DMCI GLOBAL, LTD Palm Jumeirah Monorail
Transcript
Page 1: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail

Page 2: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail

Page 3: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Aerial View of Palm Jumeirah

Page 4: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Aerial View of Atlantis Station (Atlantis Hotel in the background)

Page 5: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Aerial View of Atlantis Station (Atlantis Aquaventure water park at left)

Page 6: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Atlantis Station

Page 7: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Atlantis Station

Page 8: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Atlantis Switch Bridge

Page 9: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Village Center Station

Page 10: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Village Center Station

Page 11: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Trump Tower Station

Page 12: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Trump Tower Station

Page 13: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Rebar Fabrication

Page 14: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Inner Form Fabrication

Page 15: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Soffit Form Setting

Page 16: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

End Form Setting

Page 17: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Rebar Assembly

Page 18: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Rebar Assembly

Page 19: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Inner Form and Sheath Installation

inner form

sheath

Page 20: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Side Form Preparation before inserting rebar cage

Page 21: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Side Form Setting

Page 22: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Concrete Placing

Page 23: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Concrete Placing

Page 24: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Curing

Page 25: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Stressing

Page 26: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Lifting to Stock Area

Page 27: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Retouching

Page 28: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Stocking Area

Page 29: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

CHALLENGES Placing of Stitching Concrete

Page 30: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Page 31: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail Guideway Beam Production & Stitching Precasting of 428 beams each beam is 28m long x 1m wide x 2m high and weighs 80 tons

Joining of beams to columns at site beams are “stitched” to other beams and columns by concrete

Contract Amount: AED 11.3 Million

Page 32: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail Atlantis Station 3 floors 2100 sq m Contract Amount (Structural): AED 3.6 Million Contract Amount (Finishing): AED 11.0 Million

Page 33: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail Village Center Station 5 floors 2200 sq m Contract Amount (Structural): AED 3.9 Million Contract Amount (Finishing): AED 7.9 Million

Page 34: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Palm Jumeirah Monorail Trump Tower Station 3 floors 1700 sq m Contract Amount (Structural): AED 2.6 Million Contract Amount (Finishing): AED 9.5 Million

Page 35: Dubai monorail, Ronaldo R. Elepaño, ACF

DMCI GLOBAL, LTD

Project Features Monorail Guideway Beams 32 cu m concrete per beam (typical) 80 tons beam weight (typical) 2 beams per day average production Hollow section Pre-stressed, post-tensioned Vertically & horizontally curved and canted beams Curved soffit

Monorail Stations Structural: Concrete: 5900 cu m Rebar: 1160 tons Finishes: (1) Custom glass and aluminum external envelope (2) Spray tile finish to exterior concrete surfaces (3) Granite interior walls and floors (4) Perforated aluminum ceiling finish

Page 36: Dubai monorail, Ronaldo R. Elepaño, ACF

Benefits Derived :

Profit realized

Retention of human resource

Capability enhancement – through this

experience the company was able to win

two more projects in the Philippines.


Recommended