Management News Marco Verzocchi - Fermilab Cold Electronics Consortium Weekly Meeting 9 April 2018
Transcript
Page 1: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Management News

Marco Verzocchi - Fermilab

Cold Electronics Consortium Weekly Meeting

9 April 2018

Page 2: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Content• LBNC & DOE IPR outcomes

• WBS, Deliverables, Schedule

- Installation / Integration

- Realistic plans

• Topic 2

• Topic 3

04.09.18 Marco Verzocchi | Management News 2

Page 3: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

LBNC• Topic 1

more text

- Sub-topic 1.1

• Sub-sub 1.1.1

- Sub-sub-sub topic 1.1.1.1

- Sub-topic 1.2

• Topic 2

• Topic 3

04.09.18 Marco Verzocchi | Management News 3

Page 4: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

DOE IPR• Topic 1

more text

- Sub-topic 1.1

• Sub-sub 1.1.1

- Sub-sub-sub topic 1.1.1.1

- Sub-topic 1.2

• Topic 2

• Topic 3

04.09.18 Marco Verzocchi | Management News 4

Page 5: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

DOE IPR• Topic 1

more text

- Sub-topic 1.1

• Sub-sub 1.1.1

- Sub-sub-sub topic 1.1.1.1

- Sub-topic 1.2

• Topic 2

• Topic 3

04.09.18 Marco Verzocchi | Management News 5

Page 6: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Construction Schedule• We are being told to plan for the following

• Beneficial occupancy of integration test facility 9/1/21

• Begin integration testing of components at ITF 2/1/22

• Cryostat ready for TPC installation 5/1/23 (1st month reserved

for installation of first wall of TPC field cage)

• Begin closing TCO 5/1/24 (February 24 reserved for second

wall of TPC field cage, March and April reserved for testing and

fixes before TCO closure)

• Detector ready for filling 10/1/24

• Detector ready for operations 10/1/25

04.09.18 Marco Verzocchi | Management News 6

Page 7: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Is this feasible ?• The assumption is that we install 1 row of APAs per week (after

some ramp up time)

• Work 2 shifts per day (6:30-16:30, 14:30-00:30 ?), 1+8+1 hours

• Day 1: cable and test first APA stack

• Day 2: cable and test second APA stack, insert first APA stack inthe cryostat

• Day 3: cable and test third APA stack, insert second APA stack, connect first APA stack to penetration and test

• Day 4: insert third APA stack, connect second APA stack to penetration and test

• Day 5: connect third APA stack to penetration and test

• Day 5 was planned for fixes/repairs ….

04.09.18 Marco Verzocchi | Management News 7

Page 8: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Is this realistic ?• We don’t know that we can stack, cable, and test two APAs in

two 8 hours shifts, needs to be demonstrated (need ~8 hours for

testing alone based on protoDUNE experience)

• Can we run all the cables through the chimneys, connect them

and run a basic test to ensure that we don’t need to take the two

stacked APAs out again in 1 day ?

- This is not the protoDUNE experience, need to understand what can

be improved and whether this is realistic

- I would still prefer to have a full test before putting next row of APAs

• There are a few extra weeks in the schedule, maybe we should

relax a little bit the schedule

04.09.18 Marco Verzocchi | Management News 8

Page 9: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Workshops• There will be a one day workshop prior to the collaboration

meeting to review the needs for integration and test facility (1/2

day) and to review the installation procedure (1/2 day)

• This is clearly insufficient, probably nothing more than two 15

minutes presentations “these are the plans of the CE

consortium”

• Dedicated workshop for the single phase TPC planned, possibly

for Sat 19 May (but need to make sure that everybody who

needs to be there can actually attend)

04.09.18 Marco Verzocchi | Management News 9

Page 10: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Prototypes (i)• Availability of ITF needs to be earlier

- APA consortium plans to start building APAs in early 2021

- Will need at least to stack them at ITF already in Spring 2021

- We could be able to start populating APAs with CE already in Fall

2021

• More prototypes

- protoDUNE APA #7 will be available for testing at CERN in

November 2018

- Will need full complement of protoDUNE electronics plus FEMBs

populated with new ASICs (multiple flavors) for testing prior to TDR

submission

- Checked that we will have access to cold box (will not be moved)

04.09.18 Marco Verzocchi | Management News 10

Page 11: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Prototypes (ii)• First three production APAs will go to CERN in early 2021

• Will populate with new electronics

• Discussion of a protoDUNE run 2 in 2021 / 2022

- TCO closure will be done in such a way that we will be able to

reopen, replace 3 APAs, close again

- This sets the scale for having electronics (pre-production quality)

available in Spring 2021

04.09.18 Marco Verzocchi | Management News 11

Page 12: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

CE Timeline• We are now in the first iteration of the ASICs

• There will be time for 2 more iterations (as long as the

development + testing cycle is short) prior to pre-production

• Will need to make sure that we have a detailed plan available of

what we test and when

• Will need funding for this

• Schedule may be to aggressive, but planning for 3 cycles allows

for problems we may find in ASIC development

04.09.18 Marco Verzocchi | Management News 12

Page 13: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

FY18• The US now has a budget and this may will good for

LBNF/DUNE

• Exact allocation between LBNF/DUNE not yet clear

• We have tried to restrict expenses for FY18 (in part due to cost overruns in protoDUNE)

• Not clear that we will be given a green light to expand scope,but clearly need to do in some areas

- Need to design / fabricate FEMBs for new ASICs and have them ready for testing on protoDUNE APA #7 in November at CERN and on small TPC at Fermilab

- May start next design cycle of LArASIC early

- Please send suggestions, will try to argue with LBNF/DUNE management that this is needed and urgent

04.09.18 Marco Verzocchi | Management News 13

Page 14: DUNE PowerPoint Presentation · available in Spring 2021 11 04.09.18 Marco Verzocchi | Management News . CE Timeline •We are now in the first iteration of the ASICs •There will

Current WBS/Schedule/Deliverables

• DOE IPR recommended having updated cost/schedule ready in

October 2018

• This requires a lot of work

• Preliminary WBS ready (for DUNE international / DUNE-US) in

DocDB-5612

• Will also have a preliminary schedule available there today

• Please check for missing deliverables

04.09.18 Marco Verzocchi | Management News 14