Drinking Water on Statia
No Permanent Sweet Water Sources:
• Collecting and Storing Rain water• Wells (Brackish)
Drinking Water on Statia
1993 - “General Assessment Cistern Water St.Eustatius” (IWACO)
1996 - “Masterplan Drinking Water Supply St.Eustatius” (Intecma)
1997 - 1st Project Proposal (DEPOS)Project Proposal Denied Advisary Note (IWACO)
1998 - Design Cost Approved
Drinking Water on Statia
2000 - Tender for Production and Distribution facilities
2000 - 2nd Project Proposal submitted2001 - 2nd Project Proposal denied2001 - Project Proposal Temporary Solutions
submitted2001 - Project Proposal Temporary Solutions
submitted
Drinking Water on Statia
2004 - Temporary Solution completed and commissioned:
• SWRO Water Plant 2x 125 m3/day• 250 m3 storage tank by Plant• 1000 m3 storage tank on elev. 110m (Lodi)• Pressure line to storage tank• 2 water trucksTotal investment $ 1.350.000,00
Drinking Water on Statia
2007 - Single Programming Document submitted for 9th EDF
2009 – Preparation tender Documents2010 - Tender and Contract Awarding for
distribution2011 - Start execution2013 - Commissioning distribution
Drinking Water on Statia
• 38 km water lines• 950 house connections• 41 Fire Hydrants• 2 pumping stations