DraughtonDraughton1616thth April 2014 April 2014
John MooreJohn MooreChief Chief ExecutiveExecutiveNYnet
Areas we will cover• BT rollout – Phase 1• Lessons learnt to date• How to address final 10%? • Phase 2• Phase 3• Demand stimulation
Reminder of our Vision
Access to high-quality broadbandfor
100% of North Yorkshire premisesby
2017
To secure >> than average levels of broadband take-up, both residentially and by SMEs
BT Rollout – Phase 1• Key contract terms (Intervention Area)• 77% access to min 25Mbps • 100% access to min 2Mbps• Completion by October 2014
• Mostly FTTC• Some FTTP (3%)
cont …
BT Rollout – Phase 1• Headlines• 462+ of 670 cabinets completed
• 110,000+ of 150,000 total premises now able to access superfast speeds (25+Mbps)