+ All Categories
Home > Documents > Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Date post: 23-Feb-2016
Category:
Upload: mauli
View: 24 times
Download: 0 times
Share this document with a friend
Description:
Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator American Structurepoint , Inc. January 22, 2014. Introduction…. What is a drawing of sufficient detail? What is the purpose of a drawing of sufficient detail? - PowerPoint PPT Presentation
Popular Tags:
32
Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator American Structurepoint, Inc. January 22, 2014
Transcript
Page 1: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawings of Sufficient Detail

Natalie Parks, P.E.Utility & Railroad CoordinatorAmerican Structurepoint, Inc.

January 22, 2014

Page 2: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Introduction… What is a drawing of sufficient detail? What is the purpose of a drawing of

sufficient detail? What are the components of a drawing of

sufficient detail? Why is a drawing of sufficient detail

important? What happens when a utility cannot or will

not produce drawings of sufficient detail?

Page 3: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Question…

What is a drawing of sufficient detail?

Page 4: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator
Page 5: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer…

105 IAC 13-3-3(c)6 states that thework plan shall include the following…

“A drawing of sufficient detail and scale

to show the proposed location of the facility relocation.”

Page 6: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer…According to the rule, the answer is…

Detailed Scaled Shows proposed facility relocation

Page 7: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Example 1

Page 8: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Let’s Discuss…

Looking at the rule’s definition, is this drawing a drawing of sufficient detail? Is this drawing detailed? Is this drawing to scale? Does this drawing show what the

proposed relocation is?

Page 9: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Example 2…

Page 10: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Let’s Discuss…

Looking at the rule’s definition, is this drawing a drawing of sufficient detail? Is this drawing detailed? Is this drawing to scale? Does this drawing show what the

proposed relocation is?

Page 11: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Question…

What is the purpose of the drawing?

Page 12: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer…

To enable the utility coordinator and design staff to determine if the proposed facility relocation will resolve all known facility conflicts with the proposed design without causing additional conflicts with other utilities’ facilities or with the project.

Page 13: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Let’s Discuss…

Which drawing assists you in achieving the purpose and need for a drawing of sufficient detail?

Why?

Page 14: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Question…

What are the components of a

drawing of sufficient detail?

Page 15: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail Must use the INDOT Plans

“INDOT PLANS” REFERS TO THE USE OF THE DESIGN PROFILE,

ALIGMENT, STATIONS, RIGHT-OF-WAY.

Page 16: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail How can they be submitted?

May mark up the PDF provided by the Designer

May mark up a hard copy provided by the Designer

May provide a CAD file that uses the Base files as provided by the Designer

May provide a pdf of plans on their title block

Page 17: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail Uses the project alignment for

stations and offsets Poles, anchors, and guy wires Fire hydrants Crossings-station only unless termini are

in the right-of-way Vaults, hand holes, manholes Bore Pits Control cabinets, pedestals

Page 18: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail

Provides elevations For all underground facilities Maximum elevation at top of facility

when under Pavement, structure, ditch Minimum at bottom of facility between

facilities NOT x’ below grade – which grade?

Page 19: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail Provides cross sections showing

facilities Distinguishes between:

Proposed facilities Existing facilities Retired facilities Existing facilities to remain Existing facilities to be removed

Distinguishes between aerial and underground

Page 20: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail Method of installation

Direct Bury Bore

Type and size of pipe to be installed Any critical clearances needed Notes any areas of concern

especially to facilities remaining in place EX. – holding a pole, holding a pipe, etc.

Page 21: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Drawing of Sufficient Detail Helpful hints…

Develop a checklist to use while reviewing drawings to ensure minimums are provided

Best Practices list developed by INDOT

Page 22: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

A Note about “abandoning facilities” A utility may not abandon their facilities They may “retire in place” The may designate a facility as being

“temporarily out of service.” For either of the above designations we

should place a red “X” over the facilities

Drawing of Sufficient Detail

Page 23: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

CAD files versus PDF versus Hard Copy

Some utilities will request CAD files Ask what platform and version is used Many consultants will ask for an

electronic file transfer agreement – check with your company to determine if this is required.

Some utilities will mark up a pdf This is okay if they provide the

necessary detail Some utilities request hard copies

Drawing of Sufficient Detail

Page 24: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Question…

Why is a drawing of sufficient detail

important?

Page 25: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer… Must be able to determine WHERE

the facility will be as it relates to the proposed design

Must be able to determine if required clearances are met

Must be able to ensure environmental commitments have not been compromised

Page 26: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer… Must be able to identify potential

constructability issues Must be able to ensure that facilities

are within proposed right-of-way Must be able to verify and/or identify

conflicts with other facility relocations

Page 27: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Question…

What happens when a utility cannot or will

not produce drawings of sufficient detail?

Page 28: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer… Some utilities do not have the

personnel, expertise, or experience to produce a drawing of sufficient detail Let the project manager know Include in the risk report Meet with a representative on site Discuss the specific issues related to the

need for relocation Discuss options for relocation Determine if there is any way to include

the relocation in the project

Page 29: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer… Some utilities refuse to provide a

drawing of sufficient detail Let the project manager know Include in the risk report Meet with a representative on site Identify why they will not provide a

drawing Review the plans with the utility

representative and work together to determine with the best of our ability the station and offset of the facility

Provide minimum elevations if necessary

Page 30: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Answer… Try to gain concurrence from the

utility representative when providing the station, offset, and elevation

Contact a supervisor at the utility if cooperation is still not achieved

Document EVERYTHING

Page 31: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Note… The rule does NOT make it clear what

a “drawing of sufficient detail” is. Utilities may have a different

perspective or definition. Utilities have not received training on

what is expected. Work with the utilities to achieve a

drawing of sufficient detail.

Page 32: Drawings of Sufficient Detail Natalie Parks, P.E. Utility & Railroad Coordinator

Questions?

Thank you!


Recommended