Silver Line – UpdateStatus
• Phase 1• VDOT, WMATA, Fairfax Punchlist – Ongoing
• Fairfax County - 279 items, 203 closed• VDOT with majority of remaining punchlist
items• Project Closeout anticipated at the end of 2015• Task Order Contract awarded May 7, 2015 to
William M Schlosser Construction Co (2 Yr.)• Art in Transit Task Order issued • Final Phase 1 close out - $2.982B • Wiehle Garage – 100% parking utilization
• Phase 2• Total Project Status (all bid packages)
• Overall Project – 20%• Design – 86%• Construction – 6%
• Highlights• Tower crane at Innovation Center Station• Enabling/Utility work – Reston Town Center,
Herndon, Innovation Center Stations • Aerial Guideway at Dulles Airport under
construction• Rail Yard at Dulles Airport in design• Updated schedule for Phase 2 – Fairfax County
adjusted garage schedules to accommodate MWAA schedule adjustment
• Budget - $2.775B• Total Contingency - $551.M (Remaining $507.2M)• Contract extension costs under negotiations
between MWAA and CRC • County has drawn down $25.8m of its $403.3
million TIFIA loan for payments to MWAA
County Activities – Past 60 Days
• Phase 2 Design Reviews • County Coordination
• Town of Herndon• Adjacent Land Owners• Project Partners (MWAA, VDOT, DRPT, WMATA,
Loudoun County)• Fairfax Connector• CIT on land transfer
• Phase 1 Close Out and Punchlist• 2232 approved at Herndon Station for TPSS 13 • SE for Pavilion at Herndon Station (south side) submitted
• PC – July 22• BOS – July 28
• Innovation Center Station Joint Infrastructure Groundbreaking held June 15, 2015, clearing to begin in September
• Herndon and Innovation Center Stations Garages - Value Engineering Completed
• Herndon Station Garage – $800K savings• Innovation Center Station Garage - $4M savings
1
July 14, 2015