+ All Categories
Home > Documents > DUBAI METRO UNITED ARAB EMIRATES - Mammoet metro ines concrete ier cas an viact sements cont e sae...

DUBAI METRO UNITED ARAB EMIRATES - Mammoet metro ines concrete ier cas an viact sements cont e sae...

Date post: 20-Mar-2018
Category:
Upload: danglien
View: 216 times
Download: 3 times
Share this document with a friend
2
A 13,067-PIECE PUZZLE AND TWO YEARS TO SOLVE IT. DUBAI METRO UNITED ARAB EMIRATES
Transcript
Page 1: DUBAI METRO UNITED ARAB EMIRATES - Mammoet metro ines concrete ier cas an viact sements cont e sae transorte wit eistin eiment at a. ereore ammoets enineers create esecia esine saes

A 13,067-PIECE PUZZLE AND TWO YEARS TO SOLVE IT.

DUBAI METROUNITED ARAB EMIRATES

Page 2: DUBAI METRO UNITED ARAB EMIRATES - Mammoet metro ines concrete ier cas an viact sements cont e sae transorte wit eistin eiment at a. ereore ammoets enineers create esecia esine saes

AUG ’06 JULY ’08

AUG ’06 JULY ’08

TRANSPORTATION OF 1,215 PIER CAPS ALONG THE METRO LINE…

AND DELIVER A TUNNEL BORING MACHINE (TBM)

Discover more on www.mammoet.com

BUILDING A METRO-LINE AT THE SPEED OF DUBAI.

AUG ’06 JULY ’08

COORDINATE FOR 24 MONTHSAUG ’06 JULY ’08

…AND 11,852 VIADUCT SEGMENTS

A Z

In two decades, Dubai has

exploded into the bustling desert

metropolis it is today. Catering to

its rapid expansion, the city was

in need of a new metro line.

The 47.4-kilometer line had to be

completed within a two-year

timeframe. Mammoet was

contracted to plan, coordinate

and execute the delivery of 13,067

concrete elements that had to

be placed in a specific order and

on a strict schedule. Facing

difficult delivery locations ranging

from busy highways to areas

without road access, Mammoet

solved the complex puzzle and

successfully delivered all pieces

within the 24-month timeframe.

The biggest challenge was

maintaining a constant stream of

up to 40 concrete elements per day

- in the right order - for two years.

Any disruptions in the supply or

change in the order would impact

the overall production schedule of

the metro line. To make matters more

difficult, the deliveries had to take

place at night in order to minimize

interference with Dubai’s busy

everyday life. But being one of the

most congested cities in the world,

even nighttime operations could be

seriously hindered by local traffic

and vice versa.

Before transporting any element,

Mammoet engineers surveyed the

entire route to every location. Not

only to assess that safe delivery was

in fact possible, but also to check if

any precautions were needed, such

as reinforcing existing roads or

building temporary new ones to

accommodate the heavy loads.

The metro line’s concrete pier caps

and viaduct segments couldn’t be

safely transported with existing

equipment at all. Therefore,

Mammoet’s engineers created

especially designed saddles for

transportation.

At the peak of the operation, an

average of 20 trailers made two trips

each night for an entire month,

during which Mammoet delivered

877 viaduct segments and 84 pier

caps along the metro line. When the

metro went underground, Mammoet

delivered a tunnel boring machine 25

meters below the surface.

For two years, Mammoet worked

non-stop to ensure timely delivery of

all elements and, as a result,

contribute to a solid connection

between the far corners of the vast

city of Dubai.

RESOURCES

CRANES 1 crawler crane

TRANSPORT 20 trailers20 prime movers

SPECIAL EQUIPMENT custom designed saddles

CREW 40 Mammoet professionals


Recommended