Dec 2 2020
4 INCH PIPE
CircularDiameter (ft) = 0.33
Invert Elev (ft) = 100.00Slope (%) = 5.00N-Value = 0.012
CalculationsCompute by: Known QKnown Q (cfs) = 0.16
HighlightedDepth (ft) = 0.14Q (cfs) = 0.160Area (sqft) = 0.03Velocity (ft/s) = 4.62Wetted Perim (ft) = 0.47Crit Depth, Yc (ft) = 0.23Top Width (ft) = 0.33EGL (ft) = 0.47
0 1
Elev (ft)Section
99.75
100.00
100.25
100.50
100.75
101.00
Reach (ft)
Channel Report
Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Wednesday, Dec 2 2020
SLOT DRAIN
RectangularBottom Width (ft) = 0.17Total Depth (ft) = 0.50
Invert Elev (ft) = 100.00Slope (%) = 0.70N-Value = 0.012
CalculationsCompute by: Known QKnown Q (cfs) = 0.05
HighlightedDepth (ft) = 0.19Q (cfs) = 0.050Area (sqft) = 0.03Velocity (ft/s) = 1.55Wetted Perim (ft) = 0.55Crit Depth, Yc (ft) = 0.14Top Width (ft) = 0.17EGL (ft) = 0.23
0 .1 .2 .3 .4
Elev (ft) Depth (ft)Section
99.75 -0.25
100.00 0.00
100.25 0.25
100.50 0.50
100.75 0.75
101.00 1.00
Reach (ft)
Channel Report
Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Wednesday, Dec 2 2020
4 INCH PIPE
CircularDiameter (ft) = 0.33
Invert Elev (ft) = 100.00Slope (%) = 5.00N-Value = 0.012
CalculationsCompute by: Known QKnown Q (cfs) = 0.18
HighlightedDepth (ft) = 0.15Q (cfs) = 0.180Area (sqft) = 0.04Velocity (ft/s) = 4.76Wetted Perim (ft) = 0.49Crit Depth, Yc (ft) = 0.24Top Width (ft) = 0.33EGL (ft) = 0.50
0 1
Elev (ft)Section
99.75
100.00
100.25
100.50
100.75
101.00
Reach (ft)
Channel Report
Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Wednesday, Dec 2 2020
6 INCH PIPE
CircularDiameter (ft) = 0.50
Invert Elev (ft) = 100.00Slope (%) = 5.00N-Value = 0.012
CalculationsCompute by: Known QKnown Q (cfs) = 0.38
HighlightedDepth (ft) = 0.19Q (cfs) = 0.380Area (sqft) = 0.07Velocity (ft/s) = 5.54Wetted Perim (ft) = 0.66Crit Depth, Yc (ft) = 0.32Top Width (ft) = 0.49EGL (ft) = 0.67
0 1
Elev (ft)Section
99.75
100.00
100.25
100.50
100.75
101.00
Reach (ft)
Channel Report
Hydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Wednesday, Dec 2 2020
6 INCH ROCK LINED SWALE
TriangularSide Slopes (z:1) = 2.00, 2.00Total Depth (ft) = 0.50
Invert Elev (ft) = 100.00Slope (%) = 50.00N-Value = 0.035
CalculationsCompute by: Known QKnown Q (cfs) = 1.21
HighlightedDepth (ft) = 0.29Q (cfs) = 1.210Area (sqft) = 0.17Velocity (ft/s) = 7.19Wetted Perim (ft) = 1.30Crit Depth, Yc (ft) = 0.47Top Width (ft) = 1.16EGL (ft) = 1.09
0 .5 1 1.5 2 2.5 3
Elev (ft) Depth (ft)Section
99.75 -0.25
100.00 0.00
100.25 0.25
100.50 0.50
100.75 0.75
101.00 1.00
Reach (ft)
3 of 7
12” CATCH BASIN
Part #: 1200, 1203, 1207
GRATE CAPACITIES
Grate Number(s) Description Flow Rate with ½” Head
1210, 1211, 1212,
1212S
12” x 12” Square Grate 155.28 GPM
1211* 12” x 12” Square Grate 157.79 GPM
1213 12” x 12” Square Cast Iron Grate 113.80 GPM
1215 12” x 12” Square Galvanized Steel
Grate
348.07 GPM
1280, 1290 12’ x 12” Atrium Grate 154.79 GPM
1218, 1218S,
1218GR, 1218GY
12” Botanical Plastic 74.77 GPM
1218CI 12” Botanical Cast Iron 76.60 GPM
1224, 1224S,
1224GR, 1224GY
12” Wave Plastic 78.53 GPM
1224CI 12” Wave Cast Iron 78.31 GPM
OUTLET FLOW CAPACITIES
Part # Flow Rate per Outlet
1242, 1243 78.10
1245 Top: 70.49 GPM
Middle: 76.30 GPM
Bottom: 83.41 GPM
1266 247.12 GPM
1889 238.20 GPM
6 INCH
NOAA Atlas 14, Volume 6, Version 2 Location name: San Rafael, California, USA*
Latitude: 37.9721°, Longitude: -122.502° Elevation: 75.03 ft**
* source: ESRI Maps ** source: USGS
POINT PRECIPITATION FREQUENCY ESTIMATES
Sanja Perica, Sarah Dietz, Sarah Heim, Lillian Hiner, Kazungu Maitaria, Deborah Martin, SandraPavlovic, Ishani Roy, Carl Trypaluk, Dale Unruh, Fenglin Yan, Michael Yekta, Tan Zhao, Geoffrey
Bonnin, Daniel Brewer, Li-Chuan Chen, Tye Parzybok, John Yarchoan
NOAA, National Weather Service, Silver Spring, Maryland
PF_tabular | PF_graphical | Maps_&_aerials
PF tabularPDS-based point precipitation frequency estimates with 90% confidence intervals (in inches/hour)1
DurationAverage recurrence interval (years)
1 2 5 10 25 50 100 200 500 1000
5-min 1.85(1.64‑2.09)
2.28(2.03‑2.59)
2.89(2.57‑3.30)
3.43(3.01‑3.94)
4.20(3.54‑5.03)
4.82(3.97‑5.93)
5.51(4.40‑6.97)
6.24(4.82‑8.16)
7.31(5.38‑10.0)
8.17(5.77‑11.7)
10-min 1.32(1.18‑1.50)
1.63(1.45‑1.85)
2.08(1.84‑2.36)
2.45(2.15‑2.83)
3.01(2.54‑3.61)
3.46(2.84‑4.25)
3.95(3.16‑4.99)
4.48(3.46‑5.85)
5.23(3.85‑7.19)
5.86(4.14‑8.38)
15-min 1.06(0.948‑1.21)
1.32(1.17‑1.50)
1.67(1.48‑1.90)
1.98(1.74‑2.28)
2.42(2.04‑2.90)
2.79(2.30‑3.43)
3.18(2.54‑4.02)
3.61(2.79‑4.72)
4.22(3.10‑5.80)
4.72(3.34‑6.75)
30-min 0.784(0.698‑0.888)
0.970(0.862‑1.10)
1.23(1.09‑1.40)
1.46(1.28‑1.68)
1.78(1.50‑2.14)
2.05(1.69‑2.52)
2.34(1.87‑2.96)
2.65(2.05‑3.47)
3.10(2.28‑4.26)
3.47(2.45‑4.97)
60-min 0.560(0.499‑0.635)
0.693(0.617‑0.787)
0.880(0.780‑1.00)
1.04(0.914‑1.20)
1.27(1.08‑1.53)
1.47(1.21‑1.80)
1.67(1.34‑2.12)
1.90(1.47‑2.48)
2.22(1.63‑3.05)
2.48(1.75‑3.55)
2-hr 0.420(0.374‑0.476)
0.520(0.462‑0.590)
0.661(0.586‑0.752)
0.782(0.687‑0.900)
0.958(0.808‑1.15)
1.10(0.907‑1.35)
1.26(1.00‑1.59)
1.42(1.10‑1.86)
1.67(1.22‑2.29)
1.86(1.32‑2.66)
3-hr 0.355(0.317‑0.403)
0.440(0.392‑0.500)
0.558(0.495‑0.636)
0.661(0.580‑0.760)
0.808(0.682‑0.968)
0.929(0.764‑1.14)
1.06(0.845‑1.34)
1.20(0.925‑1.57)
1.40(1.03‑1.92)
1.56(1.10‑2.23)
6-hr 0.262(0.233‑0.297)
0.325(0.289‑0.369)
0.411(0.365‑0.469)
0.486(0.427‑0.559)
0.592(0.499‑0.709)
0.678(0.558‑0.833)
0.769(0.615‑0.973)
0.868(0.670‑1.13)
1.01(0.741‑1.38)
1.12(0.792‑1.60)
12-hr 0.185(0.165‑0.209)
0.231(0.205‑0.262)
0.294(0.260‑0.334)
0.347(0.304‑0.399)
0.422(0.355‑0.505)
0.481(0.396‑0.591)
0.544(0.435‑0.688)
0.611(0.472‑0.798)
0.704(0.518‑0.967)
0.779(0.551‑1.12)
24-hr 0.126(0.113‑0.143)
0.159(0.143‑0.180)
0.203(0.182‑0.231)
0.240(0.214‑0.275)
0.291(0.252‑0.344)
0.332(0.281‑0.399)
0.374(0.310‑0.459)
0.418(0.338‑0.526)
0.479(0.373‑0.626)
0.527(0.398‑0.712)
2-day 0.084(0.076‑0.095)
0.106(0.096‑0.121)
0.136(0.122‑0.155)
0.160(0.143‑0.184)
0.194(0.168‑0.229)
0.220(0.186‑0.264)
0.247(0.205‑0.303)
0.274(0.222‑0.346)
0.312(0.244‑0.409)
0.342(0.259‑0.462)
3-day 0.064(0.058‑0.073)
0.081(0.073‑0.092)
0.104(0.093‑0.118)
0.122(0.109‑0.140)
0.147(0.127‑0.174)
0.166(0.141‑0.200)
0.186(0.155‑0.229)
0.207(0.167‑0.261)
0.234(0.183‑0.307)
0.256(0.194‑0.346)
4-day 0.053(0.048‑0.060)
0.067(0.060‑0.076)
0.086(0.077‑0.098)
0.101(0.090‑0.116)
0.121(0.105‑0.143)
0.137(0.116‑0.165)
0.153(0.127‑0.188)
0.170(0.137‑0.214)
0.192(0.150‑0.251)
0.209(0.158‑0.282)
7-day 0.037(0.033‑0.042)
0.047(0.042‑0.053)
0.060(0.053‑0.068)
0.070(0.062‑0.080)
0.084(0.073‑0.099)
0.095(0.080‑0.114)
0.105(0.087‑0.129)
0.116(0.094‑0.146)
0.131(0.102‑0.171)
0.142(0.107‑0.192)
10-day 0.030(0.027‑0.034)
0.038(0.034‑0.043)
0.049(0.044‑0.055)
0.057(0.051‑0.065)
0.068(0.059‑0.080)
0.077(0.065‑0.092)
0.085(0.070‑0.104)
0.093(0.076‑0.118)
0.104(0.081‑0.137)
0.113(0.085‑0.152)
20-day 0.020(0.018‑0.022)
0.025(0.023‑0.029)
0.032(0.029‑0.037)
0.037(0.033‑0.043)
0.044(0.038‑0.052)
0.049(0.042‑0.059)
0.054(0.045‑0.067)
0.059(0.048‑0.074)
0.065(0.051‑0.085)
0.069(0.052‑0.094)
30-day 0.016(0.014‑0.018)
0.020(0.018‑0.023)
0.026(0.023‑0.030)
0.030(0.027‑0.035)
0.035(0.031‑0.042)
0.039(0.033‑0.047)
0.043(0.036‑0.053)
0.046(0.038‑0.058)
0.051(0.039‑0.066)
0.054(0.041‑0.072)
45-day 0.013(0.012‑0.015)
0.017(0.015‑0.019)
0.021(0.019‑0.024)
0.025(0.022‑0.028)
0.029(0.025‑0.034)
0.032(0.027‑0.038)
0.034(0.028‑0.042)
0.037(0.030‑0.046)
0.040(0.031‑0.052)
0.042(0.032‑0.057)
60-day 0.012(0.011‑0.013)
0.015(0.014‑0.017)
0.019(0.017‑0.022)
0.022(0.019‑0.025)
0.025(0.022‑0.030)
0.028(0.024‑0.033)
0.030(0.025‑0.037)
0.032(0.026‑0.040)
0.034(0.027‑0.045)
0.036(0.027‑0.049)
1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS).Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for agiven duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are notchecked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values.Please refer to NOAA Atlas 14 document for more information.
Back to Top
+–
3km
2mi
Large scale terrain
+–
100km
60mi
M
O
N
T
E
C
I
T
O
R
D
DATE: 11/30/20
JOB: 3987
DRAWN BY: AC
HYDROLOGY MAP EXHIBIT - 10 YEAR STORM EVENT
Z:\H
LS-P
ro
jects\3987 W
eiss-M
on
tecito
R
d\D
WG
\C
IV
IL\3987-H
YD
RO
C
3D
2018.d
wg
, 11/30/2020 3:39:57 P
M
29,468.09 sf
3,598.88 sf
1,302.58 sf
2,542.72 sf
1,755.06 sf
985.47 sf
348.44 sf
786 sf
12
3 45 6
8
7
(P) ROCKLINED SWALE
(P) 4" PIPE
(P) 4" PIPE
(P) SLOT DRAIN
(P) 6" PIPE
(P) 4" PIPE