Status Construction: 94% Complete Final Design: 100% Complete Utility Relocation: 100% Complete Property Acquisition: All rights of entry obtained Track Work: 100% Complete Stations: McLean – 84% Tysons Corner – 79% Greensboro – 69% Spring Hill – 69% Wiehle – 90% First Delivery of 7000-series rail cars – February 2014 Wiehle Garage: 96% Complete Garage Substantial Completions: July 19, 2013 Roadway Improvements: 70% complete September 2013 completion Estimated Cost: $87.9M Budget Revised Budget Authorized: $2.905B Expended to Date: $2.443B (84% of total budget) Fairfax County share of Project expenditures = $369.1M $150M received from Commonwealth Wiehle garage substantial completion Silver Line substantial Completion Start Rev Service JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 2013 Schedule WMATA will determine the revenue operations date (ROD) Scheduled Substantial Completion Dated (SSCD): September 9, 2013 Testing, commissioning, acceptance by WMATA ongoing thru ROD 4 sets of 2 car trains conducting testing 3 rd rail energized WMATA acceptance testing – SSCD to ROD (Sept to Dec/Jan) West Falls Church Yard Completion: January 2014 Sound Box and Tail Track – November 2013 Estimated Passenger Revenue Service: December 2013/January 2014 Current Milestones – Past 30 Days Phase 1 Maintenance and Land Conveyance process ongoing Regional planning effort underway for Phase 1 bus service (Fairfax Connector, WMATA, Washington Flyer, PRTC, Loudoun Transit) Fairfax Connector Phase 1 bus service plan approved June 4, 2013 WMATA lead for Phase 1 marketing and outreach USDOT TIFIA meeting June 21, Funding Partners presented financial plans Timeline 1 June 21, 2013
Transcript
Page 1: Dulles Rail Phase 1-Status Report: June 21, 2013

Status • Construction: 94% Complete • Final Design: 100% Complete • Utility Relocation: 100% Complete • Property Acquisition: All rights of entry obtained • Track Work: 100% Complete • Stations:

• McLean – 84% • Tysons Corner – 79% • Greensboro – 69% • Spring Hill – 69% • Wiehle – 90%

• First Delivery of 7000-series rail cars – February 2014 • Wiehle Garage: 96% Complete

• Garage Substantial Completions: July 19, 2013 • Roadway Improvements: 70% complete

• September 2013 completion • Estimated Cost: $87.9M

Budget • Revised Budget Authorized: $2.905B • Expended to Date: $2.443B (84% of total budget) • Fairfax County share of Project expenditures = $369.1M • $150M received from Commonwealth

Wie

hle

gara

ge

subs

tant

ial

com

plet

ion

Silv

er L

ine

subs

tant

ial

Com

plet

ion

Star

t Rev

Se

rvic

e

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

2013

Schedule • WMATA will determine the revenue operations

date (ROD) • Scheduled Substantial Completion Dated (SSCD):

September 9, 2013 • Testing, commissioning, acceptance by WMATA

ongoing thru ROD • 4 sets of 2 car trains conducting testing • 3rd rail energized • WMATA acceptance testing – SSCD to ROD

(Sept to Dec/Jan) • West Falls Church Yard Completion: January 2014

• Sound Box and Tail Track – November 2013 • Estimated Passenger Revenue Service: December

2013/January 2014 Current Milestones – Past 30 Days • Phase 1 Maintenance and Land Conveyance process

ongoing • Regional planning effort underway for Phase 1 bus

service (Fairfax Connector, WMATA, Washington Flyer, PRTC, Loudoun Transit)

• Fairfax Connector Phase 1 bus service plan approved June 4, 2013

• WMATA lead for Phase 1 marketing and outreach • USDOT TIFIA meeting June 21,

• Funding Partners presented financial plans

Timeline 1

June 21, 2013

Page 2: Dulles Rail Phase 1-Status Report: June 21, 2013

Status • Packet A contract award: May 2013

• Phase 2 Team - Capital Rail Constructors, Joint Venture of Clark Construction and Kiewit International

• Project estimate Packet A = $1.4B - $1.6B vs. $1.177B low bid

• Positive impact on toll rates = $251M (est.) • Packet A Notice to Proceed: July 2013 • Phase 2 Bid Packages:

• Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded

• Packet B – Yard and shop – Procurement Fall 2013 • Packet C – Parking garages (may not be issued)

• Parking garages • DPWES – Building Design Branch is leading the

design/construction effort for Herndon and Innovation Center garages

• Award for Architectural/Engineering for design and construction administration services pending

• Coordination efforts among rail project, DOT, and DPZ staff are underway to discuss the Special Exception (SE) and for the rail stations and entrance pavilions.

• Results of the “Route 28 Grid Analysis” traffic study are being reviewed by DOT planning staff. The results of this study will be used as part of the planning effort related to development and parking garage construction at Innovation Center south.

Budget • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A

savings, and garages funding outside the project: $2.6B

• Cost to build garages in Fairfax County: $135M est.

Schedule • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Current Milestones Past 30 Days • FTA oversight of Phase 2 under discussion: Ongoing • TIFIA Letter of Interest submitted: Ongoing • WMATA Art in Transit: Selection ongoing • Town Center Parkway tunnel design under review by

WMATA and MWAA • USDOT meeting on TIFIA and Funding Partners

financial plans held on June 21 • FTA oversight of Phase 2 under discussion

2

June 21, 2013

Page 3: Dulles Rail Phase 1-Status Report: June 21, 2013

3

June 2013

West Falls Church yard service and inspection building. Formwork and reinforced steel being placed for the shop floor slab. Photo courtesy Stephen Barna, Dulles Corridor Metrorail Project (DCMP).

Page 4: Dulles Rail Phase 1-Status Report: June 21, 2013

4

June 2013

West Falls Church yard new storage tracks in various stages of construction from ballast placement thru final alignment and surface dressing. Photo courtesy Stephen Barna, DCMP.

Page 5: Dulles Rail Phase 1-Status Report: June 21, 2013

5

June 2013

McLean Station Kiss & Ride nearing completion with lighting, landscaping, etc… being installed. Photo courtesy Stephen Barna, DCMP.

Page 6: Dulles Rail Phase 1-Status Report: June 21, 2013

6

June 2013

McLean Station entrance pavilion – final window and curtain wall installation; interior finish work continues. Photo courtesy Stephen Barna, DCMP.

Page 7: Dulles Rail Phase 1-Status Report: June 21, 2013

7

June 2013

McLean Station plaza area looking east with Route 123 on the right. A two stall bus bay sits where the red car is parked. Photo courtesy Stephen Barna, DCMP.

Page 8: Dulles Rail Phase 1-Status Report: June 21, 2013

8

June 2013

McLean Station passenger platform looking south/southwest. Seam roofing system and ceiling work is complete; platform paver and finish work continues. Photo courtesy Stephen Barna, DCMP.

Page 9: Dulles Rail Phase 1-Status Report: June 21, 2013

9

June 2013

Wiehle Station passenger platform looking west. Installation of the concrete pavers, windscreens, lighting, etc… continues. Photo courtesy Stephen Barna, DCMP.

Page 10: Dulles Rail Phase 1-Status Report: June 21, 2013

10

June 2013

Reston Station Blvd construction underway. The large soil stockpile was removed, utility work is nearing completion, and curb/gutter installation began. Photo courtesy Stephen Barna, DCMP.

Page 11: Dulles Rail Phase 1-Status Report: June 21, 2013

11

June 2013

Wiehle Station (north)/Reston Station. View from the top of the bus plaza escalators to the pedestrian bridge. Photo courtesy Heather Diez, FCDOT.

Page 12: Dulles Rail Phase 1-Status Report: June 21, 2013

12

June 2013

Wiehle Station (north). View of the bus plaza platform, including sawtooth bus bays. The escalators lead to the Reston Station pedestrian plaza. Photo courtesy Heather Diez, FCDOT.

Page 13: Dulles Rail Phase 1-Status Report: June 21, 2013

13

June 2013

Wiehle Station (north) parking garage. Color coding by floor and other finishes to be added. Photo courtesy Heather Diez, FCDOT.

Page 14: Dulles Rail Phase 1-Status Report: June 21, 2013

14

June 2013

Wiehle Station. Photo courtesy Andy Miller, DPWES