+ All Categories
Home > Documents > e-cd TECHNOLOGY PERFORMANCE EVALUATION ANALYSIS … · STRUCTURE OF ENI 9 ... this definition does...

e-cd TECHNOLOGY PERFORMANCE EVALUATION ANALYSIS … · STRUCTURE OF ENI 9 ... this definition does...

Date post: 23-Apr-2018
Category:
Upload: dinhcong
View: 215 times
Download: 3 times
Share this document with a friend
36
POLITECNICO DI MILANO MASTER OF SCIENCE IN MANAGEMENT ENGINEERING TECHNOLOGY PERFORMANCE EVALUATION ANALYSIS ONSHORE FIELD STUDENT: Ayan Maxutova COORDINATOR: Marika Arena April 2013
Transcript

POLITECNICO DI MILANO MASTER OF SCIENCE IN MANAGEMENT ENGINEERING

TECHNOLOGY PERFORMANCE EVALUATION ANALYSIS

ONSHORE FIELD

STUDENT: Ayan Maxutova COORDINATOR: Marika Arena

April 2013

2

POLITECNICO

DI MILANO

INDEX

1. ABSTRACTION 6

2. DESCRIPTIVE REVIEW 7

3. THE PROJECT 9

3.1 COMPANY DESCRIPTION 9

3.2 ROLE IN THE PROJECT 1914

4. INTRODUCTION 15

5. PROBLEM FORMULATION 17

6. METHODOLOGY 18

6.1 DATA COLLECTION 18

6.2 WELLS OFFSET GROUPS DEFINITION 19

6.3 STATISTICAL ANALYSIS 19

7. CASE STUDIES 22

7.1 ONSHORE WELLS 22

7.1.1 ASSUMPTIONS 22

7.1.3 LEARNING PROCESS ANALYSIS 22

7.1.4 TRIPPING TIME BENCHMARK ANALYSIS 22

7.1.5 CIRCULATING TIME BENCHMARK ANALYSIS 23

7.1.6 NPT BENCHMARK ANALYSIS 24

7.1.7 NET BENEFIT ANALYSIS 25

7.1.8 COST BENEFIT ANALYSIS 27

3

POLITECNICO

DI MILANO

7.1.9 SAFETY 27

8. CONCLUSIONS 28

8.1 PERFORMANCE (ON AVERAGE PER WELL) 28

8.1.1 12 ¼’’ PHASE 28

8.1.2 8 ½’’ PHASE 29

8.1.3 AVERAGE WELL 29

8.2 CAPABILITY TO REACH THE TARGET 30

8.3 SAFETY 30

8.4 ALTERNATIVE TECHNOLOGY (CCS) 30

8.4.1 COUPLER CONCEPT 31

8.4.2 ADDING PIPE 31

8.4.3 PRESSURE CONTROL 32

8.4.4 HOW IT OPERATES 32

8.4.5 CLOSED LOOP SYSTEM 33

8.4.6 IN COMPARE WITH PCE 34

8.5 FUTURE SUGGESTIONS 34

8. REFERENCES 35

4

POLITECNICO

DI MILANO

Table of Figures

FIGURE 3.1. STRUCTURE OF ENI 9

FIGURE 3.2. DIVIDEND AND DIVIDEND YIELD 11

FIGURE 3.3. SHARE PERFORMANCE Q4 2012 11

FIGURE 3.4. EXPLORATION AND PRODUCTION 12

FIGURE 4.1. PCE TECHNOLOGY FINAL CONFIGURATION 16

FIGURE 4.2. PCE TECHNOLOGY APPLICATION OVER TIME 16

FIGURE 6.1. METHODOLOGY 18

FIGURE 6.2. NET BENEFIT ANALYSIS 18

FIGURE 7.1. ONSHORE TRIPPING TIME BENCHMARK ANALYSIS 21

FIGURE 7.2. ONSHORE CIRCULATING TIME BENCHMARK ANALYSIS 23

FIGURE 7.3. ONSHORE NPT BENCHMARK ANALYSIS 24

FIGURE 7.4. ONSHORE TIME PERFORMANCE ANALYSIS 26

FIGURE 7.5. ONSHORE COST BENEFIT ANALYSIS 27

FIGURE 8.4. TOTAL GAIN ANALYSIS 30

FIGURE 8.5. CONTINUOUS CIRCULATING COUPLER 31

5

POLITECNICO

DI MILANO

List of Tables

TABLE 3.1. ENI IN NUMBERS 13

TABLE 8.1. PCE TECHNOLOGY PERFORMANCE – SUMMARY TABLE 28

TABLE 8.2. 12 ¼” PHASE PERFORMANCE 29

TABLE 8.3. 8 ½” PHASE PERFORMANCE 30

6

POLITECNICO

DI MILANO

1. ABSTRACT

What is a well? According to a simplistic definition, a well is just a hole in the ground.

Actually, this definition does not capture the full complexity of the design and realization of

wells in the oil industry that can reach depth of 7000 metres and encounter environments

with extreme pressures and temperatures.

Drilling operations are conducted around the world, often in extreme climatic, environmental

and technical conditions: e.g. in deep waters, arctic and desert locations, in new countries on

the edge of the world. Completion concerns the activities, subsequent to drilling, for the

installation in the well of a battery of pipes and all the equipment that permit the extraction of

hydrocarbons under secure and integral conditions for people, the environment, the reservoir

and the integrity of the well itself.

For big Oil&Gas companies, that has an innovative view of the future and is going to face

increasingly challenging goals, technological innovation in this area is critical in order to

maximise performance while ensuring compliance with international standards of safety and

environmental protection.

The revolutionary PCE – permanent circulating equipment technology permits the continuous

circulation of mud in the well, which maintains a constant down hole pressure over the entire

drilling process, even during the trip in and out of the bottom hole assembly. This makes it

possible to work in wells in which there is the risk of both fracturing the formation (if the

hydrostatic load of the mud in circulation is excessive) and not being able to counterbalance

the pressure of the fluid layer (if the hydrostatic load of the mud in circulation is insufficient).

7

POLITECNICO

DI MILANO

2. DESCRIPTIVE REVIEW

Just like any other excavation activity, drilling an oil well involves two main actions:

overcoming the resistance of rock material in order to detach parts it from the formation and

transporting these parts to the surface to continue detaching new material, so that drilling can

continue without interruption.

The technique which has been used by the oil industry for more than century is called rotary

drilling where a bit, rotated by a system of pipes, excavates the rock.

The bit is positioned at the end of a string of hollow tubular rods with circular section joined

together using special couplings. With this string the bit can be run into the hole and run out

again using a draw work, transmitting the rotating movement generated on the surface by the

rotary table, giving it the weight needed to drill and therefore continue deepening the well.

The rock material excavated in this way is transported to the surface by a drilling fluid (simply

called mud) which circulates through the hollow drill string, is expelled through openings in

the bit and returns to the surface through the annulus between the wellbore and the drill

string.

As the programmed depths are reached the well is lined with pipes, called casing, with

decreasing diameter and just a little less than that of the drilled wellbore; these pipes are 12

meters long and are joined together, run into the hole to the set depth, cemented to the

wellbore wall using a cement slurry and anchored on the surface. The casing is cemented,

with rise of the cement slurry from several hundred meters up to the surface with the aim of

anchoring the casing to the ground, hydraulically isolating the formations drilled, as they

would otherwise cause a series of problems, and protecting the hydrocarbon-bearing levels.

This process is repeated until the programmed depth is reached and the well is then put into

production if hydrocarbon-bearing, or abandoned, if dry.

Oil wells can be drilled onshore and offshore using different rigs depending on the

environment they will be operating in. Both onshore and offshore drilling must fulfill precise

requirements and, as stated above, the two do not differ greatly except in the case of drilling

in deep and ultra deep water where floating rigs or drillships have to be used. In the latter

case it is not the operating sequence that differs but the use of more complex and expensive

equipment because the wellheads, safety equipment, etc. are located on the sea floor, far

from visual and manual control.

On rotary drilling, the technique which has been used for more than a century, the largest

8

POLITECNICO

DI MILANO

and most important component is the drilling rig which has three essential functions:

Lifting the excavation organs (drill string, bit) and well casing equipment;

Ensuring that these components continue to rotate;

Circulating the drilling fluid.

Drilling fluids (called muds because they originally and simply consisted of suspension of

clay in water) are circulated downhole through pipes and flow back up to the surface via the

annulus between the pipes and the wellbore, conveying drill cuttings generated by the action

of the bit. Muds have numerous functions which are all extremely important for successful

drilling and include:

Suspending and conveying cuttings from the bottomhole;

Cooling and lubricating the bit;

Containing fluids in the drilled formations by applying hydrostatic pressure;

Consolidating the wellbore walls, depositing cake on the walls during the filtration

process.

Continuous Circulation: is the ability to maintain uninterrupted flow of drilling fluid to the well

whilst all the steps to add (or remove) joints of “drill pipe” to the drilling string are performed

within the drilling process, including trips in and out of hole.

9

POLITECNICO

DI MILANO

3. THE PROJECT

3.1 COMPANY DESCRIPTION

Eni is one of the largest integrated energy companies in the world,

operating in the sectors of oil and gas exploration & production,

international gas transportation and marketing, power generation, refining

and marketing, chemicals and oilfield services. Eni is active in 90

countries with 79,000 employees.

The commitment of eni to sustainable development means that they grow and retain their

people, contribute to the development and wellbeing of the communities in which they

operate, protect the environment, and invest in technological innovation and energy

efficiency, mitigating the risks of climate change.

Fig.3.1: Structure of eni

TRACK RECORD OF EXCEPTIONAL EXPLORATION SUCCESS

Between 2008 and 2011 eni discovered around 4 bn boe of new resources at a leading unit

exploration cost of 1.7 $/boe. New resources discovered in 2012 amounted to 3,6 bn boe.

10

POLITECNICO

DI MILANO

STRONG PIPELINE OF GROWTH PROJECTS

Between 2011 and 2015 eni will add around 700kboe/d(1) of new production, of which 80%

will come from new giant projects with long plateau periods.

COMPETITIVE COST POSITION

The production is focused on conventional projects, contributing to contain technical risks

and operating costs.

LEADING POSITION IN EUROPEAN GAS MARKET

Eni one of the largest utilities in Europe, with a diversified gas supply portfolio and a strong

position in the industrial, power generation and retail markets.

POTENTIAL VALUE CREATION FROM DISPOSALS

The ongoing disposal of their stake in Snam, the regulated gas transport, distribution and

storage business, will simplify their corporate structure and significantly reduce debt.

ATTRACTIVE RETURNS TO SHAREHOLDERS

In 2012, eni paid a dividend of €1.08/sh (or $ 2.14/ADR), a yield of 5.92%(2). Interim

dividend for 2012 was 0.54 €/share. From Q1 2013, Eni will launch a buy-back program on

up to 10% of its capital.

RECOGNISED LEADER IN SUSTAINABILITY

We are listed on the FTSE4Good and the Dow Jones Sustainability Indices.

11

POLITECNICO

DI MILANO

DIVIDENDS AND SHARE PERFROMANCES

(1) assumption of $90/bbl Brent for 2012-13 and 85$/bbl

2014-15

(2) calculated on Eni avg

share price in Dec 2012

Fig.3.2: Dividend (euro/share) and dividend yield (%)

(3) Peer Group: BP,

Chevron, Conoco,

Exxon, Shell, Total

Fig.3.3: Share performance Q4 2012 (euro)

12

POLITECNICO

DI MILANO

PRODUCTION AND EXPLORATION

Fig.3.4: Exploration and Production

E&P is the main division. It is currently present in 43

countries and is focused on finding and producing oil

and gas. Eni’s strategy is to deliver organic

production growth with increasing returns over the

medium to long term, leveraging on a high-quality

portfolio of assets, exposure to competitive giant

projects and long-standing relationships with host countries. Growth will come from a number

of key hubs around the world, a strategy which combines geographical diversification with

scale benefits and project synergies.

GAS&POWER

G&P is engaged in all phases of the gas value chain: supply,

trading and marketing of gas and electricity, gas infrastructures,

and LNG supply and marketing. Eni sells more than 60% of its

13

POLITECNICO

DI MILANO

gas outside Italy and its leading position in the European gas market is supported by

competitive advantages, including its multicountry approach, long-term gas availability,

access to infrastructure, market knowledge, wide product range and strong customer base.

REFINING&MARKETING

R&M refines and markets fuels and other oil products primarily in

Italy and Central-Eastern European countries. Eni’s R&M division

is relatively small compared to the R&M segment of eni’s peers.

Eni is the largest refiner in Italy and the leading operator in retail

marketing of fuels with a market share of around 30%. Eni’s

strategy in R&M is to cut costs and enhance margins to return to

profitability.

ENI IN NUMBERS

Tab.3.1: eni in numbers

3.2 ROLE IN THE PROJECT

Before coming to Politecnico di Milano I was working in National Bank of the Republic of

Kazakhstan as software engineer of databases. I started working in eni on second year of my

Master degree as risk management consultant for eni. I choosed this work because it was

very interesting for me comparing to other subjects during my first year classes of the master

program. And it was giving me an opportunity for growth as a specialist for my future goals.

For the current project there were 3 of us working on it, and my responsibility included

14

POLITECNICO

DI MILANO

analysing the data through VBA. The data was kept in database, and as a part of my work I

created the VBA functions which analysed the data and gave us ready results out of the

existing database. My background allowed me fastly and easy learn VBA and use it to

simplify and automize the analysis, what was very comfortable as the program could be used

also for other cases.

After getting the results, we were comparing results and completing the overall view on the

technology. It will help in the future to decide should eni use this technology for onshore field

wells.

15

POLITECNICO

DI MILANO

4. INTRODUCTION

During my internship the main responsibility I had was risk management consulting for a

Oil&Gas companies. Different interesting projects I was consulting, and this one is related to

analysis of innovative technology called PCE (Permanent Circulating Equipment) which

allows continuous mud circulation in the well to maintain constant bottom hole pressure while

making-up or laying down drill pipe connections during Drilling Operations1. In this way

bottom hole pressure is kept constant and almost equal to the pore pressure. This ensures

that there are no pressure peaks due to interruptions of circulation which increases the risk of

the formation fracturing (or ballooning effects). The main advantage is the ability to drill in

conditions where there is a very narrow margin between pore and fracture gradient. Benefits

are also achieved in operations safety and NPT reduction.

Starting from its first implementation, the technology has been modified over the years in

order to adapt it to operational needs and to improve overall drilling performances in terms of

time and cost reduction and safety increase. This analysis considers only wells drilled from

year 2009, when the final configuration of PCE Technology has been consolidated.

Permanent Circulating Equipment final configuration (see Figure 4.1) is based on:

PCE Sub, that is a dual flapper tool with a side entry port, run in hole on top of drill

pipe stands. The number of subs required depends on borehole length to be drilled

with uninterrupted circulation;

PCE Manifold, that diverts the flow from the rig stand pipe manifold directly to the PCE

Sub. It is installed on the rig floor and connected to the stand pipe manifold.

1 Reference Document: 10 Golden Rules for eni Drilling Operations

16

POLITECNICO

DI MILANO

Fig.4.1: PCE Technology Final Configuration

Since its first application, eni has drilled as Operator 81 Wells Worldwide using PCE

Technology (see Figure 4.2):

8 wells have been drilled during the development Phase of the technology (before

year 2009);

starting from year 2009 other Operators started to use PCE Technology, with a total

number of 9 applications.

Fig.4.2: PCE Technology Application over the time

Permanent Circulating Equipment (PCE)

17

POLITECNICO

DI MILANO

5. PROBLEM FORMULATION

The main objective of this analysis is to evaluate the performance of PCE Technology

considering the following indicators:

Performance: Time and Cost savings;

Capability to reach the target;

Safety.

It is important to underline that the safety indicator, i.e. improvement of Drilling Operations

due to the existence of dynamic condition when using PCE is well known, sure and

unquestionable. However, its economic impact is extremely variable and not commensurable

with the operational economic impact considered in the analysis.

The analysis will be worked on Onshore Fields, further there is a possibility to analyse

Offshore field also.

18

POLITECNICO

DI MILANO

6. METHODOLOGY

The methodology I’ve used adopted to evaluate the performance of PCE Technology is

based on the analysis of the selected case studies and it follows three main steps (see

Figure 6.1):

Data Collection

Wells Offset Groups Definition

Statistical Analysis

Fig.6.1: Methodology

6.1 DATA COLLECTION

This phase aims to retrieve from Databases all available data (daily drilling reports, surveys,

location, ...) related to:

wells drilled with PCE Technology;

wells drilled with conventional technologies that can be considered “offset” of wells

drilled with PCE.

Collection of all available data related to PCE Technology application through Database

Definition of Wells Offset Groups according to the following characteristics:

Design (Phases, Diameters,… )

Formations

Total Vertical Depth/Measured Depth

Operating environment and sequence

Production/Appraisal/Exploration Projects

Data Preparation and Consolidation

Learning Process Analysis

Selection and normalization of activities affected by PCE Technology:

o Tripping Time o Circulating Time o Non Productive Time (NPT)

Net Benefit Analysis (Time Performance)

Data Collection

Wells Offset Groups Definition

Statistical Analysis

19

POLITECNICO

DI MILANO

The output of this phase is a list of wells with all related information drilled over the years to

be used for the analysis.

6.2 WELLS OFFSET GROUPS DEFINITION

In this phase all available information about wells are analyzed in order to group them

considering similarities related to the following characteristics:

Design (Phases, Diameters, ...);

Formations;

Well Total Vertical Depth (TVD) and/or Measured Depth (MD);

Operating Environment and Sequence;

Production/Appraisal/Exploration Projects.

The output of this phase are two groups of comparable wells: the first composed by wells

drilled using PCE Technology and the second without.

6.3 STATISTICAL ANALYSIS

The analysis carried out to evaluate the performance of PCE Technology is based on the

definition of statistic distributions and Monte Carlo simulations, in order to grant:

Objectivity;

Exhaustiveness;

Replicability.

DATA PREPARATION AND CONSOLIDATION

In order to prepare and consolidate the data for the analysis, activity descriptions available in

each well daily drilling report have been carefully examined and grouped by phases (e.g. 12

¼’’, 8 ½’’, etc...).

This data analysis allows to focus the study only on specific phases where PCE Technology

had been applied.

20

POLITECNICO

DI MILANO

LEARNING PROCESS ANALYSIS

For multiple-well drilling campaigns, performances tend to improve over the time, mainly due

to job familiarization, improvement coordination, development of better and more efficient

tools.

An analysis on the existence of a learning process for each considered Field during drilling

both with and without PCE Technology has been carried out, in order to identify and evaluate

improvements in the average drilling speed [m/day] for the grouped wells. The existence of a

strong learning curve complicates the comparison of drilling performances between wells

drilled in different periods of time because it is difficult to highlight only the effect of PCE

Technology.

SELECTION AND NORMALIZATION OF ACTIVITIES AFFECTED BY PCE TECHNOLOGY

Wells drilled both with and without PCE have been analyzed by phases, in order to compare

performances related to the following parameters affected by the use of PCE System:

NPT caused by circulation losses, drill string sticking, fluid influx, hole cleaning;

Tripping Time (normalized considering the phase length);

Circulating Time (normalized considering the phase length).

Specifically, for both wells drilled with and without PCE, statistical measures (mean, standard

deviation, minimum and maximum) and NPT probability have been calculated. A normal

distribution has been created for each performance parameter, truncating distributions tails at

minimum and maximum values of the dataset, in order to exclude extreme and not relevant

values.

Tripping Time and Circulating Time have been normalized using a continuous distribution,

because they are activities always available. NPT values, instead, have been modelled using

a discrete distribution because they are uncertain events that not always occur during Drilling

Operations.

NET BENEFIT ANALYSIS (TIME PERFORMANCE)

The Total Gain is obtained as total sum of the difference between Tripping, Circulating and

NPT distributions of wells drilled without and with PCE (Net Gain). The Total Gain is

21

POLITECNICO

DI MILANO

expressed as ratio between hours and meters [hrs/m], in order to compare the performances

of wells characterized by different values of phase depth.

The figure below shows how the process of calculating Net Gain for each indicator was held.

The indicators of wells drilled without PCE technology in grey box, minus the indicators of

wells drilled with PCE technology in yellow box, and the result is the Net Gain for each

indicator in red box. After, Monte Carlo simulations have been run, in order to combine

defined distributions for each indicator and to obtain the Total Gain from the implementation

of PCE for each phase.

Fig.6.2: Net Benefit Analysis

Finally, a “target well” has been defined for each Field, considering the average of each

phase length, in order to calculate the overall well duration with and without the use of PCE

Technology.

22

POLITECNICO

DI MILANO

7. CASE STUDIES

7.1 ONSHORE WELLS

ASSUMPTIONS

PCE Technology has been used during Drilling Operations for 13 Onshore wells; the analysis

considers only 7 wells already drilled when the study started and evaluates the performances

relate to the following hole sections, where PCE Technology has been applied):

12 ¼’’ Phase;

8 ¾’’ and 8 ½’’ Phases (considered together for the scope of the analysis due to their

operational analogies).

LEARNING PROCESS ANALYSIS

For each well considered for the analysis (12 wells), an Average Drilling Speed [m/day] has

been calculated.

There is no evidence about any learning process during Drilling Operations both with and

without PCE. As a consequence, it is relevant to carry out the analysis on PCE Technology

performance considering all the reference wells dataset.

TRIPPING TIME BENCHMARK ANALYSIS

The main output of the Tripping Time Analysis is the graph in Figure 7.1. Vertical axis maps

the Tripping Time normalized on phase depth; horizontal axis maps different hole sections

and the two groups of wells (drilled with and without PCE).

The difference between the mean value of Tripping Time (brown bullet) for wells drilled

without PCE and wells drilled with PCE represents the gain (if negative) or the loss (if

positive) of the Operation times between the two groups of wells. The range of variability

between the minimum and the maximum value for each hole section in correspondence to

the two groups of wells is represented with a vertical yellow line.

23

POLITECNICO

DI MILANO

Fig.7.1: Onshore Tripping Time Benchmark Analysis

As a result, a gain of 0,7 hrs/100 m (see Drill 8 ¾’’-8 ½’’ Phase) indicates that wells drilled

using PCE Technology had a Tripping Time of 35 hours less than wells drilled with

conventional technologies in correspondence of a Total Depth = 5000 m.

Regarding Tripping Time for Onshore Field:

there is a relevant improvement of the Tripping Speed during operations using PCE

Technology in 8 ¾’’ – 8 ½’’ Phases.

Tripping Time is comparable for all analyzed wells in 12 ¼’’ Phase.

CIRCULATING TIME BENCHMARK ANALYSIS

Results of Circulating Time Benchmark Analysis are represented in the same way as for

Tripping Time Benchmark Analysis (Figure 7.2); see Paragraph 7.1 for more details.

Regarding Circulating Time for Onshore Field:

Wells WITH PCE Wells WITHOUT PCE Wells WITHOUT PCE Wells WITH PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE

24

POLITECNICO

DI MILANO

there is a relevant reduction of Circulating Time during operations using Permanent

Circulating System Technology in 12 ¼’’ Phase. Moreover, the use of the Technology

significantly reduces the variability in the performance.

Circulating Time is comparable in drilling with and without PCS in reservoir sections (8

¾’’- 8 ½’’).

Fig.7.2: Onshore Circulating Time Benchmark Analysis

NPT BENCHMARK ANALYSIS

The Figure 7.3 shows all NPT (Non Productive Time) causes for our wells in phases 8 ½”

and 12 ¾” if they exist. Both wells drilled with and without PCE Technology are characterized

to have a low level of NPT; the study is limited to Non Productive Time influenced by the use

of PCE Technology. For each field we figured out 5 different types of NPT which are colored

for better view on result (TP01: circulating loss, etc.). On the left axis of the figure 7.3 there

are hours of losses defined for each NPT.

Wells WITH PCE Wells WITHOUT PCE Wells WITHOUT PCE Wells WITH PCE Wells WITHOUT PCE Wells WITH PCE

25

POLITECNICO

DI MILANO

Fig.7.3: Onshore NPT Benchmark Analysis

As a result of Figure 7.3 we see that:

only one well drilled with PCE had non productive time related to Geological Problems

(in 8 ¾’’-8 ½’’ Phase);

wells drilled without PCE had limited NPT related to Circulation Losses and Geological

Problems (both in 8 ¾’’-8 ½’’ and 12 ¼’’ Phases).

NET BENEFIT ANALYSIS

The statistical combination of Tripping Time, Circulating Time and NPT allows to calculate

the overall Time Gain/Loss of the use of PCE Technology for the different hole sections.

Values have been normalized in order to consider the depth of each hole section.

This graph is the result of Monte Carlo Stimulation for the given depth and time spent. On the

right scale we see time (in hours) consumed for given phase and from the bottom scale we

see the depth (in meters) where the phase is. Overall the graph shows (see Figure 7.4):

the Net Benefit mean is represented by a brown line (P50);

Wells WITHOUT PCE Wells WITH PCE

Fie

ld 1

Fie

ld 2

Fie

ld 3

Fie

ld 4

26

POLITECNICO

DI MILANO

the range of variability between P25 (first quartile) and P75 (third quartile) for each

hole section is represented with a yellow area. Considering a reference Phase TD, a

wide range of values between the minimum and the maximum of the yellow area

highlights the existence of a high variability in the statistical analysis of parameters.

Fig.7.4: Onshore Time Performance Analysis

The use of PCE Technology brought relevant time reductions when used both for 12 ¼’’ and

8 ¾’’-8 ½’’ Phases; particularly:

considering 12 ¼’’ Phase, there is a relevant time gain (from about 45 hrs to about 55

hrs) that increases with the increase of Total Depth (Measure Depth) [m], with a

reduced range of variability (P25 – P75);

8 ½’’ Phase has a time gain (from about 20 hrs to about 40 hrs) that increases with the

increase of Total Depth (Measure Depth) [m], with a wider range of variability (P25 –

P75).

27

POLITECNICO

DI MILANO

COST BENEFIT ANALYSIS

The Time Benefit Analysis has been replicated for Costs, in order to evaluate the overall

economic benefit of the PCE Technology implementation. On this graph Monte Carlo

stimulation was done only for one phase.

Considering the Phase Total Depth (MD from 2500 m to 6500m), the use of PCE

Technology has brought clear advantages in terms of Costs, increasing with the length of

the wells.

Fig.7.5: Onshore Cost Benefit Analysis

SAFETY

Safety is the state of being "safe", the condition of being protected against consequences of

failure, damage, error, accidents or any other event which could be considered non-

desirable. This can take the form of being protected from the event or from exposure to

something that causes health or economical losses. PCE Technology improving safety by

simplifying the process and bringing its advantages into the work.

PCE

PCE

28

POLITECNICO

DI MILANO

8. CONCLUSIONS

The application of PCE Technology during Drilling Operations of Onshore Fields highlighted

overall positive performances in terms of:

Time and Cost savings;

Increased capability to reach the target;

Safety.

The three case studies show different levels of performances in correspondence of the

identified indicators, as summarized in the table below (Table 8.1).

Performance: Time&Cost Savings

Capability to Reach the Target

Safety

Onshore Field ++ + ++

++ : High Positive Impact + : Positive Impact

= : No Impact - : Negative Impact

Tab.8.1: PCE Technology Performance – Summary Table

Detailed analysis on three performance parameters are provided in the following Paragraphs.

8.1 PERFORMANCE (ON AVERAGE PER WELL)

12 ¼’’ PHASE

Considering both Fields, the use of PCE Technology brought relevant average Tripping and

Circulating Time reductions when used in 12 ¼’’ Phase (see Table 8.2).

29

POLITECNICO

DI MILANO

Tripping Time [h/100m] Circulating Time [h/100m]

Onshore Field -0.17 -0.83

Tab.8.2: 12 ¼’’ Phase Performances

8 ½’’ PHASE

Considering the three Case Studies, PCE Technology benefits are less relevant towards

Tripping and Circulating Time while drilling 8 ½’’ Section (see Table 8.3).

For the scope of the analysis 8 ½” Phase has been considered together with 8 ¾” Phase due

to their operational technologies.

Tripping Time [h/100m] Circulating Time [h/100m]

Onshore Field -0.70 +0.01

Tab.8.3: 8 1/2’’ Phase Performances

AVERAGE WELL

In Figure 8.4 we see the result of the distribution where Mean = -102,9 hours of saving time.

So this figure shows The Total Gain related to the use of PCE Technology when drilling an

hypothetical “average well” for the considered Case Studies, is always positive for Onshore

Field.

Time Gain

Time Loss

Time Gain

Time Loss

12 ¼” Phase

8 ½” Phase

30

POLITECNICO

DI MILANO

Fig.8.4: Total Gain Analysis

8.2 CAPABILITY TO REACH THE TARGET

The use of PCE Technology should be suggested in order to increase the probability to

successfully drill reservoir sections characterized by a high variability in the geological

structure of the area.

No relevant benefits can be identified from the analysis of the Onshore Fields.

8.3 SAFETY

The use of PCE Technology always brings a relevant qualitative benefit related to safety

increase, principally thanks to:

better capability to manage downhole pressure (mitigating influx/losses);

additional mechanical barriers (valves through drill pipe).

8.4 ALTERNATIVE TECHNOLOGY (CCS)

In December 1998, Ayling brought this continuous circulation concept before the Wells

Group of the Oil & Gas Industry Task Force, set up by the UK Government's Department of

Trade & Industry. Ayling said the concept was rated one of the top three most promising

technologies for reducing cost.

To implement the recommendations of the task force, an organization called the Industry

Technology Facilitator (ITF) was set up. ITF now has a membership of 14 oil companies. The

ITF acts as a catalyst to facilitate joint industry projects (JIP).

Maris managed to get the Continuous Circulation Coupler project approved as ITF's very first

JIP in April 2000, and funding for the project started in October 2000. By this time, Ayling

31

POLITECNICO

DI MILANO

said that he and private investors had spent over four years and $1 million in the

development of the coupler. He said that ITF had been the valuable key to bringing the

system forward and getting the operators involved.

Shell, BP, BG, Statoil, and Veba have now funded the outline design of the system, which

was carried out by Varco under contract to Maris and completed in May. At this point Varco

was selected as a natural choice to fabricate and market this product. "They know all about

the components of the coupler," Ayling said, and could distribute, market, and support the

coupler in the field.

Varco has now licensed the technology from CDL under a worldwide agreement that allows

CDL to retain ownership of the technology and receive royalties and allows Maris to continue

to develop the technology. Ayling said "The royalties from the coupler should generate

several million dollars per year, and this will fund enough research and development to make

a real difference to the industry."

COUPLER CONCEPT

At any stage in drilling operations, there is an optimum downhole pressure. The mud weight

and rate of circulation are adjusted to keep the pressure within the range required, but there

is no way to keep this pressure near constant.

Simply put, if the pressure is too low, oil and gas may begin to flow into the wellbore and

generate a 'kick.' If the pressure is too

high, the formation may fracture and

'lost circulation' may occur. In some

areas, these drilling margins are very

narrow.

As it happens, a significant component

of the downhole pressure is the

dynamic pressure drop in the annulus,

which is necessary to get the mud,

cuttings, and debris to circulate back to

Fig.8.5: Continuous Circulating Coupler

the surface. Drillers refer to this dynamic pressure drop as the Effective Circulating Density

(ECD), representing the mud density that would produce the same downhole pressure if the

32

POLITECNICO

DI MILANO

mud was not circulating. If it is possible to maintain a steady ECD, or steady downhole

pressure, continuously, there would be many benefits.

ADDING PIPE

Using the conventional system, whenever a new stand of drill pipe has to be added to the

drill string, drilling and mud circulation have to stop. The dynamic pressure drop to surface

disappears, and the downhole pressure temporarily drops, often to a level below the static

pressure. The cuttings and debris sink in the hole and settle on the bottom.

This static mud heats up. Then, when circulation begins again, there is a surge of pressure,

which usually overshoots the steady circulating pressure. The drill bit, which has usually

been raised off the bottom to lessen the chance of becoming stuck, has to drill through the

settled cuttings and debris before recommencing the drilling of the formation.

The downhole pressure difference between the circulating and static conditions can be

hundreds of psi, and the overshooting of the static pressure and the steady running

pressures can also be hundreds of psi.

Basically, at the bottom end of the hole being drilled, several miles from the drilling rig, the

effect of stopping circulation is at least highly inconvenient and can be disastrous.

PRESSURE CONTROL

With continuous circulation, the downhole pressure can be lowered to near the formation

pore pressure. This is called 'near balanced drilling' and can increase the rate of penetration

(ROP) of the drill bit dramatically. When the appropriate equipment is installed to handle oil

or gas in the returning mud, the pressure can even be maintained at a level of under

balance.

A major problem in under-balanced drilling is that the gas accumulates when drilling stops.

This has to be circulated out of the hole before drilling operations can properly resume. With

continuous circulation, the gas does not accumulate, and drilling can recommence as soon

as the new stand of drill pipe is connected.

For lateral wells, and even more so for extended reach wells, the continuous movement of

the returning mud and cuttings is vital to keeping the hole clear. Conventionally, in horizontal

sections, when circulation and drillstring rotation stop, the cuttings only have to sink a couple

of inches to settle - and perhaps, never move again. The is particularly the case since the

33

POLITECNICO

DI MILANO

renewed rotation of the drill string tends to mash the settled cuttings into the wellbore. The

resulting reduction in effective wellbore diameter can cause the 'bottom hole assembly' to

become stuck.

HOW IT OPERATES

The coupler operates like a control room airlock. The coupler is a pressure chamber that can

seal around a drillpipe tool joint. The tool joint is disconnected under pressure inside the

coupler. Mud is pumped into the lower half of the coupler and flows down the drillstring so

that the top drive sub no longer needs to supply the circulating mud.

The top drive sub can be retracted into the upper half of the coupler, and a barrier can be

closed between the two halves of the coupler. This done, the upper half can be de-pressured

and drained, and the top drive can be extracted from the coupler to fetch another stand of

drillpipe.

Meanwhile, the circulation of the drillstring continues with mud being supplied directly from

the lower half of the coupler. The new stand is inserted into the upper half of the coupler,

sealed, filled with mud, brought up to pressure, and the barrier is then removed so that the

stand can be connected to the drillstring, without any interruption to the flow of drilling fluid.

The components can be based on pipe rams for sealing against the drillpipe, a blind ram as

the barrier and upside down slips for the snubber.

CLOSED LOOP SYSTEM

The combination of a coupler and under-balanced drilling yields the 'closed loop system' that

can properly control the downhole pressure. The mud input pressure can thus be adjusted or

maintained at the optimum level through the entire drilling process. The ECD can be finely

adjusted and maintained at any desired level continuously. This is a real improvement in

safety, says Ayling.

For example, a kick is easier to detect. The pressure variations, which normally occur for up

to half an hour or more after each connection due to variations in the 'cuttings in mud

density,' the mud temperature and density itself, and accumulated gas, are now eliminated.

There are no reverberations from the last circulation stoppage to mask the subtle first signs

of a kick.

34

POLITECNICO

DI MILANO

Also, kicks are far less likely to occur since the dramatic drops in bottomhole pressure are

avoided.

A kick cannot occur while the mud is disconnected from the drillstring because it remains

connected and flowing at all times. If a kick occurs, the pressure can be immediately

adjusted and maintained, even while re-inserting stands of drillpipe to return the bit to

bottom, when this is needed.

IN COMPARE WITH PCE

CCS - Rig floor based system.

The coupler is a pressure chamber on the rig floor located over the rotary table, through

which the drillstring passes and which seals around the drillpipe pin and box during the

connection process.

LIMITATIONS:

• Complicate system to manage

• Not friendly use

• Big and cumbersome system

• Space demands on the rig floor

The most simple and effective technology that can maintain constant the bottomhole

pressure and avoid pressure fluctuation is PCE.

8.5 FUTURE SUGGESTIONS

This project gave me an opportunity to learn how the influence of the technology can be

measured and use this analysis for future development. It became very important and key

point to take a decision of using PCE technology in drilling wells on Onshore wells. The

experience got from this project will support my future work related to performance analysis

and it left good basement for my personal improvement in this field.

The qualitative part of this analysis are trusted and using real data of database in eni the

project could expand the limits and analyze also wells on Offshore field. In my opinion the

35

POLITECNICO

DI MILANO

results could be used for general evaluation of different technologies as the methodology

used in this project is covering all appeared issues. As a suggestion for a project, I would add

also the qualitative part using a questionnaire for managers who had an experience with this

technology. This absolutely could cover also all possibly appeared issues what is very

valuable when we are talking about huge investments in oil&gas industry.

36

POLITECNICO

DI MILANO

9. REFERENCES

1 ENI.COM

2 ONEPETRO.COM

3 SPE ANNUAL TECHNICAL CONFERENCE AND EXHIBITION, 26-29 SEPTEMBER 2004, HOUSTON, TEXAS

4 WWW.OFFSHORE-MAG.COM/ARTICLES/PRINT/VOLUME-61/ISSUE-11/NEWS/DRILLING-TECHNOLOGY-CONTINUOUS-CIRCULATION-COUPLER-SOLVES-PROBLEMS-WHEN-FLUID-STOPS-FOR-JOINT-CHANGE.HTML

5 WWW.ONEPETRO.ORG/MSLIB/SERVLET/ONEPETROPREVIEW?ID=00090702


Recommended