Due Diligence Report – Social Safeguards (Land Acquisition and Resettlement) Project number: 42486-016 April 2016
IND: Madhya Pradesh Urban Services Improvement
Program – Water Supply Improvement in Boda
Package Number: MPUSIP-1A Prepared by the Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank. This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
LAND ACQUISITION and RESETTLEMENT DUE
DILIGENCE REPORT
Project Number: 42486
April, 2016
IND: Madhya Pradesh Urban Services
Improvement Program –
Boda Water Supply Scheme, District: Rajgarh
1 DRA Consultants Private Limited, Nagpur
CURRENCY EQUIVALENTS
(As of April 01, 2016)
Currency unit –Conversion INR1.00 = $.0.015
$1.00 = INR 67.00
ABBREVIATIONS
ADB - Asian Development Bank
FGD Focus group discussion
GOI - Government of India
KL Kilo Liter
GOMP - Government of Madhya Pradesh
KM - Kilometer
LARR Land Acquisition, Rehabilitation and Resettlement Act
LPCD Liter per Capita per Day
MDPE Medium Density Polyethylene pipes
MLD Million Liter per Day
MPUDC - Madhya Pradesh Urban Development Company
MPUSIP Madhya Pradesh Urban Services Improvement Program
NOC No Objection Certificate
OHT - Over Head Tank
O&M - operation and maintenance
PMU - Program Management Unit
PWD - Public works Department
R&R - Resettlement and Rehabilitation
RF - Resettlement Framework
RP - Resettlement Plan
ROW - Right of Way
RWGM Raw water gravity main
SPS - Safeguard Policy Statement
SPU safeguard policy update
ULBs - Urban Local Bodies
WRD - Water Resource Department
WSS Water Supply Scheme
WTP - Water Treatment Plant
2 DRA Consultants Private Limited, Nagpur
Table of Contents
I. INTRODUCTION 4
A. BACKGROUND 4
B. PROJECT DESCRIPTION 4
C. SCOPE OF THIS REPORT 5
II. POLICY FRAMEORK, AND INTITLEMENTS 5
A. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation Error! Bookmark not defined.
and Resettlement Act , 2013 – Error! Bookmark not defined.
B. ADB Safeguard Policy Statement, 2009 (SPS) Error! Bookmark not defined.
III. SUBPROJECT DESCRIPTION 6
A. Existing Water Supply 6
B. Proposed Water Supply 8
IV. FIELD WORK AND PUBLIC CONSULTATION 10
A. Outline of Fieldwork 10
B. Field work Report 10
C. Public Consultation 11
V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS 12
A. Water Supply 12
VI. CONCLUSIONS 15
A. Summary and Conclusions 15
LIST OF TABLES
Table 1:- Service Level Benchmarks of Water Supply Sector ................................................. 6
Table 2: Program Components ................................................................................................. 7
Table 3:- Status of Existing Water Supply............................................................................. 13
Table 4: Summary of consultations, meetings and focus group discussions.................................
18
3 DRA Consultants Private Limited, Nagpur
Table 5: Proposed Sub-project components in Boda water Supply subproject District Rajgarh
And their Involuntary Resettlement impact Status ...................................................................... 20
Table 6: Budgetary provision................................................................................................ 22
LIST OF FIGURES
Figure 1: Existing water supply component in Boda Town ...................................................
15
Figure 2: Location for Floating Barge in Kunwar Chain Sagar Dam.....................................
23
Figure 3: Location for proposed WTP.................................................................................... 24
Figure 4: Location of Raw Water Feeder Mains.................................................................... 25
Figure 5: Location of Clear Water Feeder Mains................................................................... 31
Figure 6: Layout Plan for Boda WSS .....................................................................................
32
LIST OF APPENDIX
Appendix 1: Details of Land Ownership for each Water Works Component to be constructed
.................................................................................................................................................
33
Appendix 2: Details of consultation photographs and list of participants.............................. 34
Appendix 3: INVOLUTARY RESETTLEMENT SCREENING CHECKLIST................... 36
Appendix 4: Details of Khasra Map .......................................................................................
39
4 DRA Consultants Private Limited, Nagpur
I. INTRODUCTION
A. BACKGROUND
1. Government of Madhya Pradesh (GoMP) with a sector project loan funding from Asian
Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services
Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh
Urban Development Company Limited (MPUDC) shall be the Implementing Agency (IA)
and the State Urban Development and Housing Department (UDHD) shall be the executing
agency for the Project. A project management unit (PMU) created under MPUDC is
implementing MPUSIP.
2. MPUSIP’s physical components include (a) improvements to water in 64 project towns;
and (b) sewage and storm water collection and treatment services proposed in two (2)
identified towns (Khajuraho, and Rajnagar).The project also includes an institutional
strengthening component and a project management and administrative support
component.
3. The Indigenous Peoples Planning Framework (IPPF) for MPUSIP outlines the objectives, policy principles and procedures for compensation and other assistance measures for tribal people who may be displaced/ affected due to project implementation. A detailed description of compensation measures and assistance is provided in the entitlement
matrix..
4. Need of the Sub-project: It is observed that Nagar Parishad is somehow able to supply
only 0.46 MLD water to people of town with the help of 4 tube wells, 30 hand pumps and
1 open wells. There is no proper water supply infrastructure like treatment plant in the
town, also 100% distribution network are not available in the town. Water from the
existing sources like tube wells and open wells are directly supplied to existing OHT.
Around 6 Km of distribution network is being laid down around year 2000 and leads to a
water loss of approximately more than 45%. Sometimes chlorine / bleaching power is
being used for the purpose of treatment. Due to the regular extraction of water, ground
level of water is going down and down. Present ground water level in the Boda town is
approximately 700 feet below the ground level. Since 70 HP pumps are installed in 4 tube
wells, electricity consumption is also very high.
B. PROJECT DESCRIPTION
5. The salient features of the subproject are as below:
• Provision for supply of 1.5 MLD raw water from Kunwar Chain Sagar dam up to WTP for
Boda town.
• Submersible Pumps to be installed on Floating Barge / Contoon. This floating Barge /
Contoon will float on the water in Kunwar Chain Sagar Dam.
• Design, supply, construction, installation, testing, commissioning of 1.5 MLD WTP at
Khasra No – 811/1
• Reconditioning of existing 300 KL OHT and 500 KL OHT in new scheme.
• Laying of Raw Water pumping/ Gravity main from Kunwar Chain Sagar Dam to WTP of
length 12.8 KM
• Lay of clear water feeder main from WTP to OHT of total length 200 M
• Laying of distribution network of total length 9672 M
6. The main objectives of the project are as follows:
• Supplying pure drinking water.
• Promote sustainable measures to increase potable water supply to the population.
• Water supply through future sustainable source developments.
• Water supply through improvements of safe yield of existing water sources.
• Water supply through improvements to water treatment works.
• Drinking water supply contributes towards a sustainable regional development.
• To improve the current state of the water cycle of Boda through improvements in the
separate components of the water supply system in investment program.
C. SCOPE OF THIS REPORT
7. This land acquisition and resettlement due diligence report is prepared for the proposed
Water Supply package for Boda Municipal Parishad, dist. Rajgarh under which
Construction of water treatment plants, new pipe laying or pipe replacement (usually along
public roads). The proposed subproject will focus on metered water supply for domestic,
institutional and commercial users, including water resource identification and treatment,
water storage tanks, distribution pipes and metered connections to each household in the
towns covering a population of 11100 in Boda (population as in 2018) and estimated
population on which it is designed for the year 2048 is 16000. All the municipal wards of
the town are covered in the project.
8. A due diligence process was conducted to examine the land acquisition and resettlement
issues in detail, in line with ADB SPS 2009. This report describes the findings and
provides copies of relevant documents, resolutions, minutes of meetings and photographs.
This land acquisition and resettlement due diligence report needs to be read along with the
Resettlement Framework prepared for MPUSIP.
9. Upon project implementation, the Social Safeguards Personnel at PMU, MPUDC will be
required to undertake a review of this due diligence report, prepare a confirmation letter or
report documenting any modifications for the subproject and submit to ADB; and receive a
'no objection' confirmation from ADB prior to start of construction in the subproject.
II. POLICY FRAMEORK, AND INTITLEMENTS
10. The Resettlement Framework (RF) prepared for MPUSIP sets out the objectives,
principles, eligibility criteria and entitlements for APs, based on ADB SPS, 2009 and
LARR 2013 as well as national and state laws for protection of street vendors. Until
recently, all activities related to rehabilitation and resettlement in the State of MP had been
based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR) and
National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007). GoMP adopted
LARR 2013 on 3rd October,
5 DRA Consultants Private Limited, Nagpur
III. SUBPROJECT DESCRIPTION
A. Existing Water Supply
11. It is observed that Nagar Parishad is somehow able to supply only 0.46 MLD water to
people of town with the help of 4 tube wells, 30 hand pumps and 1 open wells. There is no
proper water supply infrastructure like treatment plant in the town, also 100% distribution
network are not available in the town. Water from the existing sources like tube wells and
open wells are directly supplied to existing OHTs. Around 6 Km of distribution network is
being laid down around year 2000 and leads to a water loss of approximately more than
45%. Sometimes chlorine / bleaching power is being used for the purpose of treatment.
Due to the regular extraction of water, ground level of water is going down and down.
Present ground water level in the Boda town is approximately 700 feet below the ground
level. Since 70 HP pumps are installed in 4 tube wells, electricity consumption is also very
high.
12. Details of present water supply infrastructure available in the Boda town are mentioned in
the below table:
Table 3:- Status of Existing Water Supply
Present Water Sources
Tube Wells 8 (4 Working)
Hand Pumps 30
Well 1
Lake -
Dam Kunwar Chain Singh Sagar Dam - appox 11 Km
River Utavali Nadi
Existing Water Supply Facilities
Intake Well Not Available
RWRM /
RWGM Not Available
WTP Not Available
CWRM /
CWGM Not Available
MBR Not Available
GSR 100 KL & 60 KL in Ward No 8 & 9 respectively
BPT Not Available
Nos of OHT 2 Nos
Capacity
(KL) Stagin
g Ht.
(m)
Containe
r Ht. (m) Year of
Construction Location
OHT - 1 300 21 5 2001 15
OHT - 2 500 17 5 2015 15
Available
Storage 800 Kilo Liters
6 DRA Consultants Private Limited, Nagpur
Capacity
Material Pr.
Class Diameter Length Construction
Year
Distribution ACP - 200 500 m
2000 Network Length ACP - 150 600 m
GI - 80 4500 m
Present Water Supply MLD 0.46
LPCD 17.5
Water Connections
Domestic 1200
Commercial /
Bulk 0
Total 1200
Connection Charges Connection
charges Rs. 2000 for General & Rs. 1000 for ST & SC
Water Meters
Domestic -
Commercial /
Bulk -
Total 0.00
Water Charges Domestic Rs. 50 / month
Commercial /
Bulk Not Available
Water Supplied to wards N0./s
Not Supplied - Partially -
Fully 1 to 15 on alternate day
Estimated water losses 45%
Present Staff
Engineer Chemist Lineman Operational
Staff Total
1 - 1 1 3
Miscellaneous Water Supply Coverage 35%
Existing Tube Well at Boda Tube Well at Boda
7 DRA Consultants Private Limited, Nagpur
bodExisting 500 KL OHT at Boda Existing 300 KL OHT at Boda
Sump Well from Boda Ward No 3 Pump House at 300 KL OHT
Open Well at Boda Open Well at Boda
Figure 1: Existing water supply component in Boda Town
B. Proposed Water Supply
Population Forecast
2018 (Initial) 11100
2033 (Intermediate) 13500
2048 (Ultimate) 16000
Rate of Water Supply 70 LPCD
Daily Water Demand (MLD) Water Demand (MLD)
8 DRA Consultants Private Limited, Nagpur
2018 (Initial) 1.00 MLD
2033 (Intermediate) 1.30 MLD
2048 (Ultimate) 1.50 MLD
Proposed Water Source Ground Water NA
Surface Water Kuwar Chain Singh Sagar Dam
Raw Water Pumping Hours 23 Hrs / Day
Head Works Arrangement
for Surface Water Source
Head Works
Arrangement
Water will be lifted from Kunwar Chain Sagar Dam with
the help of Submersible Floating Pumps. Submersible
Pumps will be mounted on Floating Barge / Pontoon.
Pump House cum
Store Room 10 m x 10 m will be constructed near dam.
Transformer
(KVA) 63
HT / LT Line 1 Km
Raw Water Pumping Machinery
Type Submersible Pump Sets
Discharge (LPS) 15.70
Motor (Hp) 12.50
Head (m) 29
Quantity 2 Nos (1 Working& 1 Standby)
Raw Water Pumping / Gravity Main
Main Raw Water Rising Main
Pipe Type DI K-9
Diameter (mm) 200
Length (m) 12800
Water Treatment Plant
Type Rapid Sand Filter Type
Capacity 1.50 MLD
Transformer
(KVA) 75
HT / LT Line 2 Km
Clear Water Pumping Machinery
Type Centrifugal Pumps
Discharge (LPS) 15.70
Motor (Hp) 15.00
Head (m) 30.00
Quantity 2 Nos (1 Working& 1 Standby)
Clear Water Pumping / Feeder Main
Main Clear Water Feeder Main
Pipe Type DI K-9
Diameter 150
Length 200
Required Storage Capacity 2033 (Intermediate) Not Required
Distribution Network 2048 (Ultimate) Material Pr Class Diameter Length Total
HDPE PN 10 75 7069 9672 m
9 DRA Consultants Private Limited, Nagpur
HDPE PN 10 90 665
HDPE PN 10 110 334
HDPE PN 10 125 336
HDPE PN 10 140 360
HDPE PN 10 160 47
HDPE PN 10 180 279
HDPE PN 10 225 142
HDPE PN 10 250 439
Land Requirement for WTP
Required Area (Ha) 0.21
Khasra No. 811/1
Location Near 500 KL OHT in Boda Town
Available Area
(Ha) 0.76
Number of Households 2018 (Initial) 2091
Requirement of Staff for
Scheme Management
Engineer 1
Pump Operator 2
Helper / Fitter 4
Electrician / Mechanic 1
Watchman 3
Lab Assistant / Chemist 1
Accountant 1
Total 13
IV. FIELD WORK AND PUBLIC CONSULTATION
13. The Resettlement Plan was prepared in consultation with stakeholders including affected
persons, beneficiaries/local people, and ULB officials. Consultations and focus group
discussions (FGDs) were conducted to seek feedback from local people and other important
stakeholders on the proposed development interventions, perceived impacts and mitigation
measures and their participation.
A. Outline of Fieldwork
14. During the visit, a field inspection of proposed subproject facility locations and pipeline
alignments that had been identified was undertaken. These included field visit to the
identified sites and alignments and stakeholder consultations. The entire land requirement for
the proposed subproject component will be fulfilled by government lands. The details of
selected lands for subproject components are given in the Appendix-1
B. Field work Report
• We met the ULB Officials, Public Representatives, Stake Holder and Prominent People
of Boda Town. A List of officials from whom details of the town for preparation of
water supply scheme is collected during site visit. Held various discussions during the
meeting.
• During the meeting and discussion, we have gathered the present situation of water
supply in the town and the n requirement of the stack holder. Based on present water
supply arrangements and gaps arrives are well documented.
10 DRA Consultants Private Limited, Nagpur
• With the ULB Authorities, we visited all the possible water supply sources and
identified locations for all other the components of water supply scheme.
• We have studied the all the options of possible water supply source, its dependability,
quality assurance of source available and the distance from the town.
• Water from the selected source was collected and tested from the Laboratory of Bhopal
Municipal Corporation Laboratory, Bhopal. Also test report is obtained for designing
purpose.
• We have ensured the water security from the concerned department like WRD etc such
that best chosen water source is made available to ULB for the purpose of water supply
scheme.
• We have contacted revenue authorities to ensure the land acquisition, secured in the
ownership of ULB or Revenue Department Govt. of Madhya Pradesh for WTP and
Service Reservoirs.
• After getting all the required data for the preparation of DPR, we have mobilized the
survey team for the survey work. Focusing road survey for water supply distribution
system. Based on elevation differences in individual command areas and required
pressure conditions at lines near households.
C. Public Consultation
15. Extensive consultations were undertaken with key stakeholders in line with ADB's
requirements pertaining to environment and social considerations. Focus group discussion
(FGD) conducted at nearby locations of Water Treatment Plant sites proposed. The following
outcomes of consultations:
(i) The consultations helped to identify the felt needs /concerns and apprehensions of the
communities related to the project and priorities of concerned stakeholders.
(ii) Consultations revealed that people are aware of the problems of the existing water supply
system in the town and are willing to cooperate in the proposed project.
(iii) Consultations with the key stakeholders revealed that drinking water supply system if a
problem area for the town and they will fully accept the project.
16. The major stakeholders targeted during consultations are:
(a) The municipalities, its elected members and staff who will be required to oversee the
construction of the distribution networks and WTP as well as be directly responsible for the
maintenance of the installations
(b) Local residents who will take initiative to connect their houses with the water distribution
line.
(c) Local business people and traders
(d) School Students and College Students
(f) The opinion makers are intimately acquainted to and well regarded by the community.
They need to be enlisted in spreading environmental awareness within the community as well
as in conveying the benefits of the project.
11 DRA Consultants Private Limited, Nagpur
Table 4: Summary of consultations, meetings and focus group discussions
Sr.
No. Location
No. of
Participant Topics of discussion
Issues/ Concern and Mitigation
Measures
1 Nagar
Parishad
Office,
Boda
15 Sub project design and pipe laying, location of sub project component like WTP, OHT
Solicited support from ULB staffs. Location of all component of
proposed WSS is decided by
consultation of local ULB official
and local representatives
2 Nagar
Parishad
Office,
Boda
22 The participants were
apprised about proposed
Project, its components and
their likely impacts that
may accrue and also to seek
the cooperation and support
from the community.
The community expressed their
willingness to provide support.
Concerns about affordability of
water tariff in case of increase
expressed.
Few traders expressed their concern
about impact on their business
during to excavation of road. People request to speed up the
construction work to minimize the
impact.
V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS
A. Water Supply
17. No land acquisition or resettlement impacts are anticipated for any of the proposed civil
works for Boda water supply subproject.
18. WTP capacity is of 1.5 MLD is proposed to be constructed at Khasra No – 811/1 Near 500
KL OHT in Boda Town. The ownership of land is verified and is in possession of Revenue
Department, Govt. of Madhya Pradesh and considered land is ensured for the purposed of
water supply scheme. The process has being initiated for the allocation land for
construction of WTP.
19. There exist 300 KL (OHT – I) & 500 KL (OHT – II) capacities OHTs in the Boda Town.
We have proposed to use these OHTs in new scheme with some reconditioning.
20. As per the design calculations, 1 numbers of Clear Water Feeder Main (CWFM) are
proposed to be laid from Clear Water Sump at WTP. CWFM – I having dia150 mm&
length 200 m DI K9 pipe will feed 300 KL (OHT – I).
21. Separate centrifugal pumps are proposed for each clear water feeder main having capacity
15 Hp along with 100% standby for CWFM – I.
22. House Service connections : Providing house service connection tapping from a
distribution main/ sub-main including one tapping saddles, elbows, service pipe from
12 DRA Consultants Private Limited, Nagpur
tapping point to the chamber near property boundary or inside the property boundary as per
the direction with U-ball valve, using 20mm Medium Density Polyethylene pipes (MDPE)
pipe 5 m long. The work shall include excavation, road restoration, etc complete. The
connection shall have:-
i. Electro fusion Tapping Ferrule shall be provided with a SS-304 Brass cutter with
cutting edges for making hole / tapping on the Mains and Fusion joint in sucha manner
that the 20-63mm diameter outlet depending on requirement of the house service
connections rotatable 3600
to the axis of pipeline. The town is having total number of
household’s 2091 .So all the connections are considered in this project.
ii. Domestic water meters: Supply and installation of AMR compatible water meters for
each house service water connections 2091 nos. 15 mm size, brass body, horizontal
inferential multi jet type, magnetic drive with anti-fraud shield and dry dial with IP 68.
Meter shall be made of copper or any other suitable anti corrosive metallic.
23. Site inspections and transect walk was carried all along the proposed laying of clear water
feeder mains (150mm).The proposed pipeline for clear water feeder mains will be laid
along the tow of the existing town road ROW; the clear water feeder mains to be laid in
Boda will be along the Nagar Parishad roads. The 9672 m distribution network pipelines in
Boda will be laid along the roads of the respective Nagar Parishads. Details of land
ownership for each water works component to be constructed are given in Appendix 1.
Appendix 2 provides the list of stakeholders and community people consulted.
24. Civil works in the project include linear excavation for laying pipes along the roads,
placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4
m — 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road
reinstatement will be undertaken by the contractor as part of the civil works. The roads in
the core city area of both the towns are very narrow and congested with pedestrians and
vehicles, while the roads in outer areas are wide. No necessity for full closure of roads is
identified. Proposed distribution pipe laying on roads in most part of the town will not have
any permanent or temporary IR impact. Hawkers and vendors have been witnessed along
the road side for most part of the distribution network pipe-laying.
25. Laying of transmission mains and distribution network pipelines in the project area has
been carefully planned to minimize disturbance to pedestrians and traffic and avoid income
loss to businesses. Potential temporary impacts to traffic/access to shops and residence due
to digging and excavation for pipe laying are possible during construction; however, these
will be mitigated by ensuring access to properties through provision of pedestrian planks,
provision of adequate signage, and careful traffic management.
13 DRA Consultants Private Limited, Nagpur
Table 5: Proposed Sub-project components in Boda water Supply subproject District
Rajgarh and their Involuntary Resettlement impact Status
Sr No. Component Capacity Unit
(No.)
Length Land Ownership
IR Impact IP Impact
Water Supply
1 Intake well &
pump house 1 Water
Resource Department
Intake well will be built near Kunwar Chain Sagar Dam
None
2 Water Treatment Plant
1 Revenue Land
WTP of capacity 1.5 MLD is
proposed in Boda Near 500 KL
OHT in Boda Town. The land is
vacant and of Revenue
Department.
None
4 Guard cum
operator house,
Boundary wall
with MS gate
1 Revenue Land
One proposed at treatment plant &
compound area. The land is
identified as Gov. land. Vacant Land
None
5 Transmission
mains 13000m Road RoW
(Public
land)
Transmission passed through
unused / vacant/ barren public
land
None
6 Chemical
storage and
dosing pump
house
1 Road RoW (Public
land)
At treatment plant and compound
areas. The land is of Revenue
Department. Vacant Land
None
7 Distribution
pipeline (HDPE)
9672m Road RoW (Public
land)
Pipeline pass through existing rod
RoW (Government road). Temporary impacts on traffic/
access to shops and residents in
some areas. Contractor will
provide signages indicating
available alternatives access route
to minimize traffic disruptions.
Contractor will have to ensure
access to shops and residents as
per EMP provisions.
None
8 House hold
connections 2091 During construction period, access
to residents and shops likely to be
temporarily affected. Contractor
will have to ensure access as per EMP provisions
None
14 DRA Consultants Private Limited, Nagpur
VI. CONCLUSIONS
A. Summary and Conclusions
26. No significant IR impacts are assessed at identified sites for sub-project components, as
adequate vacant land is available for the proposed facilities, within the compounds of
government lands. The site for new WTP at Boda was owned by Revenue Department. For
which, NOC is under approval. For linear components (pipe laying) or those proposed
along government road ROWs, temporary disruption to road users, pedestrians and
community members will be avoided In the most congested zones of Boda Safety measures
and mitigated during construction by the contractor through simple measures such as
provision of planks for pedestrian access to shops and traffic management.
27. A budgetary provision is made for costs likely to be incurred for updating of this Project
Table 6: Budgetary provision
S. No Description Target group Estimated cost
(INR) Source of fund
1 Consultation cost for (Due
Diligence Report
Affected persons
of project area
1,00,000 Included in
subproject cost
2 Awareness generation Affected persons
of project area
80,000
3 Grievance redress 50,000
4 tanker supply costs 1,50,000
Contingency @10% 38,000
Total 4,18,000
15 DRA Consultants Private Limited, Nagpur
Figure 2: Location for Floating Barge in Kunwar Chain Sagar Dam
Figure 3: Location for proposed WTP
16 DRA Consultants Private Limited, Nagpur
Figure 4: Location of Raw Water Feeder Mains
Figure 4.1: Location of Raw Water Feeder Mains
17 DRA Consultants Private Limited, Nagpur
Figure 5: Location of Clear Water Feeder Mains
Figure 4.11: Location of Raw Water Feeder Mains
28 DRA Consultants Private Limited, Nagpur
Figure 6: Layout Plan for Boda WSS
32 DRA Consultants Private Limited, Nagpur
Appendix 1: Details of Land Ownership for each Water Works Component to be constructed
Infrastructure Location Ownership
of Land
proposed
Land Available/ Khasra
Land Required
Availab ility of land
Status of NOC
Site Photograph
Head work
arrangement
and pump
house cum
store room
Kunwar Chain
Sagar Dam
WRD,
GoMP
Yes NOC to
be
obtained
from
ERD,
GoMP
Raw water
rising mains
(21500m)
The rising mains will
be laid along the
RoW. The road is
wide enough and of
PWD department.
Water Treatment Plant
Near 500 KL OHT Govt. Land 0.759 Hac/
Khasra
No.: 811/1
0.21 Hac yes NOC to be obtained
from Revenue
Departme
nt, GoMP
Clear Water
feeder mains
(2235m)
The feeder Mains
will be laid on
the side of the
road. The road in
Boda is in
custody of PWD.
Distribution
network
(9672 m)
The distribution
network will be laid
on the side of the
road. The road in
Boda is in custody
of PWD and ULB.
A
p
p
e
n
d
i
x
2
:
D
e
t
a
i
l
s
o
f
c
o
n
sultation photographs and list of participants
34 DRA Consultants Private Limited, Nagpur
5 DRA Consultants Private Limited, Nagpur
Appendix 3: INVOLUTARY RESETTLEMENT SCREENING CHECKLIST
A. Introduction
1. Each project/subproject/component needs to be screen for any involuntary resettlement impacts
and indigenous people impacts which will occur or already occurred. This screening determines
the necessary action to be done by the project team.
B. Information on project/subproject/component:
a. District/ Administrative Name: Rajgarh
b. Location (km): 60 Kms from Raggarh
c. Civil work dates (proposed): NA
d. Technical Description: Boda-Water Supply Subproject
C. Screening Questions for Involuntary Resettlement Impact
2. Below is the initial screening for involuntary resettlement impacts and due diligence exercise.
Both permanent and temporary impacts must be considered and reported in the screening process.
Involuntary Resettlement Impacts Yes No Not
known
Remarks
Will the project include any physical construction
work?
Construction of 1.5 MLD WTP
Does the proposed activity include upgrading or
rehabilitation of existing physical facilities? Reconditioning of existing 500 KL OHT by
providing SCADA
Will there be permanent land acquisition? Only government land sites selected for
construction of WTP
Will it require temporary land acquisition?
Is the ownership status and current usage of the
land known?
All sites on Revenue Land Sites and all are in
vacant state.
Are there any non-titled people who live or earn
their livelihood at the site or within the corridor of
impact (COI) / Right of Way (ROW)?
Land is totally vacant
Will there be loss of housing?
Will there be loss of agricultural plots?
Will there be losses of crops, trees, and fixed assets
(i.e. fences, pumps, etc.)? As distribution line will be proposed along
the road in town no losses to crop, tree and
fixed assets.
35 DRA Consultants Private Limited, Nagpur
Will there be loss of businesses or enterprises? During laying of distribution lines in
congested lanes temporary arrangements will
be made pipeline will be located in unused
Government lands alongside the existing
roads and can be constructed without causing
disturbance to houses and commercial
establishments.
Will there be loss of incomes and livelihoods? In narrow streets disruption to road users is
likely and measures like best activity
scheduling, alternative routes, prior
information to road users, houses, Street
vendors and shops will minimize the impact
to acceptable levels.
Will people lose access to facilities, services, or
natural resources? Any disruption of public facilities or services
will be taken care of during excavation.
Grievance redress cell will be formed ward
wise to settle the grievances soon
Will any social or economic activities be affected
by land use-related changes?
Will people lose access to natural resources, or
common property resources, or communal
facilities and/or services?
If land use is changed will it have an adverse
impact on social and economic activities?
Will access to land and resources own communally
or by the state be restricted?
Are any of the affected persons (AP) from
indigenous or ethnic minority groups? If yes, please describe the situation
D. Involuntary Resettlement Impact
3. After reviewing the answers above, EA/ Safeguard Team confirms that the proposed
subsection/ section/ subproject/component (tick as appropriate):
[ ] Has involuntary resettlement (IR) impact, a resettlement plan (or corrective action plan)
is required
[Y]Has No IR impact, no resettlement plan is required.
Prepared By: DRA Consultants, Nagpur
Signature:
Name:
Position: Project Co-ordinator
Verified By:
Signature:
Name:
Position:
Date: Date:
36 DRA Consultants Private Limited, Nagpur
Appendix 4: Details of Khasra Map
Khasara Map & Khasara-Khatoni Record for Water Treatment Plant Location