Dulles Corridor Metrorail Project Phase 2 – Package B Bimonthly Update to the Metropolitan Washington Airports Authority Board of Directors Michael Barker Hensel Phelps
Transcript
Page 1: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Dulles Corridor Metrorail Project

Phase 2 – Package B

Bimonthly Update to the

Metropolitan Washington Airports Authority Board of Directors

Michael Barker Hensel Phelps

Page 2: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Awarded Contract Value $252,989,000

Contract Modifications (114) $34,413,063

Directive Letters (116) $8,116,100

Current Contract Value $295,518,163 4 Change Orders issued since October Board Meeting Outstanding Changes & Time Impacts (35)

Project Status – Value

2

Page 3: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Man-Hours: 2,049,982 (2015 – 2018)

PROJECT DART RATE: 1.17

(Days Away, Restricted, Transferred) Safety Orientation: 2855

(Total Trained)

Project Occupational Safety and Health Administration Recordable Rate:

- Project Wide 0.80 - Hensel Phelps 0.18

Lost Time Rate – Project Wide: 0.09 Lost Time Rate – Hensel Phelps: 0.00

Project Safety Record

3

Page 4: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Notice to Proceed

Aug 18, 2014

Design-Build Performance Period

1,460 Days Oct 16, 2018

Revised (CO-043):

October 3, 2020

Aug 17, 2018

2016 2019 2018 2015 2014 2017

October 2019 Schedule Update

Current Substantial Completion Delays are related to the late connection to the Washington Metropolitan Area Transit Authority’s (WMATA) Operations Control Center.

Final Completion

Substantial Completion

Dec 23, 2018 Feb 21, 2019

August 4, 2020

Project Schedule Overview

4

Page 5: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

• Finish and Punch Site

• System Integration

Testing

• Dynamic Testing • Training • Demonstrations • Safety & Security

Documentation

• Project Closeout • Safety & Security

Documentation

• System Performance Demonstration

Project Schedule – 12 Month Look Ahead

• Safety & Security Documentation

• Substantial Completion

• Finish and Punch Buildings

• Finish and Punch

Site

• Commissioning of Industrial Equipment

• Energizing Third Rail • System Integration

Testing • Training

5

Page 6: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and

Commissioning 2. Installation of Industrial

Equipment 3. Completion of Change

Order Work

Project Status

6

Page 7: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

SIB Wheel Truing

Project Status

SIB Car Hoists 7

Page 8: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

SIB Wheel & Axle Press

Project Status

SIB Overhead Platforms 8

Page 9: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Project Status

SIB Control Tower Monitor SIB Break Room 9

Page 10: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Maintenance of Way Facilities 67,000 sf Percent Complete: 96%

Project Status

Remaining Work:

1. Testing and Commissioning

2. Completion of Change Order Work

10

Page 11: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Project Status – Change Order Work

MWB Parts Washer Relocation

11

Page 12: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Project Status

MWB Maintenance Bay 12

Page 13: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

MWB Second Floor

Project Status

MWB Second Floor 13

Page 14: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Transportation & Police Building 35,000 sf Percent Complete: 98%

Project Status

Remaining Work: 1. Testing and

Commissioning 14

Page 15: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

TPB Looking South

Project Status

15

Page 16: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

TPB 1st Floor TPB 2nd Floor

Project Status

16

Page 17: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

WHB Warehouse 50,000 sf Percent Complete: 96%

Project Status

Remaining Work: 1. Testing and

Commissioning

17

Page 18: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Warehouse Building

Project Status

18

Page 19: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

TWF

Train Wash Facility 14,000 sf Percent Complete: 94%

Project Status

Remaining Work: 1. Testing and

Commissioning

19

Page 20: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Train Wash Equipment Room

Project Status

Wash Bay Entrance 20

Page 21: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Project Status

Track Work Percent Complete: 99%

Asphalt Paving Percent Complete: 100%

Sitework Percent Complete: 99%

21

Page 22: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Tight Gauge at Switches

Washington Metropolitan Area Transit Authority I General Items

Issue: When the switch is moved to the closed (normal) position, the distance from rail to rail (i.e., gauge) is outside design tolerance in the middle of the rail.

Evaluation: This condition existed at the #8 switches. There are 39 #8 switches on the project.

Solution: Have manufacturer adjust the switches to meet the advertised and specified tolerance. Progress: All switches have been reinstalled and meet the design tolerance.

22

Page 23: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Insulated Joints (IJ) Washington Metropolitan Area Transit Authority

Issue: In May 2018, misaligned and oversized holes were discovered in installed IJ. In June 2018, 27 IJ were replaced due to misaligned and oversized holes. In March 2019, eight additional locations were identified and were repaired.

Solution: Repair and replace IJs.

Progress: Identified corrections to IJ have been completed. In June, July, and August, 14 random IJ were selected and evaluated. No deficiencies were found. ATC and signal testing has been performed without any issues in the performance of the IJ.

23

Page 24: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Precast Cracks

Washington Metropolitan Area Transit Authority Inspector General Items

Issue: Hairline cracks observed at the exterior face of the precast wall, primarily identified on the South Elevation of SIB in July 2018.

Evaluation: Analysis performed determined that the cracks are a result of thermal movement in the exterior face of the panel.

Solution: Replace planned sealant with a sealant that will span the hairline cracks.

Progress: Sealant has been approved by Metropolitan Washington Airports Authority (Airports Authority) and WMATA and application started the week of October 29, 2019.

24

Page 25: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Ballast

Washington Metropolitan Area Transit Authority Inspector General Items

Issue: WMATA has expressed concerns over the fines in the ballast.

Evaluation: Records of the ballast reviewed and verified to meet project requirements.

Solution: The Airports Authority and WMATA are discussing revising the requirements for ballast.

25

Page 26: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Issues Requiring Resolution (IRR) & Discrepancy Reports (DR) Status

Washington Metropolitan Area Transit Authority Inspector General Items

Total Open Responded Work Completed -

Documentation to be Submitted

Work to be Completed

IRR 80 14 9 0 5 DR 83 15 7 3 5

26

Page 27: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Project Billing Curve

27

Page 28: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Total Awarded Subcontracts $ 242,343,645 DBE Contracts Awarded $ 43,601,396 (14.75%) Countable DBE Participation $ 38,162,083 (12.91%) Hensel Phelps Current Countable DBE Participation 12.91% Hensel Phelps Contract Goal 14.0%

DBE Participation

Contracts Awarded

DBE Participation Commitment

Disadvantaged Business Enterprise (DBE) Procurement

28

Page 29: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

No. Name of Subcontractor Office Location North American Industry Classification System (NAICS) Codes Contract Value

First Tier DBE Subcontractors 1 Amtrac of Maryland Hagerstown, MD 423860 – Transportation Equipment & Supplies $4,331,823 2 Five Star Septic Reston, VA 562991 – Septic Tank & Related Services $344,000 3 EMSI Engineering, Inc. Manassas, VA 541380 – Testing Laboratories $298,964

4 Athena Construction Group Dumfries, VA 236220 – Commercial & Institutional Building Construction $3,843,589

5 Guaranteed Cleaning Services, LLC Fairfax, VA 561720 – Janitorial Services $187,939 6 Lyn-Phill Construction LLC Washington, DC 238120 – Structural Steel & Precast Concrete $3,740,165

7 Acorn Supply & Distributing, Inc.2 White Marsh, MD 423720 – Plumbing & Heating Equipment and Supplies $42,395 8 Clyde McHenry Hyattsville, MD 238150 – Glass & Glazing Contractors $891,590 9 Terra Site Constructors, LLC Front Royal, VA 237990 – Other Heavy & Civil Eng Construction $628,489

10 First Choice Masonry Washington, DC 238140 – Masonry Contractors $1,353,365

11 Tysons Carpet, Inc. Sterling, VA 423220 – Home Furnishings Merchant Wholesalers $316,335

12 Arthur Construction Company, Inc. Dulles, VA 237310 – Highway Street and Bridge Construction $2,400,896 13 T&A Construction, LLC Dumfries, VA 238130 – Framing Contractors $1,344,010

14 Alexandria Pest Services Springfield, VA 561710 – Exterminating and Pest Control Services $4,850 15 MD Partitions Annapolis Junction, MD 238990 – All Other Specialty Trade Contractors $223,183 First Tier Contracted Total $20,539,398

First Tier Countable DBE Participation $19,951,593

First Tier DBE Subcontractors

29

Page 30: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

No. Name of Subcontractor Office Location North American Industry Classification System (NAICS) Codes Contract Value

Lower Tier DBE Subcontractors 16 EPCM Inc. (MC Dean) Burke, VA 541330 – Engineering Services $1,471,314 17 Apex Petroleum (Independence) Largo, VA 424720 – Petroleum Products Merchant $1,130,000

18 Hampton Aggregates (Independence) Sterling, VA 484220 – Specialized Freight $1,223,190

19 Northeast Construction Inc.2 (Athena) Richmond, VA 238160 – Roofing Contractors $2,476,478 20 A. Esteban & Co., Inc. (SYSTRA) Falls Church, VA 323111 – Commercial Printing $112,209

21 Nassir & Assoc., LLC1 (M.C. Dean) Baltimore, MD 423610 – Electrical Apparatus & Equipment and Wiring $269,594 22 Apex Petroleum1 (Tanks Direct) Largo, VA 424720 – Petroleum Products Merchant $5,047 23 Day and Sons, Inc. (Tanks Direct) Glen Burnie, MD 238910 – Site Preparations Contractors $0

24 Molecular Systems, Inc.1 (Prospect) Mitchellville, MD 238390 – Other Building Finished Contractors $190,621

25 Nationwide Electrical (Tanks Direct) Washington, DC 423610 – Electrical Apparatus & Equipment and Wiring $134,426

26 Resource Industries, LLC1 (Tanks Direct) Bethesda, MD 423320 – Brick, Stone & Related Const Material Supplier $40,250

27 Triton Supply, Inc.1 (MC Dean) Irving, TX 423610 – Electrical Apparatus & Equipment and Wiring $7,893,792

28 Morcom International, Inc.3 (MC Dean) Chantilly, VA 238210/423690 – Electrical Contractor & Other Wiring Install $8,938,423

29 R&R Contracting Utilities (Piping & Corrosion) Olney, MD 237110 – Water Line & Sewer & Related Structures $80,000

30 Soil and Land Use Technology, Inc. (P&C) Potomac, MD 541330 – Engineering Services $18,618

31 Sungate Unlimited, Inc. (Superior Steel) Keymar, MD 238120/332312 – Structural Steel & Precast Conc Contract $1,447,784

Lower Tier DBE Subcontractors

30

Page 31: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

No. Name of Subcontractor Office Location North American Industry Classification System (NAICS) Codes Contract Value

Lower Tier DBE Subcontractors

32 Lanier Steel Products, Inc. (MC Dean) Commerce, GA 423510 – Metal Merchant Wholesalers $268,095 33 Lanier Steel Products, Inc. (MC Dean) Commerce, GA 423510 – Metal Merchant Wholesalers $370,295

34 H.C. HoodCo Inc. (Athena) Bellefonte, PA 423710 – Hardware Merchant Wholesalers $368,794

35 RJ Washington Company, Inc. (Shapiro & Duncan) Bowie, MD 236210 – Industrial Building Construction $4,569,423

36 Delaware Cornerstone Builders, Inc. (Shapiro & Duncan) Landover, MD 236220 – Commercial & Institutional Bld Constructors $864,874

37 Morcom International, Inc. (MC Dean) Chantilly, VA 238210 – Electrical Construction & Other Wiring $511,704

38 Morcom International, Inc. (MC Dean) Chantilly, VA 423610 – Electrical Apparatus & Equipment and Wiring $464,553

39 Lanier Steel Products, Inc. (MC Dean) Commerce, GA 423510 – Metal Merchant Wholesalers $210,410 40 MD Partitions (Athena) Annapolis Junction, MD 238990 – All Other Specialty Contractors $78,213

41 Acorn Supply & Distributing, Inc. (Athena) Richmond, VA 423720 – Plumbing & Heating Equipment & Supplies $159,049

42 Paradise (Superior Ironworks) College Park, MD 238120 – Structural Steel & Precast Concrete Contractors $742,589

43 TMS Supplies, Inc. (MC Dean) Manassas Park, VA 238210 – Electrical Contractors & Other Wiring Installation $1,183,817

44 Prince Construction (Lyn Phill) Washington, DC 238110 – Poured Concrete Foundation and Structure Contractor $121,087

Lower Tier Contracted Total $33,487,936

Lower Tier Countable DBE Participation $28,007,337

Lower Tier DBE Subcontractors

31

Page 32: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Current Project Labor Diversity

Professional Foreman Laborer Operator Finisher Carpenter Painter/Sprayer/Tile

Setter/Glazier Iron

Worker/Welder Electrician

African American 11 6% 1 1% 11 6% 1 1% 2 1% 1 1% 4 2%

Caucasian 56 29% 3 2% 7 4% 10 5% 0% 6 3% 0% 1 1% 14 7%

Hispanic 5 3% 7 4% 6 3% 0% 1 1% 11 6% 8 4% 1 1% 11 6%

Other 6 3% 0% 2 1% 1 1% 3 2%

Female 5 3% 4 2%

African American 31 15% Caucasian 97 49% Hispanic 50 25% Other 12 6% Female 9 5%

32

Page 33: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

*Includes other states PA, WV, NJ, AZ, OH, FL, TN, NC, KY, IN, GA & CA *Manufacturing accounts for 64% of the other states

Current Labor by State

Professional Foreman Laborer Operator Finisher Carpenter

Painter/Sprayer/Tile

Setter/Glazier Pipefitter/Plumber Iron

Worker/Welder Electrician

VA 44 22% 5 2% 8 4% 5 2% 2 1% 11 5% 8 4% 0% 1 1% 22 11%

MD 17 8% 4 2% 12 6% 2 1% 0% 8 4% 0% 0% 0% 7 3%

DC 4 2% 2 1% 0% 1 1% 0% 0% 0% 1 1%

Other 18 9% 2 1% 10 5% 4 2% 0% 0% 0% 1 1% 2 1%

VA 106 53% MD 50 25% DC 8 4% Other 37 18%

33

Page 34: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)

Erosion and Sediment Control In Compliance – No Infractions Spills/Releases In Compliance – No Releases

Environmental

34

Page 35: Dulles Corridor Metrorail Project Phase 2 – Package B...Training 5 . Service & Inspection Facility 186,000 sf Percent Complete: 98.5% Remaining Work: 1. Testing and ... (SYSTRA)