Silver Line – Update Status Phase 1 VDOT, WMATA, Fairfax Punchlist – Ongoing Fairfax County - 279 items, 203 closed VDOT with majority of remaining punchlist items Project Closeout anticipated at the end of 2015 Task Order Contract awarded May 7, 2015 to William M Schlosser Construction Co (2 Yr.) Art in Transit Task Order issued Final Phase 1 close out - $2.982B Wiehle Garage – 100% parking utilization Phase 2 Total Project Status (all bid packages) Overall Project – 20% Design – 86% Construction – 6% • Highlights Tower crane at Innovation Center Station Enabling/Utility work – Reston Town Center, Herndon, Innovation Center Stations Aerial Guideway at Dulles Airport under construction Budget - $2.775B Total Contingency - $551.M (Remaining $507.2M) Contract extension costs under negotiations between MWAA and CRC County has drawn down $25.8m of its $403.3 million TIFIA loan for payments to MWAA County Activities – Past 60 Days Phase 2 Design Reviews County Coordination Town of Herndon Adjacent Land Owners Project Partners (MWAA, VDOT, DRPT, WMATA, Loudoun County) Fairfax Connector CIT on land transfer Phase 1 Close Out and Punchlist 2232 approved at Herndon Station for TPSS 13 SE for Pavilion at Herndon Station (south side) submitted PC – July 22 BOS – July 28 Innovation Center Station Joint Infrastructure Groundbreaking held June 15, 2015, clearing to begin in September Herndon and Innovation Center Stations Garages - Value Engineering Completed Herndon Station Garage – $800K savings 1 July 14, 2015
Transcript

Silver Line – UpdateStatus

• Phase 1• VDOT, WMATA, Fairfax Punchlist – Ongoing

• Fairfax County - 279 items, 203 closed• VDOT with majority of remaining punchlist

items• Project Closeout anticipated at the end of 2015• Task Order Contract awarded May 7, 2015 to

William M Schlosser Construction Co (2 Yr.)• Art in Transit Task Order issued • Final Phase 1 close out - $2.982B • Wiehle Garage – 100% parking utilization

• Phase 2• Total Project Status (all bid packages)

• Overall Project – 20%• Design – 86%• Construction – 6%

• Highlights• Tower crane at Innovation Center Station• Enabling/Utility work – Reston Town Center,

Herndon, Innovation Center Stations • Aerial Guideway at Dulles Airport under

construction• Rail Yard at Dulles Airport in design• Updated schedule for Phase 2 – Fairfax County

adjusted garage schedules to accommodate MWAA schedule adjustment

• Budget - $2.775B• Total Contingency - $551.M (Remaining $507.2M)• Contract extension costs under negotiations

between MWAA and CRC • County has drawn down $25.8m of its $403.3

million TIFIA loan for payments to MWAA

County Activities – Past 60 Days

• Phase 2 Design Reviews • County Coordination

• Town of Herndon• Adjacent Land Owners• Project Partners (MWAA, VDOT, DRPT, WMATA,

Loudoun County)• Fairfax Connector• CIT on land transfer

• Phase 1 Close Out and Punchlist• 2232 approved at Herndon Station for TPSS 13 • SE for Pavilion at Herndon Station (south side) submitted

• PC – July 22• BOS – July 28

• Innovation Center Station Joint Infrastructure Groundbreaking held June 15, 2015, clearing to begin in September

• Herndon and Innovation Center Stations Garages - Value Engineering Completed

• Herndon Station Garage – $800K savings• Innovation Center Station Garage - $4M savings

1

July 14, 2015

Silver Line – Herndon Station Garage

2

July 14, 2015

Silver Line – Innovation Center Station Garage

3

July 14, 2015