Date post: | 09-Apr-2018 |
Category: |
Documents |
Upload: | phungkhanh |
View: | 215 times |
Download: | 2 times |
WaterNI 2018
Planning to Meet Belfast’s Drainage and Wastewater
Management Needs: Challenges and Progress
Paddy Brow - NI Water Head of LWWP
Enhance GrowProtectV3 20 Feb 2018
Enhance GrowProtect
Contents
1) Introduction
2) Progress on NI Water’s work packages
3) Planning for Implementation Delivery
4) Recognition & Support
5) Conclusions
Aim: to develop a Strategic Drainage Infrastructure Plan (SDIP) for Belfast to
protect against flood risk, enhance the environment and provide the increased
drainage and wastewater treatment capacity necessary to enable the economy to
grow
Approach: In accordance with ‘Sustainable Water’, the NI Executive’s Long Term
Water Strategy, it is following a catchment based integrated planning approach.
This is focused on developing shared sustainable solutions that will provide a wide
range of benefits, at reduced cost and disruption
Enhance GrowProtect
Creation approved by the NI Executive in 2014, commenced 2015
Belfast Drainage & Sewerage Issues: Problem
Definition
Wall?
Snake?
Tree?
Rope?
Fan?
Developed from a slide used by Alan Elwood, Risk and Reward Ltd
Rotten Egg?Spear?
Belfast Drainage & Sewerage Issues: Problem
Definition
Inadequate Capacity (Sewers, WWPS, WWTW)
Surface Water Flooding
Unsatisfactory Intermittent Discharges
Asset Deterioration
Fluvial (River) Flooding
Out of Sewer Flooding
OdourInadequate Dilution &
Dispersion of Effluent
Siltation of Sewers and Outfalls
Infiltration
FOG
Higher Water Quality
Standards
Constrained Opex
DfI Minister
Programme ManagerStuart Wightman
DfI Permanent Sec.Peter May
LWWP SROFiona McCandless
NI Executive
15 Work Packages (DfI WDPD, DfI Rivers & Roads, NI Water, NIEA, BCC)
DfI W&DP DirectorLinda MacHugh
LWWP Board
LWWP
Governance
Rivers Roads
Water & Drainage Policy Division
Living With Water Programme
Work Packages
WP Title Lead Org.
1 Belfast Capital Works Programmes, Appraisals, Resources: Gap Analysis &
Integration
DfI WDPD
2 Private Drainage Infrastructure DfI Rivers
3 NI Storm Separation Pilot Projects NI Water
4 Belfast Environmental Drivers NIEA
5 Catchment Modelling NI Water
6 Drainage Area Planning NI Water
7 Inner Belfast Lough WWTW Appraisals NI Water
8 Belfast Roads and Streets Drainage Investment TransportNI
9 Belfast Watercourses Investment DfI Rivers
10 Belfast Lough Diffused Pollution Assessment and Reduction NIEA
11 Belfast Strategic Drainage Infrastructure Plan (Belfast SDIP) DfI WDPD
12 Belfast SDIP Financing DfI WDPD
13 Stakeholder Engagement DfI WDPD
14 Belfast Strategic Environmental Assessment (SEA) & Habitats Risk Assessment
(HRA)
DfI WDPD
15 NI Integrated Drainage Investment Planning Guide & Programme DfI WDPD
Work Package 5 Catchment Modelling - Importance & Scope
Important as will inform optimum:
1) WWTW Discharge Standard
2) Storm Tank Sizing
3) Outfall Design
4) Other diffused pollution reduction measures+ Provide information for Marine Licence applications
WP5 Steering Group - Role
1) Develop strategy for catchment modelling and it’s procurement
2) Oversee procurement and management of the modelling
3) Oversee that contributing work packages are aligned and managed
WP5 Steering Group (since Sept 2015)
LWWP WP5 Catchment (Ecosystem) Modelling: Key Stages for Nutrient &
Bacteria Reduction Solution Development
Qu
alit
y p
er a
nn
um
Stage 1Determine the Overall
Quality & Carry out Source Apportionment
Stage 2Determine Quantum
Compatible with WFD Good Status
Stage 3 Determine Responsibility Aligned to Source
Apportionment (WFD Polluter Pays Principle) & Optimum Measures to Reduce
In proportion to Stage 1 findings:1) NI Water improvements
to sewers & WWTW2) Agricultural measures3) Reductions from other
sources (eg privately owned WWTW)
To Be Removed
May Remain
NI Water
Agricultural
Other
Greenisland(PE c13,000)
WP7 Inner Belfast Lough WWTW Appraisal Studies
Whitehouse(PE c90,000)
Belfast(PE c500,000)
Kinnegar(PE c85,000)
Carrickfergus(PE c33,000)
Seahill(PE c7,000)
Appraisal WWTWs Included
A Belfast, Whitehouse, Kinnegar
B Carrickfergus & Greenisland
C Seahill (for Bathing Waters)Transfer part of catchment?
Transfer part of catchment?
Designated Bathing Waters:• Helens Bay• Crawfordsburn• Ballyholme
B4
Work Package 7: Belfast WWTW Capacity Challenge
(Informed to Belfast City Council)
WWTW Loading
(Population Equivalent)
Time
Design Capacity
Chemically Enhanced Capacity
290,000
?
Projected increase in loadings
Today 2021Currently projected date
WWTW may move into non-compliance
‘Beneficial Use’ date of upgraded WWTW
(Feb 2027)
Period during which contingency measures required
Current
Currently 20 to 30% of the catchment load is not reaching the WWTW
Belfast WWTW Compliance
Phase 0: Maintain Compliance Until Phase 1 Complete
(Detailed Risk Mitigation Plan
Developed, Being Implemented)
Capital Investment Phase 1: Maintain Compliance with Existing UWWTD
Consent(start April 2021)
Capital Investment Phase 2: Comply with future WFD
Based Needs Consent incl. Storm Tanks
(to end Feb 2027)
This will allow sewerage network improvements to proceed without pushing WWTW into non-compliance
WP7 Belfast WWTW Appraisal: Nereda
WWTW Process Pilot during 2018
Key AimsTo inform the LWWP WP7 Belfast WWTW Appraisal by proving that Nereda provides a viable small footprint option for expansion of Belfast within existing NI Water lands, testing performance against key local factors such as:• Nature of catchment sewage and first flush
events• FOG• Sludge dewatering centrifuge centrate• Imported trade effluent
Arriving March 2018
Belfast WWTW
Constrained space available for increased capacity
Nereda has the potential to:• Double biological capacity by construction of the main Nereda process tanks on Bretland area – facilitating
compliance with existing standard during construction by keeping all current lanes operational • Achieve the future more stringent standards• Allow existing final settlement tanks to be converted to storm tanks• Allows area occupied by aeration lanes to be used for odour control or tertiary treatment (if necessary)
At this stage Nereda it looks to be the most cost effective whole life cost solution. The design build contract will allow a number of processes and invite innovation.
WP6 Drainage Area Planning – Resolving the ‘Busted Flush’
1) 2014 Belfast WWTW Glenmachan Sub-catchment Drainage Area Plan (DAP) recommended to
address out of sewer flooding and pollution would require:
• Additional storm tank 8 Olympic sized swimming pools, plus all Upper Falls WWTW tanks to
become storm tanks.
• Belfast WWTW treatment capacity increase by 280 l/s
2) Glenmachan represents 15% of total Belfast catchment. If approach applied across whole
catchment it would require:
• 53 Olympic sized swimming pools
• Treatment capacity increase 2 cubic metre per second
3) If all Belfast WWTW Final Settlement Tanks converted to storm tanks 26 Olympic sized swimming
pools
4) This illustrates that the LWWP must drive down any increase in FFT & storm storage through
storm separation and modelling.
‘Busted Flush’ – Key Problems
1) Very high capital costs
2) Inadequate space to build
3) Inadequate treatment capacity
4) Unsustainable operational costs
How Can We Avoid ‘Busted Flush’ Solutions?
a) Increased rates of stormwater separation – attenuate stormwater on the surface,
increase the capacity of watercourses
b) Reduce infiltration into foul and combined sewers
c) Design storm tanks to treat spills
d) Modelling to increased frequency of permitted spills
e) Convey storm overflow discharges to less sensitive watercourses / treatment wetlands
= WP11 Integrated Drainage Planning
(Led by DfI, includes DfI Roads & Rivers, NI Water, NIEA, Belfast City Council)
Inner Lough WWTWs Phase 1 (UWWTD Compliance – to start April 2021)
Belfast WWTW
Inner Lough WWTWs Phase 2(WFD needs - commission by Feb 2027)A: Belfast, Kinnegar & WhitehouseB: Carrickfergus & GreenislandC: Seahill
Capital Delivery
Business Justification
OBC
FBC
Belfast Tidal Flood Alleviation Scheme (complete by 2022)
LWWPStrategic Outline
Case(2017)
2021 to 2027 WFD RBMP catchment measures to reduce diffuse pollution
OBC FBC
Surveys, Modelling, Planning, Appraisal, Business Cases
Integrated Drainage Improvements (2019-2027)
The Ten Year Programme
Private Drainage Infra Surveys
Catchment Modelling
DfI led Integrated Drainage Investment Planning
WWTW Appraisals
Belfast SDI Plan Development
Year
Exp
en
dit
ure
Per
An
nu
m (
£m
)
Indicative High Level Spend Profile (£886m)
0
50
100
150
200
250
17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27
Defining the Shape of the Igloo - Development of the
PC21 Business Plan & LWWP Belfast Strategic
Drainage Infrastructure Plan are Inter-Dependant
PC15 Business Plan PC21 Business Plan
LWWP
Q2: Which Belfast SDIP
elements will be funded
through PC21 BP?
Time
£
Capital
Q1: Belfast SDIP
Expenditure Profile?
PJ Brow V1 19/10/17
Building Ireland's FutureNational Development Plan 2018-2027
(Launched 16 Feb 2018)
Includes €8.5bn* to be invested by Irish Water
Comparative Analysis
Population of RoI = 4.76m Population of NI = 1.85m (Ratio = 2.6:1)
€8.5bn = £7.52bn = £752m per annum = £158m per annum / million population.
For the NI Population the would equate to £293m (excl. surface water sewers*)
Large Irish Water Projects
• Dublin Wastewater (Greater Dublin Drainage, Ringsend WWTW, North Docklands Sewerage) = €708m
• Eastern and Midlands Water Supply Project = €1.2 to 1.3bn
*€8.5bn excludes investment that may be necessary by RoI Councils on surface water sewers (for which Irish Water is not responsible).
LWWP
Belfast Strategic Drainage
Infrastructure Plan
Belfast Agenda
Local Development
Plan
Economic Growth
Smart Cities
City Deal
Reservoirs & DamsAmenity
Provision
Community Greenways
Blue Green Infrastructure
Resilient Cities
Social Cohesion
Tourism & Recreation
Recognition: Resilient Drainage & Wastewater Infrastructure
Necessary to Achieve Belfast City Council Aims
Purpose: Strategic level guide to inform investment decisions & development contributions
Aims: Facilitate development of multi-functional network to provide a multitude of recreational, environmental ecological, socio-cultural and economic benefits for Belfast
Considers: Natural Heritage & Biodiversity, Water (Drainage), Open Space, Hills & Coast, Ecosystem Services
Green & Blue Infrastructure Masterplan (2018)
Local Development Plan
Green & BlueInfra Masterplan
Detailed Strategies (Open Spaces & later others:
SuDs, Greenways, Bio-diversity)
21st Century Drainage Programme
21st Century Drainage ProgrammeDrainage & Wastewater Management Plan Framework
Launch London Sept 2018, Implementation April 2020 across UK
Belfast Strategic Drainage Infrastructure Plan
The Journey
Developed from a slide used by Alan Elwood, Risk and Reward Ltd
Starting Out
Reality
Obstacles to Overcome
New Tools to Build
New Skills to Learn
Commitment & Resilience as Longer & Steeper
1) We are making good progress on plan for Belfast to protect against flooding,
enhance the environment, and enable the economy to grow.
2) Resilient Drainage & Wastewater Infrastructure Necessary to Achieve Belfast City
Council, NIEA & DfI Aims – Aligned to Programme for Government Outcomes
3) Progress enabled by the ongoing support of Participants and Stakeholders.
4) Aim is to complete a final Strategic Drainage Infrastructure Plan in June 2019,
with implementation from 2021 (subject to funding).
Conclusions
Enhance GrowProtect