Earned Value Analysisby
John Cornman
For Details -- Lewis, Ch 10
Introduction
• “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way.
• Based on just 3 data points, it can provide consistent, numerical indicators with which you can evaluate and compare projects.
The 3 fundamental metrics
• Budgeted Cost of Work Performed.
• Budgeted Cost of Work Scheduled.
• Actual Cost of Work Performed.
Budgeted Cost of Work Performed
• This is the “Earned Value.”• Abbreviated as BCWP.• For completed work, it is the cost originally
budgeted to accomplish that work.• “How much work was actually done?”
Budgeted Cost of Work Scheduled
• Abbreviated BCWS.• It is the total budgeted cost up to the
analysis date.• Approximated by the total budget
multiplied by the fraction of total project duration at the analysis date.
• “How much work should have been done?”
Actual Cost of Work Performed
• Abbreviated ACWP.• What it actually cost to accomplish all the
work completed as of the analysis date.• “What did the work that was actually done
actually cost?”
Derived Metrics
• Schedule Variance (SV)• Schedule Performance Index (SPI)• Cost Variance (CV)• Cost Performance Index (CPI)
A Few More Acronyms
• BAC - Budget At Completion • = Total Original Budgeted Cost• Same as BCWS at completion
• EAC - Estimate At Completion• = Cumulative Actuals + Estimate-To-Complete
• VAC - Variance At Completion• = Forecast of final cost variance
Doing The Math• SV = BCWP - BCWS
• Negative means Behind Schedule
• SPI = BCWP / BCWS• Less than 1.00 means Behind Schedule
• CV = BCWP - ACWP• Negative means Over Budget
• CPI = BCWP / ACWP• Less than 1.00 means Over Budget
• EAC = BAC / CPI
An Example: Lemonade
• Make 1,000 cups over 50 days• Steady rate of 20 cups per day• Budgeted cost per cup is $0.50• Total project budget is $500
Lemonade Progress
• At end of day 10:• 150 cups have been made• Total actual cost is $90 (ACWP)
Lemonade Status
• BCWS = $100• 10 days x 20 cups per day x .50/cup budget
• BCWP = $75 (Earned Value)• 150 cups x .50/cup budget
• SV = BCWP - BCWS = -$25• SPI = BCWP / BCWS = 0.75• CV = BCWP - ACWP = $75 - $90 = -$15• CPI = BCWP / ACWP = 0.833
Lemonade Forecast
• EAC = BAC / CPI = $500 / 0.833 = $600• VAC = BAC - EAC = $500 - $600 = $100
(unfavorable)• Schedule at Completion =
50 / SPI = 50 / 0.75 = 66.67 days
MS Project 98 Support
ID Task Name BCWS BCWP ACWP SV CV EAC BAC VAC1 MS Project 98 Example $1,920.00 $840.00 $960.00 ($1,080.00) ($120.00) $2,760.00 $2,400.00 $360.00
F S SNo
Five Simple Criteria forEarned Value Applications
1.Define (scope) the project. . .with a WBS2.Plan and schedule the project scope3.Budget cost account plans to functions4.Establish and maintain a performance
baseline5.Monitor performance and forecast final
resultsFleming & Hoppleman. 1996. Earned Value Management. PMI
Earned Value Management
http://www.acq.osd.mil/pm/