DTI Hongxi 2012 inspection report

Date post: 26-Mar-2016
Category:
Upload: dimpexp
View: 215 times
Download: 0 times
Share this document with a friend
Description:
Dimpexp's factory Hongxi Valve Co. Ltd. 2012 annual inspection by the D.T.I. according to rules NKB n°13 and EN 13828
Popular Tags:
13
INSPE Year of in 2012 Certificat 1.51/18 VTT-RT SC0403 1603 Approval DIMPEXP 36, rue Vig F-750009 France Manufact Hong Xi V Ind. Zone, Yuhuan C Zhejiang China Date of in 18 Octobe Inspector Eric Guan Control a No. 230 of Order No 495792 CTION nspection: ion body: 8564 TH-00030-1 3-11 holder: P SAS gnon Paris turing site: Valve Co., L , Xiao Shan County nspection: er 2012 r: n, Consultan agreement: f 10 Januar .: REPOR DZR br dimens 11 DZR br dimens DZR br Ball val td. n Wai Villag nt ry 2011 RT rass ball val sion 3/8" - 2 rass ball val sion 3/8" - 2 rass ball val ve (CR bra e lve, DX E14 " lve, DX E14 " lve, DX E14 ss), DX E14 411 and DX 411 and DX 411Z, dimen 44Z, dimen X E144Z, X E144Z, nsion 1/4" - sion 1/4" - 2 2" 2"
Transcript

INSPE Year of in2012 Certificat

1.51/18

VTT-RT

SC0403 1603

Approval DIMPEXP36, rue VigF-750009 France ManufactHong Xi VInd. Zone,Yuhuan CZhejiang China Date of in18 Octobe InspectorEric Guan Control aNo. 230 of Order No495792

Y:\Organization\C02012_495792.doc VA-INSP H 1-2 (U

CTION

nspection:

ion body: 8564

TH-00030-1

3-11

holder: P SAS gnon Paris

turing site: Valve Co., L, Xiao Shan

County

nspection: er 2012

r: n, Consultan

agreement: f 10 Januar

.:

011_Installation og Kcx

UK) Version 4_11-03-

REPOR

DZR brdimens

11 DZR brdimensDZR brBall val

td. n Wai Villag

nt

ry 2011

Kalibrering\VA Prøvn

-2009

RT

rass ball valsion 3/8" - 2rass ball valsion 3/8" - 2rass ball valve (CR bra

e

ing og Inspektion\3 V

lve, DX E14" lve, DX E14" lve, DX E14ss), DX E14

VA-kunder\DIMPEXP

411 and DX

411 and DX

411Z, dimen44Z, dimen

P\INSP\2012\Hong_X

X E144Z,

X E144Z,

nsion 1/4" -sion 1/4" - 2

Ene

Xi_Valve_for_DIMPE

2" 2"

ergy and Cl

EXP_INSP_18-10-

imate

Ins

App

Dan

ComAd TowCou

in cNK

witThe

Cond

Divi

Sign

INSP Reg

spection

proval hold

nish Techn

mpany: dress:

wn/postcoduntry:

complianceKB 13 and E

th the followe requiremen

ditions:

ision/Section

nature:

. No. 9033

n report

der: DIM36, FR-FranEm

nological In

de:

HonInd.VillZheChi

e with the pEN 13828

wing resultnts specified

The inspect17020, see „General TTechnologi

The inspectif the labora

: Energy

VA Tes

Kent LeLead Aud

t

MPEXP SARue Vignon

-750009 Parnce ail: ruixi.do

nstitute has

ng Xi Valve. Zone, Xiaolage,Yuhuanejiang na

provisions:

ts: d in the abov

tion scheme has bwww.danak.dk, aerms and Conditiical Institute“, Feb

tion report applieatory has approve

and Climatsting and In

emming ditor

AS n ris

ou@dimpex

carried ou

e Co., Ltd.,o Shan Wain County

ve rules/stan

been accredited band inspection haions regarding Cebruary 2009.

es to the inspecteded the extract in w

te nspection

Page:

MailingOrder NInitials:Numberappendi

xp.fr

ut inspectio

i ContactTel.: Fax: Mobile:Email:

ndards were m

by DANAK (Danias been carried ouertification, Inspe

d product(s) only.writing.

1

g date: 2No.: 4 Er of ices: 5

n at (manu

t person: M+++h

met.

ish Accreditationut in compliance wection or Approva

. This inspection

Eric GConsul

T

K

D

T

F

1 of 1

in

w

25 October 495792 ERIC/KLE/M

5

ufacturing

Mr. Chen +86 576 87+86 576 74+86 139 01hychen@26

n) (Reg. No 9033)with Danish Techal Bodies Associa

report may be rep

Guan ltant

Teknologiparken

Kongsvang Allé 2

DK-8000 Aarhus

Tel. +45 72 20 20

Fax. +45 72 20 10

nfo@teknologisk

www.teknologisk

2012

MRI

site):

496321 96310 051561

63.net

) according to DShnological Instituated with the Dan

produced in extra

29

C

00

0 19

k.dk

.dk

S/EN ute’s nish

act only

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 1 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

Follow-up on previous audit

0 Quality Manual

0.1 Is a quality manual available in the company? + +

0.2 Is the personnel familiar with the contents of the quality manual?

+ +

0.3 Who is responsible for maintaining the quality manual? + + Deputy General Manager

0.4 Does the company have an ISO 9000 certification? If so, which one?

+ + ISO 9001:2008

1 Organisation (applies to design, production, purchase and control)

1.0 Is the person who is responsible for the internal control organisationally independent of the production?

+ +

1.1 Have the personnel’s responsibilities been made clear regarding design, production, purchase and control? And is this allocation of responsibilities available in writing?

+ +

1.2 Is the production personnel familiar with the products that should be marked with seals of approval?

+ +

1.2.1 Who is responsible for planning the production process so the products meet the requirements of current specifications?

+ + Supervisor of production

1.2.2 Who is responsible for deciding whether the products comply with the current standards or not?

+ + Supervisor of inspection

2 Documentation

2.1 Are the product certification requirements and current standards available at the licensee/ manufacturer? (The licensee is responsible for the documentation being available at the place of production).

+ +

2.2 Are there instructions/drawings regarding current specific provisions and standards?

+ +

2.2.1 Who is responsible for instructions and drawings being available?

+ + Deputy General Manager

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 2 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

3 Purchasing routines – receiving inspection – storage

3.0 Is a list of suppliers/subcontractors available? + +

Purchasing routines

3.1 Are procedures and instructions available regarding quality control of purchased raw materials/semi-manufacture?

+ +

3.1.1 How are the mentioned procedures and instructions documented?

+ + Document according to the ISO 9000 system

3.1.2 Who is responsible for ensuring that purchased raw materials and other materials used for manufacturing the products are of the correct quality?

+ + Supervisor of inspection

Receiving inspection

3.2 Are there procedures for which products that must be inspected?

+ +

3.2.1 Is documentation available, stating who is responsible for inspecting received products?

+ +

3.2.2 Are certificates or control reports normally received from subcontractors?

+ +

3.2.3 Is the number of accepted and rejected products recorded at the receiving control?

+ +

Storage

3.3 Are there procedures for when and how components with certification right should be secured/stored to prevent damage to or confusion with other products, so that non-complying products can be avoided?

+ +

3.3.1 Who is responsible for the procedures? + + Warehouseman

4 Production process

4.0 Who is responsible for the production? + + Supervisor of production

General

4.1 What sort of internal control and testing is carried out during the production process?

+ + Dimension and 100% leak test

4.1.1 When is the internal control and testing carried out? + + When starting and during production

4.1.2 Who carries out the internal control and testing? + + Supervisor of inspection

4.1.3 Are the internal control and test results recorded? + +

4.1.4 Is the number of accepted and rejected products recorded? + +

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 3 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

Inspection during the production process

4.2 Is conformity between drawings and specifications checked? + +

4.2.1 Who inspects conformity between drawings and specifications?

+ + Deputy General Manager

4.2.2 Who is responsible for preparing the control instructions so that they comply with the current standards?

+ + Assistant General Manger

4.2.3 What procedures exist for control of materials during the production process and delivery?

+ + Measuring instructions for material inspection

4.2.4 Who carries out control during the various production stages? + + Supervisor of inspection

4.3 How are the products inspected at the final inspection? + + Spot check 100% according to standard EN 13828-2003,

Identification/marking

4.4 Who is responsible for establishing procedures for correct identification/marking?

+ + Assistant General Manager

4.4.1 Who carries out marking, and when is it carried out? + + Warehouseman

4.4.2 How are products and components identified during storage/ transport through the production premises?

+ + Identified from the packing or identification card

4.4.3 Where is marking carried out (manufacturer/distributor)? + + In workshop

Installation instructions

4.5 Are there procedures for ensuring that product deliveries are accompanied by installation instructions?

+ +

4.5.1 Which types of installation instructions are available? + + Production Manual

Record-keeping

4.6 Is the internal control recorded for tracing certified products? + +

4.6.1 Who is responsible for record keeping? + + Warehouseman

Maintenance of production tooling equipment

4.7 Is there documentation of how production tooling equipment is maintained so the equipment conforms to the product specifications?

+ +

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 4 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

5 Handling, storage and packaging/delivery of certified products

General

5.1 Are there procedures for handling, storage and packaging/ delivery of certified products?

+ +

Handling

5.2 Are there procedures for how products should be handled to prevent damage or deterioration?

+ +

Storage

5.3 Are there procedures for how finished and marked products should be stored to prevent the products from being damaged or mixed up with other products?

+ +

Packaging/delivery

5.4 Are there procedures for how the products should be packed to prevent damage during transport?

+ +

6 Handling of non-complying products and corrective action

Non-complying products

6.1 Are there procedures for how non-complying details and products should be identified and handled?

+ +

6.1.1 Are there procedures for how products not meeting the requirements of current standards should be marked/ segregated?

+ +

6.1.2 Who is responsible for the procedures? + + Supervisor of inspection

Notification of defects/customer complaints

6.2 Are there procedures for how defective products that have been returned to the manufacturer should be handled?

+ +

6.2.1 Are there procedures for which measures should be taken in case of complaints?

+ +

6.2.2 Are all complaints and corrective actions registered for products covered by the marking licences?

+ +

6.2.3 Are there procedures for how the corrective actions are followed up?

+ +

6.2.4 Are the effects of the corrective actions documented? + +

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 5 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

Deviations

6.3 Are there any descriptions of which type of defects and level of nonconformity that can be accepted before the components must be taken out of the production?

+ +

6.3.1 Who decides which type of defects that can be accepted? + + Deputy General Manager

6.4 Are there procedures for corrective actions? + +

6.4.1 Are corrective actions recorded? + +

6.4.2 Who is responsible for carrying out corrective actions? + + Assistant General Manager

7 Control equipment

Calibration

7.1 Who is responsible for the calibration and maintenance procedures?

+ + Deputy General Manager

7.1.1 Are there procedures for measuring and control equipment due for calibration/control?

+ +

7.1.2 Are there procedures for maintenance of measuring and control equipment?

+ +

7.1.3 Are calibrations performed on/with traceability to accredited calibrated laboratory/measuring and control equipment?

+ +

7.1.4 Are reports on calibrated measuring and control equipment available?

+ +

8 Updating

Updating procedures

8.1 Are there procedures for contact with the certification bodies in case of change of materials, design or production methods for verification of whether the requirements of the current standards have been met or not?

+ +

8.1.1 Who is in contact with the certification bodies? + + DIMPEXP SAS, France

8.1.2 Are there routines for when and how updates and amend-ments to the internal control documentation should be carried out?

+ +

8.1.3 Who is responsible for updating and making amendments to the internal control documentation?

+ + Deputy General Manger

Danish Technological

Institute

REQUIREMENTS FOR THE INTERNAL INSPECTION

DOCUMENTATION

Initials: KLE Appendix: 1 of 5 Page: 6 of 6

Order No.: 495792

Check questions OK

+/-

Inspected field

Remarks

9 Internal control

9.1 Has the company conducted internal control according to current standards?

+ +

9.1.1 Are the internal control results recorded? + +

9.1.2 Who is responsible for the internal control? + + Assistant General Manager

10 Samples for audit testing

10.1 Have samples been taken? + + Samples are taken in accordance with the control agreement

10.2 According to which method were the samples taken?

10.3 Which samples were taken?

10.4 Where were the samples taken?

10.5 When were the samples taken?

10.6 Who took the samples?

11 Application of licenses and identity markings

11.1 On which documents is the marking being applied? (Invoices, delivery notes, quotations, acknowledgement of orders, products)

+ +

11.2 Is the approval marking (logo) being used correctly? + +

11.3 Are the identity markings being used in connection with marketing? (see examples like catalogues, website, etc.)

+ +

11.4 How are the licenses/certificates being filed? + +

11.5 If any copies of licenses/certificates are available – in what way are the copies being used?

+ +

DaTechn

Ins

anish nological stitute

TEST RERAW MAT

EPORT TERIAL

Init

ials: KLE AppendixPage: 1 o

Order No

x: 2 of 5 of 1

o.: 495792

DaTechn

Ins

anish nological stitute

TEST AFHOT PRE

FTER ESSED

Init

ials: KLE AppendixPage: 1 o

Order No

x: 3 of 5 of 1

o.: 495792

DaTechn

Ins

anish nological stitute

SALES CONNTRACT

Init

ials: KLE AppendixPage: 1 o

Order No

x: 4 of 5 of 1

o.: 495792

DaTechn

Ins

anish nological stitute

TTOOL CERTTIFICATE

Init

ials: KLE AppendixPage: 1 o

Order No

x: 5 of 5 of 2

o.: 495792

DaTechn

Ins

anish nological stitute

TTOOL CERTTIFICATE Init

ials: KLE AppendixPage: 2 o

Order No

x: 5 of 5 of 2

o.: 495792


Recommended