DSC Delivery Sub-Group 23/04/2018
Transcript

DSC Delivery Sub-Group

23/04/2018

Agenda Defect Dashboard

UPD Address Dataset

UNC Validation Roles

Information on defects Change of Class defect

Defect 933

Release 2 update R2 Dashboard

Release 2 – Project Status Update

XRN249 – Data Migration Plan – Approve plan for ChMC to approve Implementation Plan in May 18

meeting.

XRN4361 – Final DSG approval for the R2 Implementation Plan (Option 1) – Clarification on the file

processing date/times

XRN4449 – Customer Testing

Release 3 update R3 Dashboard

CSEPs variance XRN update.

R3 Design Engagement (cont’d)

Market Breaker CP update

Release 3 CP representation overview

Release 3 Plan update including MT timelines and recommendation

Agenda (Continued)

Documentation Changes – February 2019 release

New Changes for Prioritisation Ratification.

Actions

AOB XRN4667A – Provision of Formula Year AQ/SOQ to Proposing User

Negative Consumption within the AQ Calculation

Defect Dashboard

UPD Address Dataset

ADDRS Dataset Change

• Need for change driven by ‘Irrelevant Dataset’ functionality

• At RGMA Implementation – July 2004 – Transco GT were instructed to accept a

generic ONUPD flow

• including datasets that were not relevant at all

• Including datasets provided in a context not relevant to the GT

• As a consequence the UPD GT Hierarchy was different from the ONUPD

hierarchy

• Issue identified in Market Trials – presence of ADDRS dataset was causing

rejection of UPD as Irrelevant Dataset principle was not observed initially

ONUPD RGMA Hierarchy (including Irrelevant Datasets)

Key:

Notify Update

Metering Details

Header TrailerH T

Mandatory data

set

Optional

data set

o

Name

Asset

o1.2.2.5

1.2.2

Register

Details

o1.2.2.3

Address

O

O

Transaction

1

= Site Address

Market

Participant

o1.2.2.4

= Asset Provider

Name

Contact

Mechanism

o1.1.1

1.1.1.1 o

1.1

Meter1.2.2.1 o

Converter1.2.2.2 o

Address Contact

Mechanism

o1.2.3.1 1.2.3.2 o Care

Details

1.2.3.3

= Customer

= Contact

Meter Point1.2

Appointmento1.2.2.6

Readingo1.2.2.431

Nameo1.2.3

o

= MAM

= Unattached Asset Location

= Asset Provider

= MAM

Address

o1.2.2.5.1

Contact

Mechanism

o1.2.2.5.2

Address1.2.1

= Meter Point Address

O

Key:

Notify Update

Metering Details

Header TrailerH T

Mandatory

data set

Optional

data set

o

Name

Asset

o1.2.2.5

1.2.2

Register

Details

o1.2.2.3

Address

O

O

Transaction

1

= Site Address

Market

Participant

o1.2.2.4

= Asset Provider

Name

Contact

Mechanism

o1.1.1

1.1.1.1 o

1.1

Meter1.2.2.1 o

Converter1.2.2.2 o

Address Contact

Mechanism

o1.2.3.1 1.2.3.2 o Care

Details

1.2.3.3

= Customer

= Contact

Meter Point1.2

Appointmento1.2.2.6

Readingo1.2.2.431

Nameo1.2.3

o

= MAM

= Unattached Asset Location

= Asset Provider

= MAM

Address

o1.2.2.5.1

Contact

Mechanism

o1.2.2.5.2

Address1.2.1

= Meter Point Address

O

ONUPD RGMA Hierarchy – showing annotation

Proposed UPD Hierarchy

REGISTER

DETAILS

METER POINT

ASSET

SYSTEM USER TO CDSP

Notify Metering Details ONUPD for Asset Updates or Found, Removed or Missing Assets

Mandatory

Optional

TRANSACTION

METER POINT

ASSET

=Reported

=Installed

=Removed

REGISTER

DETAILS

=Asset Provider

File Type: UPD Version 5FA

Issued 16.04.18

Implementation Release 3

HEADER

NOTIFY UPDATE

METERING

DETAILS

TRAILER

READING

APPOINTMENT

METER

MARKET

PARTICIPANT

CONVERTER

ADDRS

DSG Views Sought….

• Change needs to REMOVE ADDRS dataset from UPD File Format (there is no

context in which it is relevant)

• Proposal to amend annotation to explicitly show irrelevant datasets in hierarchy,

so that these are explicitly shown – this will include:

• NAME

• CONTACT MECHANISM

• CARE DETAILS

• This is not a functional change for Xoserve

• Shipper User views?

• Assessment that no other Users are impacted – is this correct?

• Same principle will be applied to JOB

ONJOB RGMA Hierarchy – showing annotation

Key:

Notify Metering Job

Header Trailer

Meter Point

Asset

Register

Details

Reading

o

1.1

H T

1.1.1

1.1.1.3

1.1.1.3.1 Mandatory data set

Optional data set

= installed

= removed

o

Transaction 1

Address

1.3.1 o

= Meter Worker = Requestor

Market

Participant

1.4 o

Name 1.3 o

Meter 1.1.1.1

Converter 1.1.1.2

= reported

o o Market

Participant

o 1.1.1.4

= Asset Provider

Name o 1.1.1.5

= Meter Worker

Contact

Mechanism

1.3.2 o

o

= Asset Provider

Address

o 1.1.1.5.1

Contact

Mechanism

o 1.1.1.5.2

Appointment

1.2 o

= Job Completed Date

UNC Validation Rules

Revision of Outer Tolerances

April 2018

14

Gas Meter Reads

Update on proposed changes to Outer Tolerance Levels

Summary: The original inner and outer tolerance ranges were based on a best

estimate of what the market believed to be appropriate. Post Nexus Go Live we are

seeing a number of “valid” reads failing to pass the outer tolerance check. This has a

consequential impact on a number of other processes

Latest Updates:

Xoserve don’t have full picture as reads are filtered

by Shippers i.e. reads we know would be rejected

are not sent in to Xoserve

Outer tolerance range was a best guess at Go Live

Analysis of filtered “valid” reads undertaken &

suggested changes to tolerances set out

The revised “Proposed” tolerances will allow

large numbers valid reads to be submitted

Should be a quick and easy change

Band Current Suggested Proposed

1 No Change No change

2 25,001 55,001 55,001

3 10,001 20,001 55,001

4 5,001 20,001 25,001

5 2,001 6,001 7,001

6 501 1,001 1,801

7 401 701 701

8 601 1,001 1,101

9 551 901 901

10 501 1,001 1,001

11 451 701 701

Information on Defects

Change of Class Defect

Defect 933

Release 2 Update

XRN4361 – UK Link Release 2 - Delivery

19th April 2018 Overall Project RAG Status G

Plan/Time Risks and Issues Cost Resources

RAG Status G G G G

Status Explanation

Objective Full project delivery of UK Link Future Release 2 Scope

Plan/Time

• User acceptance testing currently tracking to plan (9 CRs have been signed off), XRN4449 and XRN4249 are tracking 5 days

behind plan however analysis indicates no impact to the overall UAT Completion milestone of 18th May

• Performance testing is scheduled to begin on 30th April

• Clarification on the R2 Implementation approach/plan to be provided at the DSG on 23rd April and approved by ChMC at the

May meeting

• R2 Customer Training plan has been updated with the delivery dates and it will be discussed in DSG on 23rd April

Primary Scope (PS) Update • XRN4449 (Priority Services Code - PSR)

• Xoserve are engaging with individual participants to ensure that the testing process is clear and to answer any questions

• There 3 Shippers, 3 Networks and 3 iGT’s participating in the testing of this change

Secondary Scope (SS) Update • The build is complete for XRN4316

• System and Acceptance testing phases have been merged

• XRN4249 – Address Management • The code implementation was agreed in ChMC and the reps were received on the data migration plan

• Based on the reps received the data migration options to be discussed and agreed in DSG on 23rd April

Risks &

Issues • All risks are under control. The nearest term risk is the completion of Acceptance Testing which is currently low.

Cost • Project delivery costs are tracking to approved budgets

Resources • Weekly monitoring of SME resources supporting multiple demands (e.g. Future Releases, UIG etc) and all requirements are

able to be met

UK Link Release 2 - Plan

Primary

Scope Scoping Initiation Delivery Realisation

Stage Scope

Prioritisation

Scope

Defined Funding Initiation

Analysis

and HLD

Detailed

Design Build

Acceptance

Test

Performance

Test

Regression

Test Imp. PIS

Baseline

Plan 07/06/17 25/07/17 09/08/17 Aug 17 Aug 17 20/11/17 29/01/18 18/05/18 18/05/18 22/06/18

29/06/18

(TBC) 30/07/18

Current Plan 07/06/17 11/10/17 10/01/18 13/12/17 16/01/18 29/01/18

(12/01/18) 16/02/18 18/05/18 18/05/18 22/06/18

29/06/18

(TBC) 08/08/18

Secondary

Scope Scoping Initiation Delivery Realisation

Stage Scope

Prioritisation

Scope

Defined Funding Initiation

Analysis

and HLD

Detailed

Design Build

Acceptance

Test

Performance

Test

Regression

Test Imp. PIS

Baseline

Plan 07/06/17 25/07/17 07/02/18 NA NA 09/02/18 09/03/18 18/05/18 18/05/18 22/06/18

29/06/18

(TBC) 30/07/18

Current Plan 07/06/17 27/11/17 07/02/18 NA NA 16/02/18

09/03/18

09/03/18

30/03/18

06/04/18

18/05/18 18/05/18 22/06/18 29/06/18

(TBC) 08/08/18

RAG Key – Milestones are end dates:

Milestone date forecast to be missed Milestone date forecast to be at risk Milestone date forecast to be met Milestone completed Planning/Milestone date to be confirmed

XRN4361 – UK Link Release 2

9th April DSG Actions

23/04/2018

Actions

Action 1 : Shipper organisations who are participating in the

industry testing need to provide key contact details, for

communications to be issued directly.

Xoserve will be contacting the individual participants to ensure that we

have the details before the testing commences

Action 2 : Implementation plan - LC to confirm the rejection

code per file type.

If files are submitted after the cut off mentioned in the file format

transition plan capturing the last inbound old file format, it will be

rejected as a file level rejection (ERR rejection)

Action 3 : Implementation plan - LC to clearly advise timings

in the lower level implementation plans.

The timings mentioned in the file formats transition plan in Appendix A

refers to the processing times of the files

Decision Required – XRN4249 Migration Plan Approval

APPENDIX - A

UKL Future Release 2

Cutover/Implementation

03rd April 2018

Background

• October 2017 ChMC agreed a [target] R2 implementation of 29th June 2018

• Assessment has identified that 2 CRs in scope of R2 will require data cleansing /migration

activities to be completed (XRN4449 & XRN3283)

• Due to the scale of data migration activities ([2] days) it is recommended that these are

completed during non business days. This removes risk to core business processes (e.g. June

18 Capacity invoice) and allows downstream GT portfolio files to be provided

• Further, it has been identified that there are electricity related changes being implemented on

28th June 2018 and therefore Xoserve has been tasked to consider the option of combining the

electricity change implementation along with R2 on 28th June 2018

Implementation Options Considered

OPTION PROS CONS

Option 1:

Deploy as per agreed

R2 date (Imp

commences at the end

of the business day on

the 29th June 2018

over the weekend of

30th June & 01st July)

1. Aligned to approved Imp dates for R2 CRs

2. Avoids operational impacts as the Release will

be implemented during non-business hours

(maintenance windows)

3. Ensures that data cleansing/migration activities

allow full GT Portfolio files to be created and

submitted over the weekend

4. No CDSP outage required, file processing

updates will follow BAU batch processes

1. Need to gain industry agreement since this is not

aligned to the agreed R2 imp date of 29th June 2018

2. Possible challenges for Shippers to manage the

deployments for Electricity and Gas June 18 changes

during different implementation windows

Option 2:

Deploy R2 on 29th

June 2018 within the

scheduled

maintenance window

1. Aligns to agreed R2 implementation date

1. Imp activities would continue during business hours

and may cause operational impacts (e.g.

performance)

2. Data migration will extend beyond the maintenance

window and may impact on BAU processes

Option 3:

Deploy on 28th June

2018 to align to

Electricity release

1. Aligns to a June 18 implementation for

Electricity and Gas changes for Shippers

1. Does not align to the agreed ChMC R2 date of 29th

June 2018

2. Implementation activities would continue during

business hours and may cause operational impacts

to BAU processes (e.g. performance)

Option 1 - Xoserve Proposed High Level Cutover/Imp Plan

Option 1 File Formats – Input Files Transition Plan

Change ID Last inbound in Old File

Format

XRN4303

(UKLP267)

29/06/2018 - SFN – 20:00PM

XRN3283 29/06/2018 - ACR – 17:00PM

XRN4449

(UKLP273)

29/06/2018 - CNC – 18:00PM

29/06/2018 - CNF – 23:45PM

As the implementation is on 30th June all files in the old file format will be processed by

11:59PM on 29th June 2018

Any files submitted from 30th June 00:00AM should be submitted in the new file format. These

files will be held in AMT and processed only after the after implementation is completed on 01st

July 2018

Any files received in the old file format (eg post the below date/times) after R2 implementation

is complete on 01st July will be rejected

The detail of the file processing times will shared in the lower level cutover/implementation plan

Option 1 File Formats – All impacted File Formats Transition Plan

Note: This table aligns to Option 1 and based on the chosen option this may have to be revisited.

Full details will be defined in the lower level cutover/implementation plan

Change ID Last inbound in Old

File Format (Time =

File Processing)

Last Outbound in Old File

Format

(Time = File Processing)

First Inbound in New File

Format

(Time = File Processing)

First outbound processed in New File

format

(Time = File Processing)

XRN3477

(UKLP112)

NA 29/06/2018

AES – 23:30PM

NA 02/07/2018

AES – 23:30PM

XRN4303

(UKLP267)

29/06/2018

SFN – 20:00PM

29/06/2018

SFR will be processed as usual

as there is no file format change

30/06/2018

SFN – 20:00PM

(Files will be held and

processed on 01/07/18)

01/07/2018

SFR will be processed as usual as there is

no file format change

XRN3283 29/06/2018

ACR – 17:00PM

29/06/2018

ARS will be processed as usual

as there is no file format change

02/07/2018

ACR – 8:00AM

02/07/2018

ARS will be processed as usual as there is

no file format change

XRN4449

(UKLP273)

29/06/2018

CNC – 18:00PM

CNF – 23:45PM

29/06/2018

CNR and CFR will be processed

depending on the batch job

execution but will be completed

by 23:59PM

30/06/2018

IDL – 10:00AM

EDL – 06:00AM

EWS – 06:00AM

02/07/2018

CNC – 18:00PM

CNF – 11:00AM

02/07/2018

CFR – 12:15PM

CNR – 18:00PM

Refresh of Portfolio Files (EQL & EWS) –

17:00PM

01/07/18

IDL – 10:00AM

EDL – 06:00AM

EWS – 06:00AM

APPENDIX - B

XRN4361 – UK Link Release 2

Data Migration Plan for XRN4249

28/03/18

Introduction/Problem Statement

Change XRN4249 is part of the scope of changes planned to be implemented as part of UK

Link Release 2 on the 29th June 2018.

Following analysis of this change, discussion was held with Customers at both ChMC and

DSG. Concerns were raised around the migration of the PAF updates from when the process

was suspended in April 2017. These concerns relate to the volume of updates required over

the period April 17 through to June 18 that could have a downstream impact to Customer

systems and business processes.

To minimise the impact of loading all retrospective PAF updates from April 2017, Xoserve are

recommending a staggered approach to migrate the data over a number of weekends. This

would have checkpoints built into the plan to review the process and agree the volume of

updates to be loaded on the next planned date. This approach is expected to reduce the

impacts to Customer systems and business processes.

Data Migration Plan

No Activity Start Date End Date

1 Code Deployment as part of R2 Cutover/Implementation 30/06/2018 01/07/2018

2 Initial 10K Load 07/07/2018 07/07/2018

3 NAC File / Portfolio Files / Daily Delta on the back of the initial 10K address update 08/07/2018 08/07/2018

4 Data Load to SAP BW 09/07/2018 09/07/2018

5 Agreement with Shippers to load safe volume (100k) records into SAP ISU (BW?) 09/07/2018 13/07/2018

5 Load the safe volume (100k) records 14/07/2018 14/07/2018

6 NAC File / Portfolio Files / Daily Delta on the back of the initial safe volume (100K) address

update

15/07/2018 15/07/2018

7 Daily Load to SAP BW 16/07/2018 16/07/2018

8 Agreement with Shippers to load the next set of safe volume records (100k) into SA 16/07/2018 20/07/2018

9 Load the 2nd set of safe volume (100K) records into SAP ISU 21/07/2018 21/07/2018

10 NAC File / Portfolio Files / Daily Delta on the back of the 2nd set of safe volume (100K)

address update

22/07/2018 22/07/2018

11 Agreement with Shippers to load the remaining updates (approx. 40K) 23/07/2018 27/07/2018

12 GB places the first Regular PAF file received 28/07/2018 28/07/2018

13 Load the remaining updates (approx. 40K) into SAP ISU 28/07/2018 28/07/2018

14 NAC File / Portfolio File / Daily Delta on the back of the remaining (approx. 40K) address

updates

29/07/2018 29/07/2018

15 Daily Load to SAP BW 30/07/2018 30/07/2018

16 PO Team to pull the first regular file from GB Mailing shared area 01/08/2018 01/08/2018

17 First regular file load into SAP ISU (and SAP BW) - Proposed 1st production BAU run 05/08/2018 05/08/2018

18 NAC File / Daily Delta on the back of the first regular PAF file 06/08/2018 06/08/2018

Next Steps

Present options to Customers at the Delivery Sub Group on 09th April

Agree if proposed approach is acceptable to Customers

Split XRN4249 into 2 Change Packs, to agree: Implementation of the SAP ISU solution to reinstate the GB Mailing Update file process

Agreement of the proposed Data Migration Plan to apply updates from April 17 to June 18

Update the DSC ChMC Implementation Plan to reflect XRN4249 code

implementation and Data Migration Plan

Review and approve proposed Data Migration plan with ChMC on 11th April

Release 3 Update

XRN4572 – UK Link Release 3 - Design

23rd April 2018 Overall Project RAG Status G

Plan/Time Risks and Issues Cost Resources

RAG Status A G G G

Status Explanation

Objective Full project delivery of UK Link Future Release 3 Scope

Plan/Time

• Approval of BER for Full Delivery cost and scope achieved at Change Management Committee (ChMC) on 11th April.

• Design commenced on 5th March and due to conclude by first week of May (including CP approval).

• All 14 Change Packs have been published to plan for the CRs in scope of Release 3

• 4 x Change Packs published on 21st March. Representation period closed on 4th April.

• 5 x Change Packs published on 4th April. Representation period closed on 18th April.

• 2 x Change Packs published on 11th April. Representation period open until 25th April.

• 3 x Change Packs published on 16th April. Representation period open until 30th April.

• High Level Design Engagement at last DSG was well received, final session planned for 23rd April.

• Cadent & NG design overview sessions are in progress to ensure all requirements for XRN 4454 are successfully catered

for within Design.

• Initial Market Trial engagement to commence with DSG over the next 8 weeks.

• Build for Release 3 commences on 30h April as per plan.

Risks and

Issues

• XRN4431 agreement on solution at risk (dependent on Change Pack sign off).

• Notional Go Live Date dependent on Design closure and a number of plan variables e.g. Market Trials, training

requirements and cutover/implementation approach

• R3 Delivery plan has a degree of parallelism due to timescales. Risk is closely managed, plan is holding trajectory as

forecast to date.

Cost • Costs are holding approved budget

Resources • Weekly monitoring of SME resources supporting multiple demands (e.g. Future Releases)

• Currently we have SMEs booked to support all Detailed Design discussions.

UK Link Release 3 - Plan

Primary

Scope Scoping Initiation Delivery Realisation

Stage Scope

Prioritisation

Scope

Defined Funding Initiation

Analysis

and HLD

Detailed

Design Build

Acceptance

Test

Performance

Test Market Trials

Regression

Test Imp. PIS

Baseline

Plan 10/01/18 07/02/18 11/04/18 13/04/18 13/04/18 27/04/18 N/A N/A N/A N/A N/A N/A N/A

Current

Plan 10/01/8 07/02/18 11/04/18 13/12/17 13/04/18 02/05/18*

30/04/18

09/07/18 13/08/18 10/09/18 27/08/18 02/10/18 06/01/19

RAG Key – Milestones are end dates:

Milestone date forecast to be missed Milestone date forecast to be at risk Milestone date forecast to be met Milestone completed Planning/Milestone date to be confirmed

*including CP signoff

Release 3 Plan Overview

1. Release 3 Plan is based on Design outputs of 14 CRs & need date of hitting November Release.

2. All phases required to deliver Release 3 have been factored in, including Market Trials

3. Market Trials is expected to include all 14 CRs and XRN 4453 expected to be the most complex.

4. MT will be open to testing for 5 weeks including defect retests. Connectivity testing expected during MT preparation phase with all parties.

5. Integrated Dress Rehearsal also expected to be undertaken with Market parties to ensure Cutover practice and transition arrangements are practiced before Go-Live

6. Further engagement on MT and IDRs expected to occur through DSG

7. High Level MT plan agreement required to finalise plan and achieve commitment to November 2018 implementation from all parties

Mar 2018

12 19 26

Apr 2018

9 16 235

May 2018

14 21 28 4

June 2018

18

Jul 2018 Aug 2018 Sep 2018

17 242 7 11 6 10

Oct 2018

Detailed Design

13 20 27 39 162 23 8 15 221

Nov 2018

29 12 19 26

1 3 5 6 9 11 12 14 15 27 28 294 8 13 21 2622 23 2416 251917 20 32 3330 34 3718 31 35 36

Dec 2018

3 10 17 24 31

2 7 10

25 30

38 39 42 4340 4441

30 5

Build

System Testing Perf. Testing

Regression Testing IDR

IDR Prep (2

weeks)

MT Prep(5 weeks)

Market Trials (5 weeks)

CTGY

GO LIVE

Post Implementation Support

CTGYGo Live

Acceptance Testing

MT Approach

Test ScenariosMT

Planning

Training Approach

Training plan Training execution

UKL FR Release 3.0

Industry Design Engagement Session

23rd April 2018

R3.0 Scope of changes

# Change Number Change Description

1 XRN3656 Read Validation Tolerances

2 XRN4273 Installed Status of Failed MOD614

3 XRN4337 To change the optionality of the Supply Point confirmation reference for the T51 file

4 XRN4431 Reads failing market breaker tolerance to be accepted for correct date following AQ Correction

5 XRN4443 File Format Changes Aug 16 Unique Sites (deferred items from CR252)

6 XRN4453 File Format Should Have changes

7 XRN4454 DN Sales (Outbound Services) Requirements for UKLP enduring solution

8 XRN4458 Class 4 CSEPS Reconciliation Variance Identification

9 XRN4481 Resolution of penny mismatches within invoice supporting information for Core invoices.

10 XRN4486 Meter Type O = Oriffice to be an acceptable value in file formats and reports

11 XRN4495 Energy Tolerance Rejection Code

12 XRN4534 Amendment to RGMA Validation Rules for Meter Asset Installation Date

13 XRN4538 Insertion of Maximum Number of Occurrences in Meter Inspection Date Notice (MID) File

14 XRN4539 New File Level Rejection

R3 Change Summary

Direct Change Impact Process Areas

Wider Impacts considered whilst defining solution

Design Summary – XRN4273

File Format Change Process

Yes RGMA

Batch Job Reporting Requirement

No change No

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Change ID Solution / Process Changes

XRN4273

(Installed Status

of Failed

MOD614)

This change is to include a new value F (Failed IHD Asset) for this field. List out the impacted file types and configure the new value

in Market flow to avoid warning. Impacts functions in both ISU and Marketflow applications. As part of this change, new allowable

values will be introduced in ‘In Home Display Status’ of ‘F’ - ‘Failed IHD Asset’. High Level changes needed within application

outlined below:

• This changes is to Add ‘F’ as new allowable value for field IHD_INSTALL_STATUS in S98 record type .

• Impacted file types are PAC,CRS, NMR,TRS,CFR,NRF,SNR,MRI,TRF,ONJOB and ONUPD .

• Xoserve Testing is primarily around Market Flow and SAP ISU application for all Site types and classes along with unique sites

Performance Impact

Envisaged? CR Complexity

No Low

File Format Change Process

Yes Winter Consumption

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Medium

Change ID Solution / Process Changes

XRN4337

(To change the

optionality of the Supply

Point confirmation

reference for the T51 file)

This change is for NRL process. T51 (Winter consumption calculation failure) segment is sent to the shipper which has a

Live contract as on the file creation date and also to the incoming shipper if the confirmation status is CO. High Level

changes needed within Xoserve applications outlined below:

• Supply point confirmation reference number is a mandatory data item in this segment which impacts SPA required

process optionality needs to be changed from mandatory to optional .

• Xoserve Testing spans across SAP PO and Market flow applications. Impacted files due to the change are: JOB, UPD,

PAC (S98), CRS (S98), NMR (S98), TRS (S98), CFR (S98), NRF (S98), SNR (S98), MRI (S98), TRF (S98).

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4337

File Format Change Process

Yes All

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Medium

Change ID Solution / Process Changes

XRN4453

(File Format ‘Should

Have’ changes)

This change was raised during UKLINK programme and deferred. It contains c.230 changes out of which majority are

cosmetic corrections and c.11 changes are related to functionality/format changes which form the design outlined below.

The changes include Optionality changes, adding new fields and hierarchy changes for file types like

FSI,CUN,CCN,CIN,ZCS,SFR. Changes, not limited to below, but needed to be carried out within files and application is

outlined below:

• Change IGT_PROJECT_REFERENCE filed Optionality from ’ M’ to ‘O’ in C65,C64,C67 Record type for CUN,CIN and

CCN.

• Add new filed as NWO_NAME in K29 record type for FSI file type and Optionality of field is ‘M’.

• The hierarchy Level of the I09 record to be changed from 3 to level 4 for ZCS file type .

• Hierarchy change from /Q28/K42/I09 to /Q28/K42/K80/I09

• Impacted file types are FSI, CUN, CCN, CIN, ZCS and SFR for this change.

• Xoserve Testing spans across all functionality, hierarchy and format changes.

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4453

File Format Change Process

No SPA / Reads

Batch Job Reporting Requirement

No No

Performance Impact

Envisaged? CR Complexity

No Medium

Change ID Solution / Process Changes

XRN4458

(Class 4 CSEPS

Reconciliation Variance

Identification)

This change will introduce new rules for identification of rec variances for CSEP sites. The process will be initiated from SPA

area. While performing the meter read reconciliation or adjustments during the period for all IGT sites linked to a project,

system has to see if there is a change in either the Max AQ or Max SOQ for the concerned CSEP during the billing period. If

there is a change, all rec adjustments billing and Support information will need to consider correct time slices and applicable

rates for charging on primary and amendment invoices.

• Xoserve Testing is across CSEP Amendment, read reconciliation, adjustment billing.

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4458

File Format Change Process

Yes Billing

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Medium

Change ID Solution / Process Changes

XRN4481

(Resolution of penny

mismatches within

invoice supporting

information for Core

invoices)

Penny mismatches were identified while validating the financial values within invoice supporting information against the

actual invoice values for Capacity and Commodity invoices. This change is to make necessary field level amendments in

ZCS, COM, CZI and COI files which will help to validate the thin supporting information files generated from ISU with the

SAP BW thick supporting files without any penny differences. These files are important for Billing. High Level changes

needed within Xoserve applications outlined below:

• This change is to make necessary field level amendments in ZCS, COM, CZI and COI files which will help to validate the

thin supporting information files generated from ISU with the SAP BW thick supporting files without any penny differences

• This change requires Xoserve testing in Billing, BW and integration space.

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4481

File Format Change Process

Yes SPA

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Low

Change ID Solution / Process Changes

XRN4486

(Meter Type O = Orifice

to be an acceptable value

in file formats and

reports)

Current UK Link file format has following meter type values: D - Diaphragm of Unknown Material, R - Rotary, L - Leather

Diaphragm, S - Synthetic, T - Turbine, U - Ultrasonic, Z – Unknown. During migration and IDR few MPRNs were identified

with meter Type value as O (Orifice).

Change is identified in 4 SAP BW files and involves regression impacts.

New Allowable value for meter Type ‘O’ = Orifice .

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4486

File Format Change Process

No RGMA

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Complex

Change ID Solution / Process Changes

XRN4534

(Amendment to RGMA

Validation Rules for

Meter Asset Installation

Date)

Currently, when an asset install comes through a ONJOB or ONUPD once the contract is live for a date prior to the contract

going live, system will allow asset installation on or after CO date (ONJOB) / LI date (ONUPD). As part of this change, the

system will be modified to allow asset install on any date provided there is no other shipper.

• This rule is applicable to both Green Field and Brown Field sites as follows:

a) If the site is green field (1st LI confirmation) and is/was not attached to any device then LI shipper can send the

device activity request for any date in the past (Not earlier to LIS date)

b) If the site is brown field and is not attached to any device then LI shipper can send the device activity request for

any date in the past but not in ownership of the last shipper provided the last shipper is different to the current LI

shipper. Device activity date cannot go beyond the last read date present in the system for the MPRN.Existing

LIS date validation applicable.

• Xoserve testing is needed from RGMA perspective and also changes related to Metering, AQ and Billing as downstream

processes

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4534

File Format Change Process

Yes Marketflow

Batch Job Reporting Requirement

No change No

Performance Impact

Envisaged? CR Complexity

No Low

Change ID Solution / Process Changes

XRN4539

(New File Level

Rejection)

Change involved in FRJ file type, rejection code need to be added. Design to cater to all the possible scenarios.

There are certain file types where the L1 records are defined as mandatory. System expects at least one mandatory

record in the file with all valid fields. If it is not received then reject the whole file and create a FRJ response with error

code FIL00020 (No Valid Message - File contains incorrectly formatted records).

File level rejection testing is to be undertaken by Xoserve at Market flow interface.

Application Topology Impacted Applications

Incoming to SAP ISU Outgoing from SAP ISU

Design Summary – XRN4539

Recap – Design Summary for 8 Changes

# Change

Number

Impacted Process

Area Complexity

Impacts to

File Formats?

Impacts on

Exceptions?

Performance

Testing Required?

External Screen

Changes?

1 XRN4273

Marketflow, SAP PO

Low No No No No

2 XRN4337

Marketflow, SAP PO

Medium Yes No No No

3 XRN4453

Marketflow, SAP PO,

Reads

Medium Yes No No No

4 XRN4458 Reads Medium No No No No

5 XRN4481

Marketflow, SAP PO,

Billing, Invoicing,

SAP BW

Medium Yes No No No

6 XRN4486

Marketflow, SAP PO,

SPA, SAP BW

Medium Yes No No No

7 XRN4534 RGMA Complex No No No No

8 XRN4539 Marketflow Low No No No No

Glossary of Terms

# Abbreviation Description - Definition

1 ISU Industry Specific Solution for Utilities

2 RGMA Review of Gas Metering Arrangements

3 SAP PO SAP Process Orchestration

4 SAP BW SAP Business Warehouse

5 CMS Contact Management Service

6 SPA Supply Point Administration

Documentation Changes – February

2019 release

February 2019 Release

3 implementations are proposed annually within the gas industry

In previous years these dates have been determined as ‘the Friday

following the last Thursday in February and June, and that following the

first Thursday in November’. These are aligned to SPAA release dates

Xoserve have provisioned for 2 major system releases in the budget plan

for 2018-2019 and 2019-2020 with these proposed for June and

November

However, to support additional industry change, it is proposed to

implement in February where Xoserve does not need to introduce system

changes

Current process

Following internal Xoserve agreement and ChMC approval to proceed with a change:

Evaluation

Quotation

Report (EQR)

produced

Business

Evaluation

Report (BER)

produced

Taken to

ChMC for

approval

Taken to

ChMC for

approval

Xoserve

completes

detailed

design

Change Pack is

issued with the

solution and

associated impacted

documents

• The EQR estimates the cost for the

BER to be produced

• The BER estimates the

implementation costs of the change

• Both are required for external funding

to be approved

Proposed ‘documentation only’ process

Whereby it is a documentation process change, and therefore no impact to

Xoserve, no EQR or BER is required as there is no approval for external funding

necessary

The process will be that a change proposal (CP) is raised. The CP will go through

internal Xoserve approval and ChMC approval to ensure the industry supports the

change

An Xoserve Reference Number (XRN) is assigned to the CP which is added to the

change register, this will allow participants to see the change through its lifecycle

A Change Pack will be issued to the industry that details the solution, with 6

months notice of the change; this will be approved at ChMC within the

implementation plan

Exemptions

Changes will not be considered for a documentation release

where:

Large scale testing is required i.e. market trials. Testing would be

considered on a case by case basis per each change, based on

industry requirements

There is a system impact to Xoserve

Interface impacts

6 months notice has not been given whereby Users need to make

system changes

Proposed February Release change

Currently it is proposed to introduce one change in February 2019: Ability

to Accept Extended Reading Indexes of up to 12 Characters

This was issued for early views in the Change Pack 1884.3 on 9th March

Users confirmed 6 months was required for the system changes that

needed to be implemented to support 12 character indexes

There are no system impacts for Xoserve

Further information will be issued within the Change Proposal and

Change Pack in May

Next Steps

A Change Proposal will be issued to the industry in readiness for ChMC in

May

Following approval an XRN will be assigned to the change

A Change Pack will be issued to notify the industry of the change and

invite representation comments

Users will vote to proceed at ChMC based on the representation

comments and approvals within the implementation plan

The XRN will be added onto the change register

February release will be included on the ‘Plan on a Page’ for visibility

New Changes for Prioritisation

Ratification

Actions

Actions Title Meeting Date Action Owner Status Update

0109 22/01/2018

XRN3656 -Read Validation Tolerances - Analysis from

across the industry / Xoserve analysis needs to be

completed prior to the 5th February meeting. Xoserve (RH) Open

This information is currently not available from SAP-BW until after R2.

Request for the industry to share any analysis undertaken by 5th

March DSG meeting

0110 22/01/2018

XRN4484 - Remove restriction on nominated SOQ (as

per MOD 445)- To issue within a Change Pack for

ratifying at ChMC Xoserve Open This is an internal impact to Xoserve. A CP will be issued when the

change is being delivered

0209 19/02/2018

XRN4449 - PSR - Xoserve to issue the final version of

PSR mapping rules via the [email protected] box

account. Xoserve Open Require confirmation from Tahera regarding the latest mapping rules.

0304 05/03/2018

XRN4449 - Customer Team to write out to request any

further organisations wanting to test, to confirm by Friday

16th March. DSG Open

0307 05/03/2018 XRN4449 - Xoserve (CF) to assess whether there is a

limit on the number of test files that can be submitted. Xoserve Open

0308 05/03/2018 Meeting participants to provide a direct contact who will

be part of the XRN4449 process. DSG Open

0311 05/03/2018 Volume of CNC Update - Daily Cap to be defined by

Xoserve to share to Shippers. Xoserve Open

0312 05/03/2018 Release 3.0 Update - Xoserve (PD) to assess feasibility

of booking early engagement meetings in advance. Xoserve Open

0317 19/03/2018 Defect Dashboard - to be confirmed which date and

defect release it is proposed to be completed within. Xoserve Open

0322 19/03/2018 XRN4249 - Catch up exercise - Xoserve (CF) to provide

the plan for catch up activies. Xoserve Open

0323 19/03/2018 Implementation Plan - Xoserve to confirm this can be

completed and discussions at the next DSG to discuss Xoserve Open

0401 09/04/2018 Xoserve (DJ) to advise where in the process defect 655

currently is and if a fix has been identified. Xoserve Open

0402 09/04/2018 Xoserve (EL) to provide an update on ASP penny-

mismatching. Xoserve Open

0403 09/04/2018

Shipper organisations who are participating in the industry

testing need to provide key contact details, for

communications to be issued directly. DSG Open

0404 09/04/2018 Xoserve (LC) to confirm the rejection code per file type. Xoserve Open

Actions (Continued)

Title Meeting Date Action Owner Status Update

0405 09/04/2018 Xoserve (LC) to clearly advise timings in the lower

level implementation plans. Xoserve Open

0406 09/04/2018

Xoserve (RH) to make documentation clear that the

number of needs codes are per MPRN and not per

file. Xoserve Open

0407 09/04/2018

Xoserve (LW) to speak with (MD) about training

process. (ES) to compile an information document

and send out to the industry. Xoserve Open

0408 09/04/2018

Npower (JB) to provide further details on the issue for

Npower on implementing XRN4431. Xoserve (MD) to

organise a teleconference with meeting participants to

further discuss this issue. Npower/Xoserve Open

0409 09/04/2018 Xoserve (PD) to outline the impacts to DES

separately for XRN4454. Xoserve Open

0410 09/04/2018 Xoserve (RH) to provide a list of workarounds which

will be retired as a result of XRN4454. Xoserve Open

0411 09/04/2018 Xoserve (RH) to correct the error within the

documentation. Xoserve Open 0411 was corrected and issued in a revised change summary -

1917 on the 11th April.

0412 09/04/2018 Xoserve (RH) to update the meeting times for DSG

on Xoserve.com Xoserve Open

0413 09/04/2018 Xoserve (RH) to send out a notification about AQs of

1. Xoserve Open

AOB

XRN466.7A – Provision of Formula

Year AQ/SOQ to proposing user

Negative Consumption within the AQ

Calculation

Overview

Negative Consumption is generated when a Shipper submits a

subsequent Actual read that is less than the last Xoserve Estimated read

on UK Link (without a TTZ count).

This occurs in UK Link when Xoserve provides Estimated Readings in the

following scenarios:

Change of Shipper event

Class change

LDZ / exit zone change

A new fail to calculate reason was introduced where an AQ calculation

was not calculated owing to negative consumption. This was applied to

negative consumption's created from legacy meter readings where read

validations were less stringent.

Overview

Negative consumption generated post 01st June 2017 is

considered ‘valid’ with the introduction of more stringent Meter

Read validations

Negative Consumption is included within AQ Calculations

Reads can be replaced by the User registered on the date of the

Meter Reading. With the exceptions of:

Readings connected to RGMA updates

Actual Reads on Class 1 and Class 2 SMPs

Increase in AQs of 1 / Understated AQs

There has been an increase in the number of AQs of 1 and

understated AQs as a result of a lower actual meter reading being

submitted following an Xoserve estimated reading

This has occurred where the transfer reading is the AQ closing

reading, and therefore not taken into account with the AQ

calculation. The next meter reading, which is an actual, is the AQ

opening read. Only the negative consumption is considered within

the AQ calculation

Analysis shows the maximum impact is less than 0.03% of total

NDM AQ, therefore this is not considered a high material impact

Options – for DSG discussion

1. Shipper Action

Replace the Xoserve estimated reading and submit a subsequent meter reading which

will trigger a new rolling AQ calculation. The AQ will be a correct reflection of the gas

being consumed on the SMP. These meter readings can be submitted at the same

time.

Considerations

If this action is completed the SMP will have a reflective AQ

There are no impacts to UNC rules/calculations with this solution

This retains the original requirement from Nexus that all reconcilable reads should be

used for AQ calculation

Any UIG implications will be rectified once the readings are taken into account within

reconciliation

Options – for DSG discussion

2. Apply Fail to Calculate validation for all negative consumption period

Extend the code previously introduced whereby negative consumption is excluded

from AQ calculations and the prevailing AQ is carried forwards

Considerations

The prevailing AQ will be in situ until there are 9 months of accurate readings and a

new AQ can be calculated, impacts NDM gas nominations, any further estimated

transfer reads (should it transfer) will generate poor estimates

Less meter points will be subject to regular rolling AQ updates

UNC Modification 0638V and 0570 are both implemented which enact the CMA order

and the requirements for all Users to submit reads (0638V - monthly where smart and

AMR is present and annual read submission with 0570). PAC are monitoring

performance and may choose to incentivise Read submission

3. Another AQ correction reason – for example- the last calculated AQ is

not a reflection of the annual AQ

Considerations

Would correct the AQ

Creates a back stop date however analysis on SMPs impacted do not have a frequent

read submission profile.

Yes leave in question do DSG have further solution options

4. Option for the system to recalculate the estimated transfer read based

on previous read and latest submitted actual

Would require further analysis and complete impact assessment

Other Options – for DSG discussion

DSG Options Discussion


Recommended