    elcome

    LDRRF Approval Committee

    Meeting

    Sunday| April 6th, 2014

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

  • 7/23/2019 DRR Project in Mongla Pouroshova

    2/14

    Comprehensive DRR Project in Mongla Pouroshova

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Major Hazard:

    Cyclone prone area

    Salinity

    River erosion in some parts

    Vulnerabilities :

    Major cyclones in 1988 and 2007 caused heavy

    damages to settlements and other properties of

    the Pouroshova.

    Due to effect of climate change and lack ofemployment in the neighboring districts, a large of

    people are migrating and coming to this small

    municipality for employment creating unplanned

    urban slums within the city.

    Available resources:

    The Sundarbans

    Mongla port

    Few cottage industries

  • 7/23/2019 DRR Project in Mongla Pouroshova

    3/14

    Background of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    During the devastating cyclone Sidr and Aila, around 1953HHs have

    been affected in the mongla pouroshava itself who has lost their housesand had disruption in the livelihood, mostly living in the urban slums.

    Not only within the municipality itself, a large number of people are

    migrating and coming to this area due to effects of climate change and

    also for better employment from the neighboring districts like Bagerhatand Satkhira.

    This huge number of population are settling within the city forming

    unplanned urban slums occupying major resourceful land of the Mongla

    port and other government entities.

  • 7/23/2019 DRR Project in Mongla Pouroshova

    4/14

    Selection of Beneficiaries and land acquition

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Among this long list of beneficiary, 120HH have been identified andverified in the 1stphase as to be the most vulnerable families living in

    the Balur mat area.

    This Balur mat area is owned by Mongla port, where the HHs are

    residing in shanty houses forming a very unplanned urban slum.

    Recently the port authority issued eviction letter to the slum peoplewhere the port is planning to build a recreational park to attract more

    visitors

    As a result, the slum dwellers are relocating in other parts of the

    municipality forming another urban slum.

    Mongla municipality took initiative to relocate this people and acquired5.06 acre of Khas land from the DC office where they will be relocated.

    This settlement will be built in 2 phases, 1stphase comprising of 120HHs

    with all related facilities.

  • 7/23/2019 DRR Project in Mongla Pouroshova

    5/14

    Location of sites

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Proposed site Present location of the selected beneficiary

  • 7/23/2019 DRR Project in Mongla Pouroshova

    6/14

    Picture of the proposed site

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

  • 7/23/2019 DRR Project in Mongla Pouroshova

    7/14

    Components of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    A Complete Disaster resilient Habitat comprising of: Earth raising of 5.06 acre of land up to 6 : BDT 1,08,52,874

    Cyclone resilient houses (120 HHs@ 2,90,231): BDT 3,48,27,710

    Construction of raised sanitary latrine

    (120@15,328): BDT 18,39,358

    Multipurpose Community: BDT 40,50,878

    Solar panel (120@ 13,800): BDT 16,56,000

    Construction of internal roads (BFS): BDT 15,99,219

    Construction of Mosque: BDT 6,87,999

    Peripheral tree plantation: BDT 1,42,500 IGA support (120@8000) : BDT 9,60,000

    Awareness training (10batch @5000): BDT 50,000

    Total: BDT 5,66,81,538

  • 7/23/2019 DRR Project in Mongla Pouroshova

    8/14

    Acquisition of land by components

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Total 120 Nos. house including latrine area (HH 20x 10 each)

    (latrine 4 x 4)25920 Sft

    Internal road communication 47224 Sft

    Pond 2 nos : (A: 90 x 60); (B: 138 x 55) 12990 Sft

    Playground-1 nos: (138 x 55) 7590 Sft

    community meeting room (80 x 40) 3200 Sft

    Mosque + Graveyard 3575 Sft

    Green space/ cultivable land (999.46 Sft each HH) 119935.2 Sft

    Grand Total 220434.2 Sft

    Total area of land2,20,434Sft, 506Decimal

  • 7/23/2019 DRR Project in Mongla Pouroshova

    9/14

    Complete Layout of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

  • 7/23/2019 DRR Project in Mongla Pouroshova

    10/14

    Design of different components of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

  • 7/23/2019 DRR Project in Mongla Pouroshova

    11/14

    Design of different components of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

  • 7/23/2019 DRR Project in Mongla Pouroshova

    12/14

    Design of different components of the Project

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Front view of MCS Rear view of MCS

  • 7/23/2019 DRR Project in Mongla Pouroshova

    13/14

    Comprehensive Disaster Management Programme (CDMP II)Ministry of Disaster Management & Relief

    Rehabilitation of 120 ultra poor families with a legalentity and the migrated people will have this habitat

    in urban community Unauthorized scattered urban slum will be evicted

    from the municipality.

    Sustainable livelihood will be ensured

  • 7/23/2019 DRR Project in Mongla Pouroshova

    14/14

    Thank you

    For more information contact:

    Comprehensive Disaster Management Programme (CDMP II)

    United Nations Development Programme (UNDP)

    Department of Disaster Management Bhaban (6th Floor)