Due Diligence Report – Social Safeguards (Land Acquisition and Resettlement) Project number: 42486-016 April 2016
IND: Madhya Pradesh Urban Services Improvement
Program – Water Supply Improvement in Pawai
Package Number: MPUSIP-6D Prepared by the Government of Madhya Pradesh for the Asian Development Bank. This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
1 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Land Acquisition and Resettlement Due Diligence Report
Document stage: Draft for consultation Project Number: 42486 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} April 2016
IND: Madhya Pradesh Urban Services Improvement Program – Pawai Water Supply Scheme, District: Panna
This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
2 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
3 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Compliances
With reference to email dated 4th May 2016 ,Clarification required by ADB on BUXWAHA,
HATTA AND PAWAI Package 11,MPUSIP
PAWAI Water Supply subproject
S.no. Observation of ADB Clarification Refer Annexure
DDR IR 1 WTP site: Provide information
the year of land acquisition of the WTP land. If the land was recently acquired for the MPUSIP funding due diligence on the process of land acquisition will be required and attached in the DDR.
The land for proposed WTP is government land and no private land acquisition is required. The Govt. land get transferred to ULB. Therefore, DDR needs no change.
Appendix 1 , 4 ,5
2 Provide the picture of the WTP locations
It is marked on google map & photograph of site is also appended along land details
Appendix 1 & figure 2.1,2.2
3 Consultation: Include the consultation records with the boatmen and washer-men in the consultation report.
As Boatmen & washer men communities do not have any particular location they are scattered in all 15 wards. Consultation done in slum areas also where we are not able to capture people during visit.
4 OHT/GLSR: Provide the picture of the assigned land of the proposed OHT/GLRS
As 2existing OHTs are there ,one OHT is taken in project other one are not in good condition so proposed to discard and same place new OHT of higher capacity get constructed.
Figure 2.3,2.4
3. Attach in the appendix copy of the land ownership records/statement letters (in English) from the responsible ULBs on the ownership of the OHT, Intake areas and WTP lands and confirmation that the assigned land is vacant and free of IR impacts.
The copy of land ownership (in the form of Khasra record) is already attached with DDR. However, it is further clarified that the lands proposed for construction of various components of water supply project including WTP, OHT etc, are State Government lands and the process of transfer of land by the District Revenue Department to the concerned ULB is in advance stage. As far as Intake well and/or anicut is
Appendix 1,4 & 5 NOC of WRD for extraction is send separately with meeting minutes.
4 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
concerned, No objection from State Water Resource Department (the competent authority for rivers in M.P.) is in advance stage. A certificate of land status from the concerned Chief Municipal Officer is being sent shortly. The same will be annexed with DDR to be appended with Bid document.
4. Provide the google earth maps with bigger resolution/ lower elevation for the location of: 1. Intake area 2. WTP areas 3. Raw water pipe alignment / ROW from intake to WTP 4. ROW of feeder main (treated water) from WTP to OHT/GLSR
The Site locations and alignment of all the components on Google map will be annexed with the report.
Figure 2.1, 2.2, 2.3,2.4 please refer distribution design of DPR for details (Figure 3)
5 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
CURRENCY EQUIVALENTS
(as of April 01 ,2016)
Currency unit = Rupee (INR) INR 1.00 = USD015
USD 1.00 = INR 68.70
6 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
ABBREVIATIONS
ADB - Asian Development Bank
AP - Affected Person
BPL - Below Poverty Line
DP - Displaced Person
EA - Executive Agency
GOI - Government of India
GOMP - Government of Madhya Pradesh
HHs - Households
IA - Implementing Agency
IR - Involuntary Resettlement
KM - Kilometer
MPUDC - Madhya Pradesh Urban Development Company
OHT - Over Head Tank
O&M - operation and maintenance
PHED - Public Health Engineering Department
PIU - Project Implementation Unit
PMC - Program Monitoring Consultant
PMU - Program Management Unit
PO - Project Officer
R&R - Resettlement and Rehabilitation
RF - Resettlement Framework
RFCTLARR - The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
RP - Resettlement Plan
ROW - Right of Way
RWA - Resident Welfare Associations
SPS - Safeguard Policy Statement
TA - Technical Assistance
UADD - Urban Administration and Development Directorate
UDED - Urban Development and Environment Department
ULBs - Urban Local Bodies
WRD - Water Resource Department
WTP - Water Treatment Plant
7 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
CONTENTS
I INTRODUCTION 05 A Background of subproject 05 B Project description 05 C. Scope and Nature of Resettlement 06
II Policy Framework & entitlement 06 III SUB-PROJECT DESCRIPTION 10 III FIELD WORK AND PUBLIC CONSULTATION 12 A. Public Consultation
IV INVOLUNTARY RESETTLEMENT SAFEGAURD
GUIDELINES
14
V. LAND AVAILABILITY AND RESETTLEMENT IMPACTS 17 VI CONCLUSIONS 19 A. Summary and Conclusions B. Next Step
LIST OF TABLES
Table 1 Potential Social impact of MPUSIP 05 Table 2 Summary of Stakeholder Consultations 13
LIST OF FIGURES
Figure 1 Location of water extraction arrangements in Patne
river
20
Figure 2
Site locations on Google map 21
Figure 3
Proposed Distribution Network for Pawai Water Supply Subproject
22
LIST OF APPENDIX
Appendix 1. Details of Land ownership for different sites 23 Appendix 2. Stakeholder photograph and list of Stakeholder
Consultation
24
Appendix3 Involuntary Resettlement Screening Checklist 26 Appendix4. Khasra details and maps 30
8 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
I. INTRODUCTION
A. Background
1. Government of Madhya Pradesh accords high priority to urban infrastructure
development. Mission 81 of Madhya Pradesh vision 2018 is dedicated to water supply,
and aims at universal coverage and reforms to improve efficiency of service delivery.
Government has initiated various programs – with own funds, Government of India funds, and also from external funding agencies (ADB, World Bank, DFID and KFW) to
improve infrastructure.
2. Proposed Madhya Pradesh Urban Services Improvement Program (MPUSIP), funded by the Asian Development Bank (ADB) will support the State Government programs for improving urban services in 128 Tier II towns in the state. The Program objectives are consistent with the Vision 2018 and ADB’s Country Partnership Strategy (CPS), focusing on infrastructure development, access to basic services and environmental sustainability. The Program will focus on water supply and sewerage and sanitation services and complement the ongoing government programs to improve these services in urban Madhya Pradesh, and will contribute to poverty reduction.
3. MPUSIP will result in improved and sustainable urban services, improved institutional and financial capacity of Urban Local Bodies (ULBs) to deliver sustainable urban services. The Program will also support the development and operationalization of Madhya Pradesh Urban Development Company (MPUDC). The proposed program will be implemented over 10 years (2016-2026). B. Program Description 4. Coverage. Trench 1 of the program will cover water supply interventions for 50 towns, sewerage and storm water collection system for 4 towns and non-physical investments in the participating local bodies as mentioned above. As per the preliminary estimates the proposed Program is estimated to cost about $820 million with Trench I is expected to cost about $390 million. 5. Components. MPUSIP’s physical component includes: 1 A. Universal Coverage (i). Expand drinking water supply coverage to provide 135lpcd in urban areas to each household, and (ii) Make a paradigm
shift from overwhelming dependence on ground water to surface water sources. B. Regulatory and monitoring reforms (i) Establish a water sector regulator to regulate service levels, tariffs, new investments etc. (ii) New and innovative models shall be developed to attract private partners in water supply distribution and maintenance. (iii) Detailed O&M guidelines shall be prepared and systems established for their implementation. Capacity building and training will be made an integral part of the O&M system, and (iv) Implement a major initiative, including an ICT campaign, to sensitize the urban communities about their responsibilities towards operation and maintenance of piped water supply systems.
9 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Table 1:Program Components
C. Scope of this Report
6. This land acquisition and resettlement due diligence report is prepared for the proposed Water Supply package for Pawai Municipal Parishad, dist. Chhatarpur under which construction of water intakes, water treatment plants, storage reservoirs (ground- level and elevated), new pipe laying or pipe replacement (usually along public roads).The proposed subproject will focus on metered water supply for domestic, institutional and commercial users, including water resource identification and treatment, water storage tanks, distribution pipes and metered connections to each household in the towns covering a population of 14465 in Pawai (population as per census 2011) and estimated population on which it is designed for the year 2048 is 23769 all the municipal wards of the town are covered in the project 7. A due diligence process was conducted to examine the land acquisition and resettlement
issues in detail, in line with ADB SPS 2009. This report describes the findings and
provides copies of relevant documents, resolutions, minutes of meetings and
photographs. This land acquisition and resettlement due diligence report needs to be
read along with the Resettlement Framework prepared for MPUSIP.
8. Upon project implementation, the Social Safeguards Personnel at PMU,MPUDC will be
required to undertake a review of this due diligence report, prepare a confirmation letter
or report documenting any modifications for the subproject and submit to ADB; and
receive a ‘no objection’ confirmation from ADB prior to start of construction in the subproject.
II.POLICY FRAMEWORK, AND ENTITLEMENTS
9. The Resettlement Framework (RF) prepared for MPUSIP sets out the objectives, principles, eligibility criteria and entitlements for APs, based on ADB SPS, 2009 and LARR 2013 as well as national and state laws for protection of street vendors. Until recently, all activities related to rehabilitation and resettlement in the State of MP had been based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR) and National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007). GoMP adopted LARR 2013 on 3rd October, 2014 with some specifications for operationalizing its implementation in the state1. Details of policies are in the Resettlement Framework for MPUSIP.
1These GOs issued separately in September 2014 (i) notifies administrative cost of land acquisition; (ii) appoints Divisional
Commissioners as Commissioner for Rehabilitation & Resettlement within their respective jurisdictions; (iii) authorizes District
Subproject Main Components Infrastructure (New or Refurbished)
Water Supply Source development Intake works (for surface water sources) Tube wells
Treatment works Water treatment plant Chlorination unit
Water Transmission Raw Water Transmission mains Clear water Transmission mains
Water Storage Ground level reservoirs Overhead tanks
Water Distribution Distribution mains and network Bulk valves and flow meters House connections Household meters
10 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
III. SUBPROJECT DESCRIPTION
25. Project area: The Municipal area of Pawai is 6.38 Sq Km or.It comprises of the urban
area and surroundings of the Pawai Municipal Corporation. Population of Pawai is 14465
(as per 2011 census). The Project area of Pawai town is 638 hectares excluding water
bodies. The developed area is only 480 hectare which is about 40%.
B. Existing Water Supply
26. Ground water is the only source of water supply in Pawai town. The town gets water supply from the tube wells. Water is supplied through pipes at spot source from the tube wells. A significant volume of ground water is also extracted through a network of bore-wells and hand pumps. The quality of groundwater is fairly good but the groundwater level is depleting rapidly due to abiding of laws. The current groundwater level is at 80 to 100 ft. PNP is in charge of operations and maintenance.
27. There is only one Over Head Tanks (OHTs) in ward no 9 with a capacity of 5.25 Lakh Litter & other is Gravity Service reservoir (GSR) in ward no 1with a capacity of 1.31 Lakh Liter. Presently the water supply is being provided to the population at the rate of less than 30 Liter Per Capita Daily (LPCD) from 7:00 AM to 9:00 AM which is far less than the minimum needs. There are 1460 houses are connected with water supply with 15 Public Stand Post & 56 Hand Pumps in the town). The water charged is at fixed rate at Rs. 25 per month for residential.
. 28. Existing distribution system is having1 OHTs & One GSR in the city. The water is
supplied by gravity flow from OHT. The distribution pipelines are very old with Cast Iron (CI) pipes. In many areas these pipes are in dilapidated conditions and losses through leakage are very high. There are 4 pumping station in the town which serve water in different wards. Jasganpura tube well , Daua Kaun ward no 9, Semra wala maharaja house in ward no 13 & lehardariya Kaun Pumping station is in ward no 14 direct supply from tube well.
29. On other hand, Nagar Parishad has installed hand pump in every wards. There are approx 56 hands Pumps & 35 well which serve the population of Pawai. There is no water pipeline in ward no 4 & 6. There are partially having water pipe line in ward no 1, 5, 7 & 8. Ward no 2, 3, 4, 9, 10, 11, 12, 13, 14 & 15 are serves fully water pipe line supply system. There are 700 old connection & 515 new water connections proposed in the town. After implementation of water augmentation schemes 45 LPCD is supplied through water pipeline.
30. Water distribution takes place with piped water supply in the town. The existing network of pipe line, which was laid couple of decades ago is totally in dilapidated situation. Water is distributed to separate water supply zones and areas through localized distribution networks from the 35 tube wells located at various parts of the town. There is two elevated service reservoir one is 1.31lacs litres capacity very old and Second is 5.25 Lac Liters Capacity.
Collectors for constituting an Expert Group separately in respect of each project, (iv) notifies the factor which the market value is to be multiplied in case of rural areas, (v) appoints Officer-in charge of Land Acquisition Section in the Office of the Collector as Administrator for Rehabilitation and Resettlement and (vi) limits agricultural land acquisition, as required by the RTFCLARR, 2013.
11 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
31. There are 6 water tankers (2-6000 litres and 4-4000 litres) available with Nagar Parishad use to distribute the water for special occasions and in summer season Though, the piped water distribution is available in the city the coverage seems to be very poor with only 22% of the households has connectivity. Most of the old city wards water requirement is met by the hand pumps and open wells. Total length of transmission and distribution line is 32.26 kms in which is laid out to be 30 years. So 100% inhabitants of Pawai town are not getting water supply due to non-availability of distribution network where as other main components have been executed fully or partly.
B. Proposed Water Supply
32. Proposed project components. The design population & water demand of the Pawai town is as under:-
Sr. No.
Project Component Design Period
in Years
1 Pumping
(i) Pump house(civil works) 30
(ii) Electric motors and pumps 15
2 Water treatment units 15
3 Pipe connection to several treatment units and other small appurtenances
30
4 Raw water and clean water conveying mains 30
5 Clear water reservoirs at the head works. Balancing tanks and services reservoirs (other head and ground)
15
6 Distribution System 30
33. The primary objective of the proposed water supply subproject:
(i) service improvements is to achieve safe and sustainable water services both in
terms of services to residents and cost recovery
(ii) conservation of precious water resources. The project envisages providing 100
percent coverage of population with continuous, pressurized and safe drinking
water services and achieving progressively increasing cost recovery by
expanding the coverage and increasing operating efficiency.
34. DETAILS OF PROPOSED WATER SUPPLY WORKS 1. Proposed Renovation of Existing Bridge/Annicut on Patne river 2. Proposed Intake well for 3.70 MLD at Patne river 3. Proposed Water Treatment Plant for 3.70 MLD. 4. Proposed Clear Water sump for 3.5 LL capacity at WTP Headwork. 5. Existing OHT of 5.25 LL capacity is to be utilized for Zone-1 6. Proposed GSR of 2.00 LL capacity for Zone-2
12 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
III. FIELD WORK AND PUBLIC CONSULTATION
A. Public Consultation 32. Consultations were undertaken with key stakeholders in line with ADB’s requirements
pertaining to environment and social considerations. Tools used for consultation were stakeholder meetings and focus group discussions (FGD). Consultant has carried out extensive consultations with affected communities, municipalities and stakeholders, including individual face to face interviews and public consultations.
The major stakeholders are: (a) The municipalities, its elected members and staff who will be required to oversee the construction of the distribution networks and WTP as well as be directly responsible for the maintenance of the installations (b) Local residents who will take initiative to connect their houses with the water distribution line. (c) Local business people and traders (d) School Students and College Students (e) Community whose livelihood is related to the river e.g., Washer men, boatmen
(f) The opinion makers are intimately acquainted to and well regarded by the community. They need to be enlisted in spreading environmental awareness within the community as well as in conveying the benefits of the project.
33 Field visits were made to all proposed sites and pipeline alignments and the potential impacts and mitigation measures discussed with stakeholders. These consultations helped identify the felt needs/concerns and apprehensions of the communities related to the project and priorities of concerned stakeholders. Discussions were held with people residing at and/or having businesses at/near the proposed subproject locations. Consultations revealed that people are aware of the problems of the existing water supply system in the city as they are getting 35lpcd and are willing to cooperate in the proposed project. The field visits and interactions helped ascertain that no further survey and inventories are required. The following table 2 provides a summary of consultations and discussions held.
13 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Table 2 : Summary of Consultation with Stakeholders Date Locatio
n No. of Participants
Participants Topics Discussed Issues
7th
Jan. 2016
At community hall
Total=25 M=12 F=13
Chairperson of ULB, Chief Municipal Officer, elected representatives, Junior Engineer
Present drinking water supply source and its condition
Need of improvement of the present situation
Briefing on project objectives probable implementation procedures
Potential positive and negative impacts due to project implementation
Land use and area to be covered under the project
Drinking water user charge
Concerned shown about the a financial burden on the Nagar Parishad.
The Nagar Parishad do not have capacity or resource to be party in sharing the loan repayment.
The Chairman of the ULB expressed willingness to accept the project;
Pawai Nagar Parishad is operating water supply system for the town but capacity to be build.
Operation and maintenance of the facilities developed under the project and community participation;
Probability of keeping the poor and the vulnerable out of the user charge
15th Jan. 2016
Pawai Nagar Parishad
Total -20 (Female- 09 Male -11)
Residential welfare Association ,Vyapari Sangh and
Project effective for Pawai community people
Community participation in project implementation
Completion of project on time. Vyapari Sangh cooperate when laying
done in congested whole sale market
Assured full support during implementation.
27th Jan., 2016
Slum area
M=10 F=9 T=19
Slum dwellers Briefing on project objectives probable implementation procedures
Potential positive and negative impacts due to project implementation
Experiences sharing on - livelihood activities, Resettlement and
None of the people knew about the proposed project. On learning about the project, they expressed that they were happy that the entire community would be benefited from the upgraded water supply.
14 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes etc.
Grievance Redress procedures
They are agreed on house connections but they face problem in paying hiked water tariff.
30th Jan. 2016
Ward 4&6
Total= 34 F=14 , M=20
Residents of ward 4 & 6 not having existing distribution line
Knowledge of project No coverage of present system Willingness to connect
The residence of ward become happy to know that they get distribution line in new scheme
They showed willingness to take connections
7th Feb. 2016
ward no. 14
Total - 29 (Female 15, Male - 14)
Community People Status of existing drinking water supply system;
Need for improvements to present system;
Relevant information of the upcoming project and benefits of the project.
Potential positive and negative impacts due to project implementation
Ensuring no income loss
The area has insufficient and inadequate drinking water resource. Water supply to the area is done through two tube wells that supplies water to the community people. The area faces severe water crisis during the summer season when the ground water level drops.
The community willingly accepted the project. The community members expressed that their economic situation would prevent them from paying water user charges. (The men work as daily laborers and the women Housewives).
7th Feb..2016
Market area
Total=15, male-10 Female-5
Street vendors & shopkeepers
Temporarily shifting of weekly vegetable market during excavation.
shifting of Street vendors. Shifting or adjusting extended potion
of shopkeepers.
As excavation not been able to done at night because labour will not get agree to work in night shift so shifting will be done at a vacant place near or next lane such that no income loss takes place due the civil work. Vendors get agreed on proposal
Like small hotels owners showed
15 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
concern during excavation dust spoils eatable items.
8th Feb.. 2016
Ward no-8
Total – 27 ( Female – 11 & Male – 16)
Community People
Status of existing drinking water supply system;
Need for improvements to present system;
Relevant information of the upcoming project and benefits of the project.
Potential positive and negative impacts due to project implementation
Ensuring no income loss
The area has insufficient and inadequate drinking water resource. They purchase water from private source and have to pay INR 200 per month (per family). The area faces severe water crisis during the summer when the ground water level drops.
The community willingly accepts the project and are willing to pay user charges.
Note: Boatmen and washermen were not observed near the proposed intake well location on Mahanadi river, hence need for a separate consultation with them was not perceived.
16 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
IV. INVOLUNTARY RESETTLEMENT SAFEGUARD PRINCIPLES
Based on the ADB’s SPS, 2009 and LARR Act, 2013, following core safeguard principles govern the MPUSIP :-
Table 3: Screening of Safeguard principles for subproject
S.
no
Safeguard principles applicable for subproject Screening done or
Action taken
Screening of the sub-projects to identify involuntary resettlement
impacts and risks and endeavor to avoid or minimize resettlement
impact by exploring viable alternative design or alternate locations
for infrastructure components in public land
Appendix-1
Carrying out consultations with stakeholders, host communities
and non-government organizations; ensuring their participation in
planning, implementation, and monitoring and evaluation of IR
programs
Table 2
Vulnerable groups, including households headed by women, the
elderly, the differentially able, and indigenous groups, those
without legal title to land and property, and those living below
poverty line (BPL) will be given special assistance to improve their
socioeconomic status and also ensure their participation in the
consultation process.
Table 2
Ensure that displaced persons without titles or any recognizable
legal rights to land are eligible for resettlement assistance and
compensation for loss of non-land assets. Absence of formal title
to land should not be a bar to policy entitlements
No, displaced.
During designing of
subproject taken into
consideration to
avoid displacement.
Compensation for all lost assets acquired or affected is based on
the principle of replacement cost2 to be determined by a Valuation
Committee3 formed under the District Collector will determine the
replacement cost.
No, Displacement
Provide physically and economically displaced persons with
needed assistance, including the following: (a) if there is
relocation, secured tenure to relocation land, better housing at
resettlement sites with comparable access to employment and
production opportunities, integration of resettled persons
economically and socially into their host communities, and
No, Displacement
17 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
extension of project benefits to host communities; (b) transitional
support and development assistance, such as land development,
credit facilities, training, or employment opportunities; and (c) civic
infrastructure and community services, as required.
All payments, including compensation for the loss of land, assets,
structures, trees, income, and common properties will be made
prior to physical or economic displacement and the
commencement of civil works construction under close monitoring
and supervision.
No, Displacement
Preparation of a draft resettlement plan (RP) detailing the
entitlements of APs/DPs, the income and livelihood restoration
strategy, institutional arrangements, monitoring and reporting
framework, budget, and time-bound implementation schedule.
No, Resettlement
Disclose the draft RP, including documentation of the consultation
process in a timely manner to APs and other stakeholders.
Disclose the final RP and other documents such as the monitoring
reports to APs and other stakeholders; and to be approved by
ADB prior to awarding contract.
No, Resettlement
In accordance with the involuntary resettlement principles of this Resettlement
Framework, no resettlement issue in Pawai Water Supply subproject.
18 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS Water Supply 34. No land acquisition or resettlement impacts are anticipated for any of the proposed civil works for Pawai water supply subproject.. The Existing Annicut on patne river is constructed, height proposing 3.00 mt to meet the ultimate water demand. The geographical condition of the area around upstream side of proposed renovation Annicut it is measured that the width of patne river is about 120 to 160 mt and depth of water pool is around 7 mt and 1500 mt long. The calculation for available water quantum of
water by increasing the height of proposed Annicut about 3.0 mt are as under.
Calculation of storage will be made available after renovation of Annicut :- (I) Existing Pool capacity 4 mt depth x 100 mt width x 1000 mt long=0.40 MCM.
19 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
(II) Strorage increasing after Construction of Annicut of 3 m hight ,average width of
river 120m to 160m and Length of Water storage is around 3000m = 2 x 120 x
1500=0.36 MCM
(III) Total Storage is 0.40 MCM +0.36 MCM =0.76MCM
River flows up to november end therefore 8 month storage will be available and no impact on downstream users. As patne river flows around more than 8 months the downstream users not get effected by increasing the height of Annicut. So no impact .
35. Intake well is proposed on pateni river around 1/2 km from Pawai Nagar Parishad. WTP
is proposed at near patne river .The Pawai WTP/DTW land is now in the government’s possession /ownership. The permission from Water Resource Department for construction of Annicut and extraction of water from patne river , its conditions for granting of NOC. As other sites(OHT and WTP) are coming in the jurisdiction of MP Govt. land so only transfer is required from Revenue Department and laying comes under jurisdiction of Pawai Municipal Parishad.
35. In Pawai town raw water abstraction 3.8 MLD will be done from Patne river, then treated and supplied to the town. Construction of Intake well, raw water pump house, the proposed water treatment plant (WTP) will be undertaken on land belonging to Water Resource Department (WRD) and Government of Madhya Pradesh. The land has been in the Revenue Department’s possession for many years and was not acquired in anticipation of ADB funded MPUSIP, as revealed through discussions with the Revenue officer of Revenue Department’s during meeting on 7th March 2016.
36. The existing 1 OHT capacity 5.25 lakhs litre is in good condition and GSR of capacity 1.16 LL is not in a good it is proposed to be discarded and new proposed to be constructed at same place .The raw water rising mains will be laid underground from the intake well to WTP site along an existing road belonging to Municipal. Total land requirement for the proposed WTP is 1.5 ha; as the land parcel belongs to GoMP, The ULBs shall apply for No Objection Certificate (NOC) from WRD for raw water extraction and construction of Intake well at source. The other sites are revenue land (GoMP), for construction of the proposed water works ULB has to take NOC or transfer of land.
37. New distribution pipelines (32.26kms) are proposed to be laid along existing road ROWs. Proposed pipe diameters range between 75 mm and 350 mm. Pipe laying activity on roads in the most congested market areas and densely built-up areas has been carefully planned to avoid IR impacts including temporary economic impacts to hawkers, shops and businesses. Measures will be taken to minimize excavation, disturbance to pedestrians and traffic and avoid income loss to business, while minimizing road reconstruction costs.
37. Temporary impacts to traffic/access to shops and residences due to digging of pits for trenchless pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management. Mobile hawkers will be assisted to move to places nearby, to ensure their earnings are not affected. No income loss is anticipated.
38. House Service connections: Providing house service connection tapping from a distribution main/ sub-main including one tapping saddles, elbows, service pipe from tapping point to the chamber near property boundary or inside the property boundary as per the direction with U-ball valve, using 20mm Medium Density Polyethylene pipes
20 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
(MDPE) pipe 5 m long. The work shall include excavation, road restoration, etc complete. The connection shall have:- i) The town is having total number of households 3581.So all the connections are considered in this project. ii)Domestic water meters: Supply and installation of AMR compatible water meters for each house service water connections 3581of 15 mm size, brass body,horizontal inferential multi jet type, magnetic drive with anti-fraud shield and dry dial with IP 68. Meter shall be made of copper or any other suitable anti corrosive metallic
39. Site inspections and transect walk was carried all along the proposed laying of clear water feeder mains (150.00 m ).The proposed pipeline for clear water feeder mains will be laid along the tow of the existing village road ROW (75m common pipeline )and 350.00m along ROW); the clear water feeder mains to be laid in Pawai will be along the Nagar Parishad roads. The 32.26kms distribution network pipelines in Pawai will be laid along the roads of the respective Nagar Parishads. Details of land ownership for each water works component to be constructed are given in Appendix 1.
40. The distribution network will pass through a Mandi or Haat areas in outer area of Pawai
near college and weekly vegetable market area in ward number 10 (every Thursday)
approximately spread over a stretch of 50 m. The Nagar Parishad officials suggested
that it can be temporarily shifted to a vacant place in front of Mandi area, such that no
income loss takes place due the civil work involved for laying of pipelines for distribution.
The weekly market day will be avoided for construction. Only mobile vendors will be shifted to a nearby location during the period of construction and assistance to shift will be provided by the contactor.
Appendix 2 provides the list of stakeholders and community people consulted.
41. The roads in the core city area of both the towns are very narrow and congested with
pedestrians and vehicles, while the roads in outer areas are wide. No necessity for full
closure of roads is identified. Proposed distribution pipe-laying on roads in most part of
the town will not have any permanent or temporary IR impact. Hawkers and vendors
have been witnessed along the road side for most part of the distribution network pipe-
laying. Laying of transmission mains and distribution network pipelines in the project
area has been carefully planned to minimize disturbance to pedestrians and traffic and
avoid income loss to businesses.
42. Potential temporary impacts to traffic/access to shops and residences due to digging and excavation for pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management. Though there are no mobile hawkers along the internal roads where the water works will be implemented, if any such cases are reported, they will be assisted to move to nearby location to ensure that their business remains uninterrupted. In case temporary shifting of vendors with temporary structures is necessary, such shifting will be undertaken on a weekly holiday, to avoid income loss on the day(s) of shifting. The vendors will be assisted to shift and will be able to continue plying their trade during the construction period at the alternative location. No income loss is anticipated.
21 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Table 4: Raw water rising,Clear water and Distribution network
Raw water rising main and Clear water feeder main
Distribution network
22 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Table 5: Proposed sub-project components in Pawai Water Supply Subproject and their involuntary resettlement impact status
Components Capacity Unit (No.)
Length Land ownership
IR Impact IP Impact
Water Supply
1 Renovation of Existing Annicut
0.76 MCM Water Resource Department
Existing Bridge /Annicut is on Pateni river renovated to increase the storage capacity
None
1 Intake well 3.70 MLD 1 Water Resource Department
The water source is pateni river. Intake well is proposed near Annicut. Land identified belongs to WRD. Its vacant land.
None
2 Water Treatment plant for surface water
3.70 MLD 1 Government land in possession of UlB
10.0 hectares of vacant land belonging to Revenue Department, GoMP identified for proposed water treatment plant (WTP) near existing WTP.Khasra details and Khasra map refer Appendix -1. The land has been in the Revenue Department’s possession for many years and was not acquired in anticipation of ADB funded MPUSIP
None
3 Clear Water Sump
3.5 LL 1 Government land in possession of UlB
The vacant land belonging to Revenue Department, GoMP identified for proposed near proposed water treatment plant (WTP).The land has been in the Revenue Department’s possession for many years and was not acquired in anticipation of ADB funded MPUSIP
3 Over Head Tank (OHT)
5.2LL 1 Government land
The vacant land belonging to Revenue Department, GoMP identified for proposed Over Head Tank at zone -1. Khasra details and Khasra map refer Appendix -1.
None
4 GSR 2.0LL 1 Government land
The vacant land belonging to Revenue Department, GoMP identified for proposed Ground level Service Reservoir at zone -2 .Khasra details and Khasra map refer Appendix -1.
4 Guard cum operator house at WTP and Boundary
3 Government land
A guard cum operator house and a boundary wall with gate are proposed at water treatment plant complex (vacant land). Details of land availability and
None
23 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Components Capacity Unit (No.)
Length Land ownership
IR Impact IP Impact
wall with gate ownership are given in Appendix-1. Boundary walls are also proposed at the 2 OHT sites, both existing.
6 Chemical Storage and dosing pump house
1 Government land
Proposed within the water treatment plant complex. Vacant land, belonging to Revenue Department, GoMP (serial no. 2).
None
7 Distribution Pipeline
HDPE pipe -62483 mtrs
32.26kms Road RoW (public land)
Pipelines pass through existing road RoWs (government roads). Temporary impacts on traffic/access to shops and residences anticipated in some places, will be avoided/mitigated. Contractor to provide signages indicating available alternate access route to minimize traffic disruptions. Contractor will have to ensure access to shops and residences as per EMP provisions, and will have to avoid construction on weekly haat / market day.
No additional impacts on IPs other than temporary access disruptions identified as IR impacts for all people in coverage area.
8 Household connections with domestic metres
3581 - During construction period, access to residences and shops likely to be temporarily affected. Contractor will have to ensure access as per EMP provisions.
No additional impacts on IPs other than temporary access disruptions identified as IR impacts for all people in coverage area
24 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
CONCLUSIONS
A. Summary and Conclusions
43. No significant IR impacts are assessed at identified sites for sub-project components, as adequate vacant land is available for the proposed facilities, within the compounds of government lands. The site for new OHT and WTP at Pawai was owned by Revenue and Intake well is constructed on Water Resource Department Land NOC for that is under approval. The land records and details of acquisition if any, of these sites, shall be appended to the updated DDR. For linear components (pipe laying) or those proposed along government road ROWs, temporary disruption to road users, pedestrians and community members will be avoided In the most congested zones of Pawai Safety measures and mitigated during construction by the contractor through simple measures such as provision of planks for pedestrian access to shops and traffic management. A budgetary provision is made for costs likely to be incurred by PMU/PIU for updating of this Project . Table 5:Budget for replenishment
S.no Description Target group Estimated cost Source of fund 1 For consultation (Due
Diligence Report ) project area INR 20,000; Included in
subproject cost 2 Communication (Plan) and
grievance redress project area(grievance cell zone wise)
INR 700,000 Included in subproject cost
3 Tanker supply for areas where existing water supply disrupted during construction
Affected areas INR 150,000 Included in subproject cost
4 10% contingencies persons of project area
INR 87,000 Included in subproject cost
Total INR 9,57000 , B. Next Steps
. The DDR needs to be updated with the following information:
Land records for each subproject site which are appended (Intake well, WTP ) in DDR; NOC from Water Resource Department for proposed Intake well at Patne river to be
taken will be included in updated DDR:
NOCs from concerned departments for Intake well and for WTP proposed on Water resource Department land and Revenue land; included in updated DDR
Properly labeled photographs of all existing/new Project sites(as location photograph appended with this report area required (Appendix-4)
In addition to the above, in order to improve the quality of consultations, local community organizers will be appointed for Project under package; record of consultations held with
local communities and other stakeholders to be included in updated/final DDR.
25 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Figure 1. Options for location of water extraction arrangements in patne dam
Figure 2.1 Site locations on Google map
Figure 2.2. location of Existing OHT & GSR with ROW
26 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Figure 2.3. Complete locations with ROW
Figure 3. Proposed Distribution Network for Pawai Water Supply
27 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
28 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Appendix -1. Details of Land Ownership for each Water Works Component to be Constructed
Component Location Ownership of Land proposed
Plot No. (Khasra No)
Land Available(Sqm)
Availability of land Record
Status of NOC Sites
Annicut On the downstream of Patne river
Owned by Water Resources Department
Not required - - NOC to be obtained by ULB from concern department
Intake well On Patne river near
chandah ghat
Owned by Water Resources Department
2532/1
120.00
Yes
NOC to be obtained by ULB from concern department
Water Treatment plant
near kalahi mandir road
Owned by Government of Madhya Pradesh
2820/1 (15.74 Ha.)
30000.00
Yes
NOC to be obtained
CWS Owned by Government of Madhya Pradesh
2414/1 Yes NOC to be obtained
OHT near Toriya old water tank
Owned by Government of Madhya Pradesh
2412/1(6.07 & 6.073 Ha.)
Yes
29 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
GSR near Cheel Ghar (postmartum center)
Owned by Government of Madhya Pradesh
3387
225
Yes
30 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Appendix 2. Stakeholder Consultation photographs and list of participants
Community Consultation during Transect Walk
31 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
List of participants
32 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
33 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Consultation with elected representatives
34 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Appendix-3. INVOLUNTARY RESETTLEMENT SCREENING CHECKLISTS
A. Introduction
1. Each project/subproject/component needs to be screen for any involuntary resettlement impacts and indigenous people impacts which will occur or already occurred. This screening determines the necessary action to be done by the project team.
B. Information on project/subproject/component:
a. District/ Administrative Name: Panna
b. Location (km): Pawai ,110 Kms
c. Civil work dates (proposed): NA
d. Technical Description: Pawai-Water Supply Subproject
C. Screening Questions for Involuntary Resettlement Impact
2. Below is the initial screening for involuntary resettlement impacts and due diligence exercise. Both permanent and temporary impacts must be considered and reported in the screening process.
Involuntary Resettlement Impacts Yes No Not known
Remarks
Will the project include any physical construction work?
Construction of WTP and OHT proposed
Does the proposed activity include upgrading or rehabilitation of existing physical facilities?
One existing OHT is taken in project SCADA is proposed as rehabilitation.
Will there be permanent land acquisition? Only Revenue land sites selected for construction of WTP and OHT
Will it require temporary land acquisition? As per Bid document temporary site for workers camp and storage of material site will be decided. According to that temporary land acquisition will be done on rent basis.
Is the ownership status and current usage of the land known?
All sites on Revenue Land sites and all are in vacant state.
Are there any non-titled people who live or earn their livelihood at the site or within the corridor of impact (COI) / Right of Way (ROW)?
Land is totally vacant
Will there be loss of housing? Will there be loss of agricultural plots? Will there be losses of crops, trees, and fixed assets (i.e. fences, pumps, etc.)?
As distribution line will be proposed along the road in town no losses to crop, tree and fixed assets.
35 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Involuntary Resettlement Impacts Yes No Not known
Remarks
Will there be loss of businesses or enterprises?
During laying of distribution lines in congested lanes temporary arrangements will be made, pipeline will be located in unused Government lands alongside the existing roads and can be constructed without causing disturbance to houses and commercial establishments.
Will there be loss of incomes and livelihoods? In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses, Street vendors and shops will minimize the impact to acceptable levels.
Will people lose access to facilities, services, or natural resources?
Any disruption of public facilities or services will be taken care of during excavation.Grievance redress cell will be formed wardwise to settle the grievances soon
Will any social or economic activities be affected by land use-related changes?
Will people lose access to natural resources, or common property resources, or communal facilities and/or services?
If land use is changed will it have an adverse impact on social and economic activities?
Will access to land and resources own communally or by the state be restricted?
Are any of the affected persons (AP) from indigenous or ethnic minority groups?
If yes, please describe the situation
D. Involuntary Resettlement Impact
3. After reviewing the answers above, EA/ Safeguard Team confirms that the proposed subsection/ section/ subproject/component (tick as appropriate):
36 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
[ ] Has involuntary resettlement (IR) impact, a resettlement plan (or corrective action plan) is required
[ Y ] Has No IR impact, no resettlement plan is required. Prepared By: MARS consultant
Signature:
Name: Jay Mehta
Position: Project coordinator
Verified by:
Signature:
Name:
Position:
Date: 13.03.2016 Date:
37 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Appendix-4. Khasra Details and Maps Pawai khasra map for WTP land
Note: Khasra is land record maintained by the state government, which depicts for each land parcel, the parcel number, ownership, area and land use. The Khasra/land record is usually accompanied by a scaled map. The above records depict that the proposed WTP site is owned by government and has an total area around 12.62 hectares.
38 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
39 MaRS Planning and Engineering Pvt. Ltd., Ahmedabad
Appendix 5. Certificate of Land Status from Chief Municipal Officer