+ All Categories
Home > Documents > Drum Buffer Rope System

Drum Buffer Rope System

Date post: 27-Mar-2015
Category:
Upload: ashwath-puttur
View: 199 times
Download: 3 times
Share this document with a friend
33
Drum-buffer-rope System Vs Just In Time Systems Production and Operations Management
Transcript
Page 1: Drum Buffer Rope System

Drum-buffer-rope SystemVs

Just In Time Systems

Production and Operations Management

Page 2: Drum Buffer Rope System

DBR system

• DBR is “a planning and control system that regulates the flow of work-in-progress materials at the bottleneck or the capacity constrained resources(CCR) in a productive system”

• To achieve this optimum flow, the entry of materials into production is synchronized with the current production rate of CCR

04/10/2023 2

Page 3: Drum Buffer Rope System

Key terms

• Capacity constraint resource (CCR): Resource with the least capacitylimits the organization's ability to meet product

volume, product mix or demand fluctuationsIt is the least capable resource in the system but

at a the time can still be of higher capacity than the market demand

• Bottleneck: CCR whose capacity or output rate is less than market demand

04/10/2023 3

Page 4: Drum Buffer Rope System

DBR is based on key principles of TOC :

1. Identify The System Bottleneck(s) Physical or Managerial

2. Exploit The Bottleneck(s) Elevating the bottleneck An hour added in bottleneck is an hour for the system

3. Subordinate All Other Decisions To Step 2 Every other component must be adjusted to support maximum effectiveness of the constraint

4. Elevate The Bottleneck(s)Rigorous improvement efforts on constraints to improve their performance

5. Do Not Let Inertia Set In04/10/2023 4

Page 5: Drum Buffer Rope System

Drum:

Capacity constraint resource schedule

It is effectively the master production schedule which establishes the "drum beat" and control for the entire system

linked to market demand

04/10/2023 5

Page 6: Drum Buffer Rope System

60 70 40 60

Capacity Constraint Resource(Drum)

A CB D

04/10/2023 6

Page 7: Drum Buffer Rope System

Buffer:

placed before the CCR ensuring that the constraint is never starved

04/10/2023 7

Page 8: Drum Buffer Rope System

6070 40 60

Capacity Constraint Resource(Drum)

BufferA B C D

time buffer is created to ensure that work-in- progress arrives at the CCR well before it is scheduled to be processed

04/10/2023 8

Page 9: Drum Buffer Rope System

Rope : • Communication from Drum to upstream• connects the CCR to the material release

point• ensures that raw material is not inserted

into the production process at a rate faster than the CCR can accommodate

04/10/2023 9

Page 10: Drum Buffer Rope System

6070 40 60

Capacity Constraint Resource(Drum)

Buffer

Rope

A B DC

04/10/2023 10

Page 11: Drum Buffer Rope System

EXAMPLE

04/10/2023 11

Page 12: Drum Buffer Rope System

Drum-Buffer-Rope System with CCR

Material Release

Schedule

Process ACapacity

800 units/week

Process C Capacity

700 units/week

Process B Capacity

500 units/week

Shipping Schedule

Market Demand650 units/week

CCR (bottleneck)

Non-constraint Non-constraint

04/10/2023 12

Page 13: Drum Buffer Rope System

STEPS

STEP 1:

Identify the CCRs in the system

04/10/2023 13

Page 14: Drum Buffer Rope System

Drum-Buffer-Rope System with CCR

Material Release

Schedule

Process ACapacity 800 units/week

Process C Capacity

700 units/week

Process B Capacity

500 units/week

Shipping Schedule

Market Demand650 units/week

CCR (bottleneck)Non-constraint Non-constraint

04/10/2023 14

Page 15: Drum Buffer Rope System

STEP 2:

Develop a Drum or a schedule for the CCR which is in-line with the needs of the market

04/10/2023 15

Page 16: Drum Buffer Rope System

Drum-Buffer-Rope System with CCR

Material Release

Schedule

Process ACapacity 800 units/week

Process C Capacity

700 units/week

Process B Capacity

500 units/week

Shipping Schedule

Market Demand650 units/week

CCR (bottleneck)Non-constraint Non-constraint

Drum

04/10/2023 16

Page 17: Drum Buffer Rope System

STEP 3:

Create Time-buffers at critical locations

04/10/2023 17

Page 18: Drum Buffer Rope System

Drum-Buffer-Rope System with CCR

Material Release

Schedule

Process ACapacity 800 units/week

Time Buffer

Inventory

Process C Capacity

700 units/week

Process B Capacity

500 units/week

Finished goods

inventoryShipping Schedule

Market demand 650 units/week

Constraint Buffer CCR (bottleneck)

Non-constraint

Non-constraintShipping Buffer

Drum

04/10/2023 18

Page 19: Drum Buffer Rope System

STEP 4:

Use logistical ropes tied to the CCR drum schedules for each resource

04/10/2023 19

Page 20: Drum Buffer Rope System

Drum-Buffer-Rope System with CCR

Material Release

Schedule

Process ACapacity 800 units/week

Time Buffer

Inventory

Process C Capacity

700 units/week

Process B Capacity

500 units/week

Finished goods

inventoryShipping Schedule

Market demand 650 units/week

Constraint Buffer CCR (bottleneck)

Non-constraint

Non-constraintShipping Buffer

DrumROPE

04/10/2023 20

Page 21: Drum Buffer Rope System

Just-In-Time

04/10/2023 21

Page 22: Drum Buffer Rope System

Definition

“A philosophy of manufacturing based on planned elimination of waste and continuous improvement of productivity ……”

04/10/2023 22

Page 23: Drum Buffer Rope System

A repetitive production systemin which the processing and movement of

materials and goods occurjust as they are needed!

04/10/2023 23

Page 24: Drum Buffer Rope System

The Primary Elements

to have only the required inventory when needed

to improve quality to zero defects

to reduce lead times by reducing setup times queue lengths, and lot sizes

to incrementally revise the operations themselves

to accomplish these things at minimum cost04/10/2023 24

Page 25: Drum Buffer Rope System

Pull system (Kanban)

• In a push system, such as an MRP system, we look at the schedule to determine what to produce next

• In a pull system, such as JIT, we look only at the next stage of production and determine what is needed there, and then we produce only that

04/10/2023 25

Page 26: Drum Buffer Rope System

26

Pre-JIT: Traditional Mass Production

Big lot sizesLots of inventory”PUSH” material to nextstage

Lowerper unit

cost

Big purchase shipments

Big “pushes” of finished goodsto warehouses or customers

???

04/10/2023

Page 27: Drum Buffer Rope System

27

Post-JIT: “Lean Production”

Smaller lotsFaster setupsLess inventory, storage space”PULL” material to next stage

Minimalor no

inventoryholding

cost

Smaller shipments

Goods are pulled out ofplant by customer demand

Tighter coordination along the supply chainGoods are pulled along

— only make and ship what is needed

04/10/2023

Page 28: Drum Buffer Rope System

Synonyms

• IBM - Continuous Flow Manufacturing• HP - Stockless Production

- Repetitive Manufacturing System

• GE - Management by Sight• Motorola - Short Cycle Manufacturing• Japanese - The Toyota System• Boeing - Lean Manufacturing

04/10/2023 28

Page 29: Drum Buffer Rope System

Advantages

• Inventory levels are drastically reduced:free up working capital for other projectsless space is neededcustomer responsiveness increases

• Total product cycle time drops• Product quality is improved• Scrap and rework costs go down• Forces managers to fix problems and

eliminate waste .... or it won’t work!04/10/2023 29

Page 30: Drum Buffer Rope System

Summary

• Management philosophy• Pull system though the plant

• WHAT IT IS

• Employee participation• Industrial engineering/basics• Continuing improvement• Total quality control• Small lot sizes

• WHAT IT REQUIRES

• Attacks waste• Exposes problems and bottlenecks• Achieves streamlined production

• WHAT IT DOES

• Stable environment

• WHAT IT ASSUMES

04/10/2023 30

Page 31: Drum Buffer Rope System

JIT & DBR- Comparison

JIT

1. JIT requires the plant to be balanced so each task has the same output level

2. JIT creates batches of equal size

DBR

1. DBR uses a buffer in front of the constrained resource to reduce the build-up of unnecessary WIP and allow for a continuous flow of products through the system

2. DBR allows different sized batches, making it better suited for use in a job order shop that takes custom orders of differing sizes

04/10/2023 31

Page 32: Drum Buffer Rope System

References

• Operations Management – Krajewski, Ritzman, Malhotra

• http://maaw.info/ArticleSummaries/ArtSumHuff01.htm

• http://maaw.info/ArticleSummaries/ArtSumHuff01.htm

04/10/2023 32

Page 33: Drum Buffer Rope System

Thank you

Ashwath PutturBakul Sanakal

SarahVinay Darbi

04/10/2023 33


Recommended